You are on page 1of 2

No.

INSTANSI Pekerjaan KETERANGAN


14/Apr 15/Apr 16/Apr 17/Apr 18/Apr 19/Apr 20/Apr
A. STAFF DAN HARIAN TATA
1 Staff Staff TATA 63 63 14 60
2 Rigger TC Staff TATA 2 2 2 2
3 Operator Mobile Crane harian TATA 1 1 1 1
4 Operator Scissor Lift harian TATA 22 22 22 22
5 Operator Boomlift harian TATA 2 2 2 2
6 Operator Forklif harian TATA 2 2 2 2
7 Operator Excavator harian TATA 1 1 1 1
8 Security Keamanan 6 6 6 6
9 OB harian TATA 2 2 2 2
SUBTOTAL 101 101 52 98 0 0 0
B. MANDOR
1 Mdr. Bambang Cor 26 26 26 24
2 Mdr. Sirin Cleaning 17 18 18 13
3 Mdr. Margono Besi 20 20 10 18
4 Mdr. Kuriman Kayu 43 43 37 40
5 Mdr. Oziel Scaffolder 18 18 17 15
6 Mdr. Sabar Las 15 15 14 15
7 Mdr. Doni Safetyman 8 8 8 7
8 Mdr. Cahyo Scaffolding 39 40 37 40
9 Mdr. Pudin Finishing 50 51 43 40
10 Nuri Finishing 35 40 38 30
11 Carto Finishing 23 23 22 22
12 Nanang Finishing 62 63 60 61
13 Eman Finishing 18 19 16 18
14 Pardi Keramik 17 17 14 14
15 Sugih Clening halus 6 6 6 6
16 Surono Finishing 17 15 14 15
17 Panjul Finishing 22 20 18 15
18 Jupri Finishing 16 15 13 20
SUBTOTAL 452 457 411 413 0 0 0 0
C. SUBKON
Staff 2 2 0 0
Ade Karta ( Electrikal 49 47 40 60
Ade Karta (Mekanikal) 26 26 25 24
Ade Karta (welder) 5 5 7 4
Sucipto (Plumbing) 20 20 19 20
Bimo (mekanikal) 42 40 32 32
Bimo ( Plumbing) 9 9 9 8
1 PT. HAMANROKO
Bimo (Welder) 5 5 3 4
Didi (Mekanikal) 24 23 19 0
Didi (Welder) 1 1 1 0
Turiman (Ducting) 10 10 4 8
Nurbasar (Mekanikal) 10 10 4 0
Edi (Elektrikal) 24 24 20 17
Op. Scissor 2 2 2 0
Worker 68 65 17 55
OP. Mobile Crane 0 0 0 0
2 PT. BMB Rigger Mobile Crane 0 0 0 0
Operator Boomlift 1 1 0 0
Scaffolder 0 0 0 0
3 PT. AWT Atap 40 37 25 21
4 PT. DPJ 0 0 0 0
5 PT. PENINDO Railing 4 4 2 2
6 PT. SANWAMAS Rolling Door 3 3 0 3
7 PT. SINAR GADING 2 2 2 2
8 PT. INTERDESIGN PLAFON 8 8 5 7
9 PT. TKE (Elevator) 7 7 4 7
10 PT. HANCO Tangga Baja 12 12 10 10
11 PT. LION 6 5 4 4
SUBTOTAL 380 368 254 288 0 0 0 0
TOTAL (A+B+C) 933 926 717 799 0 0 0