Required data for short-circuit calculation for buses include:
z Nominal kV (when the prefault voltage option is set to use nominal kV)
z %V (when the prefault voltage option is set to use bus voltage)
z Type (such as MCC, switchgear, etc.) and continuous and bracing ratings
z X-factor (IEEE 1584-2002)
z Electrode Configuration
z Height
z Width
z Depth
z Gap between conductors
z Working Distance
z Equipment Name (not actually required, but is displayed by the program on arc flash labels)
z Insulated Glove Class (required for some labels)
z Insulated Glove V-rating in Volts (required for some labels)
z Main Protective Device Isolation
Branch Data
Branch data is entered into the Branch editors (i.e., 3-Winding Transformer, 2-Winding Transformer,
Transmission Line, Cable, Reactor, and Impedance). Required data for short-circuit calculations for branches
include:
mk:@MSITStore:C:\ETAP%202101\Etaps.chm::/Required_Data_Arc_Flash.htm 14/04/2023
Required Data - Arc Flash Page 2 of 6
z Transformer winding connections, grounding types, and grounding parameters to determine the K2
factor per IEEE 1584.
z Nominal kV
z %V and Angle
z 3-Phase MVAsc and X/R
z Grounding types and parameters to determine the K2 factor per IEEE 1584.
z Grounding types and parameters to determine the K2 factor per IEEE 1584.
Inverter Data
Required data for short-circuit calculations for inverters include:
mk:@MSITStore:C:\ETAP%202101\Etaps.chm::/Required_Data_Arc_Flash.htm 14/04/2023
Required Data - Arc Flash Page 3 of 6
z Grounding types and parameters to determine the K2 factor per IEEE 1584.
z Grounding types and parameters to determine the K2 factor per IEEE 1584.
z % motor load
z Grounding types and parameters to determine the K2 factor per IEEE 1584.
z Max kV
z Cycle (not the contact parting time but the rated interrupting time)
z Rated kV
mk:@MSITStore:C:\ETAP%202101\Etaps.chm::/Required_Data_Arc_Flash.htm 14/04/2023
Required Data - Arc Flash Page 4 of 6
ETAP needs to know the opening time of the circuit breakers only. The SC Duty parameters are required only
for device evaluation (please see Chapter Short-Circuit Required Data for device evaluation).
z Type (power, molded case, or insulated case). This information is needed based on IEEE 1584 2002
Table1 (Power Circuit Breaker Operating Times).
z Rated kV
z Type (power, molded case, or insulated case). This information is needed based on IEEE 1584 2002
Table1 (Power Circuit Breaker Operating Times).
z Rated kV
Trip Device
Fuse Data
Required data for short-circuit calculations for fuses include:
z Fuse ID
z Fuse rated kV
z Fuse rated kV
Overload Heater/49
Required data for short-circuit (Clipping kA and Sequence-of-Operation) calculations for OLH/49 includes:
mk:@MSITStore:C:\ETAP%202101\Etaps.chm::/Required_Data_Arc_Flash.htm 14/04/2023
Required Data - Arc Flash Page 5 of 6
z Resistance / Tolerance
CT/PT Data
Required data for short-circuit (Clipping kA and Sequence-of-Operation) calculations for CT and PT includes:
z Rating (Ratio)
Relay/MVSST Data
Required data for short-circuit (Clipping kA and Sequence-of-Operation) calculations for Relay includes:
Other Data
There are some study case related data, which must also be provided, and you can enter this data into the
Short-Circuit Study Case editor. The data includes:
z Standard (ANSI/IEC)
z Prefault voltage
z Faulted buses
z Cable/OL heater (select this option to include cable and overload heater elements for Arc Flash)