You are on page 1of 46

Revinal Dela Rosa

Education:
● Master of Science in Electric Power System engineering
(North Carolina State University) - 2020
● Bachelor of Science in Electrical Engineering
(Bulacan State University) - 2003
Licenses:
● Professional Engineer in New York, California, Texas, North
Carolina, Tennessee, Washington, Alabama, Pennsylvania (Sign and
seal)
● Registered Electrical Engineer - Philippines (Expired)
● Registered Master Electrician - Philippines (Expired)

Standard:
● Working group/co-author “IEEE Guide for the Design of Low-Voltage
Auxiliary Systems for Electric Power Substation” IEEE Std. 1818-
2017
Notable Projects

● Vietnam Omon Thermal Power Plant


Lead Electrical and Instrumentation Construction Design Engineer
(Assigned in Nagasaki, Japan for 2 years and in Vietnam <year)
● 230kV/115KV Embarcadero and Potrero Substation
(Supplying more than 60% of downtown San Francisco California,
USA)
Lead Electrical Engineer who Signed and Sealed the Electrical
Design drawings & calculations and consider as Engineer in Record
● Project Lead Engineer who supported Google in creating
Specifications on High Voltage Substation Equipments to be used in
their Data Centers.
● Working now in some projects of US Government.
High voltage substation (basic) &
ac & dc auxiliary system
calculation guide

By: Revinal Dela Rosa PE, MSEPSE


Overview:

1. Generation, transmission, distribution background


2. HV Substation
3. HV equipments
4. HV bus configurations
5. Factors affecting design and engineering of HV
substation
6. Basic calculations HV equipments
7. AC and DC auxiliary system calculation
● Power
Generation ● Generation Step- ● Transmission
DER up Transformer Line

● Customers ● Distribution
Source: https://kiewit.com/markets/power/ ● Distribution Substation
DER

Source: https://en.wikipedia.org/wiki/Electric_power_transmission
Substation
● Transmission
Substation

● Distribution
Substation

● AIS and GIS


AIS
“Air Insulated
Substation”
GIS
“Gas insulated
switchgear”
Substation Equipments
● Transformer
● Breaker
● Switch
● Surge Arrester
● Potential
Transformer/CCVT
● Current Transformer

Source: pfiffner, ABB, Siemens


Bus Configuration

Source: IEEE
Bus Configuration

Source: IEEE
Bus Configuration

Xfmr 1 Line 1

Line 2 Xfmr 2

Source: IEEE
Bus Configuration

Xfmr 1

Xfmr 2
Line 2

Line 1

Source: IEEE
Bus Configuration

Source: IEEE
Bus Configuration
Factors Affecting the Design and Engineering

Physical
-Spacing and Clearances (ANSI C29.8 & 29.9, NESC,
IEEE 1427-2006, NFPA 70E), To check Client Standard
(Utility or Industrial clients)
Structural
-Applied forces (Wind, Ice, Short Circuit) (IEEE 605-Rigid
Bus), To check Client Standard
Protection, Control and Automation
-Type of communication Protocol (Modbus, DNP3 or
IEC61850)
-Do we need redundancy? How many Panels we need?
Do we need MIMIC Panel? What is the existing P&C and
Automation set up? Security??
Basic Calculation in Substation

Main Transformer (3 phase)


Legend:
VA = (√3) x VL x IL MVA : Mega Volt Amp
VL : Line Voltage
IL : Line Current

1. What is the minimum Transformer size given the


Line Voltage equal to 115kV and Line Current of
600 A?
119.5 MVA

MVA Base
First Stage Fan is on

Source: Augusta RFP 2nd Stage Fan is on


Basic Calculation in Substation

HV CB & Disconnect Switch rating Legend:


MVA : Mega Volt Amp
HV CB rating (IL) = 1.25 x VA / [(√3) x VL] VL : Line Voltage
IL : Line Current

Safety factor

1. What is the rating of HV Breaker given the Line


Voltage equal to 115kV and protecting the
158MVA Transformer?

Source: pfiffner, ABB, Siemens


991A

Source: Augusta RFP


Basic Calculation in Substation
KAIC (kiloampere interrupting
capacity) Calculation
Considering Infinite Bus
I short Circuit = MVA base Base Rating
(√3) x VL x %Z

1. What is the KAIC rating of the breaker of


secondary side of Transformer having
impedance of 10%?

Source: pfiffner, ABB, Siemens


19 kA

Source: Augusta RFP


Surge Arrester

Source:
http://www.arresterworks.com/ArresterFacts_files/ArresterFacts%2
0016%20Selecting%20Arrester%20MCOV-Uc.pdf
Current Transformer:

Minimum size:
Primary Winding = Full Load Current
Secondary winding = 5A
Note: Need to verify to P&C, P&C need to consider CT matching, burden and
short circuit considering.

Example size : 600/5A, 1200/ 5A, 3000/5A


Potential Transformer/ CVT,
CCVT:

Minimum size:
Primary Winding = Line to Ground Voltage (HV system)
Secondary winding = 115V
Note: Need to verify to P&C, P&C need to consider system requirement

Example size :
Auxiliary Systems of High
Voltage Substation
AC & DC
What do we need?

1. Main Single Line Diagram/Single Line and Metering Diagram


Includes all the electrical equipments such as:
a. Breaker
b. Transformer
c. Relay
d. Current Transformer
e. Potential Transformer
2. Lay-out of Substation (lighting, equipments, receptacles)
What do we need?

3. Need to identify the DC Loads


a. Charging Motor of Circuit Breaker
b. Trip/close coil of Circuit Breaker
c. Lockout relay
d. Relay
e. Communication
4. Need to identify the AC Loads
a. Heaters of Circuit Breakers, Potential Transformers, Current
Transformers
b. AC Loads of Transformer
c. Lighting, HVAC, receptacles etc.
HV Substation Lay out

From http://www.quad3.com/69kv-13-2kv-substation-feasibility-design.php
Building Layout
Catalogue Sheets
In order to get the AC Loads,
we need to get the DC loads
first.

Are we going to include and


get the sum of all the DC
loads?
The answer is “No”, but we
need to create a different
scenarios and simulate the
location of the faults and
look where there will be the
highest consumption of DC
loads.
Worst Case scenario
Creating a load profile
Creating a load profile
Calculation of Battery/DC
Loads:

Source: IEEE std 485-1997


Simulation example:
Simulation Result:
Factors in Battery sizing:
1. Voltage
2. Amp Hour (Capacity)
3. Depth of Discharge
4. Physical size
5. Location
6. Temperature
Calculation of AC loads:
Factors in AC Aux
1. Voltage (Phase- Single Phase, Three
Phase)
2. Ampere
3. KAIC
4. Connection of the Transformers
(Wye-Delta?)
5. Location (NEMA 1, NEMA 3R)
6. Temperature
7. Brown field/Green field Substation
Thank you for Listening!
Keep safe and God Bless!

revinald_77@yahoo.com

You might also like