Professional Documents
Culture Documents
PROJECT REPORT
OF
SIMLONG OCP (2.00 MTY)
EASTERN COALFIELDS LIMITED
March, 2011
Regional Institute-1
Central Mine Planning & Design Institute Ltd.
( A Subsidiary of Coal India Ltd.)
G.T.Road (West End )
Asansol-713 304.
STRICTLY RESTRICTED
FOR COMPANY USE ONLY
The information given in this report
is not to be communicated either
directly or indirectly to the press
or to any person not holding an
official position in the CIL / Government
PROJECT REPORT
OF
SIMLONG OCP (2.00 MTY)
EASTERN COALFIELDS LIMITED
VOLUME - I
(EXECUTIVE SUMMARY)
March,2011
Regional Institute-1
Central Mine Planning & Design Institute Ltd.
( A Subsidiary of Coal India Ltd.)
G.T.Road (West End )
Asansol-713 304.
Project Report of Simlong OCP(2.0 MTY) CMPDI, RI-1
VOLUME – I
CONTENTS
A. Summarised Data I – VI
B. Executive Summary
1. Introduction ES - 1
2. Marketability & Justification ES – 3
3. Project Site Information ES – 4
4. Geology ES – 5
5. Mine Boundary, Reserves & Mine Life ES – 7
6. Method of Mining ES – 9
7. Mining & Dumping Strategy ES – 11
8. Mining Schedule & Equipment Phasing ES – 12
9. Coal Quality ES – 15
10. Pumping & Drainage ES – 16
11. Coal Handling & Despatch Arrangement ES – 16
12. Workshop, Store And Magazine ES – 17
13. Power supply, Illumination & Communication ES – 18
14. Civil Construction ES – 19
15. Safety And Conservation ES – 20
16. Environment And Management ES – 21
17. Land Requirement ES – 22
18. Mine Closure Planning ES – 24
19. Manpower, Productivity & Training ES – 24
20. Project Implementation Schedule ES – 25
21. Financial Evaluation ES – 26
22. Outsourcing Option ES - 28
SUMMARISED DATA
B. GEOLOGICAL
1 Name of geological blocks Name Simlong OCP Block
considered
2 Area of the geological blocks sq. km 2.40
3 Borehole Density within the block BHs/sq.km 14.6
4 Description of all coal seams within block
Stratigraphic Thickness (m) No. of Geological Remarks
Sequence Min. Max. borehole Reserves
intersections (Mt)
Seam-VII 0.54 - 1 - Unworkable
Parting 29.52 -
Seam-VI 0.89 2.88 4 1.383
Parting 15.17 18.20
Seam-V 2.65 5.03 7 6.123
Parting 24.06 25.31
Seam- 0.65 1.99 5 0.334
IV(BOT)
Parting 13.12 17.65
Seam-III(TOP) 0.22 1.45 12 1.073
Parting 1.21 8.75
Seam-III(BOT) 0.25 1.51 12 1.056
Parting 6.31 19.60
Seam-L3 0.10 1.48 10 - Resvs. Not considered
Parting 3.05 8.72
Seam-II(TOP) 1.14 5.93 10 6.127
Parting 1.02 7.01
Seam-II(BOT) 1.09 4.51 11 5.317
Parting 6.21 9.99
Seam- 6.99 11.65 12 16.309
II(COMB)
Parting 5.89 12.30
Seam- L-2 0.10 3.32 20 2.007
Parting 6.01 17.08
Seam- I(TOP) 1.00 5.22 12 3.045
Parting 0.50 4.90
Job No.102177 I
Project report for Simlong OCP CMPDI, RI-1
Sl. No. Particulars Unit Value
Seam- I(MID) 0.12 1.60 11 0.192
Parting 0.90 8.75
Seam- I(BOT) 0.28 1.72 11 0.281
Parting 1.97 11.33
Seam- 6.86 22.37 19 46.536
I(COMB)
Parting - -
Seam- - - - 0.410
I(TOP)/(MID)
TOTAL 90.193
C. TECHNICAL
1 Area of the proposed mine block sq. km 2.40
(with break-up of different
geological blocks)
2 Borehole density within mine area BHs/sq. km 15.00
3 Mine parameters
Extent along strike (min. – max.) km 3.00 – 3.20
Extent along dip (min.-max.) km 0.35 – 0.80
Area of Excavation Ha 210.00
4 Description of coal seams proposed to be worked along with the parting details
Name of seam Thickness Av. Parting / Top Av.Grade Depth Mineabl Volume of
range OB Thickness (UHV/ range (m) e OB
considered( (m) GCV) Reserve (Mcum)
m) s (Mt)
23.00 37.73
Seam-VI 2.00 D 0.32
Parting 15.50 8.28
Seam-V 4.50 F 2.13
Parting 24.00 17.60
Seam- 1.15 E 0.23
IV(BOT)
Parting 14.50 15.30
Seam-III(TOP) 1.15 F 0.77
Parting 5.50 5.94
Seam-III(BOT) 1.10 E 0.63
Parting 15.00 24.20
Seam-II(TOP) 4.00 G 1.87
Parting 4.50 1.08
Seam-II(BOT) 3.80 G 1.60
Parting - -
Seam- 8.50 F 11.54
II(COMB)
Parting 10.50 11.77
Seam- L-2 2.00 E 1.34
Parting 25.00 12.27
Seam- I(TOP) 2.50 F 3.10
Parting 3.00 1.11
Job No.102177 II
Project report for Simlong OCP CMPDI, RI-1
Sl. No. Particulars Unit Value
Seam- I(MID) 3.00 F 0.64
Parting 2.59
Seam- I(BOT) G 0.78
Parting 3.00 -
Seam- 14.00 E 13.85
I(COMB)
Total F 38.80 137.80
3
5 Av. Stripping Ratio m /t 3.55
6 Method of Mining Shovel And Dumper
7 Target Output
Nominal production capacity (at
100%) Mt 2.00
Peak production capacity (at Mt 2.30
115%) Mt 1.70
Production capacity (at 85%)
th
8 Year of achieving Target 5 Year
Production
(from zero date)
th
9 Year of start of Internal Dumping 8 year
10 Production Phasing ( from zero date upto target year)
Year / Year 1 Year 2 Year 3 Year 4 Year 5 Upto Target year
Coal Seam
Coal (Mt) - 0.50 1.00 2.00 3.50
3
OB (Mm ) - 2.00 2.80 5.60 10.40
11 Total Mine Life (at Nom.
production capacity)
Construction period Years 5
Production build-up period Years 3
Production period Years 24
Mine closure period Years 5
Job No.102177 IV
Project report for Simlong OCP CMPDI, RI-1
Sl. No. Particulars Unit Value
No. of villages within mine Nos. 4
boundary
No. of land oustees 823
No. of PAFs to be rehabilitated 165
9 Cost of land & Rehabilitation Rs. crores
Total Cost 36.00
R&R only 6.75
10 Total EMP Capital Rs. crores 24.06
Social cost 6.75
Environment cost
17.31
11 Average annual rainfall mm 1350
12 Make of Water (during rainy Cu.m/day 93800 (approx)
season)
13 Total proposed pumping capacity lps 250
14 Drainage of the Area (Name of Gumani River
river/nala)
15 Any proposed diversion of nala or No
power line
1A Total Additional Capital Investment Rs. Crores 457.67 428.46 117.23 90.39
3 Total Capital Investment on P&M Rs. crores 336.38 308.92 36.31 11.74
5 Capital requirement upto target Rs. crores 402.90 373.67 107.70 81.24
year
6 Year of opening of Revenue Not applicable Not applicable
account (from zero date)
7 Earnings per manshift (EMS) Rs. 1921.35 1939.52 2139.87 2211.21
Job No.102177 V
Project report for Simlong OCP CMPDI, RI-1
Sl. No. Particulars Unit Value
11 Financial Internal rate of return %
(FIRR)
- - 47.64 62.85
At 100% production level
At 85% production level 38.16 52.10
12 Economic rate of return (only for % - -
projects to be approved by Govt.)
At 100% production level - -
At 85% production level
13 Desired av. Selling Price to yield Rs. / tonne
12% FIRR
1337.83 1253.34 645.28 575.68
At 100% production level
1491.01 1396.69 659.69 615.37
At 85% production level
14 Break-even point
Production Mty 3.93 3.47 0.86 0.70
Production level % 196.60 173.33 42.97 34.87
15 Cost of Outsourcing (average) Rs/tonne 310.63 290.95
16 Mine Closure Cost (for corpus Rs. crores 38.69
fund)
17 Expected Completion Capital Rs. crores 509.54 478.10 127.07 97.99
Job No.102177 VI
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
EXECUTIVE SUMMARY
1.0 INTRODUCTION
1.1 The Simlong Opencast mine is located in the Pakur sub-division of Sahebganj
district and part of the Rajmahal coalfields under the jurisdiction of Eastern
Coalfield Ltd. At Simlong, which is a small part of Chuperbhita basin, a manual
quarry had been worked earlier on the bed of the stream ‘ Lada’ which flows almost
along the outcrop of the bottommost seam in the geological block.
1.2 A scheme called “ Scheme on Simlong Quarry” was prepared by ECL in January
1981, with a targeted production of 0.10 Mty on the basis of data available from old
quarry workings. Subsequently, 17 no. exploratory boreholes were drilled by ECL
and a “ Revised Feasibility Report For Simlong Opencast Project “ was prepared
by CMPDI in July 1983 with a targeted production of 0.10 Mty.
1.3 The Revised Feasibility Report estimated a mineable coal reserves of 2.34 Mt. at a
stripping ratio of 1.61 cum./te. with part diversion of Lada nala. The report
envisaged a capital investment of Rs. 310.27 lakh and mine life of 24 years. The
existing mine working is as per this Revised Feasibility Report. The mine has been
run departmentally till 2007-08. After survey off of all the departmental HEMM,
mining is being done by outsourcing since 2008-09.
1.4 Mining work within the quarriable limit of the” Revised Feasibility Report” is going to
be finished shortly. This current PR envisages to extend the working further,
covering the entire geological block (excluding forest area in the N-E part and the
indicated reserves part) and to enhance the target to 2.00 MTY. Along with
extension of mine-take area, it also proposes building up of infrastructural facilities.
1.5 The exploration of Simlong block has been completed by MECL in January 1992
and the present report incorporates the complete data of the 33 boreholes drilled in
this block by MECL, besides 1 borehole drilled by CMPDI earlier in the block. The
overall borehole density within the proposed mine take area is 14.6 per sq. Km
considering two additional boreholes from adjacent block. The total number of
boreholes drilled by different agencies are as follows:
Job No.102177 ES - 1
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
1.6 The present PR envisages two different options for operation e.g. Departmental
option and Outsourcing option. In the outsourcing option only production of coal
and removal of OB along with pumping of mine water have been proposed to be
outsourced and all other activities under departmental responsibility. In both the
Departmental and Outsourcing options, two variants have been considered. In
one variant, total excavation job has been envisaged by shovel dumper
combination, and in other variant OB removal has been proposed by Shovel-
dumper method and coal winning by surface miner.
1.7 There are several constraints towards the implementation of the proposed PR.
The identified problems areas are listed below:
A number of villages are located within the mine-take of Simlong (OCP)
block., which are to be rehabilitated.
The nearest railhead is at a distance of 60 km from the Simlong block.
Presence of a no. of hillocks around the block. Some part of the leasehold
area lies within the forest land.
Godda-Sahibganj PWD road passes through the middle of the property.
No power supply arrangement at the site for operating the
HEMM/equipment.
1.8 Output from the proposed OCP is power grade coal meant to be consumed by
power plants. Presently, coal from Simlong mine is dispatched to Bakreswar
Thermal power plant of west Bengal government, at a distance of 180 Km. by road
transport. The Simlong OCP is proposed to be linked to two STPPs namely,
Farakka and Kahalgaon of NTPC for meeting their increasing demand. The
production from Simlong OCP is to be dispatched from the proposed siding near
Kumarpur, adjacent to the existing MGR track connecting Rajmahal and Farakka
STPS.
Job No.102177 ES - 2
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
2.2 The entire production of coal from Rajmahal coal fields (i.e, Rajmahal OCP,
Chuperbhita OCP and Hura-‘C’ OCP) is linked to the two Super Thermal Power
Stations (STPS) of NTPC. At present, the existing Super Thermal Power Stations
(STPS) of NTPC, which are linked to Rajmahal Group of coalfields of ECL, are
Farakka STPS (1600 MW) and Kahalgaon STPS, stage- I (840MW) & stage-
II(1500MW). The demand of power grade Coal of these two STPS is 27.59Mt.
(11.30 Mt. for Farakka STPS + 5.85 Mt. for Kahalgaon STPS, stage-I and 10.44 Mt.
For Kahalgaon STPS, stage-II ).
2.3 Farakka STPS, stage – III (1 x 500 MW) of NTPC is likely to be commissioned in
2011 - 12. Thus the total ultimate demand of Power grade Coal for the two STPS,
i.e. Farakka & Kahalgaon STPS has been projected as 31.12 Mt. in the year 2011–
12 & beyond, including 3.53 Mt. for Farakka STPS, (stage-III).
In view of the massive demand of coal from two STPPs of NTPC , the proposed
Simlong OCP will play a significant role in bridging the gap between demand and
supply.
Job No.102177 ES - 3
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
3.0 PROJECT SITE INFORMATION
3.1 Simlong OC block falls in the district of Sahibganj of Jharkhand state and is located
between latitudes 24044’33” to 24045’55”(N) and longitudes 87026’30” to
87028’38”(E). The total area of the block is about 2.40 sq .km and is covered in the
Survey of India Toposheet no.72 P/5. Simlong OCP Block occupies the south-
western part of the Chuperbhita coalfields.
3.2 Gumani river runs along the western boundary of the block. Simlong OCP block is
well connected by metalled road. Godda-Sahebganj road passes in the north-
western part of the block. The block is located at a distance of 80 km from
Sahibganj district headquarter and 30 km from Godda district headquarter. Some
important cities like Bhagalpur, Deoghar, Asansol are located at a distance of 100,
110 and 218 Km. respectively and are well connected by all weathered road.
3.4 The drainage of the block is mainly controlled by the Gumani river which flows at
the western boundary of the block. Damro Nala meanders along the south-western
boundary of the block. Gumani is a perennial river and its catchment area extends
to about 1096 sq. km. The Simlong OCP block also falls in this catchment area.
3.5 Existing mine is being run by shovel-dumper combination under outsourcing mode.
Mined out ROM coal is kept in pit-head coal depot, from where it is transported to
power plant by contractual tracks. Presently, coal is being despatched to
Bakreshwar Thermal Power Plant of West Bengal at a distance of 180Km. There is
no CHP at the mine. However, all the existing infrastructural facilities are situated
on the coal bearing area within the proposed quarry. Quarterly environment
monitoring is being done and compliance report is being submitted to Jharkhand
State Pollution Control Board regularly. However, the existing mine has no
approved EMP.
Job No.102177 ES - 4
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
4.0 GEOLOGY
4.2 Sequence of Coal Seams – Seven regionally correlative and two local coal seams
have been identified in the block on the basis of sub-surface data accrued by way
of exploratory drilling as well as surface geological mapping.. The local Seam L-3
has a very limited development in the block it has only been encountered in one
borehole i.e RCH-105. Sequence of coal seam as established in the block is given
below.
Job No.102177 ES - 5
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
4.3 The geological report of Simlong OCP has been prepared by MECL in 1992. The
overall borehole density in the Simlong (OCP), Geological block covering a total
area of 2.40 sq km is about 14.2 per sq. km. However, considering the two
additional boreholes (RCH-98 and RCH-105), overall borehole density within the
proposed mine take area is 14.6. per sq. km. which is sufficient for deposit
appraisal.
4.4 Coal measures in Simlong (OCP) block, are trending in NW-SE direction and
dipping towards north-east. Dip and strike of the beds interpreted on the basis of
floor contours are in conformity with the fields observation. The dip is generally 8 0-
100.
4.5 The geological structure of the block is simple. Three faults (numbered F1, F2 and
F3) have been deciphered in this block. Faults F1 and F3 mark partly the northern
and eastern boundaries of the block respectively. Fault F3 is a majore fault having
a throw of about 150m, while fault F1 has a throw varying from 20m. to 65.m. A
minor fault , F2 having a throw varying from 0 to 5m. has been observed within the
quarry. During the exploration, no dyke or sill is found to exist within the block.
4.6 The total geological reserves within Simlong block have been categorised as
‘Proved’ and ‘Indicated’. In the south-eastern part of the block the zone of influence
of the borehole has been taken upto 200m. from boreholes RCH-146 & 117 and
beyond that zone the reserves have been put under Indicated category.
4.7 Total reserves in Simlong OCP Block is 90.193 million tonnes, of which 54.196 Mt.
Falls within 1:5 coal:OB ratio. 34.427 Mt. Fall beyond 1:5 coal to overburden ratio
and 1.570 Mt. Occurs in incrop region. Proved reserves are 63.982 Mt. Indicated
reserves are 24.641 Mt and in incrop region reserves are 1.570 Mt. Summary of
reserves is given below.
Job No.102177 ES - 6
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
5.1 The quarry area of the proposed OCP has been decided including the entire coal
reserves under proved category within the geological block excluding the area
under thick forest cover.
5.2 Out of the proved reserves of 63.982 Mt. and in-crop zone reserves of 1.57 Mt.,
geological reserves considered for the proposed project is 45.40 Mt. The total
mineable reserves within the above selected quarry boundary, has been estimated
(as on 1.04.2011) as 38.80 Mt. (considering a production of 0.30 Mt during 2010-
11from the existing working) with a corresponding volume of OBR of 137.80 Mm 3 at
an average S.R. of 3.55 m3/te. Mineable reserves have been estimated taking into
account 10% deduction on account of geological uncertainties and 5% mining
losses. The detail of geological reserves is given below:
Job No.102177 ES - 7
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
Geological Considered For Remaining Geological
Reserves Of The Proposed Reserves
The Block Project (Mt.)
63.982 44.40 2.00 Mt worked out by
Proved existing mine; Rest 17.582
Category Mt. under dense forest cover
5.3 Considering the large strike length of the property and problem of outside OB
dumping, the total quarry area is proposed to be worked in two parts e.g. East Part
and West Part. The East Part which consists of the existing mine working is
proposed to be worked first. The mineable reserves and Volume of OBR within the
proposed quarry are shown below.
5.4 With this mineable reserves, the life of the proposed Simlong OCP has been
estimated as 26 years including 2 years of construction period. Considering the
geo-mining condition, the rated capacity in the Eastern Part has been fixed at
2.00 Mt. of coal per year, which will be achieved in the 3 rd year of production
period. This 2.00 MTY production is scheduled to be continued till 11 th year of
production period, the penultimate year of Eastern Part of the mine.
Job No.102177 ES - 8
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
5.5 In the Western Part of the mine, the rated capacity has been fixed as 1.50 Mt. of
coal per year, due to overall coal thickness being much less, thinner coal seams
and higher stripping ratio. Since, 12th year of production period, the mine will
produce at a rate of 1.50 MTY till the end of mine life.
6.1 It is proposed to start initial excavation along the in-crop of seam-I at the East part
where existing mining activity is going on. Some of the existing infrastructure like
work-shop and ‘C’ type quarters have to be shifted before that. After establishing
connection of the proposed access trench with the existing working, the mine is
proposed to extend towards east to increase the strike length. East Part with a
mineable reserves of 20.60 M.te. will be exhausted in the year P12 of quarry
operation. Excavation will be started at the west part through a new access in the
P12 year of production period and continued till the end of mine life.
. The sequence and thickness of coal seam and parting along with other geo-
mining parameters are shown below:
Quarry parameters
Sl. No. Parameters Unit Value
East Part Wes Part Total
1. Av. Seam thickness
I m. 2.20 1.80
VI
ii m. 4.5 4.5
v
iii m. - 1.15
IVB
iv m. 1.10 1.20
III(Top)
v m. 1.10 1.10
III(Bot)
vi m. 4.00 -
II (Top)
vii m. 3.80 -
II (Bot)
viii m. - 9.00
II (Comb.)
ix m. - 2.00
L2
x m. 14.00 2.50
I
2. Av.OB/ parting thickness
I m 22.00 24.00
Top OB
ii m 15.50 16.00
Parting Bet. VI & V
iii m 23.50 24.50
Parting Bet. V & IVB
iv m 13.00 16.50
Part. Bet. IVB & III (T)
V m 3.20 7.50
Part. Bet. III(T) & III(B)
vi m 14.00 16.00
Part. Bet. III(B) & II(T)
Job No.102177 ES - 9
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
vii m 4.50 -
Part. Bet. II(T) & II (B)
viii m - 10.50
Part. Bet. II(B) & L2
ix m 30.00 20.00
Part. Bet. L2 & I(T)/Comb.
x m - 3.00
Part. Bet. I(T)/I(M) & I(M)/(B)
3. Dip of the seams Degree 8-10 8-10 8 – 10
4. Maximum depth m 160 160 160
5. Strike length: Km 1.30-1.60 1.25 -16.80 1.50
6. Width of the quarry: Km 0.35 - 0.75 0.55 -0.80 0.75
7. Area of Excavation Ha 106 120 210
8. Dip-Rise length on floor m. 550 500 500
9. Mineable Reserves Mt 20.60 18.20 38.80
3
10. Total OB Volume Mm 66.70 71.10 137.80
11. Average Stripping Ratio Cum./te 3.24 3.91 3.55
6.2 Excavation will be done by inclined slicing method. It has been envisaged that
shovel-dumper combination is the suitable option for overburden removal for this
project. As making provision of power supply is a difficult affair, all HEMM for the
project have been chosen to be diesel operated. The following arrangement of
equipment combination has been considered for the project.
6.3 10-12 cum diesei Hyd. Shovel is to work with 100T Rear Dumpers for main OB
workload (i.e. Top OB & thick partings). 5-6 cum Diesel Hyd. Shovel is to work with
60T Rear Dumpers for removal of thin partings and coal winning.
6.4 As an alternative option, coal winning has been considered by surface miner. In the
surface miner option, coal is envisaged to be extracted by surface miners (2200mm
dia drum). Extracted coal is envisaged to be loaded at the face by 3-4cum. pay-
loaders into 25T dumpers for transportation to pit-top dispatch point.
6.5 The OCP involves working of multiple seams with thickness varying in wide range.
Considering the rather steep gradient(80 to 100) of the coal seams and flexibility of
operation, shovel-dumper method has its own advantage whereas, the applicability
of surface-miner has some limitations. Major advantage of surface miner option is
the elimination of crushing arrangement at CHP and the process of drilling-blasting.
However, owing to the limitation of surface miner working in gradient (Max. 5 0 ), a
considerable amount of coal will be left by surface miner. These left out coal have
to be extracted by drilling-blasting or ripping. Sizing of this coal will be a problem
area. Point wise comparison between the two options is given in the summarized
data.
Job No.102177 ES - 10
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
7.0 MINING AND DUMPING STRATGY
7.1 East part is envisaged to start from the year P1 and continue up to the year P12
and the West part to run from year P12 till the end of mine life. Attempts have been
made to minimize the requirement of land for final external OB dump. OB from East
part will be placed at temporary external dump in site- 1&2 (at the west part of the
proposed quarry) and permanent external dump in site – 3 (beyond the eastern
boundary of the quarry). At the end of quarry operation in East Part, temporary
external OB dump-1&2 will be re-handled into the void of East part as well as West
part. The OB from West part will be placed at void of East part before starting of
internal dumping.
7.2 Total volume of OBR is 137.80 M.cum including 67.70 M.cum from East part and
71.10 M.cum from West part. Out of the 67.70 M.cum of OB from the East part,
24.00 M.cum is envisaged to be placed as external dumps, major part (18.0 M.cum)
of which are later proposed to be re-handled and placed as internal dump. The
remaining 6.0 M.cum shall be kept as permanent external OB dump at site-3.
7.3 Effort has been made to keep the volume of permanent external OB dump as small
as possible. The deck-wise capacity of the dumps is shown in the following table.
Job No.102177 ES - 11
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
7.3 The height of the external dumps is envisaged as 60 m above the surface with top
RL being +165 m at site-1 & 2. and +215 m at site-3. The dumps will be formed in 2
decks of 30 m each. Slope of individual deck does not exceed natural angle of
repose. Overall slope of the dump will be about 28 degree from the horizontal. East
part will be completely back-filled. However, some area will remain void at the end
of mining operation in West part.
8.1 The calendar plan of excavation has been formulated based upon the adopted
sequence of mine development and optimum condition of mining operation for the
entire life of the opencast mine.
8.2 Initial two years have been considered as construction period for the project. In
these two years of construction, no excavation has been proposed, only
infrastructure will be developed during this period. Excavation as well as coal
production has been proposed from the year P1 i.e. after 2 years of construction
period.
8.3 The East part which consists of the existing working is envisaged to be worked first.
Working in this part will be finished in the year P12. The rated annual capacity of
2.00 MTY is envisaged to be achieved in the year P3. Excavation at the Western
part will be started in the year P12. Rated capacity in this part has been envisaged
to be 1.50 MTY. Since year P12 till the end of the mine life, coal production is
envisaged to be at a rate of 1.50 Mt. per year.
8.4 The peak volume of OBR is 7.00 Mm3 at a stripping ratio of 3.50 m3/te.. The
average stripping ratio for the entire life of the mine is 3.55 m 3/te. The temporary
external OB dump (at west part of proposed quarry) created during the operation of
East part is proposed to be re-handled and re-handling programme is envisaged to
be started at end of East part e.g in the year P12. Overall stripping ratio considering
the volume of re-handling for entire life of mine works out to 4.02 m 3/te. The
summarised calendar programme of excavation is given below.
Job No.102177 ES - 12
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
C1
C2
P1 0.50 1.00 0.50 2.00 2.00 4.00 2.00 4.00
P2 1.00 2.00 1.00 2.80 2.80 2.80 2.80 2.80
P3 2.00 3.40 2.00 5.60 5.60 2.80 5.60 2.80
P4 2.00 4.50 2.00 5.80 5.80 2.90 5.80 2.90
P5 2.00 4.50 2.00 6.40 6.40 3.20 6.40 3.20
P6 2.00 4.50 2.00 6.40 6.40 3.20 6.40 3.20
P7 2.00 4.50 2.00 6.40 6.40 3.20 6.40 3.20
P8 2.00 4.50 2.00 6.50 6.50 3.25 6.50 3.25
P9 2.00 4.50 2.00 7.00 7.00 3.50 7.00 3.50
P10 2.00 4.50 2.00 7.00 7.00 3.50 7.00 3.50
P11 2.00 4.50 2.00 7.00 7.00 3.50 7.00 3.50
P12 1.10 0.40 1.50 3.80 2.20 6.00 4.00 1.00 7.00 4.67
P13 1.50 1.50 6.20 6.20 4.13 1.00 7.20 4.80
P14 1.50 1.50 6.20 6.20 4.13 1.00 7.20 4.80
P15 1.50 1.50 6.00 6.00 4.00 1.20 7.20 4.80
P16 1.50 1.50 5.40 5.40 3.60 1.80 7.20 4.80
P17 1.50 1.50 5.40 5.40 3.60 1.80 7.20 4.80
P18 1.50 1.50 5.40 5.40 3.60 1.80 7.20 4.80
P19 1.50 1.50 5.60 5.60 3.73 1.70 7.30 4.87
P20 1.50 1.50 6.00 6.00 4.00 1.30 7.30 4.87
P21 1.50 1.50 6.00 6.00 4.00 1.40 7.40 4.93
P22 1.50 1.50 6.00 6.00 4.00 1.40 7.40 4.93
P23 1.50 1.50 6.00 6.00 4.00 1.40 7.40 4.93
P24 1.30 1.30 4.70 4.70 3.62 1.20 5.90 4.54
Total 20.60 18.20 38.80 66.70 71.10 137.80 3.55 18.00 155.80 4.02
0
8.4 The requirement of HEMM, e.g., shovel, dumpers, drills and dozers etc. have been
estimated as per annual productivity based on adopted design criteria and
workload determined by the calendar plan considering the physical location of
equipment within the operating mine. For calculating the number of dumpers, the
Job No.102177 ES - 13
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
OB and Coal transportation leads have been taken as 2 - 3 Km and 1 - 4 Km
respectively. The total strength of required HEMM is given below.
Population of HEMM
Job No.102177 ES - 14
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
8.5 It is envisaged that SMS will be used for blasting. With the use of SMS, a magazine
of 5Te capacity is sufficient to cater the need of proposed OCP. Though SMS will
meet the major part of the explosive requirement, some cartridge explosive will also
be required for thin coal seams and partings Considering the powder factor of 3.33
m3/ Kg and 5.0 Te/Kg. for OB and coal respectively, the total annual explosive
requirement for the OCP with peak OB removal will be about 2155 te or about
7.20 tpd.
9.1 The coals of this block are primarily high moisture, non-coking coal. Seam-wise,
grade-wise Mineable reserves distribution along with over all specific gravity is
shown below.
Grade-wise, Seam-wise Mineable reserves along with overall Specific Gravity
Gradewise Mineable Reserves (Mt)
Name Of Seams Specific
Gravity
E F G Overall
The UHV of combined coal product of all the seams is 2818 Kcal/kg with
corresponding ash %age being 36.40. Thus the overall grade of coal will be of
grade F.
Job No.102177 ES - 15
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
10.0 PUMPING AND DRAINAGE
10.1 General topography of the project shows that surface drainage is not likely to
pose any major problem. The surface within the mine intake area is highly
undulating and is not traversed by major river/nallah. The lay-out of the quarry
provides suitable gradient along the quarry floors and the benches to facilitate
self-drainage of water to the lowest level of the quarry. For outsourcing option,
quarry pumping shall be under responsibility of outsourcing agency.
10.2 Accumulation of water within the mine has been estimated as 93805 cum/day, on
the basis of single day maximum precipitation. Peak required pumping capacity per
day (Quarry-wise) worked out to 18761 cum/day (approx).
Besides the above main pumps, adequate number of slurry/sludge pump (50
m3/Hr, 30m head) and face pump (30 m3/Hr, 30m head) have been provided.
11.1 A coal handling plant has been proposed to downsize ROM coal upto (-) 100
mm size. Initially, in the primary crushing system, ROM coal will be crushed
upto (-) 200 mm size with the help of Single Roll Crusher (i.e. Primary Crusher)
& in the next stage (-)200 mm coal will be crushed to (-) 100 mm size in the
secondary crushing system. (-)100 mm sized coal will thereafter, be stored into
4 X 100 Te. overhead steel fabricated truck loading hoppers or onto ground as
stock pile.
11.2 On the basis of 330 working days / year and 5 hours/shift, the rated capacity of
the CHP works out to be 600 tph. In order to meet the fluctuations of coal output
from the mine due to irregularities of transport system and seasonal fluctuations,
the design capacity of the CHP has been fixed as under :-
11.3 The CHP described above shall be provided for Shovel-Dumper method of
working under both departmental and outsourcing option. But for coal winning
by Surface Miner, no crushing facility is required and the proposed CHP will be
just an arrangement for surface storage and loading of coal to transporting
trucks. At CHP, 3 X 150 Te. overhead steel fabricated truck receiving – cum –
truck loading hoppers shall be provided . There shall be provision of loading of
coal onto trucks by means of sector gate fitted below hoppers.
12.4 Coal transportation from coal handling plant to the MGR siding at Kumarpur
shall be done contractually. NTPC has agreed to provide the required land
space for building up a warf wall by ECL.
12.1 Workshop and Project Stores have been envisaged for maintenance and repair of
equipment deployed in Simlong OCP Proposed workshop shall have following
facilities.
Job No.102177 ES - 17
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
b) Capital repair and major overhauling of equipment at Central workshop/
Regional workshop.
c) Mobile repair team with crew and facilities to cater the maintenance and minor
repair needs of field equipment at site.
12.2 Existing Simlong OCP has small magazine for licence of 450 Kg only. In the
current PR a magazine has been proposed for a capacity of 5 Te. The proposed
magazine will be situated near the existing one at the foot of existing External
dump. The magazine will be used for storing small cartridge explosives ( for
blasting thin partings and coal seams) and other blasting accessories.
13.1 Initially the project will receive power at 3.3 KV from two DG sets. Finally it will
receive power from Chuperbhita Sub-station after the establishment of H/T
line(132KV) in Chuperbhita. .Chuperbhita will receive power from Rajmahal Sub-
station of Jharkhand State Electricity Board.
13.2 The DG sets will supply power at 3.3 KV to the quarries, CHP, workshop, one no.
50 KVA 3.3/0.220(L-L) lighting transformer will be used to illuminate sub-station &
office
Capacity of the DG sets: Departmental Outsourcing
Variant-1 2.5 MVA 3.3 KV 1 MVA 3.3 KV
variant-2 1.5 MVA 3.3 KV 0.5 MVA 3.3 KV
13.3 The estimated annual energy consumption at target year for the proposed systems
are as follows :
DEPARTMENTAL OPTION
Variant -1
Job No.102177 ES - 18
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
Variant -2
OUTSOURCING OPTION
variant -1
S.N. Power Annual Energy Energy Power cost/Te
consumer consumption consumption/Te of production
(KWH x 106) of production (Rs.)
(KWH/Te)
1 Coal 2.55 1.28 6.40
2 Common 1.52 0.76 3.80
Total 4.07 2.04 10.20
Variant –2
14.1 Based on prevalent rate of different building materials in the project area, the
Building Cost Index for this project has been worked out as 2355 with respect to
100 base at Delhi as on 1.10.76.
14.2 The Civil Construction envisages the estimated capital requirement of the project
for 2.0 MTY target capacity of coal and envisaged manpower as detailed
elsewhere in the Report. Specifications towards the civil construction are based
on BPE guidelines, CMPDI Norms & practice for planning of coal mines.
Job No.102177 ES - 19
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
14.3 The service buildings include community buildings, offices, workshop & stores,
sub-stations, magazine & other statutory buildings. With around 70% housing
satisfaction, residential units have been envisaged. Hostel accommodation has
been proposed as 20% of type quarters. The proposed site for the colony to
accommodate these houses and other community/welfare facilities has been
identified and is located in the area adjacent to the proposed township
Chuperbhita OCP.
14.4 Gumani river has been identified as the source of raw water required for the
Project and residential colony. The requirement has been estimated as 0.45
MLD of potable water and 0.32 MLD of industrial water.
15.2 The haul road has been designed at a gradient of 1 in 16. The spoil will be stacked
in the external and internal dump space at the natural angle of repose to avoid the
sliding of OB bench. The surface of OB dump will be leveled and graded. Plantation
will be made on the slope of OB dumps to avoid the sliding of spoil.
15.3 Provision of embankment, with top RL being 3m above the last recorded HFL line,
has been suggested along the surface edge of quarry at places where the river is in
proximity of the quarry. Exposed coal faces are proposed to be mined out well
within the incubation period. Water spraying has been envisaged on the haul roads
starting from the quarry bench to external dump yard and around CHP to prevent
rising of dust in the air.
15.4 Measures have to be taken to minimize coal loss during mining operations.
Selective mining of in-seam dirt bands has been proposed. It is suggested to
practice controlled blasting. It is proposed not to dump any spoil material over coal
bearing area, amenable for opencast mining.
Job No.102177 ES - 20
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
16.2 Capital provision for pollution control arrangements, technical & biological
reclamation and rehabilitation / resettlement have been made in the project report.
The details of capital provision is given below.
Job No.102177 ES - 21
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
b. Equipment for Environmental work (Appendix – A.3.6) 24.50
Sub-total (III) 338.03
IV Capital for anti-pollution measures in mine & industrial
area.
a. 6 nos. 28 KL water sprinklers (Appendix – A.3.1) 493.79
b. Sewerage disposal system (Appendix – A.8.3.4) 247.29
c. Other developments in Industrial area viz road,drains/tree 1775.03
guards etc. (Appendix – A.8.2.2, A.8.2.3, A.8.2.4 & A.8.2.5)
d. Garland drains (Appendix – A.8.1) 15.00
e. Dust suppression in CHP (Appendix – A.3.5.1) 25.00
f. Settling Pond (Appendix – A.8.1) 53.00
g. Effluent Treatment Plant (A.2.1) 21.20
Sub-total (IV) 998.08
V Environmental control measures in township
a. Sewerage disposal in colony (Appendix – A.8.3.3) 114.16
b. Water treatment plant (Appendix – A.8.3.1) 18.00
c. Drains & tree guards in colony (Appendix – A.8.2.1) 0.82
d. Fencing in quarry and township (Appendix – A.8.1) 25.00
Sub-total (V) 157.98
VI Steps for prevention of mine inundation (Appendix – A.8.1) 27.00
Flood protection Embankments
VII Environmental data generation (Appendix – A.8.1) 15.00
VIII Preparation of EMP (Appendix – 8.4) 30.00
Grand Total (I to VIII) 2406.15
16.3 As per the directive of MoEF, quarterly Environment monitoring survey is being
done in Simlong OCP since 1999 and Environment statements submitted to JSPCB
annually.
17.1 For the proposed Simlong opencast mine, the total requirement of land is
estimated as 337.74 Ha, including 84.57 Ha of forest land 253.16Ha. of Non-
forest land . Majority of Non-forest land falls under the category of tenancy
Job No.102177 ES - 22
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
land. Non-forest land includes 39.96 Ha of Government land and 213.21 Ha of
tenancy land. Breakup of the requirement of land has been given below.
Requirement of Land(Ha)
Sl.No Particulars Total land Type of land.
. Required
Forest Govt. Tenancy
1 Quarry area (incl. Safety zone) 270.69 81.19 33.54 155.97
2 External dump 34.67 3.38 3.20 28.09
3 Infrastructure & others 32.37 - 3.22 29.15
Total Requirement 337.74 84.57 39.96 213.21
Under Possession 28.00 3.48 24.52
To Be Acquired 309.74 81.09 39.96 188.69
17.2 Four number of villages are lying within mining leasehold area which needs to be
rehabilitated. The number of household and population of each village are given
below:
17.3 On the basis of 20% increase over the 2001 census data, number of household
and population in above four villages is arrived at 222 and 1111 respectively.
However, considering only a small part ( less than 10%) of Chota Ghaghri
required to be shifted, number of population and house-hold for the purpose of
rehabilitation have been estimated to be 823 and 165 respectively. On the basis
of these data, rehabilitation and resettlement cost has been provided.
Job No.102177 ES - 23
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
18.0 MINE CLOSURE PLANNING
18.1 Simlong OCP is being planned upto a certain depth for a specified life of the
mine. There is scope for further deepening/extension of the mine in the eastern
part of quarry where dense forest exists and part of the reserves is of indicated
type.
18.2 If the decision for further extension of the mine is taken before closure of the
proposed quarry, approval for final mine closure plan may be deferred as mining
activities shall continue beyond present dip side limits. In the event of no further
deepening beyond the proposed mine limits, mine closure plan becomes
necessary and MOEF also desires the submission of such plan five years in
advance of closure.
18.3 As per the guide line of MOC, estimated closure cost for Simlong OCP works out
to Rs. 38.69 crores (@ Rs.6.00 lakh per Ha. for 337.74 Ha.). Accordingly, annual
closure cost is Rs. 1.55 crores which will be deposited throughout the mine life, in
an Escrow account to be opened with any scheduled bank at a rate compounded
5% annually. Provision of the above expenditure has been envisaged in this PR.
19.1 For the rated capacity of 2.0 MTY of coal, the total manpower requirement for
Simlong Opencast project has been estimated as 742 and 694 under
departmental option for coal winning by shovel-dumper method and surface
miner respectively. In outsourcing option the estimated requirement of
departmental manpower is 254 and 196 for shovel-dumper method of working
and coal winning by surface miner respectively. The break-up of manpower for
both the options are given below:
Job No.102177 ES - 24
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
Break-up of total manpower requirement & OMS
SL. Particulars Peak Strength(nos)
No Shovel-Dumper Option Surface Miner Option
Dept. Outsourcing Dept. Outsourcing
I Operation 360 23 366 19
II HEMM Maintenance 64 - 64 -
III CHP & Despatch 62 62 8 8
IV Common Manpower 248 166 248 166
V Environment 8 3 8 3
TOTAL (I+II+III+IV+V) 742 254 694 196
OMS (Te.) 10.75 11.53 33.97 45.91
19.2 Existing strength of manpower in the OCP is 53, which includes 33 time rated
employees, 17 monthly rated employees and 3 executives. 233 employments are
envisaged to be given against 466.25 acres of tenancy land required to be
acquired for the proposed project. Considering the number of retirement and
gradual process of land acquisition, the land losers can be absorbed in the project
or elsewhere in ECL.
19.3 At the targeted production capacity of 2.0 MTY of coal the OMS of proposed
Simlong Opencast project under different options and different variants are given
in the above table.
19.4 For efficient, effective and safe operation of the mine, a comprehensive and
meticulous training programme for all levels of employees is imperative. The
training would be
i) On the job
ii) In the training centers of nearby opencast mines
iii) Conducted by the external agencies, including the equipment
manufacturers.
Job No.102177 ES - 25
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
20.2 The zero date of project implementation is the date of obtaining competent
approval for the project.
The proposed implementation schedule, has been developed considering two
years of constructions (viz C1 & C2). It is a running mine and some activities as
envisaged during pre-construction stage are:
20.3 For Simlong OCP, five years of construction (year1 to year5) has been
considered. During the construction period, most of the basic infrastructure
facilities like CHP, development activities, service buildings, water supply
arrangement, power supply arrangement etc. required for implementing the
project will be completed.
20.4 It has been envisaged that coal will be transported to Kumarpur MGR (of NTPC)
siding at a distance of 46Km by contractual trucks. Estimated fund for widening
and strengthening of this coal transportation route has been provided. However,
part of this road passes through both the proposed simlong OCP and the
adjoining Chuperbhita OCP(proposed), and needs to be diverted. Cost of
diversion of the road has been already taken into account in the financial
provision of Chuperbhita OCP.
21.1 Two options have been studied for financial evaluation of the project viz.
Departmental option and Outsourcing option. Outsourcing option envisages
outsourcing of excavation job along with pumping of mine water only, other
ancillary jobs remaining under departmental responsibility. In both the options,
Job No.102177 ES - 26
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
two variants have been considered for coal winning; one by shovel-dumper and
other by surface miner.
21.2 The total capital expenditure required for the project under different options and
different variants are given below. The break-up of capital expenditure is shown
in the following table.
Rs. In crores
Department Option Outsourcing Option
21.3 Mine is an existing mine, hence no revenue expenses has been capitalized.
Grade “F”
Basic Price (Annexure-V) 870.00
Coal deterioration @5% of value 43.50
Add for sizing upto -100mm 61.00
Total in Rs per te 887.50
Job No.102177 ES - 27
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
21.5 In Departmental option loss per te at 100% capacity utilization works out to Rs
373.80 and Rs.303.70 for the two options respectively. Salient financial indices for
the two variants are presented below.
22.3 The outsourcing agency will have to maintain the haul-roads and arrange for dust
suppression within the mine and surroundings. Back-filling of in-pit voids and
grading of the final dump to proper slope will the responsibility of outsourcing
agency. The outsourcing party will operate with its own resources.
Job No.102177 ES - 28
Executive Summary Of PR For Simlong OCP (2.0 MTY) CMPDI, RI-1
22.4 Apart from the excavation job, the following services are also proposed to be
outsourced separately.
i) Security services,
ii) Canteen services,
iii) Rest house services,
iv) Biological reclamation services
v) Sweeping and cleaning.
Cost of outsourcing (coal winning & transportation and OB Removal) works out to
Rs. 310.63 per tonne. for variant-I and Rs. 290.95 per tonne for variant-II. These
estimate is based on the rates of outsourcing job awarded in ECL of ECL. However
these rates are considered for evaluation purposes only and have no relation to the
actual tendering process that may follow.
Job No.102177 ES - 29
STRICTLY RESTRICTED
FOR COMPANY USE ONLY
The information given in this report
is not to be communicated either
directly or indirectly to the press
or to any person not holding an
official position in the CIL / Government
PROJECT REPORT
OF
SIMLONG OCP (2.00 MTY)
EASTERN COALFIELDS LIMITED
VOLUME - II
(TEXT & APPENDICES)
March, 2011
Regional Institute-1
Central Mine Planning & Design Institute Ltd.
( A Subsidiary of Coal India Ltd.)
G.T.Road (West End )
Asansol-713 304.
Project report for Simlong OCP CMPDI, RI-1
VOLUME – II
TEXT
CONTENTS
Sl.No. Chapter Particulars Page No.
Job No.102177 i
Project report for Simlong OCP CMPDI, RI-1
VOLUME – II
TEXT
CONTENTS
Sl.No. Chapter Particulars Page No.
CONTENTS
Sl.No. Chapter Particulars Page No.
10.1 Introduction 10 – 1
11-1 Introduction 11 - 1
11.2 Design parameters 11 - 1
CONTENTS
Sl.No. Chapter Particulars Page No.
13.2 Illumination 13 - 6
Job No.102177 iv
Project report for Simlong OCP CMPDI, RI-1
VOLUME – II
TEXT
CONTENTS
Sl.No. Chapter Particulars Page No.
15.6 Fire 15 - 2
15.7 Blasting 15 - 2
15.10 Lighting 15 - 3
15.11 Power Line 15 - 3
15.12 Conservation oc Coal 15 - 3
17.3 Rehabilitation 17 - 3
Job No.102177 v
Project report for Simlong OCP CMPDI, RI-1
VOLUME – II
TEXT
CONTENTS
Sl.No. Chapter Particulars Page No.
19
19 Manpower Productivity And Training 19-1 to 19-3
19.1 General 19 - 1
19.3 Productivity 19 - 2
19.5 Training 19 - 3
20
20 Project Implementation 20-1 to 20-4
20.1 Introduction 20 - 1
Job No.102177 vi
Project report for Simlong OCP CMPDI, RI-1
VOLUME – II
TEXT
CONTENTS
Sl.No. Chapter Particulars Page No.
21
21 Financial Evaluation 21-1 to 21-6
21.1 General 21 - 1
22
22 Outsourcing Option 22-1 to 22-4
22.1 Introduction 22 - 1
VOLUME – II
LIST OF TABLES
2. 2.2 2-2
Projected coal demand of NTPC
3. 2.3 2-3
Projected coal availability of Rajmahal coalfields
4. 4.1 4-2
Boreholes drilled by various agencies
5. 4.2 Special test and Ultimate analysis 4-7
7. 4.4 4-6
Generalized Geological Sequence in Rajmahal C.F
8. 4.5 4–8
Sequence of coal seams
9. 4.6 Brief Description of faults in the Block 4 - 11
VOLUME – II
LIST OF TABLES
28. 13.3 13 - 8
Year wise Power Bill
29. 17.1 17 - 1
Requirement of land
30. 17.2 17 - 2
Villages and households to Rehabilitated
31. 17.3 Resettlement & Rehabilitation Package 17 - 3
Job No.102177 ix
Project report for Simlong OCP CMPDI, RI-1
VOLUME – III
LIST OF PLATES
PLATE PARTICULARS DRAWING NO. SCALE
NO.
1 Location Plan R1-OCM-7161 NTS
2 Geology & Surface Features Plan R1-OCM-7162 1:4000
3 Existing Plan R1-OCM-7163 1:4000
4 Final Stage Quarry Plan R1-OCM-7164 1:4000
5 Mine cross sections along 1-1’.2-2’,3-3’ & 4-4’ R1-OCM-7165 1:4000
6 Seam Folio Plan of Seam-VI R1-OCM-7166 1:4000
7 Seam Folio Plan of Seam-V R1-OCM-7167 1:4000
8 Seam Folio Plan of Seam-III(Top) R1-OCM-7168 1:4000
9 Seam Folio Plan of Seam-III (Bot) R1-OCM-7169 1:4000
10 Seam Folio Plan of Seam-II(Top) R1-OCM-7170 1:4000
11 Seam Folio Plan of Seam-II (Bot) & Comb. R1-OCM-7171 1:4000
12 Seam Folio Plan of Seam-L2 R1-OCM-7172 1:4000
13 Seam Folio Plan of Seam-I(Comb.) R1-OCM-7173 1:4000
14 Plan showing Stage End Of East Part R1-OCM-7176 1:4000
15 Plan showing infrastructure R1-OCM-7177 1:4000
16 Land use plan R1-OCM-7178 1:4000
th
17 10 Year Stage Plan R1-OCM-7199 1:4000
18 Final Stage Dump Plan R1-OCM-7200 1:4000
Job No.102177 x
Project report for Simlong OCP CMPDI, RI-1
CHAPTER-1
INTRODUCTION
1.1 BACKGROUND
1.1.1 The Simlong Opencast mine is located in the Pakur district and part of the
Rajmahal coalfields under the jurisdiction of Eastern Coalfield Ltd. At Simlong,
which is a small part of Chuperbhita basin, a manual quarry had been worked
earlier on the bed of the stream ‘ Lada’ which flows almost along the outcrop of
the bottommost seam in the geological block.
1.1.2 A scheme called “ Scheme on Simlong Quarry” was prepared by ECL in January
1981, with a targeted production of 0.10 Mty. This scheme was prepared on the
basis of data available in old quarry workings and outcrops of the seams visible in
the river bed.
1.1.3 Subsequently, ECL had put 17 no. boreholes in the area and a geological note
was prepared by planning division of Eastern Coalfields Ltd. The geological note
indicated existences of two seams within quarriable limit in the area. On the basis
of that geological note a “ Revised Feasibility Report For Simlong Opencast
Project “ was prepared by CMPDI in July 1983 with a targeted production of 0.10
Mty.
1.1.4 The Revised Feasibility Report estimated a mineable coal reserves of 2.34 Mt. at
a stripping ratio of 1.61 cum./te. with part diversion of Lada nala. The report
envisaged a capital investment of Rs. 310.27 lakh and mine life of 24 years. The
existing mine working is as per this Revised Feasibility Report. The mine has
been run departmentally till 2007-08. After survey off of all the departmental
HEMM, mining is being done by outsourcing since 2008-09. In the year 2009-10
the mine has produced 0.44 Mt. of coal and 0.64 Mm3 of OB.
1.1.5 Mining work within the quarriable limit of the” Revised Feasibility Report” is going
to be finished shortly. This current PR envisages to extend the working further,
covering the entire geological block (except forest area in the N-E part and the
1.2.1 The exploration of Simlong block has been completed by MECL in January 1992
and the present report incorporates the complete data of the 33 boreholes drilled
in this block by MECL, besides 1 borehole drilled by CMPDI earlier in the block.
The total number of boreholes drilled by different agencies are as follows:
12.2 The objectives of the exploration was to prove lay and disposition of all the coal
seams occurring within the Simlong OCP Block and to assess the feasibility of
the seams for open-cast mining potentiality as well as to ascertain their quality.
The overall borehole density within the proposed mine take area is 14.6 per sq.
Km considering two additional boreholes from adjacent block..
1.5.2 The present PR envisages two different options for operation e.g. Departmental
option and Outsourcing option. In the outsourcing option only production of coal
and removal of OB along with pumping of mine water have been proposed to be
outsourced and all other activities under departmental responsibility.
1.5.3 In both the Departmental and Outsourcing options two variants have been
considered. In one variant, total excavation job has been envisaged by shovel
dumper combination, and in other variant OB removal has been proposed by
Shovel-dumper method and coal winning by surface miner.
1.7.2 The production from Simlong OCP is to be dispatched from the proposed siding
near Kumarpur, adjacent to the existing MGR track connecting Rajmahal and
Farakka STPS. A separate Railway track is proposed to be. laid from
Chuperbhita to Barharwa (located at a distance of 50 km from Chuperbhita) on
Sahibganj loop line of Eastern Railway for onward transmission to Farakka STPS.
In that case, the siding for simlong may be shifted to some suitable nearer place
along this Proposed rail track. It is indicated in the letter no. 47011/14/99 –
CPAM dated 20.1.2000 issued by Ministry of Mines & Minerals, Department of
Coal, that NTPC will provide dedicated Rail infrastructure from Chuperbhita OCP
to Farakka STPS.
CHAPTER - 2
MARKETABILITY AND JUSTIFICATION
ECL has two major coalfields namely Raniganj coal fields and Rajmahal coal
fields. Production from Raniganj coal fields which is mostly covered by
underground mines has reached a state of stagnation. Though proposal for some
big u/g mines are under process, projected increase of production from Raniganj
coalfields is miniscule to the overall demand on ECL.
Major demand on ECL is from power sector for which mines in the Rajmahal coal
fields are the only source to meet the requirement. The scenario of ECL for
Demand – supply of coal in the next three years is given below.
(11.30 Mt. for Farakka STPS + 5.85 Mt. for Kahalgaon STPS, stage-I and 10.44
Mt. For Kahalgaon STPS, stage-II ).
Power Stn. 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
Farakka 11.30
11.30 11.30 11.30 11.30 11.30 11.30 11.30
STPS
(1600 MW)
The New Coal Distribution Policy (NCDP) of the Government makes it mandatory
for coal supplying companies to sign legally enforceable bi-lateral FSAs with
performance based ‘take or pay’ provision. A new Fuel Supply Agreement (FSA)
has been signed between CIL and NTPC with the trigger level (the minimum
assured quantity of coal supply) fixed at 90% of Annual Contracted Quantity
(ACQ). CIL has agreed to supply 114.7 Million Tonnes of coal in 2009 –10 to the
15 existing NTPC Power Stations.
As on 31.03.09 (based on the CEA projection) the ACQ from ECL to NTPC is
12.20 Mt., of which 6.87 Mt for Farakka STPS and 5.33 Mt for Kahalgaon STPP.
In view of the massive demand of coal from two STPPs of NTPC , the proposed
Simlong Expansion OCP will play a significant role in bridging the gap between
demand and supply.
As the existing mine has no approved EMP, this project report is necessary for
preparation and submission of EMP.
3.1 LOCATION
3.1.1 Simlong OC block falls in the district of Sahibganj of Jharkhand state and is
located between latitudes 24044’33” to 24045’55”(N) and longitudes 87026’30” to
87028’38”(E). The total area of the block is about 2.40 sq .km and is covered in
the Survey of India Toposheet no.72 P/5. Simlong OCP Block occupies the
south-western part of the Chuperbhita coalfields. This is the second largest
coalfield out of the five which constitutes the Rajmahal coalfield. Seam VII to I
are developed in the block. The basal seams viz. seam II and seam I had been
exploited in the incrop region through small quaries. Present mine working
which is merely extension of these quarries involves only this two seams.
3.1.2 Gumani river runs along the western boundary of the block. Simlong OCP block
is well connected by metalled road. Godda-Sahebganj road passes in the north-
western part of the block. The block is located at a distance of 80 km from
Sahibganj district headquarter and 30 km from Godda district headquarter.
Some important cities like Bhagalpur, Deoghar, Asansol are located at a
distance of 100, 110 and 218 Km. respectively and are well connected by all
weathered road.
3.4.2 The drainage of the block is mainly controlled by the Gumani river which flows
at the western boundary of the block. Damro Nala meanders along the south-
western boundary of the block. Gumani is a perennial river and its catchment
area extends to about 1096 sq. km. The Simlong OCP block also falls in this
catchment area. A barrage over this river is under construction near Berhait
which is at a crow fly distance of 20 km from this block. The high flood level
(HFL) of the barrage is 50.63 m (as per Gumani Barrage Project, Irrigation
Department Report).
CHAPTER - 4
GEOLOGY
4.1 INTRODUCTION
4.1.2 Simlong OCP forms the south-western part of the Chuperbhita basin. Most of
the litho units of Chuperbhita basin are either exposed or encountered in
boreholes drilled in Simlong OCP. The details are provided in subsequent
paragraphs.
4.2.2 The overall borehole density in the Simlong (OCP), Geological block covering a
total area of 2.40 sq km is about 14.2 per sq. km. However, considering the two
additional boreholes (RCH-98 and RCH-105), overall borehole density within
the proposed mine take area is 14.6. per sq. km. which is sufficient for deposit
appraisal. Thus, the area considered for opencast working is fully explored.
However, production support borehole drilling may be needed during the
exploitation of the deposit and sufficient fund provision for the same has been
made. Seam-wise no. of borehole intersection within the block area is given
below.
4.3.1 In Simlong OCP area lower coal bearing units of the Barakars have been found
to occur and are represented by medium grained to pebbly sandstones, shales
and coal seams. Coal seams and sandstones are exposed in the lower reaches
of the Damro nala and in the quarries. The Barakars are overlain by Dubrajpurs
and/or rocks of the Rajmahal Traps. While rocks belonging to the Rajmahal
Traps occupy the higher reaches of the topography those of the Dubrajpur
Formation occur along the slopes of the hillocks.
4.3.2 On the basis of geological mapping and subsurface data, the sequence of
formation is as follows :
Barakar Formation – The lower Barakars, occurring in the Simlong OCP area,
contain coal seams-I and VII along with three local seams viz. L-1, to L-3. These
lower Barakar are mostly medium to coarse grained and occasionally pebbly
sandstones with subordinate shales.
Based on the geological exploration carried out by MECL in the adjoining
Chuperbhita OCP block the rocks of the Barakar Formation have been divided
into four horizons (Ref. : MECL report Chuperbhita OCP Block-1991). In the
area under report only two lower horizons have been identified. The litho units
belonging to the bottom horizon are represented mostly by coarse grained to
gritty sandstone with subordinate preparation of intercalations of sandstone and
shale. This horizon, which ranges in thickness from around 100m to 150m,
contains a few thin coal seams which are not economically significant. The
stratigraphic column overlying this horizon can be subdivided into three sub-
units on the basis of the development of coal seams. The stratigraphic column,
having a thickness range of 30-40m, contains seams-I and II which have a
cumulative thickness ranging from 9 to 26m. Thus the thickest coal column
occurs within this sub-unit. The sub-unit overlying this, contains the coals seams
L-III to IV and has significant development of medium to gritty sandstones. The
coal seams occurring within this sub-unit in general, are of marginally workable
thickness. This sub-unit has a thickness varying from about 55m to 80m. The
topmost sub-unit contains seam-V and VII. It is dominantly arenaceous, being
represented by medium to coarse grained sandstones. Coal seams occurring
within this sub-unit are of moderate thickness and are better in quality than
those occurring in other unit/sub-units.
Soil and Weathered Mantle – The lower grounds adjoining the Damro Nala are
covered by a fairly thick veneer of soil. The soil is generally clayey. But at higher
reaches weathering of basalt has given rise to black cotton soil at places.
Thickness of weathered mantle varies from 2.00m. (RCH-175) to 26.00m (RCH-
85).
4.3.3 The Gondwana sedimentaries are exposed mainly along the course of
prominent river basins, namely, Gumani (around villages Dhamni, Chhotapur,
Chatkam, Jiajori, Jawardaha, etc.) They are also exposed in Kewari valley
around village Jitpur, Sahapi and Damro valleys around villages Simlong,
Simaldhap and along Mahuldabar valley around village Dopahari.
The generalised geological sequence Rajmahal coalfields/basin , as worked out
by GSI is given in table no. 4.4
4.3.4 Sequence of Coal Seams – Seven regionally correlative and two local coal
seams have been identified in the block on the basis of sub-surface data
accrued by way of exploratory drilling as well as surface geological mapping..
The local Seam L-3 has a very limited development in the block it has only been
encountered in one borehole i.e RCH-105. Sequence of coal seam as
established in the block is furnished in Table-4.5
4.3.5 Coal measures in Simlong (OCP) block, are trending in NW-SE direction and
dipping towards north-east. Dip and strike of the beds interpreted on the basis
of floor contours are in conformity with the fields observation. The dip is
generally 80- 100.
4.3.6 The geological structure of the block is simple. Three faults (numbered F1, F2
and F3) have been deciphered in this block. Faults F1 and F3 mark partly the
northern and eastern boundaries of the block respectively. Fault F3 is a majore
fault having a throw of about 150m, while fault F1 has a throw varying from
20m. to 65.m. A minor fault , F2 having a throw varying from 0 to 5m. has been
observed within the quarry. During the exploration, no dyke or sill is found to
exist within the block
The characteristic features of the faults within the block boundary is given in
Table no.4.6.
Thickness of coal seams have been generally arrived at on the basis of band by
band analysis or on visual estimates where analysis is not available. While
delineating coal seam, if coal and dirt bands occur alternately and the thickness
of coal band has exceeded that of the latter, it is considered as a part of the
seam whereas if the coal thickness is less than the thickness of dirt band the
entire section is deleted from the seam.
However, for seam-II (TOP) for a single borehole i.e. RCH-II, this norm has not
been strictly followed. The seam II (TOP) in this borehole is encountered from
62.89 m to 68.00 m. The top portion of the seam is represented by inter-banned
coal, shaly, carb. Shale and shale. The cumulative thickness of the coal plus
shaly coal is 1.21m whereas the total thickness of shale and carb. shale
together is 1.00 m.
For quality determination, the useful heat value (in K.Cal./kg) and grade have
been calculated considering Ash + Moisture content from the proximate analysis
on 60% RH and at 40oC ., where data not available the same has been
calculated by converting band-by-band analytical data as per standard M-100
formula.
The sequence of coal seams, variation in parting between seams, moisture, Ash
content and grade is given in Table no. 4.8. The grade of seam varies from D to
G.
4.4.2 SEAM I
General
Seam-I is the oldest seam developed in the block. In major part of the block it
occurs as a combined seam. In the north-western part of the block it initially
splits into two sections designated as Seam-I (TOP + Middle) and seam
I(BOTTOM). The line of the split between these two sections as shown in the
seam folio plan passes west of RCH-113, RCH-7 and RCH-40A from north to
south. Further westward the upper section splits into two sections which have
been designated as Seam-I (TOP) and seam –I(MIDDLE). The line of split
between the top and middle sections passes south of RCH-98 and east of
CHB/MA/006 and RCH-1-9. The details of these seams / sections are as under.
Occurrence
This seam has been intersected in 19 boreholes. Weathered section of the
seam has been encountered in 2 boreholes (RCH-138 and 139). The seam
occurs at a depth varying from 9.14 m (RCH-39) to 196.02 m (RCH-175). The
incrop of the seam marks the south-western boundary of the block. It is aligned
in NW-SE direction and passes north of RCH-85 and south of RCH-40A, 39
while RCH-139 and 138 are located on the incrop of the seam. The incrop is
displaced by the fault F2-F2 in the vicinity of RCH-39 and is fuarther displaced
by fault F-3F3 in an area around borehole RCH-137.
Parting
The overlying parting upto seam L-2 varies from 1.97 m (RCH-175) to 11.33 m
(RCH-9). This parting shows a gradual increase from south-east to north-west.
Reserves
The total net reserves of coal contained within this seam is 46.536 million tones
out of which 25.137 million tones fall within 1 : 5 Coal : Overburden. 0.475
million tones fall within incrop region.
Occurrence
Seam-I (Top) has met within 12 boreholes confined to the south-western part of
the block. Out of the three splits of Seam-I, this one is the most significant. It
has been intersected at depths ranging from 16.85 m. (RCH-118) to 92.27 m
(RCH-115). The incrop of the seam having an E-W trend is located around 200
m south of RCH-80. Further eastward the incrop swings to the south-east
passing south of RCGH-118, through RCH-111 and extends upto the west of
RCH-85. Seam-I (Top + Middle)) occurs as a narrow strip extending almost
north-south in a area surrounded by boreholes RCH-113,110, 7 & CHB/MA/006.
Parting
The underlying parting upto seam L-2 varies from 5.01 m (RCH-161) to 17.08 m
(RCH-80). In the region of the boreholes RCH-161,-112, -115 and -81 this
parting ranges from 6 m to 9m. Sharp increase in parting is noticed both in the
east and west of RCH-112.
Quality
The grade of the seam ranges between E to G. The deterioration in the quality
of the seam is gradual from west to east.
Reserves
A total of 3.045 million tones of reserves have been estimated for this seam, out
of which 2.031 million tonens fall within 1 : 5 coal : overburden ratio and 0.927
million tones fall beyond 1 : 5 coal to overburden ratio. 0.087 million tones occur
in incrop region. Total reserves of seam Top / Middle are 0.410 million tones of
which 0.317 million tones fall within 1 : 5 coal to overburden ratio and 0.007
million tones fall within incrop region.
Occurrence
Seam L-2 has been encountered in 20 boreholes. It is developed in two
isolated areas within the block. It is not developed in the central part in and
around RCH-99,7,9,90 and 93 and for a small region I the south-eastern part
around borehole RCH-117. The seam has attained workable thickness mainly in
the north-western part of the block. In the remaining area it is not workable
except around RCH-87 falling in the south-eastern part of the block. It occurs at
a depth ranging from 29.70 m. (RCH-80) to 192.95 m (RCH-175). The incrop of
the seam, running in almost NW-SE, has been delineated south of RCH-80 and
north of RCH-118, -97, -83, -109 and -85.
Parting
Seam L-2 occurs below seam-II with a parting varying from 5.89 m (RCH-1261)
to 12.30 m (RCH-110). This parting is predominantly represented by
sandstones and in subordinate proportion with intercalations of shale and
Job No.102177 Chapter-4, Page-15
Project report for Simlong OCP CMPDI, RI-1
sandstone and occasional shales. In general, the parting gradually decreases
towards west, south and east from north-central part of the block.
Quality
From the analytical data obtained from 8 boreholes it is observed that the grade
of the seam varies from D to F with a gradual deterioration towards east.
.
Reserves
Total reserves estimated for this coal seam is 2.007 million tones, out of which
1.530 million tones occur within 1 : 5 coal : overburden ratio. 0.472 million tones
fall beyond 1 : 5 coal : overburden ratio 0.005 million tones occur in incrop
region.
4.4.4 SEAM II
General
Immediately overlying seam L-2, Seam-II is manifested throughout the block. In
the area around boreholes RCH-8, -9 and -148 the seam starts splitting and
further southward it splits in two sections designated as Seam-II (Top) and
Seam-II (Bottom).
Parting
Parting with respect to the overlying seam L-3 varies from 6.21 m
(CHB/MA/006) to 9.99 m (RCH-115). Lithologically, it is represented by
sandstones, shales and their intercalations. Occasionally, a thin band of coal is
also developed within this parting.
Quality
Qualitatively, Seam-I (Combined) varies in grade from F to G with Useful Heat
Value (K.cal./kg) ranging between 3029 (RCH-110) and 2055 (RCH-9).
4.4.4.2SEAM-II (BOTTOM)
Occurrence
As already stated seam-II (Bottom) is developed in the southern and eastern
parts of the Simlong OCP Block. It has been intersected in 11 boreholes. Depth
of occurrence of this seam ranges between 22.09 m (RCH-93) and 186.18 m
(RCH-175). Incrop of the seam is trending in NW-SE direction.
Parting
The overlying parting upto Seam-II (Top) varies from 1.02 m (RCH-148) to 7.01
m (RCH-175). In the area where the seam has started splitting the parting is
dominantly represented by rocks of argillaceous facies which changes to
arenaceous facies as the parting increases towards south and east of the block.
Quality
The seam is of poor quality being of grade G for most part of the area except
for a small patch near borehole RCH-90 where it has improved to grade F.
4.4.4.3SEAM-II (TOP)
Occurrence
Seam-II (Top) is developed in the south-eastern part of the block. It has been
encountered in 10 boreholes and is missing in one borehole (RCH-87) due to
fault. The seam occurs at a depth varying from 22.09 m to (RCH-93) to 176.58
m (RCH-175). Incrop of the seam is trending in NW-SE, direction has been
traced to the south of RCH-8, 9, 10, 90, 92 and upto the fault F3-F3. Incrop of
the seam is observed in the northern face to quarry no.2. Incrop in the area
around borehole RCH-90, -93 and upto the fault F3-F3 occurs below Trap and
Dubrajpurs.
Parting
The overlying parting of the seam upto seam L-3 varies from 3.05 m (RCH-10)
to 8.72 m (RCH-175). Parting is gradually inreasing towards eastern and south-
eastern part of the block. Parting is represented by sandstones and shales with
thin coal bands.
Reserves
Net reserves of 6.127 m tones of the seam has been estimated. Out of which
3.508 m tones fall in 1 : 5 coal : overburden ratio. 2.605 m. tones fall beyond 1 :
5 coal : overburden ratio 0.014 million tones occur in incrop region.
The seam L-3 occurs at depths varying from 50.60 m (RCH-161) to 162.62 m
(RCH-146). It has been intersected in 10 boreholes. In 6 boreholes (RCH-7, -8,
-9, -11, -93 & -97) seam is not developed while in borehole RCH-99, the entire
seam is converted to carbonaceous shale. In major part of the block the seam is
of unworkable thickness except in and around borehole RCH-146 and RCH-161
where it has attained workable thickness. Keeping in view the limited area of
development seam to workable thickness, the seam folio of the seam is not
prepared and reserves have not been estimated.
Occurrence
The seam has been intersected in 12 boreholes. It has developed through out
area except in an area around borehole RCH-115. In RCH-87, the seam is
faulted by fault F3-F3. Depth of seam from surface varies from 11.80 m (RCH-8)
to 150.98m (RCH-175). The incrop of seam is trending NW-SE and extends
from north of borehole RCH-7, near RCH-9 , north of RCH-90,93 and upto the
fault F3-F3. The incrop of the seam is covered by Trap / Dubrajpur almost in the
entire area except in two isolated patches around borehole RCH-8 and RCH-9.
The incrop is slightly shifted due to fault f2-F2 in the area north-west of borehole
RCH-9.
Quality
The quality of seam is mostly E grade except in an area around borehole RCH-
8 where it is of grade F (Plate-X.5). The useful heat value of the seam varies
from 3270 k.cal/kg (TCH-8) to 3615 k.cal/kg (RCH-99 and 146).
Reserves
1.056 million tones of net reserves have been estimated for the seam. 0.499
million tones occur in 1 : 5 coal : overburden ratio. Reserve beyond 1 : 5 coal :
overburden is 0.555 million tones. Reserves in incrop region is 0.002 million
tones.
4.4.9 SEAM- V
Occurrence
Seam-V is one of the thickest seams occurring in upper part of the Barakars. It
has been encountered in 7 boreholes and is partly encountered in borehole
RCH-110, due to weathering. The seam is developed in the entire area. The
seam occurs at depths varying from 9.78 m (RCH-110) to 92.87 m (RCH-175).
The incrop of the seam is trending NW-SE and entends from north of RCH-110
to south of RCH-99 , 106,117 and upto the fault F3-F3. The incrop of seam is
depicted below trap from west of borehole RCH-99 to fault F3-F3 in the south-
eastern part of the block (Plate-III).
Parting
The overlying parting upto Seam-VI varies from 15.17 m (RCH-148) to 18.20 m
(RCH-99). Parting is represented predominately by sandstones with occasional
intercalations of sandstone and shale. Variation in parting is marginal.
Roof and Floor
The immediate roof of the seam is carbonaceous shale except in one case
where it is shale. The immediate floor of the seam is mostly represented by
shale and carbonaceous shale with sandstone at places.
4.4.10 SEAM VI
Occurrence
The seam has been intersected in 4 boreholes. In RCH-99, the seam is partly
weathered. The seam is of workable in entire area except in a small patch in the
central part of the block around borehole RCH-146 where the seam thickness
has reduced, rendering the seam unworkable. The seam occurs 29.60 m
(RCH-99) to 74.52 m(RCH-175) depth. The incrop trending NW-SE is located
east of borehole RCH-99, south of (RCH-148 & 146). The incrop is displaced by
fault F1-F1 north-west of borehole RCH-99 and by fault F3-F3 in the area west
of borehole RCH-175.
Parting
The overlying parting of the seam upto seam-VII is 29.52 m (RCH-175). The
parting consists mainly of sandstone with occasional intercalations of sandstone
and shale.
Thickness & Dirt Bands
The thickness of seam varies from 0.89 m (RCH-146) to 2.88 m (RCH-148).
Minimum workable thickness of 1.80 m is intersected in borehole RCH-175.
This seam is free from any dirt band.
Roof & Floor
The immediate roof of the seam is sandstone while the immediate floor of the
seam is represented by rocks of argillaceous to arenaceous facies.
Quality
Quality data of only two borehole is available. The grade of the seam varies
from D to E. The Useful Heat Value varies from 4829 K.cal/kg (RCH-175) to
4042 K.cal/kg (RCH-148).
Reserves
Total reserves of the seam are of the 1.383 million tones, out of which 0.288
million tones fall within 1 : 5 coal : overburden ratio & 1 .05 million tones fall
beyond 1 : 5 coal : overburden. Reserves in incrop region is 0.044 million tones.
4.5.1 No borehole within the Simlong block has been tested for Physico-mechanical
properties of rocks.
4.5.2 Hydrogeology
CMPDI has carried out detailed hydrological investigations and Ground Water
Modelling (under UNDP) of the adjoining Rajmahal OCP which is at a radial
distance of 25 km from the Simlong block. The Simlong block is an extension of
the Rajmahal Coalfield.
Surface Hydrology
The drainage of the block is mainly controlled by the Gumani river which flows
at the western boundary of the block. Damro nala meanders along the south-
western boundary of the block and finally joins the Gumani River. Overall the
drainage is poor and sparsely developed. Though the first order drainage is
observed in the topo sheets no specific drainage channels were noticed during
the field investigations The main reason for the disappearance of these first
order drainage channels is the agricultural activity which is the main source of
income for the local tribals in this region and also due to high permeability of the
sandstones exposed along the foot hill. The only surface water bodies are small
ponds spread over the fields with no apparent drainage. During the summer
these ponds are almost dry.
Lithological data from the exploration boreholes in the area indicate broadly the
presence of five aquifers. The top acquifer is in pheratic condition where as
other aquifers are in semi to confined condition.. The parting between the coal
seams consist of poor to moderately consolidated very coarse to fine grained
sand stones are gritty sandstones which act as aquifers due to their permeable
Ground Water Recharge: The major drainage in the study area is Gumani
river, which flows at the western boundary of the Simlong block. This perennial
river flows in the east-west direction. The drainage system in this block is
sparsely developed and many first and second order streams are abruptly
disappearing. This indicates high infiltration percentage of rainfall. The monsoon
starts in middle of June and lasts till the end of September. The average annual
rainfall in this area is around 1340 mm. It is calculated that 13% of the rainfall
will go as potential annual infiltration and the rest 87% of rainfall will go as
runoff. Phereatic aquifer is recharged from precipitation and surface water
bodies whereas the deeper aquifers get recharge from the rainfall in outcrop
regions and through leakage of water from top aquifer. Except for a few dug
wells and hand pumps in the phereatic aquifer which are used mainly for
domestic water supply no deep tube wells are located in the area. Thus there is
no heavy with drawl of ground water in this block from the aquifers.
While determining the in-band thickness of coal seam for quarriable proposition,
the carbonaceous shale band and obvious band together up to a thickness of
1.00m
If coal & dirt bands are alternating & if the coal thickness has exceeded to that
of the later, it is taken as Seam, whereas, if the coal thickness is less than the
dirt band, the entire section/ seam is taken as non-workable.
The grade of the coal has been arrived at after determining the Useful Heat
Value (UHV) considering the Moisture and Ash values on equilibrated basis.
Where the section/seam overall were not available the grade has been
determined from band by band analysis, after determining the weighted /
lengthwise average of Moisture and Ash on equilibrated basis by applying M-
100 formula.
No fault is passing through the block. So block has not been divided into
sectors. Entire block has been considered as a single sector for reserves
estimation. In individual seam-folio segments are formed due to different
variants such as Isochore, grade and coal to overburden ratio line. Each
segment has been separated out for measurement of its area. The area of
incrop of different seams has been measured separately. A 10% deduction
have been made from the gross reserves to account for data gap and minor
faults etc. to arrive at the Net geological reserves.
Total reserves in Simlong OCP Block is 90.193 million tonnes, of which 54.196
Mt. Falls within 1:5 coal:OB ratio. 34.427 Mt. Fall beyond 1:5 coal to overburden
ratio and 1.570 Mt. Occurs in incrop region. Proved reserves are 63.982 Mt.
Indicated reserves are 24.641 Mt and in incrop region reserves are 1.570 Mt.
Summary of reserves is given in table no. 4.7.
SUMMARY OF RESERVES OF SEAMS OCCURING IN SIMLONG OCP BLOCK TABLE NO.: 4.7
Seam UP TO 1:5 C:OB RATIO 1 : 5 C:OB RATIO IN INCROP TOTAL
REGION RESERVES
I (Comb.) 25.137 20.924 0.475 46.536
I (Bot) 0.279 0.002 - 0.281
I (Middle) 0.189 - 0.003 0.192
I (Top) 2.031 0.927 0.087 3.045
I (top / Middle) 0.317 0.006 0.007 0.410
L-2 1.530 0.472 0.005 2.037
II (Comb.) 13.483 2.168 0.658 16.309
II (Bot.) 3.328 1.950 0.039 5.317
II (Top) 3.508 2.605 0.014 6.127
III (Bot) 0.499 0.555 0.002 1.056
III(Top) 0.840 0.223 0.010 1.073
IV (Bot) 0.228 0.092 0.014 0.334
V 2.539 3.372 0.212 6.123
VI 0.288 1.051 0.044 1.383
Total 54.197 34.427 1.570 90.193
MINE FLOOR
The floor of seam I forms the floor of Simlong opencast project. The floor
generally consists of shale. The quarry floor, on an average, dips 80-100
towards NE. and the strike, in general, is NW-SE.
3 faults varying in throw from 5m to 150m occur within the property. A minor
Fault, F-2 with 5m throw is within the mining zone. Other two faults are
boundary faults.
Continued.....
Geo-Mechanical Properties of Rock Core of Borehole No. RCH-114
Table No. 4.9
Box Depth Lithological Bulk Protodykonov Unconfined Tensile
Job No.102177 Chapter-4, Page-31
Project report for Simlong OCP CMPDI, RI-1
No. (m) Section density strength compressive strength
kg/cu.m index strength m/sq.
N/sq.m. mm.
13 56-63 Cgd 2000 0.68 8.88 0.51
1970 0.68 7.76 1.43
1980 0.68 9.02 0.53
-------- -------- ------- --------
1983 0.68 8.55 0.49
14 68-71 Mgd 2090 0.38 8.88 0.54
2040 0.38 9.66 0.59
2100 0.37 16.15 0.66
-------- -------- --------\ ----------
2083 0.38 11.23 0.59
14 & 15 71-74 Mgd 2080 0.40 12.32 0.56
2150 0.40 8.87 0.63
2110 0.40 9.18 0.35
-------- -------- -------- -------
2114 0.40 10.29 0.51
15 74-77 Mgd 1950 0.33 7.44 0.51
1860 0.37 5.76 0.75
1820 0.37 7.00 0.51
------ -------- -------- ------
1886 0.39 6.73 0.59
15&16 77-80 Cgd 1780 0.43 4.17 0.56
1780 0.43 5.30 0.29
1780 0.43 4.25 0.38
------- ------ ------ ------
1780 0.43 4.59 0.41
16&17 80-83 Mgd 1790 0.44 6.67 1.08
1780 0.42 5.76 1.05
1940 0.43 9.83 0.85
-------- ------ ------ -------
1837 0.43 7.22 1.33
17 83-85 Mgd 1790 0.42 9.21 0.61
1790 0.42 - 0.52
1940 0.42 9.66 0.59
------ ------- ------- --------
1840 0.42 9.40 0.59
5.1 GENERAL
Based on the data provided in the geological report of Simlong (OCP) block,
final stage quarry plan, seam folio plans of each seam showing floor contours,
iso-chore & iso-UHV, have been prepared. The mine boundaries of the
proposed Simlong OCP have been fixed considering the various surface
constraints and geological information given in the G.R. A large number of Coal
horizons/seams (seam VII at the top to seam I at the bottom) have been
encountered in the block. All the seams, seam VII to seam I (from top to bottom)
are fully explored and their reserves have been placed under proved category
(except in the south-eastern part of the block) and have the quarriable
potentiality (except seam VII and L3). Thus Seam VI at the top to seam I at the
bottom are envisaged to be worked by opencast method. The floor of seam I is
envisaged as the base of the proposed quarry.
Eastern Boundary - The indicated / proved reserves line has been considered
as the boundary.
Western Boundary – Geological block boundary and Gumani river has been
fixed as the mine boundary
The mineable reserves and Volume of OBR within the proposed quarry are
shown in table no 5.1
The mineable reserves of different seams has been estimated with the help of the
following seam Folio plans:
1. Seam Folio Plan of Seam VI – Drg. No. RI-1-OCM-7166
2. Seam Folio Plan of Seam V - Drg. No. RI-1-OCM-7167
3. Seam Folio Plan of Seam-III(TOP) – Drg. No. RI-1-OCM-7168
4. Seam Folio Plan of Seam-III(BOT) – Drg. No. RI-1-OCM-7169
5. Seam Folio Plan of Seam-II(TOP) – Drg. No. RI-1-OCM-7170
Job No.102177 Chapter-5, Page-3
Project report for Simlong OCP CMPDI, RI-1
6. Seam Folio Plan of Seam-(BOT&COMB) – Drg. No. RI-1-OCM-7171
7. Seam Folio Plan of Seam-L2 – Drg. No. RI-1-OCM-7172
8. Seam Folio Plan of Seam-I(COMB) – Drg. No. RI-1-OCM-7173
The OBR volume has been estimated with the help of isopachytes of total
excavation plan given vide Drg. No. RI-1-OCM-7177.
The seam-wise mineable reserves and parting-wise OBR volume for the three
quarries are given in table no. 5.2
For the purpose of reserves calculation and drawing of calendar plan the whole
mining block has been divided into several sectors. Each part has been divided
each into three sectors. East Part comprises of Sector-1,2 &3 and West part
comprises of Sector-3,4 &5. Sector-wise volume of OB and quantity of mineable
reserves are given in table no. 5.3.
In the Western Part of the mine, the rated capacity has been fixed as 1.50 Mt. of
coal per year, due to overall coal thickness being much less, thinner coal seams
and higher stripping ratio. Since, 12th year of production period, the mine will
produce at a rate of 1.50 MTY till the end of mine life.
OBR S1 S2 S3 S4 S5 S6 TOTAL
Top OB 5.79 4.54 7.00 7.28 4.06 9.01 37.73
Parting Bet. VI & V 0.00 0.89 4.42 0.00 0.37 2.60 8.28
Parting Bet. V & IVB 0.00 4.40 6.74 0.00 2.56 3.86 17.60
Part. Bet. IVB & III (T) 0.00 3.80 4.75 0.49 2.67 3.60 15.30
Part. Bet. III(T) & III(B) 0.69 1.06 1.33 0.24 1.34 1.28 5.94
Part. Bet. III(B) & II(T) 2.60 3.77 5.00 2.12 5.66 5.04 24.20
Part. Bet. II(T) & II (B) 0.35 0.28 0.33 0.10 0.01 0.00 1.08
Part. Bet. II(B) & L2 1.12 1.51 2.00 1.93 2.46 2.75 11.77
Part. Bet. L2 & I(T)/Comb. 1.05 1.56 1.64 3.13 2.67 2.22 12.27
Part. Bet. I(T) & I(M) 0.03 0.00 0.01 0.59 0.31 0.18 1.11
Part.Bet. I(M) & I(B) 0.03 0.00 0.01 1.12 0.88 0.56 2.59
METHOD OF MINING
6.1 GENERAL
The entire Simlong (OCP) geological block has been studied in respect of different
surface constraints as mentioned in chapter V and, geological features like faults,
disposition of the seams. The boundary of the proposed quarry has been fixed
considering different surface/geological features. The Geology & Surface features
plan is given vide drg. No. R1-OCM-7162. From this plan, it may be seen that a
number of villages are located within and outside the quarriable area. All the existing
infrastructures are also situated within the proposed quarry area. The rehabilitation of
these villages and dismantling/replacement of existing infrastructure are of utmost
importance for the smooth working of the proposed OCP.
It is proposed to start initial excavation along the incrop of seam-I at the East part
where existing mining activity is going on. Some of the existing infrastructure like
work-shop and ‘C’ type quarters have to be shifted before that. After establishing
connection of the proposed access trench with the existing working, the mine is
proposed to extend towards east to increase the strike length. East Part with a
mineable reserves of 20.60 M.te. will be exhausted in the year P12 of quarry
operation. Excavation will be started at the west part in the P12 year of production
period and continued till the end of mine life.
2.00 MTY of coal production is envisaged from East Part and 1.50 MTY of coal
production is envisaged from West Part. The entry to the two parts of the quarry have
been shown in drg. No. R1-OCM-7164. Box-cut will be made along the incrop of
seam-I and the quarry is to be worked towards the dip side.
The project area is free from any geological disturbance. However, seam-I and
seam-II have been split and merged at the middle of the property. In the Eastern part
of the quarry, seam-I is mostly combined, barring a small zone in the middle, where
all the sections, e.g. seam-I(top), seam-I(mid) and seam-I(bot) exist. In the Western
part of the quarry only seam-I (Top) is workable. Similarly, seam-II is fully combined
at the western part of the quarry, whereas it is split in two at the eastern part.
Different geo-mining parameters of the three quarries are given in table no. 6.1
It has been proposed to work the Simlong (OCP) by shovel - dumper combination.
The points in favour of shovel-dumper application are as follows:
Multiple seams with variable thickness. The major seam I & II are merged in one
side and split in the other side, which requires selective mining.
Presence of a number of villages scattered over the mine-take which may require
mining operations in different sections which can be dealt with by shovel-dumper
combination conveniently.
It has been envisaged that shovel-dumper combination is the suitable option for
overburden removal for this project. As making provision of power supply is a difficult
affair, all HEMM for the project have been chosen to be diesel operated. The
following arrangement of equipment combination has been considered for the
project.
10-12 cum diesei Hyd. Shovel to work with 100T Rear Dumpers for main OB
workload i.e. Top OB, parting between seam V & IV(B) , parting between seam IV(B)
& III(Top), parting between III(B) & II(Top) and the parting between IIBot) & I. 5-6
cum diesel Hyd. Shovel to work with 60T Rear Dumpers for intervening partings, i.e.
parting between seam III(Top) & III(B), seam II(T) & II(B), seam II & L2 , seam L2 &
I. 5-6 cum Diesel Hyd. Shovel to work with 60T Rear Dumpers for the total coal
winning and transportation.
The OCP involves working of multiple seams with thickness varying in wide range.
Considering the rather steep gradient(80 to 100) of the coal seams and flexibility of
operation, shovel-dumper method has its own advantage whereas, the applicability of
surface-miner has some limitation.
Considering the geo-mining characteristics of the deposit & other factors, the mine is
proposed to be worked by shovel-dumper combination as stated above. Mining will
be done by inclined slicing method. The Top OB and major partings are proposed to
be dealt with 10-12 cum Hyd. shovel and 100T dumpers. The rest of
overburden/intervening parting is proposed to be excavated by 5-6 cum hydraulic
shovel and 60 T dumpers. The Coal from all the seams is proposed to be extracted
by 5-6 cum hydraulic Front End shovel and 4-5 cum. Hyd. Backhoe in conjunction
with 60T dumpers. As an alternative coal winning may done by deployment of
surface miner where the process of drilling and blasting will be almost eliminated.
. Bench height m 15 10 m
Eastern Part of the Simlong OCP is a hilly terratn with top R.L at hillock varying
between 148m 140m. The R.L. at the valleys varies between 126m. and 130m.
Western part of the Proposed OCP is comparatively flat, general surface R.L
varying from 100m to 105m. Large forest cover exists in the south and north side of
the OCP with scattered forest land within the quarry. A PWD road passes through
middle of property. A village road passes along the south side of the OCP In
addition to this, a large no. of villages are scattered within the quarry and external
dump area.
The mine boundaries have been fixed considering the above constraints. All
attempts have been made so that requirement of forest land is reduced to the
minimum. About 165 families are to be rehabilitated in different stages of mine
operation.
In the existing Mine Plan (Drg. No. R1-OCM-7163), it may be seen that a number of
villages lie in the middle, and at the eastern part of the proposed quarry. Without
village rehabilitation, excavation cannot be progressed. The initial excavation area
is free from any surface built-up (except the existing workshop and ‘C’ type quarter)
and excavation can be started and continued for initial three years. By this time all
the villages need to be rehabilitated.
East part is envisaged to start from the year P1 and continue up to the year P12
and the West part run from year P12 till the end of mine life. Attempts have been
made to minimize the requirement of land for final external OB dump.
OB from East part will be placed at temporary external dump in site- 1&2 (at the
west part of the proposed quarry) and permanent external dump in site – 3 (beyond
the eastern boundary of the quarry). At the end of quarry operation in East Part,
temporary external OB dump-1&2 will be re-handled into the void of East part.
Total volume of OBR is 137.80 M.cum including 67.70 M.cum from East part and
71.10 M.cum from West part. Out of the 67.70 M.cum of OB from the East part,
24.00 M.cum is required to be placed as external dumps, major part (18.0 M.cum)
of which are later proposed to be re-handled and placed as internal dump. The
remaining 6.0 M.cum shall be kept as permanent external OB dump at site-3. At the
East part internal dumping will start in the P6 year. Initial OB from the West part is
proposed to be dumped in the void of worked out East part and internal dumping is
proposed to be started in the year P17. Re-handling of external OB dump from the
west part of quarry is envisaged to start in year P12, the last year of excavation at
East part. The plan showing the location and capacity of both external and internal
dumps is given vide drg. No. R1-OCM-7176.
No non-forest and non-coal bearing land is available for external OB dumping near
the proposed quarry site. Hence, it has been decided to mine the quarry in two
parts and void of the East part will be used as external dump for West part. For the
external dump of East part three sites have been identified. The site-1&2 (18.0
M.cum capacity) is located at the west part of the proposed quarry which needs to
be re-handled before the start of mining operation there. The site -3 (6.0 Mcum.
capacity) is on non-forest zone at the eastern border of the quarry. This site is on
coal bearing area, the mining potential of which is almost nil. A village named Bara
Ghaghari is located in the above site which needs to be rehabilitated. The drawing
no. R1-OCM-7178 shows the site.
Effort has been made to keep the volume of permanent external OB dump as small
as possible. In west part of the quarry, at the temporary external Dump of site-1&2,
a volume of 18.0 Mcum can be accommodated. These two dumps have been kept
restricted to two lifts (60m.) to avoid problem during re-handling. Any external dump
Job No.102177 Chapter-7, Page-2
Project report for Simlong OCP CMPDI, RI-1
at the dip side of East part has not been considered, because during the running
life of the mine, the in-pit void is barely capable of accommodating the running OB
leaving any scope of accommodating re-handled OB.
Internal dumps have been made in the total quarry. The temporary external OB
dumps (at western part of the quarry) to be formed during the working of Eastern
part is proposed to be re-handled after the end of working in east part.
External OB dump will be formed in two lifts, each of 30m height. Internal dumping
will be started in 6th year of production (year P6) at the east part. In-pit dumping at
West Part will be started in year P17.
Volume of external and internal dumping at every 5 years interval along with
area of excavation is given in the Table no. 7.2
The height of the external dumps is envisaged as 60 m above the surface with
top RL being +165 m at site-1 & 2. and +215 m at site-3. The dumps will be formed
in 2 decks of 30 m each.
The top RL of the internal dumps at east part has been kept as 165 m, which is
highest RL at the earth edge. At the West part, the highest R.L of internal dump has
been raised upto 130m i.e. one lift above the surface to accommodate the
excavated/re-handled OB Volume.
Slope of individual deck does not exceed natural angle of repose. Overall slope of
the dump will be about 28 degree from the horizontal.
East part will be completely back-filled. However, some area will remain void at the
end of mining operation in West part. Final stage dump plan has been shown in the
drawing no: R1-OCM-7200.
The design criteria adopted for mining operations of Simlong opencast mine are
as follows:
b. No of daily shifts 3
a. Excavation category:
OB 50% cat III + 50% cat IV
Coal cat III
b. Material density:
OB 0.72
Coal 0.74
d. Availability of Excavator:
The calendar plan of excavation has been formulated based upon the adopted
sequence of mine development and optimum condition of mining operation for the
entire life of the opencast mine.
Initial two years have been considered as construction period for the project. In
these two years of construction, no excavation has been proposed, only
infrastructure will be developed during this period. Excavation as well as coal
production has been proposed from the year P1 i.e. after 2 years of construction
period. The East part which consists of the existing working is envisaged to be
worked first. Working in this part will be finished in the year P12. The rated
annual capacity of 2.00 MTY is envisaged to be achieved in the year P3.
The peak volume of OBR is 7.00 Mm3 at a stripping ratio of 3.50 m3/te.. The
average stripping ratio for the entire life of the mine is 3.55 m3/te. The temporary
external OB dump (at west part of proposed quarry) created during the operation
of East part is proposed to be re-handled and re-handling programme is
envisaged to be started at end of East part e.g in the year P12. Overall stripping
ratio considering the volume of re-handling for entire life of mine works out to 4.02
m3/te. The summarised calendar programme of excavation is given in table no.
8.2. The seam-wise calendar programme of excavation for Coal and OBR is
given in Table no. 8.3 .
The requirement of HEMM, e.g., shovel, dumpers, drills and dozers etc. have
been estimated as per annual productivity based on adopted design criteria and
workload determined by the calendar plan considering the physical location of
equipment within the operating mine. For calculating the number of dumpers, the
OB and Coal transportation leads have been taken as 2.0-3.0 Km and 1.0-4.0 Km
respectively.
The total strength of HEMM for the selected option is given in table no. 8.4.
Requirement of the equipment for the selected option with different digging and
transport HEMM configurations along with year-wise phasing have been worked
out and given in table no. 8.5.
C1
C2
P1 0.50 1.00 0.50 2.00 2.00 4.00 2.00 4.00
P2 1.00 2.00 1.00 2.80 2.80 2.80 2.80 2.80
P3 2.00 3.40 2.00 5.60 5.60 2.80 5.60 2.80
P4 2.00 4.50 2.00 5.80 5.80 2.90 5.80 2.90
P5 2.00 4.50 2.00 6.40 6.40 3.20 6.40 3.20
P6 2.00 4.50 2.00 6.40 6.40 3.20 6.40 3.20
P7 2.00 4.50 2.00 6.40 6.40 3.20 6.40 3.20
P8 2.00 4.50 2.00 6.50 6.50 3.25 6.50 3.25
P9 2.00 4.50 2.00 7.00 7.00 3.50 7.00 3.50
P10 2.00 4.50 2.00 7.00 7.00 3.50 7.00 3.50
P11 2.00 4.50 2.00 7.00 7.00 3.50 7.00 3.50
P12 1.10 0.40 1.50 3.80 2.20 6.00 4.00 1.00 7.00 4.67
P13 1.50 1.50 6.20 6.20 4.13 1.00 7.20 4.80
P14 1.50 1.50 6.20 6.20 4.13 1.00 7.20 4.80
P15 1.50 1.50 6.00 6.00 4.00 1.20 7.20 4.80
P16 1.50 1.50 5.40 5.40 3.60 1.80 7.20 4.80
P17 1.50 1.50 5.40 5.40 3.60 1.80 7.20 4.80
P18 1.50 1.50 5.40 5.40 3.60 1.80 7.20 4.80
P19 1.50 1.50 5.60 5.60 3.73 1.70 7.30 4.87
P20 1.50 1.50 6.00 6.00 4.00 1.30 7.30 4.87
P21 1.50 1.50 6.00 6.00 4.00 1.40 7.40 4.93
P22 1.50 1.50 6.00 6.00 4.00 1.40 7.40 4.93
P23 1.50 1.50 6.00 6.00 4.00 1.40 7.40 4.93
P24 1.30 1.30 4.70 4.70 3.62 1.20 5.90 4.54
Total 20.60 18.20 38.80 66.70 71.10 137.80 3.55 18.00 155.80 4.02
0
Both coal and OB require drilling and blasting prior to excavation. Electric drills of
160 mm are proposed for coal benches & intervening small partings. Electric
drills of 250 mm size are proposed for drilling the major OB benches.
The following specific consumption of explosives has been adopted for estimating
the annual requirement of explosives:
a. OB - 0.3 kg/m3
The explosive magazine capacity for the project has been worked out as 50t
based on explosive consumption for one week. Hence, 50t magazine is required
for the proposed OCP if cartridge explosive is used.
If SMS type of explosive will be used, then required magazine capacity will be
very small. In that case, magazine will be required only for storage of cast
boosters, detonator, cord-relay, detonating fuse etc. However, for thin coal seams
and partings and also for watery hole, cartridge explosive is necessary. With the
use of SMS, a magazine of 5Te capacity is sufficient to cater the need of
proposed OCP.
Considering the powder factor of 3.33 m3/ Kg and 5.0 Te/Kg. for OB and coal
respectively, the total annual explosive requirement for the OCP with peak OB
removal will be about 2155 te or about 7.20 tpd. However, if coal winning is
done by surface miner, explosive requirement will be marginally reduced.
9.1 GENERAL
The coals of Simlong block are primarily high moisture, non-coking coal. The
seam delineation has been done on the basis of ash + moisture percentage.
Bands containing upto 40% ash + moisture are termed as ‘coal’, 40-55% as
‘shaly coal’, 55-70% as ‘carbonaceous shale’ and above 75% as ‘obvious band’.
For quality determination, the Useful Heat Value and grade has been
calculated considering Ash plus Moisture from proximate analysis at 60% R.H.
& 400 C. Where it is not available, the same has been calculated by converting
band-by-band analytical data as per standard M-100 formula. In case of band
of shale & sandstone, which had not been analysed earlier, but, form part of the
seam while considering I- 100 thickness, the ash & moisture of such shale &
sandstone bands have been taken as below:
The weighted /lengthwise average values of moisture and ash contents for the
entire seam have been determined based on the above.
9.2.1 SEAM-VI
Quality data of only two borehole is available. The grade of the seam varies
from D to E. The Useful Heat Value varies from 4829 K.cal/kg (RCH-175) to
4042 K.cal/kg (RCH-148).
The quality parameters of the seam are given in table no 9.2
9.2.2 SEAM V
The seam varies in grade from E to G. To the east of borehole RCH-146 &
RCH-117 the seam falls in grade G while in the remaining area it is of grade F,
Job No.102177 Chapter-9, Page-1
Project report for Simlong OCP CMPDI, RI-1
except in a small area, around borehole RCH-106, where, the seam is of grade
E quality. The Useful Heat Values vary from 3380 k.ca,/kg (RCH-106) to 2303
k.cal/kg (RCH146).
The quality parameters of the seam are given in table no. 9.2
9.2.10 SEAM I
Seam-I is mostly combined in the eastern part and only seam-I(Top) is workable
at the western part. In the combined portion Useful heat value varies from 2055
K.Cal,/ Kg to 4111 K.Cal./ Kg. The grade of seam ranges from F to E though for
major part of the area of the seam is of grade F. In seam-I(Top), from the
analytical data obtained from 8 boreholes it is observed that the grade of the
seam varies from D to F with a gradual deterioration towards east. The quality
parameters of the seam are given in table no. 9.2
9.2.11 Seam-wise, grade-wise Mineable reserves distribution along with over all
specific gravity is show in table no. 9.1
Quarry-wise quality parameters incld. 10cm layer from Roof & Floor(considering anticipated
mining dilution) Table No 9.4
The quality parameter have also been assessed considering anticipate dilution in
coal quality during mining activity. It has been assumed that 10cm layer from roof
and floor of each seam will be added to coal during mining process, which is
likely to deteoriate the coal quality as shown in table no 9.4. From this table, it
may be concluded that the UHV of the combined coal product will be more than
2400 Kcal/kg, as the contribution from quarry-3 is more than that of quarry-2.
Thus the grade of coal will be of grade F even after considering mining dilution.
It is to be noted that, in case of dilution of extraneous matter in coal, quality from
quarry-2 is deteriorating and in such case UHV of coal of quarry-2 is 2299
Kcal/kg. Under such case, when both quarry-2 and quarry-3 will be operating, the
final product will be delivered after proper blending of ROM coal in CHP in the
planned production ratio. In this case, the UHV of final product will be 2472
Kcal/kg. Hence, in any case, the final product will be delivered as ROM coal of
Grade “F”.
CHAPTER - 10
10.1 INTRODUCTION
The pumping system of Simlong Opencast mine has been designed to dewater
the inflow of water due to precipitation falling within the active pit limit during the
monsoon season to enable the mining activity to continue round the year.
General topography of the project shows that surface drainage is not likely to
pose any major problem. The surface within the mine intake area is highly
undulating and is not traversed by major river/nallah.
The Planning of de-watering of the mine has been done in such a way that as far
as possible the working faces and haul roads remain dry. The lay-out of the
quarry provides suitable gradient along the quarry floors and the benches to
facilitate self-drainage of water to the lowest level of the quarry.
The rain water intake to the opencast mine is non-uniform during the year. The
maximum rain water intake will be during the period of about five months (June to
October) in a year. During dry season, say November to May, seepage from
strata is expected to be moderate and the same can be dealt by running a few
number of pumps provided for monsoon pumping. During this period repair &
overhauling of the pumps will be done by rotation.
The quantity of water inflow during a day of peak rainfall in monsoon will be
handled by the main pumps.
The general criteria for determining the number of pumps, layout and design of
the pumping installation are as under:
Volume of rain water entering to the mine and accumulating in the quarry (make
of water) has been assessed on the basis of the following formula:
Q = A x H x m3/day
The external dump area has not been considered in the area beyond excavation
because of natural gradient of dump towards the river adjacent to the quarry.
The area of working benches has been included in the mined out area.
ii) Seepage water from the strata has been considered as 10% of the water
accumulation in the mine.
iii) Catchment Area (A) has been considered to be comprised of the
following areas :
Surface area of mine or excavation = A1
Area beyond excavation = A2
Internal dumped area = A3
iv) Following run off co-efficients, ROC has been considered for the
following areas:
For mined out area – n1 = 0.60
For area beyond excavation – n2 = 0.10
For internal dumped area – n3 = 0.15
v) Accumulated mine water in the day of maximum rainfall is to be pumped
out in five days with twenty hours pumping.
Water accumulation in the mine (Q) :
Based on the data available, the water accumulation for mined out area with
internal dump in the day of maximum rainfall is as follows :
A1 = 120 hactare
A2 = 6 hactare
A3 = 35 hectare
Q = { (A1 – A3) x h x n1 } + ( A2 x h x n2) + ( A3 x h x n3) cu.m. per day
= ( 85 x 104 x 150/103 x 0.6 ) + ( 6 x 104 x 150/103 x 0.1 ) + ( 35 x 104 x
150/103 x 0.15)
= 76500+900+7875 = 85275 cum/day.
The capacity of the sump should be such that it can hold one day’s maximum
rainfall and the location of the sump should be at dipper side so that water can
flow towards sump from the adjoining areas.
Peak pumping capacity per day has been worked out as under :
Considering 10% seepage from strata, the total water accumulation will be Q1 =
1.1 x Q = 1.1 x 85275 = 93802.5 cum/day,Say – 93805 cum/day.
Quantity of water to be pumped out per day = Q1/W where W is the number of
pumping days to dry the sump.
Considering single day maximum precipitation to be pumped out in five
days,quantity of water to be pumped out per day = Q1/W = 93805/5
= 18761 cum/day (approx)
Above high discharge, high head pumps i.e 300 Cum/hr, 200 m head, 250 kW
Main pumps have been proposed.
It is planned to utilise the low capacity, low head pumps in the initial years of
working. With the increase in area and depth of mine, high capacity, high head
pumps will be used.
For initial stage of quarry working, 4 pumps (3 working & 1 standby) of 38 lps,
100 M head with 55 kW motor have been proposed. These pumps will work as
Main pumps in the initial years of mining.
During heavy rainfall, overburden may be washed away from the edges of
slopes and internal dumps, needing pumps capable of handling slime/slurry.
Pumping of clear water and slime will be from upper and lower part of the sump
respectively. For pumping slurry/sludge containing large solid particles,2 pumps
(1 working & standby) of 15 lps,30 M head with 37 kW motor have been
proposed for transfer of slime from main sump to slime ponds at suitable
The delivery pipe lines from the pumping station are proposed to be taken out
through the side of haul road provided in the middle of the quarry. These pipes
are eventually brought to the surface, from where, the water will be discharged
to the garland drain, dug around the quarry.
The suction and delivery ranges have been selected on the basis of the
pumping capacity during probable maximum rainfall and velocity of flow within
the reasonable limit. The ranges thus selected for pumps are of 250 mm, 200
mm,150 mm, 100 mm and 80 mm nominal diameter.
In the outsourcing option, pumping of mine water has been excluded from the
departmental responsibility. Accordingly, no capital has been provided for
pumping in the outsourcing option.
11.1 INTROUDCTION
A coal handling plant has been proposed to downsize ROM coal upto (-) 100
mm size. Opencast coal cannot be crushed in a single stage, therefore, 2 stage
of crushing has been envisaged. Initially, in the primary crushing system, ROM
coal will be crushed upto (-) 200 mm size with the help of Single Roll Crusher
(i.e. Primary Crusher) & in the later stage (-)200 mm coal will be crushed to (-
) 100 mm size in the secondary crushing system. (-)100 mm sized coal will
thereafter, be stored into 4 X 100 Te. overhead steel fabricated truck loading
hoppers or onto ground as stock pile.
There shall be provision of loading of coal onto trucks by means of sector gate
fitted below hoppers.Coal stacked at ground stockpile shall be reclaimed by
means of contractual pay loaders and loaded onto trucks. Two nos. 50 tonne
road weigh bridge has been envisaged for weighment of coal loaded trucks.
Coal transportation from coal handling plant to the MGR siding at Kumarpur
shall be done contractually. NTPC has agreed to provide the required land
space for building up a warf wall by ECL.
The handling capacity of the CHP has been decided to match with the
production capacity of the mine. On the basis of 330 working days / year and 5
hours/shift, the rated capacity of the CHP works out to be 600 tph. In order to
meet the fluctuations of coal output from the mine due to irregularities of
transport system and seasonal fluctuations, the design capacity of the CHP has
been fixed as under :-
Two numbers of Heavy Duty Single Roll Crusher of 600 tph (avg.)
capacity [1Op.,1SB] for primary crushing of R.O.M. coal to (-) 200
From the mine R.O.M. Coal of (-) 1200 mm size shall be brought at the CHP by
50 t rear dumpers and same shall be delivered at the receiving pit.600 tph
capacity apron feeder shall feed R.O.M. coal to of 600 tph (avg.) capacity
Heavy Duty Single roll crusher (2 Nos.,1 in Op.,1 SB).Roll Crusher shall crush
coal to (-)200 mm. (-) 200 mm crushed coal from Roll Crusher shall be received
Job No 102177 Chapter-11, Page-3
Project report for Simlong OCP CMPDI, RI-1
onto 1000 mm wide conveyor C1 and same shall be fed to Secondary Crusher
of 600 tph (avg.) capacity to crush (-)200 mm coal to (-) 100 mm size.
Crushed coal of (-) 100 mm size shall be stored into 4 X 100 tonne over head
steel hoppers or onto the ground for stockpile with the help of 1000 mm wide
elevating cum tripper belt conveyor C2. Coal will be loaded into the trucks by
opening sector gate fitted below hoppers or reclamation from ground stockpile
with the help of contractual pay loaders. Coal loaded trucks shall be weighed at
50 tonne road weigh bridge (2 Nos.)
Average capacity of Heavy Duty Single Roll Crusher shall be 600 tph. Apron
feeder of 600 tph capacity shall reclaim coal from receiving pit and shall feed
the same to Single Roll Crusher. The gap of the primary crushing rolls shall be
set in such a way so that the ROM coal may be fragmented up to (-) 200 mm
size. An elevating belt conveyor will be used for feeding (-) 200 mm size coal to
the secondary crushing complex. Keeping in view the crushing ratio i,e 1:6, size
of in feed coal, the availability of primary crusher may go down, therefore, one
more standby feeder breaker has been provided. A belt conveyor C1, 1000 mm
x 60 m x 75 kW shall receive (-)200 mm size coal from Single Roll Crusher i.e.
Primary Crusher. A metal detector and a magnetic separator shall be installed
over belt conveyor C1.
(-) 200 mm coal fed to 600 tph capacity Secondary Crusher shall be crushed to (-)
100 mm. (-) 100 mm size coal shall automatically fall to the belt conveyor C2
installed below the Secondary crusher.
Job No 102177 Chapter-11, Page-4
Project report for Simlong OCP CMPDI, RI-1
A belt conveyor C2, 1000 mm x 130 m x (2x55) kW will receive coal from
secondary crusher outlet chute for conveying (-) 100 mm size coal to either 4
nos. 100 te each overhead truck loading hopper or ground stock pile. Sector
type gates will be fitted below the truck loading hoppers. The same belt
conveyor will have the facility to deliver coal to truck loading hoppers or to
ground stock pile. Ground stock provision has been kept for exigency. Pay
loaders for reclamation of coal from ground stock shall be under the scope of
the contractor.
The objective of this system is to eliminate the air borne coal dust or suppress
the dust at its source. The system involves confinement of the dust within the
dust producing area by a curtain of moisture and wetting the coal dust by direct
contact between the particles and droplet of water. Adequate number of
precision anti-clog nozzles
shall be installed at suitable locations for suppressing dust by spraying plain
water . Suitable control for dust suppression shall be provided and the system
shall be so inter-locked that it functions only when the conveyor system is
operating or the loading operation is on.
Necessary fire fighting system shall also be envisaged for the plant, which
includes fire hydrant tees at strategic locations at equal spacing of 25 to 35
meters with suitable water supply pipe lines. Also portable type fire extinguishers
Job No 102177 Chapter-11, Page-5
Project report for Simlong OCP CMPDI, RI-1
to deal with electrical / oil /ordinary fires shall be provided at all strategic locations
in the plant.
For effective maintenance of all the equipment, sufficient working space shall be
kept around the equipment/machinery. All the equipment and conveyor
discharge drums/transfer points, etc shall
be covered with well ventilated housing complete with access stair ways, hand
rails, platforms, cross-over ladders, etc as required.
Necessary mono-rails electric hoists and chain pulley blocks at suitable points
of adequate capacity shall also be provided on respective floors.
11.2.6.9 Weighment
Earthling
There shall be provision of loading of coal onto trucks by means of sector gate
fitted below hoppers. In case of exigency, ground stock of coal shall be made by
tipping trucks. Coal stacked at ground stockpile shall be reclaimed by means of
contractual pay loaders and loaded onto trucks. Two nos. 50 tonne road weigh
bridge has been envisaged for weighment of coal loaded trucks. There shall be
provision of dust suppression system in CHP.
Till the Railway (MGR) siding at or Kumarpur is Built up, coal from simlong shall
go to Bakreswar Thermal power plant and also despatched through Rajmahal
Railway siding. Negotiation with NTPC is going on for setting up a siding at
Kumarpur. Hence, necessary fund for widening and strengthening of coal
transportation route from mine site to Kumarpur Siding has been provided in
Appendix-A.8.1
CHAPTER - 12
WORKSHOP, STORES AND MAGAZINE
Facility planning has been done for providing maintenance and repair facilities to
all the major equipment deployed in the opencast project and a comprehensive
layout plan for unit workshop and project store has also been prepared. The
proposed unit workshop and project store will facilitate the maintenance and
repair requirement of mining, mechanical, electrical, transport and other auxiliary
equipment and storage of spare-parts, sub- assemblies and consumables.
In general, two-shift working has been envisaged for the unit workshop with
only essential maintenance facilities in the 3rd shift and one shift working for
project store.
Facility planning of project workshop and project store has been done based on a
comprehensive maintenance and repair programme to achieve the high level of
equipment availability, reliability and longer life.
Maintenance and repair load of workshop has been assessed on the basis of
annual operating time, inter repair period, life of the equipment/ assemblies/ sub-
assemblies, weight and size of the equipment/ assemblies/ sub-assemblies, man-
hours required per repair etc.
Particular Area ( m2 )
Excavation workshop unit has been planned for maintenance and repair work of
dumpers, dozers, shovels, drills, cranes, water sprinklers and other mining,
mechanical and electrical equipment except the capital repair, which is planned to
be carried out at Central/ Regional workshop or, by OEM. The area of excavation
workshop unit will be 3576 m2.
This workshop has been designed to cater the needs of dumpers upto 100 T
capacity. Detail description of major functional shops are given in the following
Table.
The overall area of E&M workshop will be 588 m 2. Sizes of major functional
shops of E&M workshop are given in the following table.
Major Shops No. of bays Bay size Shop size EOT Crane
Capacity (t)
Machine - - 18m x 12m 5 t - 1 no.
Shop
Provision of E.O.T. cranes, mobile cranes, tyre handler, fork-lift trucks, trolleys,
electric hoist, chain pulley blocks, jacks etc. has been made for quick and
effective handling of heavy materials and tyres within and outside the shops.
Provision has been made for Fire fighting equipments, ventilation equipment in
the work-shop.
A list of plant and equipment with their prices required for maintenance and repair
unit are given in Appendix-A.3.3 .
The Project Stores shall have the facility for reception, storage and issue of all
kinds of materials, equipment and consumables required for mine operation and
maintenance of mining, mechanical and electrical equipment. The storage capacity
is planned for 30 to 45 days consumption of materials. Due consideration has also
been given for proper working environment, cleanness and safety measures.
Proper equipment and material handling facilities have also been provided.
The entire operation of the project store will be controlled and coordinated by
material management division. The project store will be located adjacent to the
workshop complex near the mine entry.
Layout plan of the project store has been given in Drg NoRI-1/E&M/200002.The
project store will meet the total store requirement of project and unit workshop.
Overall size of the project will be 80m x 130m. The size of main sheds/ buildings of
the project store will be as given in the following Table.
Existing Simlong OCP has small magazine for licence of 450 Kg only. In the
current PR a magazine has been proposed for a capacity of 5 Te. The proposed
magazine will be situated near the existing one at the foot of existing External
dump. The magazine will be used for storing small cartridge explosives ( for
blasting thin partings and coal seams) and other blasting accessories.
The capital requirement of plant and machineries for workshop and store has
been given in Appendix – A.3.3.
In all the options the main Substation shall be located in between the CHP &
western access trench of quary..The DG sets will supply power at 3.3 KV to
the quarries, CHP, workshop, one no. 50 KVA 3.3/0.220(L-L) lighting
transformer will be used to illuminate sub-station & office
Capacity of the DG sets: Departmental Outsourcing
Option-I 2.5 MVA 3.3 KV 1 MVA 3.3 KV
Option-II 1.5 MVA 3.3 KV 0.5 MVA 3.3 KV
DG sets, the control relay panels of 3.3KV circuit breakers, capacitor banks,
AC/DC switch board, batteries, battery charger etc. will be installed in the
indoor substation.
A. Departmental Option
Option -I
There will be a 3.3 Kv panel having sixteen nos circuit breakers of which two
are incoming ,one coupler & thirteen are outgoing.
Out of thirteen outgoing panels two nos. will supply power to CHP, two nos will
supply power to workshop, two nos.will supply power to colony,two will supply
Option -II
There will be a 3.3 Kv panel having fifteen nos circuit breakers of which two
are incoming ,one coupler & twelve are outgoing.
Out of twelve outgoing panels one no. will supply power to CHP, two nos will
supply power to workshop, two nos.will supply power to colony,two will supply
power to quarry, two nos. will supply power to capacitor bank,one no. will
supply power to lighting tranaformer and there will be two spares .
B. OUTSOURCING OPTION
Option –I
There will be a 3.3 Kv panel having fifteen circuit breakers of which two are
incoming ,one coupler & twelve are outgoing.
Out of twelve outgoing panels two nos. will supply power to CHP, one no will
supply power to workshop, two nos.will supply power to colony,two will supply
power to quarry, two nos. will supply power to capacitor bank,one no. will
supply power to lighting tranaformer and there will be two spares .
Option –II
There will be a 3.3 Kv panel having twelve nos circuit breakers of which two are
incoming ,one coupler & nine are outgoing.
Out of nine outgoing panels one no. will supply power to workshop, two
nos.will supply power to colony,two will supply power to quarry, two nos. will
supply power to capacitor bank,one no. will supply power to lighting tranaformer
and there will be one spare .
LT Switch Board:-
110V DC Switch Board:- (In all Options)
DC power at 110V will be obtained from battery and also rectifier. DC power will
be required for emergency lighting, closing and tripping of circuit breakers,
signalling, Interlocking etc.
Departmental
Outsourcing
Interlocking :-
-There will be interlocking between the two incoming 3.3 KV circuit breakers &
the coupler such that the two circuit breakers cannot be made ON when the
coupler is ON.
- when two incoing circuit breakers are “ON” then the coupler will be “OFF”.
Earthing :
The earthing system has been chosen as solidly earthed system for 415 volt and
Restricted Earthed neutral system for 3.3 KV,( for restricting the earth fault
current to 50 Amp). The main substation and the other substations shall be
surrounded by earthing grid. The equivalent resistance of earthing grid shall
preferably be as per latest IS Standard(IS 3043). Lightning protection system with
separate earthing shall also be provided.
DEPARTMENTAL OPTION
Option -I
Option -II
OUTSOURCING OPTION
Option -I
S.N. Power Annual Energy Energy Power cost/Te
consumer consumption consumption/Te of production
(KWH x 106) of production (Rs.)
(KWH/Te)
1 Coal 2.55 1.28 6.40
2 Common 1.52 0.76 3.80
Total 4.07 2.04 10.20
13.2 ILLUMINATION
The main sub-station & office will receive power at 220 volt(L-L) from a 50 KVA
3.3/0.220 KV(L-L) lighting Transformer.
llumination has been proposed at quarry & haul road,OB dump,substation &
mine site area by High Pressure Sodium Vapour Lamps from the group of lights
installed on towers/poles & power fed from lighting transformers.HPSV lamps
have also been used for street lighting.
Departmental Option-I
S.N. Description Inst. KW DF PF KW KVAR KVA Working Annual Energy
Hrs Consumption
(KWH x 106)
A COAL:
1 Chp 810 0.70 0.70 567 575 4500 2.55
B COMMON
1 Workshop 800 0.50 0.70 400 406 1500 0.60
2 Pump 703 0.80 0.80 562 422 2160 1.21
3 Colony 650 0.90 0.90 585 283 3650 2.85
4 Quarry light 100 0.90 0.90 90 44 3650 0.33
5 Surface light 50 0.90 0.90 45 22 2920 0.13
B.1 Total Common 2303 0.73 0.82 1682 1176 2052 5.12
C Total(A+B) 3113 0.72 0.79 2249 1751 2850 7.67
C.1 Taking 80% div 2253 0.80 0.79 1800 1400 2280
C.2 Improving PF to 0.98 2253 0.80 0.98 1800 380 1840
Capacitor 2X3X170 (1400-380)
KVAR
Outsourcing Option
OPTION-I
S.N. Description Inst. DF PF KW KVAR KVA Working Annual
KW Hrs Energy
Consumption
6
(KWH x 10 )
A COAL:
1 Chp 810 0.70 0.70 567 575 4500 2.55
B COMMON
1 Workshop 100 0.50 0.70 50 91 1500 0.08
2 Colony 225 0.90 0.90 203 98 3650 0.99
3 Quarry light 100 0.90 0.90 90 44 3650 0.33
4 Surface light 50 0.90 0.90 45 22 2920 0.13
B.1 Total Common 475 0.82 0.88 388 214 443 1.52
C Total(A+B) 1285 0.74 0.77 955 789 1238 4.07
C.1 Taking 80% div 1285 0.59 0.77 764 631 991
C.2 Improving PF to 0.98 1285 0.59 0.98 764 151 779
Capacitor 2X3X80 KVAR (631-151)
OPTION-II
Description Inst. KW DF PF KW KVAR KVA Working Annual Energy
S.N. Hrs Consumption
6
(KWH x 10 )
A COAL:
1 Chp
B COMMON
1 Workshop 100 0.50 0.70 50 91 1500 0.08
2 Colony 160 0.90 0.90 144 70 3650 0.53
3 Quarry light 100 0.90 0.90 90 44 3650 0.33
4 Surface light 50 0.90 0.90 45 22 3650 0.13
Total
B.1 Common 410 0.80 0.87 329 186 378 1.07
Improving
C.2 PF to 0.98 410 0.80 0.98 329 66 336
Capacitor 2X3X20 (186-66) KVAR
Option-I
Sl No. Power Consumer Annual Energy
Consumption(KWHX10
1 Coal 2.55
2 Common 4.23
Total 6.78
OPTION-II
Sl No. Power Consumer Annual Energy
Consumption(KWHX)
1 Coal 0.28
2 Common 4.08
Total 4.36
OUTSOURCING:
OPTION-I
OPTION-II
DEPARTMENTAL
OPTION-I
OPTION-II
Sl.No Year Production Cost/Te
1 1st - Rs5637717/-
2 2nd - Rs7721064/-
3 3rd 0.5 29.72
4 4th 1.0 18.40
5 5th-8th 2.0 10.90
6 9th-13th 2.0 11.32
7 14th-25th 1.5 15.10
8 26th 1.3 17.42
OUTSOURCING
OPTION-I
OPTION-II
OUTSOURCING
OPTION-I
Maximum Demand 779 KVA
Annual Energy Consumption 4.07X06 KWH(Ultimate)
Power Factor 0.98(lagging)
Rs./Te 15.65(ultimate)
Rs./KWH 5.00
OPTION-II
Maximum Demand 336 KVA
Annual Energy Consumption 1.06X106 KWH(Ultimate)
Power Factor 0.98(lagging)
Rs./Te 4.04(Ultimate)
Rs./KWH 5.00
Cost Estimate:-
Details of capital for electrical items with phasing have been furnished in
Appendix-A 3.2
Coal production has become highly capital intensive due to large scale
mechanization for production and transportation using the modern technology.
To cope with mechanization, to maintain safety and to improve the efficiency
there is a need to establish an efficient means of voice and data
communication. The effectiveness and reliability of decision making process
depends on a reliable means of information exchange among the different
units of surface and underground which totally depends upon the integrated
telecommunication systems for voice and data.
While preparing the system, due consideration has been given to the state-of-
art networking architecture involving the communication of voice, data and
multimedia over the same network path, so as to avoid duplicated investment
in network and proper conservation of bandwidth.
To meet all the requirements of data and voice communication, 128 lines of IP
Enabled Exchange is proposed having the following main features:
A 200 line automatic telephone exchange has been envisaged for the effective
communication between the various units on the surface. The EPABX will
preferably employ PCM-TDM technique with a non-blocking structure. The
EPABX shall have all the latest features like E1 port, LAN/WAN port, etc.
EPABX shall be interfaced with BSNL exchange for extending external
communication having STD & ISD facility. Self-diagnostic facility shall be
provided for EPABX extensions. Sufficient no. of junction lines is to be
provided for terminating BSNL, Tie and Trunk lines.
- The line cards slots/channels in the main cabinet must be universal type,
so that any type of line can be used in any line slot/channel and there
shall be no limitation in slot position.
- The IP Gateway port of the exchange can be connected with the LAN
backbone network for VOIP communication.
B. Networking Facility:
C. Features:
A BSNL 2 Mbps leased line is proposed for communication with area HQ. This
leased line shall be used both for voice and data communication with area
HQ. A multi service voice and data router shall be used in this network. The
router will be equipped with 2 nos. of WAN port and one 1 no. of LAN port
minimum.
The type of computer would be small business computer with broad facilities
and also have specific facilities to carry out:
- Pay rolls
- Financial accounting
- Inventory control
- Material management
- Production, dispatch schedule and variances.
- Accident records etc.
- Resource utilization & MIS.
Before initiating action for installation and implementation of the above EDP
system, a detailed system study would have to be carried out, with clearly
defined system objectives for identifying the data processing needs and
management information system needs of the project. Based on the results
and findings of the study, the system configuration and specification have to
be decided.
A Local Area Network with 10 PCs is proposed for this project. The PCs will
be connected to a 24 port L2 switch. The proposed network structure will be
that of a workgroup. Suitable OS and other application software will be
provided and the network shall facilitate sharing of information and computing
resources amongst different departments/disciplines. The network shall be
capable to add more nodes as and when the number of users grow and it will
be equipped with the latest state-of-art technology.
Point to point radio system is proposed for connecting the important locations
with the area office. This will be integrated with LAN and EPABX Exchange to
serve the data and voice communication.
A) Technical Specification
CIVIL CONSTRUCTION
14.1 GENERAL
Based on prevalent rate of different building materials in the project area, the
Building Cost Index for this project has been worked out as 2355 with respect to
100 base at Delhi as on 1.10.76. The details of Cost Index have been furnished in
Appendix A.2.3.
The Civil Construction envisages the estimated capital requirement of the project
for 2.0 MTY target capacity of coal and envisaged manpower as detailed
elsewhere in the Report. Specifications towards the civil construction are based
on BPE guidelines, CMPDI Norms & practice for planning of coal mines.
The service buildings include community buildings, offices, workshop & stores,
sub-stations, & other statutory buildings. All these buildings have been provided
as per the requirement of the project. The comprehensive list of various service
buildings has been given in Appendices A.2.1.
The proposed location for the service buildings and the statutory buildings shall
be around project site. The proposed site for the community/welfare facilities has
Job No.102177 Chapter-14, Page-1
Project report for Simlong OCP CMPDI, RI-1
been identified and is located in the south-west part of the project, where the
residential colony will be located.
In this project report, for departmental option, provisions have been made for
different shades for excavation workshop and E&M workshop. Accordingly,
workshop and stores to cater for the needs of their repairs and maintenance
have been considered. The area of various shops and facilities are envisaged on
the basis of technological & operational requirements. In outsourcing option
excavation workshop has not been considered.
A new magazine room has been provided near the existing magazine room. The
existing magazine is not sufficient to cater the need of proposed OCP.
14.3.3.2 Sub-station
The Sub-stations envisaged in the project will cater the requirements of the
project. This will be of brick masonry, RCC beam and slab construction with RCC
louvers for ventilation and ducts with proper size for electric cables.
14.3.3.3 Office
Provision has been made for Project office and mine site office. These buildings
have been envisaged as RCC-cum-brick masonry structures.
There are provisions for canteen, first aid centre, rest shelter, training centre, pit
head bath, fire fighting station etc. The areas for various statutory buildings have
been considered on the basis of BPE guidelines.
These include dispensary, primary school, officers' and staff rest houses, clubs,
community centre etc.
The manpower requirements for Simlong Opencast Mine for departmental and
outsourcing option have been estimated as 742 and 254 respectively. The
project is located in the districts of Godda & Pakur. The nearest town of
Sundarpahari (Block office) is about 13kms from the proposed Project. With this
background, around 70% housing satisfaction has been considered for the
project. Thus, 520 and 178 nos. of residential units have been envisaged for
departmental and outsourcing option respectively and detailed in appendix A.2.2.
All the buildings have been envisaged as permanent type and of RCC cum
brick masonry structure.
The proposed site for the colony to accommodate these houses and other
community/welfare facilities has been identified and is located in the area
adjacent to the proposed township Chuperbhita OCP. Land area required
towards this works out to around 12Ha and 4 Ha.for departmental and
outsourcing option respectively .
The length of colony roads has been estimated on the basis of the number of
quarters and the specification has been furnished in Appendix A.8.2.1.
For Departmental option the total length of haul roads has been estimated as
1Kms for plying of 100T dumpers. The details have been furnished in Appendix
A.8.2.2. For outsourcing option no haul road has been proposed in the report.
A 1.0 Km long service road is proposed for connecting the service buildings with
estimated amount as detailed in Appendix A.8.2.5.
The capital expenditure of different roads and culverts are furnished in appendix
A.8.2.
Gumani river has been identified as the source of raw water required for the
Project and residential colony. The requirement has been estimated for
Departmental option as 0.45 MLD of potable water and 0.32 MLD of industrial
water. For Outsourcing option, only potable water demand for project and
residential colony has been estimated as 0.21 MLD.
Water from Gumani river has been considered to be stored in bulk reservoir at a
point in the colony area through intake well & pump arrangement proposed at
Gumani river. Water received in the bulk reservoir shall be treated first for both
colony and industrial requirements. This treated water has been envisaged to be
Colony sewage has been proposed to be dealt through septic tanks and soak
pits. The details have been given in Appendix A.8.3.3.
For the purpose of fire fighting in the industrial areas like workshops, stores and
quarry area, separate distribution networks have been proposed from the ground
reservoir. Provision towards requirement of water for public utilities like park,
garden, afforestation etc. has been made in this report. It has been envisaged
that the distribution network for fire fighting shall also be utilised for these
purposes.
The estimated capital investment towards the purpose of industrial water supply
for Departmental option only has been detailed in Appendix A.8.3.2.
It has been considered that the industrial wastes from workshop and other
industrial establishments would be led through oil & grease traps. The effluent
coming out of the industrial premises is proposed to be led to the settling tank and
is proposed to be recycled for various industrial uses for this project. The
domestic sewage generated in industrial premise has been considered to be dealt
in septic tanks and soak pits. The details have been furnished in Appendix
A.8.3.4. for departmental option only.
The capital requirements under the head of Colony water supply, industrial water
supply, Colony sewerage system & Industrial sewerage system have been
furnished in appendix A.8.3.
15.5 INUNDATION
Western part of the quarry is very close the high flood level of Gumani river (i,e.
91m above MSL). Hence, it is proposed to construct flood protection
embankments between Gumani river and the quarry to protect the quarry from
floods during the monsoon. Provision of embankment, with top RL being 3m
above the last recorded HFL line, has been suggested along the surface edge
of quarry at places where the river is in proximity of the quarry. Capital
investment for this purpose has been made in Appendix-A.8.1. Garland drains
around the proposed quarry boundaries will be provided and periodically
maintained as far as possible for adequate safety measure. Proper drainage
system will be provided in haul roads and other roads to guard against damage
of pavement and slippery condition during heavy shower.
15.6 FIRE
Exposed coal faces are proposed to be mined out well within the incubation
period. Stocks of coal depot will be cleared in routine manner. To take care of
accidental fire, adequate provision of fire fighting apparatus has been made.
15.7 BLASTING
Controlled blasting techniques including muffled blasting will be adopted during
blasting within 300 m zone but beyond 100m from the village, dwellings, surface
structure, road etc. total quantity of explosive to be detonated at a time will be
so regulated that ground vibration which may affect the nearby surface
structures, are kept within the stipulated value.
15.10 LIGHTING
Adequate lighting arrangement will be provided at all working places. In addition
to this some mobile lighting arrangement should be made in the proximity of the
equipment to prevent accident during power failure.
16.1.1 Simlong is a running mine, though mining activity is going in a very small scale. As
per the directive of MoEF, quarterly Environment monitoring survey is being done
in Simlong OCP since 1999 and Environment statements submitted to MOEF and
JSPCB annually.
Air quality study
The maximum and minimum values of various parameters as observed
during the period 23th Sep. /24th Sep.2010, are given below :
Observations
In residential areas, season-wise average values for SPM, RPM, SO2 and NOX
are within the prescribed limits as per NAAQS .
General ground water quality in the area represented through well water and
Hand pump have been found to be fresh with lower level of hardness, pH
value within quite normal range, less iron content, fluoride content within
desirable limit and turbidity value slightly higher occasionally. Marginal
increase in turbidity may be attributed to the shallow depth of the tubewell.
Other various parameters of the samples are found to be within the
permissible limits.
The water quality of the Gumani river and Ladha Nallah is also within the
prescribed limits.
The treated mine discharge water quality of Simlong OCP is within the limits
of the Effluent Standards for Coal Mines.
Observations
Noise levels in the residential areas are within the prescribed limits.
16.1.5 The proposed block falls within the catchment area of Gumani river which controls
the drainage of the area. Overall drainage is poor and sparsely developed..
Ground water in the area occurs under both unconfined and confined conditions.
The weathered mantle, recent alluvium and latarite act as unconfined aquifer. The
water table configuration coincides with the topography of the area.
The depth of water level in the Simlong Block ranges from 2 m to 5 m. The
average depth of water in the pre-monsoon range is about 8.8 m below ground
level. Further, water level fluctuation is around 3.5 m in the area..
The ambient air quality is influenced due to the presence of RPM, SPM, SO 2,
NOx, etc., which are generated due to various activities of the project.. The
concentration of pollutants may vary depending upon the various micro-
meteorological parameters and the seasons of a year.
Considering the wind directions for winter season, the areas likely to be affected
due to air pollution lie in south-east, w.r.t. the core zone .
The air quality w.r.t. SPM, RPM, SO2 and NOX, as obtained from the quarterly
survey (for the existing mining operation) are within the limits.. So the ambient
air from this project will have no effect on human being, flora and fauna, soil
quality, surface structures and aesthetic value of the surrounding environment
as suitable mitigatory measures are taken and will be taken to make the
operation eco-friendly.
As the project area (core zone) is very small in comparison to the region, there
will be no impact on ambient air temperature, rainfall and other climatic
conditions due to mining and related activities.
16.2.2 For the proposed Simlong OCP project, suitable protective measures have been
envisaged to minimize the impact on surface water sources such as change in
relief pattern of the area in the core zone, flooding, siltation and pollution of
surface water bodies.
16.2.3 The decoaled area will be backfilled. It will restore the continuity of aquifers.
Further, sufficient rainfall recharge of aquifers will supplement the restoration of
ground water regime of the surrounding area.
16.2.4 The ambient noise level of existing project will be monitored regularly. Noise
levels monitored at various locations are within the limits of the prescribed
standard barring a few isolated values. So the noise produced from this project
will not have auditory, non-auditory, masking effects, etc. as suitable preventive
measures are taken and will be taken..
16.2.6 The impact of opencast coal mine on land is the change in land use pattern.
The changes in this project are due to quarrying and construction of
infrastructure. The alteration in land use pattern due to infrastructure is not to be
considered as true change as these facilities can be utilized for some other
purposes after the mining operation is over. The change in land use pattern due
to activities of quarrying may be considered as true change.
16.2.7 Skilled manpower required for the project may not be available in the area.
Only semi-skilled and unskilled workers will be available from the local
population. So people will migrate to this segment both from within and outside
the district as well as the state due to creation of new employment opportunities.
Educational facilities
The migration of population may strain the local educational facilities
already available. A number of educational institutes must be provided in
the proposed project to cater to the need of increased poulation.
Healthcare facilities
The coal company has to open healthcare centres to cater to the need of
employees of the proposed project and the local people .
Employment opportunities
This project will create direct and indirect employment opportunities in the
area.
Economic impact
The following are economic impacts:
Job No.102177 Chapter-16, Page-5
Project report for Simlong OCP CMPDI,RI-1
Loss of agricultural land
General improvement of economy of the area
Increase in revenue of the state exchequer
The drilling equipment will be equipped with dust arresting devices so that fugitive
dust generation is minimal. Blasting will be done in controlled way to minimize the
generation of fugitive dust. The blasting will be done once in a day to give sufficient
time for settling of dust and for settling of the coarse particles. The haul road will
be regularly sprayed with water sprinkler to prevent dust from getting air borne.
The coal transportation will be made through Coal Handling Plant (CHP), CHP will
be equipped with nozzle sprinkler at dust generation points to suppress the fugitive
dust emission. The coal will then be transported from CHP to MGR siding via
covered trucks.
17.1.1 For the proposed Simlong opencast mine, the total requirement of land is
estimated as 337.74 Ha, including 84.57 Ha of forest land 253.16Ha. of Non-
forest land . Majority of Non-forest land falls under the category of tenancy
land. Non-forest land includes 39.96 Ha of Government land and 213.21 Ha of
tenancy land.
17.1.2 It is estimated that within the core zone, about 50 percent of total land is under
agriculture use. About 8 percent land is covered by existing mine. Another 24
percent (approximately) is under forest cover. Waste land is less than 12
percent. Cultural land such as settlements, roads occupy about 6 percent.
17.1.3 Breakup of the requirement of land has been given in table no 17.1. The
external dumping sites have been identified and shown in the drawing no.R1-
OCM-7178. The sites for external dumping has been envisaged on coal bearing
areas. which are not suitable/viable for mining.
The sites for infrastructure, residential colony and rehabilitation colony for
Chuperbhita opencast project have been proposed on non-coal bearing area.
The above assessment of land requirement has been done by Simlong OCP
authority.
17.3 REHABILITATION
17.3.1 Four number of villages are lying within mining leasehold area which needs to
be rehabilitated. The number of household and population of each village are
given below in table no. 17.2
Villages & Households To Be Rehabilitated Table no. 17.2
Sl. No. Name of Village As per census 2001 As per EIA, April 92
(Richardson & Cruddas Ltd)
No. of Population No. of Population
households households
1 JHAPANI 272 37 189
2 CHHOTA GHAGHRI 267 45 211
3
BARA GHAGHRI 182 21 107
4 SIMLONG 205 36 192
TOTAL 926 139 699
The above data pertain to 2001 censes. The current number of household and
population has been assessed based on 20% increase over 2001 census data.
The precise requirement of rehabilitation and resettlement will be assessed from
the latest census figures at the time of preparation of EIA/EMP and final costs
be estimated for the same for incorporating these costs in the EMP.
17.3.2 On the basis of 20% increase over the 2001 census data, number of household
and population in above four villages is arrived at 222 and 1111 respectively.
However, considering only a small part ( less than 10%) of Chota Ghaghri
required to be shifted, number of population and house-hold for the purpose of
rehabilitation have been estimated to be 823 and 165 respectively. On the basis
of these data, rehabilitation and resettlement cost has been provided in
appendix A.8.1.
17.3.4 18.5 ha land will be provided by the project authority for resettlement colony.
The displaced families will be resettled at the site by the project authority in
consultation with the district authorities. The basic infrastructure facilities will be
provided in the resettlement colony. For economic rehabilitation of project
affected persons, facilities like financial assistance for self-employment &
vocational training will be offered.
Mining is only an intermediate use of land and a mine has to close once the
mineable mineral deposit is exhausted. It is also an imperative job for mining
company to leave the mine in a safe and stable condition eliminating all form of
risk for the community as they finally leave the mine.
Today it is accepted that mine closure requires the return of land to a viable post-
mining use, such as agriculture. It is not even sufficient to simply physically
reclaim mine lands any more as the socio- economic impact of the closure must
also be assessed. Mine closure has assumed a greater relevance of late due to
increasing environmental concern arising out of surface coal mining and is
cascading impacts in various downstream impact. Mine closure can be viewed as
rehabilitation of disturbed lands to a safe, stable and productive post mining
landform, which is suitable and/or acceptable to the community.
For the non-coal minerals, Mine closure plan has been introduced in the year
2003 through promulgation of an amendment to the MCDR (Mineral Conservation
and Development Rules)1988 under the MMDR Act 1957. For the coal sector,
preparation of Mine Closure Plan has not become a legal necessity yet. But under
the MEOF directive a chapter on Mine Closure Plan has been mandatory part of a
project Report and it has become obligatory on the part of the management.
As per the directive of MOC vide letter no. 55011-01-2009-CPAM dated 27th
August, 2009 Mine Closure Plan has got to be approved along with the Project
Report by competent authority. The Mine Closure Plan should comprise final
closure plan as well as progressive closure plan.
After the closure of the mine, the reclaimed leasehold area and any structure
thereon, which is not to be utilized by the mine owner, shall be surrendered to the
State Govt. concerned following a laid down procedure as in vogue at that point of
time
The spoil will be stacked in the external and internal dump space at the natural
angle of repose to avoid the sliding of OB bench. OB dump will be terraced at
intervals of 30m height, so that overall slope does not exceed 280 from the
horizontal.
19.1 GENERAL.
For the rated capacity of 2.0 MTY of coal, the total manpower requirement for
Simlong Opencast project has been estimated as 742 and 694 under
departmental option for shovel-dumper method of working and coal winning by
surface miner respectively. In outsourcing option the estimated requirement of
departmental manpower is 254 and 196 for shovel-dumper method of working
and coal winning by surface miner respectively.The break-up of manpower for
both the options are given below:
The CMPDI norm of manpower calculation has been used for arriving at the
manpower requirement in respect of HEMM operation and maintenance for 330
days of annual working. The year-wise manpower requirement is given in
Appendix – B. Scale/Grade/Category wise manpower strength are given in
Appendix – B.1. Services for security, canteen, rest house, colony maintenance,
biological reclamation and sanitation are proposed to be outsourced. Financial
provisions for these have been made.
19.3 PRODUCTIVITY
At the targeted production capacity of 2.0 MTY of coal with total manpower of
742 the OMS of Simlong Opencast project works out to 10.75 under
departmental option for shovel-dumper method of operation. In outsourcing
option, the required strength of departmental manpower being reduced to 254,
the OMS works out to 33.97.
For coal winning by Surface Miner, the required strength of manpower under
departmental and outsourcing option are 694 and 196 respectively. And the
corresponding OMS under the two option works out to 11.53 and 45.91
respectively.
19.4 TRAINING
For efficient, effective and safe operation of the mine, a comprehensive and
meticulous training programme for all levels of employees is imperative. The
training would be
i) On the job
ii) In the training centers of nearby opencast mines
iii) Conducted by the external agencies, including the equipment
manufacturers.
20.1 INTRODUCTION
The proposed Simlong OCP is located in an isolated area, hence, this project
has to be provided with all infrastructural facilities independently in order to
ensure its proper development. The two main phases in project construction
would be pre and post sanction activities.
5. Creating facilities for erection and commission of P&M and temporary power
supply.
6. The cost of road diversion and the cost of haul road have been taken in
appendix A.8.1.
ZERO DATE
Figure - 20.1
Sl.No. Year Advance Action C1 C2 P1 P2 P3 P4
Months from Zero Date 0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 63 66 69 72
Construction
Construction
Construction
FINANCIAL EVALUATION
21.1 GENERAL
Simlong OCP is a very small running mine. Earlier a “ Revised Feasibility Report
For Simlong Opencast Project “ was prepared by CMPDI with a targeted
production of 0.10 Mty and a capital investment of Rs. 310.27 lakh The existing
capital investment in Simlong OCP till 31.03.10 is Rs.188.73 lakh. The present
proposal is for the targeted production of 2.0 Mty (1.50 Mty after 11th year) with
an average stripping ratio of 3.55. To achieve this, two options viz. departmental
and outsourcing option has been examined. In both the options, two variants,
one with shovel/Dumper combination and the other with surface miner have also
been examined. The basic parameters considered for estimating the financial
indices are tabulated below:
Departmental Option:
PR to exploit Simlong OCP has been planned with shovel/Dumper combination
as well as deployment of Surface-miner for coal winning.
The basic parameters considered for estimating the financial indices are
tabulated below:
Additional Capital up to target year, capital investment beyond target year etc.
presented below;-
Variant-1 Variant-2
Existing Capital Rs in Crore 1.89 1.89
Additional Capital Rs in Crore 457.67 428.46
Total Capital (Crore) Rs in Crore 459.56 430.35
Capital requirement up to target year Rs in Crore 402.91 373.67
Specific investment Rs/te 2297.80 2151.74
Specific investment(P&M) Rs/te 1681.91 1544.58
( in Lakhs)
Replacement Capital
Year Variant-1 Variant-2
1
0 0
2
0 0
3
0 0
4
0 0
5
0 0
6
6 0
Job No. 102177 Chapter-21, Page-2
Project report for Simlong OCP CMPDI, RI-1
7
0 19
8
7 10
9
14 263
10
2225 1553
11
1165 916
12
5025 4898
13
3818 4656
14
7000 6824
15
1327 1576
16
1221 1476
17
2198 1742
18
2037 1334
19
1804 1574
20
1135 647
21
6700 5908
22
4174 4368
23
7030 7482
24
3287 2374
25
4527 4042
Resdual Value
-19729 -17816
Variant-1 Variant -2
Wages per te(`) 225.69 209.62
% of wages to total cost 17.89% 17.60
Variant-1 Variant-2
Particulars Rs. per te Rs. per te
Diesel 306.75 293.68
Lubrication 91.23 87.47
Repair & maintenance 71.03 68.90
Other P&M stores 7.20 3.94
Explosives 42.59 37.09
Misc stores including Dumper tyre & Tubes 23.06 21.39
Total 541.87 512.47
Specific consumption (litres/te) 7.65 7.32
c. Power Cost: The average power cost per te works out to Rs 22.79 and 13.84
per te for the two options respectively.
Selling Price:-
Grade “F”
Basic Price (Annexure-V) 870.00
Coal deterioration @5% of value 43.50
Add for sizing upto -100mm 61.00
Total in Rs per te 887.50
Profitability (profit/loss) :- The project makes loss per te at 100% works out to Rs
373.80 and Rs.303.70 for the two options respectively. And as such the
departmental option is not financially viable.
Variant-1 Variant-2
Investment Rs in Crores 117.23 90.40
Manpower No 254 196
Cost of production Rs/te 604.50 545.86
Selling Price Rs/te 887.50 887.50
Profit/loss Rs/te (+) 283.00 (+)341.64
IRR % 47.64 62.85
Cost of outsourcing (coal winning & transportation and OB Removal) works out
to Rs. 310.63 per te. and Rs.290.95 for the shovel-dumper option and surface-
miner option respectively. These estimate is based on the rates of outsourcing
job awarded (given below)in ECL. However these rates are considered for
P16-24 2-3
Transportation rate has been adjusted taking the transportation rates from “
Schedule of rates for Transportation of Coal /Sand effective from 01/04/2009 to
31/03/2011” issued by CGM( CMC) cell of ECL.
However these rates are considered for planning purposes only and have no
relation to the actual tendering process that may follow.
Different appendices viz. cost sheet, cashflow statement , sensitivity statements
etc are presented in the report.
Outsourcing option is financially viable.
CHAPTER – 22
OUTSOURCING OPTION
22.1 INTRODUCTION
CHP, required to handle 2.00 Mty of coal including primary and secondary
crushing is proposed to be installed, operated and maintained by departmental
means.
Land acquisition, village rehabilitation and environment related subjects will also
be under departmental responsibility.
In this option total excavation job have been envisaged to be outsourced. The
annual quantity of coal to produce and volume of OB to remove has been
shown in table no. 8.2 at Chapter-8.
Different lead distances for both coal and OB during different period of mine life
are shown in table no. 22.1.
REHANDLING
YEAR Lead For Re-handl. (Km) Volume (M.cum)
P12 to P19 2–3 18.00
Total 18.00
At 100% capacity, IRR comes out to be 43.80 % and 62.85% respectively for
the two variants. And specific investment works out to Rs.595.59 and
Rs.461.41per tonne for the two variants respectively.
30'
30'
A
G
AN
G
RI
VE
R
PIRPOINTI RS
KAHALGAON R.S
15' 15'
SAHIBGAN
J RS
KAHALGAON
STPS PIRPAINTI/BARAHAT
PIRTAINTI/BARAHAT
LALMATA BLOCK
RAJMAHAL RS
RAJMAHAL OCP
BORIO
UR
TINPAHAR RS
0'
A
0'
LP
AR
NT
PC
TH
MG
PA
BERHAIT R.
BARAHAT
PANJWARA
BARHARWA RS
SUN
DER
PAH 45'
45' RI
LITIPARA
DWAN
SIMLONG OCP
R
PAKUR RS
U
TO B
O DHAR HANSDIHA
DE
TO
AMRAPARA
PLATE No. 1
EASTERN COALFIELDS LTD.
JAMA P.R. FOR SIMLONG OCP ( 2 MTY )
LOCATION PLAN
DUMKA 1:4000
H ANBA
D CMPDI R 1 OCM 0 0 7 1 6 1
TO D
15' 15' 45' 15'
30'
0'
SURFACE & GEOLOGICAL
PLAN
CMPDI
N 214800
SE
TT
PO LING
ND PROPOSED CHUPERBHITA OCP LEGEND
10
1 VILLAGE
2
RCH-161
100
RL 99.64
98
96
2 ROAD
N 214400
2
3 NALA
10
ER
104
96
IV
T
102
4 PROP. QUARRY
EN
IR
6
10
M
98
NK
98 RCH-115 RCH-98
AN
BOUNDARY
BA
RL 103.83
110
EM
RL 106.57
R
M
108
100 U
D
8
106
GU
10
RCH-80
SE
104
A K 104
O
8
RL 99.63
102
R
OP
10
A
108
RCH-112
104
106
110
PR
2
H
RL 104.75
10 D 106 No.-B3
TO
4
N 214000 RCH-79 RCH-113 106 RCH-105
AD
108
8
10
RL 105.65 RL 106.78 RL 108.60
6
10
108
O 110
10
11 08
R 6 SURFACE
0
10
110
4
11
1
0
.
6
112
10
112
.D RCH-81
11
1164
8
114
W 118
CONTOUR
P.
106 12
12 0
10
RL 109.97
8
106
1242
10
116
8
0 2
11 11 4
108
08
128
RCH-110 118 10
132
6
1
SIMLONG 120
10
7 EXISTING
108 MA KALI CHB/MA/006 124
144 126
SCHOOL RL 105.80 MANDIR 128
VILLAGE 108
110
RCH-97 N.H.S RL 113.15 14
8
130
132
106
104
RL 110.29
108
N.H.S
NHS
134
136
138
WORKINGS
WE
IG 1 140
H
RCH-111 BR
ID 12 26
108 GE 13130 8 142
N 213600 2 144
104 RCH-83
106 RL 110.40 14 1 13 146
110
0 36 4
CO .-B
148
No
1
AL 3
108 RL 113.87 150
14 14 44
DE
HO
'C 8 6
P
'T 160
OT
110 112 YP KS RCH-99
E
OR
'T CO
No AL D
110 YP
E
O
FF .-B
1
EP
O
109.8 RCH-7 148 JHAPANI VILLAGE RL 137.93 180 1. ALL DIMENTIONS ARE IN METERS.
IC
E
RL 115.65 T KA 6
182
112
RL 127.37 TC 144
116 184
CA C
142
NT
116.3 O
No AL D
105.4
HA 186 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
112 EE RCH-85-B2 E PO 14
108 N 114 T
105.5 101.5 RO 14
0 188
100 108 100
102.6 AD 136 LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
RLMAGAZINE
116.08 106 134
102.11 132 130
118 HOUSE RCH-40 101.2
100.0 128
116.7 104 RCH-40A 126 18
0
EXISTING 102
100 RL 102.68 RL 103.05 97.8
12242RCH-8
1
102.0
95.5 JHAPANI VILLAGE RCH-148
17
DUMP 100
102.2
93.090.9
90.9
9*1.9 88.3
105.4
94.0 RL 116.98
0 190
200
13 136
138
91.8
TH.1.50 RL 153.42 210
140
90.5 90.8
100 Prop.
13
144
114
160
116
104.8
103 89.5 0 200
13 4
Bridge
13
86.0
142
106
104.5 118.04
2
110
210
100
108
104.8
102
88.1 85.9
12
104
10 84.5 220
106
230
8
N 213200
110 114
4
108
.
12
82.4
116
EX
106.4
87.3
240 SL. NO. NAME DRAWING NO.
6
RCH-139108.07 76.5 87.1
142 150
108.6
IST 75.7
73.7
86.0
84.9
115 140 250
IN
RL 109.39 98.8 RCH-9
110.5 84.8 73.6 JHAPANI 260 TOPOGRAPHICAL MAP
71.6 83.4 117.7
1
G
RL 123.25
RCH-39 95.0 RCH-146
13 32
72.9 99.8 270
100
WO
1
13 4
280
6
80.7 72.5 86.2 RCH-106 RL 172.86
RL 106.24 71.5
2 FLOOR CONTOUR PLANS
RK 13
8JHAPANI RL 141.04 142
20
114.27 72.4 82.5
102
IN
0
77.0
113.25 89.1 72.1
1 36
GS
SUMP
86.1
13 34
280 SEAM FOLIO PLANS
1
104 116
3
19
80.6
2
96.3
0
71.9 102.3
106 92.6 82.54 130 136
119 SUMP 90.3 RCH-10
96.1 97.4 128 138
109.5 0
18
92.6 14
142
0
108 114.9 120.52
RL 122.31
144
110.4 103.0
103
17
110 118.4 108.1
0
109.7
124 270
4
13 14 142 14
107.7 107
11
16
107.7 RCH-90 126
150
0
0
130 12
112
114 8 260
8 0
RL 127.83 13 13 RCH-11
120
116 140 8 6 BARA GHAGHARI 250
BARA GHAGHARI RCH-117
112 108 142 RL 134.72
N 212800 RCH-138 6 240
13
136 RL 146.26
116 RL 120.73 134 220
118
4
132 20
13
0 210
118
116 112 116 RCH-93 130
128 190
114 12 220
116 RL 126.56 6 180
120
120 12 RCH-87
118 114 4
1 12
11 20 2 RL 125.54 170
118 8 220
122 1
116 1 16
112 1114
114 RCH-137 11 2
0 210
4
160
15
RL 109.77
200
110 NG RCH-94
LI
TT ND
13
SE PO
12
118
0
RL 112.42
8
12 0
RCH-175 190
12
4
11
114 120
110 118
6
118 RL 161.38
116 15
114 TH.049
8 0
112 11
120 146
N 212400 110 120 BARA GHAGHARI
RCH-95
144
122
126 142
112 RL 116.55
114 146 RCH-82 150
0
120 180
14
118
142
15
116 120 144
2
RL 138.09 170
116
1
142 44
120
148
112
VILLAGE
12
122
2
126 RCH-126
112 128 124
122
120
RL 132.08
120 122
126
N 212000
11 4
12
116
6 0
12 140
122
118
126
PLATE No. 3
114
116
114
122
4
120
11
118
118
EASTERN COALFIELDS LTD.
124
6
11
122
120
RCH-86
P.R. FOR SIMLONG EXTENSION OCP ( 2 MTY)
122 RL 123.56
122 124
E 196800
12
E 195600
E 196000
E 196400
E 197200
120 128
E 197600
E 198000
E 198400
E 198800
124 118 12 6
118 132
120 4
136
122 116 140
N 211600
124126
2
12
116 12
12 4
118
12
6
120
130
134
1:4000
CMPDI R 1 OCM 0 0 7 1 6 3
N 214800
10
2
RCH-161
10
0
RL 99.64 1 QUARRY BATTER
T
EN
M
NK
98
BA
EM
EA
RT
HE
DG
4
96 EO
FQ
UA 2 HAUL ROAD
RR
Y
N 214400
5
R
D
10
WESTERN PART
SE
3 FLOOR CONTOUR
VE
15
80
PO
20
102
RI
RO
25
P
I
30 RCH-98
RCH-115
SE
AN
98 RCH-98
4 PROP. QUARRY BOUNDARY
35
3
M
45
OR
GU
RCH-80 5 EMBANKMENT
104
50
102 RL 99.63
55 RCH-112 SE -6
RL 104.75 CT 6 RIVER / NALA
RCH-79
OR 106
N 214000
PROP. RL 105.65
-5 RCH-113
RCH-113
RL 106.78
RCH-105
RCH-105
RL 108.60
108
F
RL 106.78 RL 108.60
7 FAULT. X X X
CHP
10
F
10
4
6
10
8
SE RCH-81
4'
106
CT RL 109.97 8 EARTH EDGE OF DIFFERENT SECTORS.
35
108
PROPOSED 10
8 OR RCH-110
106
RCH-110
108
106
WORK-SHOP 108
VILLAGE ROAD RCH-118
-4 CHB/MA/006 RL 115.44
RL 115.44
9 SURFACE CONTOUR
STORE SCHOOL RL 105.80
108
110
RCH-97
RL 113.15
2
104
10 DUMP BATTER
RCH-111
108
N 213600 104 RCH-83 70
106 RL 110.40
110
150
(-)
108 RL 113.87
15
'C
(-)
'T 75 160
110 YP
EAST PART RCH-99
10
112
(-)
E 170
5
'B RCH-109
0
'T +10
PROPOSED YP OF
5
110 RCH-7 RL 137.93 180
E FI 80 182
CE RL 115.65
3'
112
15
RL 127.37
184
CA
20
10
NT 186
REHABILITATION
25
11 EE RCH-85
108 2 188 1. ALL DIMENTIONS ARE IN METERS.
30
N 114
35
100102 RL 116.08 108
40
. MAGAZINE 106RCH-40 THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
2.
45
HOUSE +60
SITE
50
104 RCH-40A 18
0
EXISTING
55
102 RL 103.05
RL 102.68 RCH-8 LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
SE
60
100 RCH-148
17
55
102
DUMP RL 116.98
0 190
200
CT
70
100
TH.1.50 RL 153.42 210
108
100
114 +40 160
116
200
O
106
210
110
100
108
R-
102
220
104
106
230
110 3
N 213200 . 116
RCH-139
114
EX +30 240
RL 109.39 IS RCH-9
250 SL. NO. NAME DRAWING NO.
TI 260
1
100
RCH-39
NG
RL 123.25
EASTERN PART RCH-106
RCH-146 270
280
1 TOPOGRAPHICAL MAP
RL 106.24 RL 172.86
20
RL 141.04
102
IN
0
E SE 280
GE
2'
104
19
3 SEAM FOLIO PLANS
0
106
DA CT RCH-10 SE OL
CT OG
18
M
25
RO
OR
0
108 PROVED
RL 122.31 INDICATED
17
110 NA
O
30
0
0
LA
- 1 R-
270
IC
35
5
11
RCH-90
AL
40
0
2
10
112
114 260
45
RL 127.83 RCH-11
15
120 250
BL
50
116
20
RCH-117
55
112 108 RL 134.72
RCH-138
OC
60
240
N 212800
65
RL 146.26
70
116 RL 120.73 220
K
75
118 20
0 210
118
116 112
114
116 RCH-93 190 BO
116
120
120
RL 126.56 RCH-87 180 UN
118 114
118 RL 125.54 170 DA
116
114
122
112
RCH-137
220
RY
210
1'
160
RL 109.77
NG RCH-94 200
110 LI
TT ND
13
SE PO
12
118
0
RL 112.42
8
12
RCH-175 190
12
4
11
120 15
0
114 110 0
6
118 118 RL 161.38
116
114 TH.049
8
15
112 11
2
120 146
110 120 RCH-95
N 212400 144
122
126 142
112
120 114
RL 116.55
146 RCH-82 Proposed150 DUMP 180
0
NO-3
14
118
116 120 1Diversion
42 Road
116 RL 138.09 144 170
1
SIM
142 44
120
148
112
112 126
124
130
128
E AST
EXT
116
12
122
EN
2
126 RCH-126
112 128 124
122 SIO
120 122
120
RL 132.08
NB
N 212000 11 24
126
138 LOC PLATE No. 4
K
116
6 1
0
12
122
118
126
116
4
11
124 118
P.R. FOR SIMLONG EXTENSION OCP ( 2 MTY)
6
11
122
E 197000
E 195800
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
124
120
122
FINAL STAGE QUARRY PLAN
N 211600
124126
1:4000
CMPDI R 1 O CM 0 0 7 1 6 4
QUARRY
CROSS-SECTIONS
1-1', 2-2', 3-3' & 4-4'
CMPDI
N 214800
RCH-161
PROPOSED CHUPERBHITA OCP. 1 ISOGRAD LINE
E
F
RL 99.64
2 COAL OVERBURDEN LINE (COMPOSITE)
1:5
5 FLOOR CONTOUR
N 214400 80
6 ISOCHORE LINE 16
V
ER
16
V
IV
P
7 INDICATED & PROVED LINE
IR
I
RCH-115
AN
RCH-98
RL 106.57 RL 103.83
M
8 RIVER / NALA
GU
RCH-80
RL 99.63
RCH-112
RL 104.75
F3
9 FAULT. X X X
F3
N 214000
RCH-79 WEST PART RCH-113 RCH-105
RL 105.65
RL 106.78 RL 108.60
RCH-110
RCH-118
CHB/MA/006 RL 115.44
RL 105.80
RL 113.15
RCH-97
1 TOPOGRAPHICAL MAP
RCH-111
2 FLOOR CONTOUR PLANS
N 213600 RCH-83
RL 110.40
3 SEAM FOLIO PLANS
RL 113.87
RCH-99
RCH-109
RCH-7 RL 137.93
RL 115.65
RL 127.37
1:5
RCH-85
90
SE
10
0
D
AM
RL 116.08
RCH-40 20
0
VI
RCH-40A D
RL 102.68 RL 103.05 RCH-8
RCH-148
RL 116.98
TH.1.50 RL 153.42
1:5
90
D
2 20
V
N 213200 0
D
2
RCH-139 V
1:5
RL 109.39 RCH-9 100
RL 123.25
RCH-39 110 RCH-146
RL 106.24
EAST PART RCH-106
RL 141.04
RL 172.86
1:5
RCH-10
DA
M
RO D
RL 122.31 20
NA 0D
P
LA
90
RCH-90
RL 127.83 RCH-11
RCH-117
RL 134.72
RCH-138
10
N 212800
0
RL 146.26
RL 120.73
RCH-93 GE
RL 126.56
OL
RCH-87
OG
11
0
RL 125.54
IC
RCH-137
AL
BL
RL 109.77
LIN
G RCH-94
O CK
TT ND
SE PO A3 X
RL 112.42
RCH-175 BO
RL 161.38
UN
X TH.049
DA
N 212400 RCH-95
X
RY
RL 116.55
RCH-82 X
X A3
RL 138.09 X
RCH-102 SIMLON
G SOUT
RL 111.67
H EAST
EXTENS
ION BL
OCK
RCH-126
RL 132.08
N 212000
PLATE No. 6
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM - VI
1:4000
N 211600
CMPDI R 1 O CM 0 0 7 1 6 6
N 214800
PROPOSED CHUPERBHITA E
OCP 1 ISOGRAD LINE
RCH-161
F
RL 99.64
2 COAL OVERBURDEN LINE (COMPOSITE)
1:5
5 FLOOR CONTOUR
N 214400 80
6 ISOCHORE LINE 16
ER
V
16
V
IV
P
IR
RCH-98
MA
RL 103.83
RL 106.57
F1 RL 103.83
GU
RL 99.63
RCH-112
X F
RL 104.75
9 FAULT. X X X
F
RCH-79
N 214000 RCH-113 RCH-105
RL 105.65
RL 106.78 RL 108.60
X
1. ALL DIMENTIONS ARE IN METERS.
RCH-81 10
WEST PART 0 X 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
RL 109.97
LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
RCH-110
RCH-118
CHB/MA/006 RL 115.44
RL 105.80 X X
RL 113.15
RCH-97
RL 110.29
11
0
RCH-111 X
N 213600 RCH-83
RL 110.40
RL 113.87
X
RCH-99
1:5
RCH-109
RCH-7
10
0 RL 137.93
X
RL 115.65 X F1
SE
RL 127.37
EAST PART
AM
RCH-85
R-V
D1 70
50 D
D 20
0
D
RL 116.08 80
RCH-40
1:4
RCH-40A
90
RL 102.68 RL 103.05 RCH-8
RCH-148
RL 116.98
TH.1.50 RL 153.42
GRADE-F
GRADE-G
1:5
70
N 213200
RCH-139
RL 109.39 RCH-9
RL 123.25
80
E -G GE
RCH-39 RCH-146
AD -F OL
RCH-106 GR DE OG
RA
RL 106.24 RL 172.86
1:4
90 G IC
RL 141.04
AL
BL
P
OC
I
V
4
K
V
RCH-10 4
DA
M
10
0 BO
RO
NA RL 122.31 UN
LA
D
DA
RCH-90 20
0
RY
D
RL 127.83 RCH-11
70
RCH-117
V
RL 134.72 4
RCH-138
V
N 212800 4
RL 146.26
80
RL 120.73
60
RCH-93
90
1:5
50
RL 126.56 RCH-87 D1
50
D
E-F
RL 125.54
E-E
AD
AD
GR
10
RCH-137
GR
V
4
V
RL 109.77 4
G RCH-94
LIN
TT ND
SE PO
RL 112.42
RCH-175
RL 161.38
TH.049
V
4
N 212400 RCH-95
V
4
RL 116.55
RCH-82
RL 138.09
RCH-102 SIMLON
G SOUT
RL 111.67
H EAST
EXTENS
ION BL
OCK
RCH-126
RL 132.08
N 212000
PLATE No. 7
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM - V
1:4000
N 211600
CMPDI R 1 O CM 0 0 7 1 6 7
N 214800
E
1 ISOGRAD LINE
F
F1
X 2 COAL OVERBURDEN LINE (COMPOSITE)
RCH-161 1:5
X
RL 99.64 X
3 WORKABLE LIMIT OF THE SEAM
X
X
X X
4 DEPTHLINE OF SEAM I FLOOR
D D 150 D
X X
X
5 FLOOR CONTOUR
X 80
25
X X
N 214400 6 ISOCHORE LINE 16
V
16
V
X
X
P
ER
X
7 INDICATED & PROVED LINE
X
I
IV
X
IR
RCH-115
X
AN
RCH-98
X
8 RIVER / NALA
RL 106.57
w
X RL 103.83
M
30
TH.1.09 D
10
0
GU
RCH-80 D X
X
RL 99.63
F
9 FAULT. X X X
RCH-112 1:5 X X F
RL 104.75
X
X
RCH-79 1:4
N 214000 RCH-113 X X RCH-105
RL 105.65
RL 106.78 RL 108.60
TH.1.23
X
X
D 10
X
RCH-81 G 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
X
RA
G
RL 109.97
RA DE X
LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
1:5 DE -G
1:4
-F X
X
RCH-110
RCH-118 WEST PART X
D150
CHB/MA/006 RL 115.44 X
TH.1.05 30
RL 105.80
D
w w 35 X
RL 113.15
RCH-97
40 X
w 45 (-)1
1:5 0
RL 110.29 X
50 w (-)5
X
55
X
RCH-111 60 X
N 213600 RCH-83 65 X
RL 110.40
w X
70
RL 113.87
X
75
X
RCH-99
1:5
80
RCH-109 X
w
RCH-7 85 RL 137.93
D200D
RL 115.65 X X
90 F1
TH.0.76
RL 127.37
RCH-85
95 EAST PART
w 0
RL 116.08 5
RCH-40
RCH-40A 10
1:2
RCH-139 40
X
w
1:3 45
RL 109.39 F2 RCH-9
50
1:4
RL 123.25
RCH-39 RCH-146
RCH-106 55
RL 106.24 RL 172.86
RL 141.04
60 TH.0.48
TH.0.74 65
0
D 70
RCH-10 10 5
DA 0
D w
M
75
RO 10
RL 122.31
NA 80
LA
15
TH.1.24
RCH-90 85
20
D1
RL 127.83 RCH-11 90 50 w
G
1:4
D
RA
25
D RCH-117
RL 134.72
RCH-138 E-F
N 212800 95
30
TH.1.45 RL 146.26
RL 120.73 10
0
35
10 1:5 TH.0.99
5
40
RCH-93
45
RL 126.56
50
RCH-87
X w
F3 X
55
RL 125.54
X
60
X
RCH-137
65
X 70
RL 109.77 X
G RCH-94 X
LIN
TT ND
SE PO X
RL 112.42 w RCH-175
X
RL 161.38
1:5
D2 TH.049
X 00
D TH.1.09
N 212400 RCH-95 X
(-)1
RL 116.55 X w (-)5 0
RCH-82 X
(-)1
X
5
RL 138.09 X
X
X
X
X
RCH-102 SIMLON F3
G SOUT
RL 111.67
H EAST
EXTENS
ION BL
OC K
RCH-126
RL 132.08
N 212000
PLATE No. 8
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM III TOP
1:4000
N 211600
CMPDI R 1 O CM 0 0 7 1 6 8
N 214800
PROPOSED CHU E
RCH-161 PERBHITA OCP 1 ISOGRAD LINE
F
PR
OP
RL 99.64
OS 2 COAL OVERBURDEN LINE (COMPOSITE)
1:5
ED
PIT
3 WORKABLE LIMIT OF THE SEAM
LIM
IT
4 DEPTHLINE OF SEAM I FLOOR
D D 150 D
5 FLOOR CONTOUR
N 214400 80
6 ISOCHORE LINE 16
V
ER
16
V
IV
P
7 INDICATED & PROVED LINE
IR
I
RCH-115
AN
RCH-98
RL 106.57 RL 103.83
F1
M
X
8 RIVER / NALA
GU
RCH-80
D X
RL 99.63
RCH-112 D
20
0
D
X
RL 104.75
F
1:5 X 9 FAULT. X X X
LIN
D
F
E O
RCH-79 X
N 214000 RCH-113 RCH-105
X F1
F
RL 105.65
RL 106.78 RL 108.60
SEA
D
M
2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
RL 109.97
LIN
1:5 E LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
O
OF
PM
RCH-110 SE
E
RCH-118 AM
NT
CHB/MA/006 RL 115.44 DE
RL 105.80 V EL
RCH-97
RL 113.15
D OP
ME
NT
RL 110.29
1:5 D
RCH-111 15
0
D
N 213600 RCH-83
RL 110.40
RL 113.87
GR
1:5
AD
E-E
GR
RCH-99
A
RCH-109 D
DE
-F
RCH-7 RL 137.93
RL 115.65
D 20
RL 127.37
1:5 (-)5
0D
D 10 D
0D
RCH-85 90 D
1:5
0
5
95
10
RL 116.08 100
15
D
RCH-40
RCH-40A EAST PART
20
RL 102.68 RL 103.05 RCH-8
25
D
GR
RCH-148
30
AD
D
35
10
RL 116.98
E-E
GR
40
0D
TH.1.50 RL 153.42
AD
45
E-F
F2 D
50
1:4
1:4 55
10
5
60
N 213200
X
2m
D
65
RCH-139
X
70
F2 D
X
75
1:4
RL 109.39 RCH-9
80
RL 123.25
GE
85
RCH-39 RCH-146
90
OL
95
RCH-106 RL 172.86
RL 106.24
OG
10
0
RL 141.04
IC
1:3
AL
D
BL
D
10 OC
1:2
RCH-10 0
D
DA
M K
RO
NA RL 122.31
BO
LA UN
RCH-90 D 1:4
D
15 DA
0
D RY
(-)1
RL 127.83 RCH-11
(-)5
0
RCH-117
(-)1
RL 134.72
10
5
RCH-138
15
5
N 212800
RL 146.26
20
25
RL 120.73
95
30
1:3
35
D
10
0D
RCH-93
10
40
0
10
45
50
90
5
55
80
RL 126.56
60
RCH-87
X 65 D D
85
70
X
F3 RL 125.54
75
X
RCH-137 D 20
0D
(-)2
0
RL 109.77 X
G RCH-94
LIN 1:5
TT ND X
SE PO
RL 112.42
RCH-175
X RL 161.38
TH.049
D
N 212400 RCH-95 X
RL 116.55
RCH-82
X
(-)2
5
RL 138.09 X
X
X F3
X
RCH-102 SIMLON
G SOUTH
RL 111.67
EAST EX
TENSIO
N BLOC
K
RCH-126
RL 132.08
N 212000
PLATE No. 9
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM III BOTTOM
1:4000
N 211600
CMPDI R 1 O CM 0 0 7 1 6 9
N 214800
4 WORKABLE LIMIT
5 DEPTHLINE OF
SEAM I FLOOR D D 150 D
N 214400
6 FLOOR CONTOUR 80
R
VE
7 ISOCHORE LINE 16
RI
V
16
V
NI
RCH-115
RCH-98
P
8 INDICATED &
MA
RL 106.57 RL 103.83
I
PROVED LINE
GU
RCH-80
RL 99.63
RCH-112
9 RIVER / NALA
RL 104.75
F
10 FAULT. X X X
F
RCH-79
N 214000 RCH-113 RCH-105
RL 105.65
RL 106.78 RL 108.60
RCH-110
RCH-118
CHB/MA/006 RL 115.44
RL 105.80
RL 113.15
RCH-97
RCH-99
RCH-109
RCH-7 RL 137.93
RL 115.65
RL 127.37
EAST PART
RCH-85
V
RL 116.08
V
EXISTING QUARRY
RCH-40 +60
V
D 50
RCH-40A
65
V
RL 102.68 RL 103.05 RCH-8
D 70
V RCH-148 V V
ED
V
V
BIN
V
RL 116.98
75
M (-)2
TH.1.50 CO RL 153.42 5
II
80
AM
V
+40 P (-)2
1:4 SE TO 0
85
II 1:5
V
A M
SE D200D (-)
90
V 15
V
95
N 213200 (-)
2
X 10
F2
4
1:4
2
RCH-139 V
4
G (-)5
X
X V
10
1:4
E
0
F LIN 0
GE
V
RL 109.39 RCH-9 LIT
SP
F2
RL 123.25 5
RCH-39 RCH-146
OL
V
10
1:5
RL 106.24
RCH-106
15
RL 172.86
OG
1:5
RL 141.04
I CA
1:4
20
P
EXISTING QUARRY NO 2
LB
1:3
I
D 4
GRAD
10
V
1:2
GRAD
25
0 4
D 30
LO
V
RCH-10
DA
CK
E-G
E-F
M
35
RO
RL 122.31
NA
40
LA D1
50
BO
45
D
U
1:4
RCH-90
ND
50
RL 127.83 RCH-11
E-G AR
55
GRAD (-)4
E-F RCH-117
Y
60
RL 134.72 0
1:5
RCH-138 GRAD
P
(-)3
D 20
N 212800
GR ADE
SE
5
65
I
RL 146.26
AM
1:3
GR
AD
V
70
V
0D
II
RL 120.73 (-)3
2
75
TO
E-G
0
2
80
1:1
85
-F
(-)2
90
5
RCH-93
95
(-)2
1:3
0
10
10
(-)1
5
RL 126.56 RCH-87
25
D 5
50 X 30 (-)1
D X
11
X 0
0
X
RL 125.54
35
X
X X (-)5
X
P
0
F3
X
RCH-137
I
X
X 5
RL 109.77
X 10
G RCH-94
LIN X
15 1:5
TT ND
SE PO
RL 112.42
X 20
X 1:5 RCH-175
X RL 161.38
TH.049
X
RCH-95 X
(-)5
N 212400
0
X
(-)4
5
RL 116.55 X
RCH-82 X
X
RL 138.09 X
X
X
(-)5
X
X
5
X X X
RCH-102 SIMLON F3
G SOU
RL 111.67
TH EAS
T EXTE
NSION
BLOCK
RCH-126
RL 132.08
N 212000
PLATE No. 10
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM II TOP
1:4000
N 211600
CMPDI R 1 O CM 0 0 7 1 7 0
N 214800
1 PROP. SURFACE
F1
PROPOSED CHUPERBHITA OCP EDGE OF QUARRY
RCH-161
RCH-161 X
E
X 2 ISOGRAD LINE
RL 99.64 X F
E
X X 3 COAL OVERBURDEN 1:5
LIN
IER
RR X X
BA
m
4 WORKABLE LIMIT
30
60
X X
35
40
X X
5 DEPTHLINE OF
V
1:5 8
SEAM I FLOOR
V
1:4 D D 150 D
8
25 X X
45
N 214400
1:5
50 X X
6 FLOOR CONTOUR 80
1:5
X X
R
55
GR
VE
X X
60
GR AD
AD E-G X 7 ISOCHORE LINE 16
V
RI
65 E-F X
16
V
V
V X
1:3
8
I
1:4
70 RCH-115 X
P
AN
D X RCH-98
10
75 8
0
D 8 INDICATED &
V
RL 106.57
I
1:3
RL 103.83
X X
PROVED LINE
M
30
V
8
GU
RCH-80 35 X
1:3
1:5 1:4 X
RL 99.63
40
X
X 9 RIVER / NALA
RCH-112
45 1:5 X
RL 104.75
V
V
X F
D
50 X
10 FAULT. X X X
8
50 V
8
D 55 F
V X X
8
RCH-79
8
V
N 214000 60 RCH-113 RCH-105
1:3
V
RL 105.65 8 X
1:4
65 RL 106.78 RL 108.60
1:4
X
X
70
80 75 X 1. ALL DIMENTIONS ARE IN METERS.
X
RCH-81
2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
V
X
1:5 RL 109.97 10 X
1:5 LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
V
10 X
X
RCH-110
GR ADE
X
GR
RCH-118
AD -G
CHB/MA/006 X
WEST PART
E-F
RL 115.44
RL 105.80 X
RL 113.15
RCH-97 X
(-)1 X
0 SL. NO. NAME DRAWING NO.
RL 110.29 X X
1:3
(-)5
1:5
D1 TOPOGRAPHICAL MAP
0
5 1
0D
GRAD
X
GRAD
X
RCH-111 D 10
SE
5
0D 2 FLOOR CONTOUR PLANS
X
AM
E-G
G
E-F
II
RL 110.40 X
CO
R
1:3
AD
R
BIN
RL 113.87 X
E-
AD
85
ED
X
F
20
E-
F1
D200D
G
90 25 RCH-99
1:5
GRADE-F
GRADE-G
1:3
RCH-109
30
RCH-7 35
RL 137.93
RL 115.65
40
RL 127.37
1:5 45
RCH-85 1:5
50
V
(-)3
RL 116.08
QUARRY-1 55 5
RCH-40 +60
1:4
RCH-40A 60
V
V V
V
RL 116.98 70 (-)30
TH.1.50 7 RL 153.42
5 (-)25
ED
80 BIN
V
OM (-)20
85 F2 II C T.
X
AM OT (-)15
II B
1:4
90 SE M
N 213200 A
X SE (-)10
V
RCH-139
(-)5
V
X
RL 109.39 RCH-9 0
RCH-39 X RL 123.25
V
5
RCH-146 GE
F2
QUARRY-2
RCH-106 RL 172.86
OL
RL 106.24
RL 141.04
10 OG
15 I CA
EAST PART 20
LB
DA
M
RCH-10
25 LO
RO
NA RL 122.31
30
CK
L A
RCH-90 35
BO
UN
RL 127.83 RCH-11 40
DA
(-)3
RY
SE
RCH-117
5
(-)3
RL 134.72 45
AM
RCH-138 0
(-)2
II
N 212800
TO
5
50
SE
(-)2
RL 146.26
P
AM
0
RL 120.73 65
(-)1
55
II B
5
70
OTT
75 60 (-)1
.
80 0
RCH-93 (-)5
85
90 (-)4
0
RL 126.56 RCH-87
95
0
10 X
0 X
X
5
RL 125.54
X X 10
F3 (-)4
RCH-137 X 5
15
X
RL 109.77
X 20
G RCH-94 (-)5
LIN X
0
TT ND
SE PO
RL 112.42 X RCH-175
(-)5
X RL 161.38 5
TH.049
X
N 212400 RCH-95 X
RL 116.55 X
RCH-82
X
RL 138.09 X
(-)6
X
0
X
X
SIMLON X
X
F3
RCH-102
G SOU
RL 111.67
TH EAS
T EXTE
NSION
BLOCK
RCH-126
RL 132.08
N 212000
PLATE No. 11
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM II COMB. & BOTT.
1:4000
N 211600
CMPDI R 1 O CM 0 0 7 1 7 1
N 214800
PROPOSED CHU
F1
PERBHIT A OCP
E
1 ISOGRAD LINE
RCH-161
X F
X
RL 99.64
2 COAL OVERBURDEN LINE (COMPOSITE)
1:5
X X
PR
LIN
E
GR
O PO
IER A SE 3 WORKABLE LIMIT OF THE SEAM
RR GR DE X
m
BA AD -D 1:5 X D
50 E-E PIT
20 X
LIM 4 DEPTHLINE OF SEAM I FLOOR
X IT D D 150 D
1:5
25 5 FLOOR CONTOUR
N 214400 X X 80
1:4
30
6 ISOCHORE LINE 16
G
ER
V
X
RA
35 X 16
V
G
DE
RA
-E
IV
DE
40 P
-F
IR
1:3 X
45 X
RCH-115
AN
RCH-98
1:3
1:4
50
RL 106.57 RL 103.83
M
D 50 2
V
D X X
55 2 D
1:5
1:3
8 RIVER / NALA
GU
RCH-80 10
V
1:4 0 D
D 50 D
RL 99.63 60 X
RCH-112 1:5
1:3
X
RL 104.75
F
1:4 65 X X
9 FAULT. X
70 F
E-E
D
50
E-F
1:5
AD
D RCH-79 1:4 X
AD
GR
RL 105.65 1:4
1:5
RL 106.78 RL 108.60
W
W
X
F
G
W
X 1. ALL DIMENTIONS ARE IN METERS.
1:4 RCH-81
2
2
W
V V X 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
RL 109.97
1:3
W
RCH-110
RCH-118
CHB/MA/006 RL 115.44
RL 105.80
W
RL 113.15
RCH-97
WEST PART
RL 110.29
W
RCH-111
N 213600 RCH-83
RL 110.40
RL 113.87
RCH-99
RCH-109
RCH-7 RL 137.93
RL 115.65
RL 127.37
RCH-85
NT
ME
RL 116.08
OP
RCH-40
EL
RCH-40A
V
DE
RL 116.98
OF
TH.1.50 RL 153.42
E
LIN
N 213200
RCH-139
RL 109.39 RCH-9
RL 123.25
EAST PART
RCH-39 RCH-146 GE
OL
RCH-106 OG
RL 106.24 RL 172.86 IC
AL
RL 141.04 BL
OC
K
BO
UN
DA
RY
RCH-10
DA
M
RO
RL 122.31
NA
LA
RCH-90
RL 127.83 RCH-11
RCH-117
RL 134.72
RCH-138
N 212800
RL 146.26
RL 120.73
RCH-93
RL 126.56 RCH-87
RL 125.54
RCH-137
RL 109.77
G RCH-94
LIN
TT ND
SE PO
RL 112.42
RCH-175
RL 161.38
TH.049
N 212400 RCH-95
RL 116.55
RCH-82
RL 138.09
RCH-102 SIMLON
G SOUT
RL 111.67
H EAST
EXTENS
ION BL
OCK
RCH-126
RL 132.08
N 212000
PLATE No. 12
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM - L 2
1:4000
N 211600
CMPDI R 1 OCM 0 0 7 1 7 2
N 214800
N 214400 X
2
V 1:5 5
6 FLOOR CONTOUR
2
80
R
X
V
10
VE
X
15
-E
20
7 ISOCHORE LINE
E
16
RI
V
AD
E-F
1:4 25
X
65m 16
V
GR
AD
X
NI
30
GR
RCH-115
1:3 35
P
10
8 INDICATED &
MA
RL 106.57 0 X RL 103.83
40
I
X PROVED LINE
1:3
45
GU
RCH-80
1:4
1:5 50 50
V
X
RL 99.63
9 RIVER / NALA
E-F
55 RCH-112 X
1:5
4
E-G
GRAD
60 RL 104.75 V V
F
X
ABLE
GRAD
10 FAULT.
V
X
GRADE-G
WORK X X
GRADE-F
65 NOT F
X
RCH-79 BLE
WORKA
V
75 RL 105.65
OM RL 106.78 RL 108.60
TT
1:4 I BO X
V
85 80
E-F
E-E
SEAM-I I MIDDLE
50
TOP X 35m
GRAD
X
V
8 THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
V
SEAM-I 2.
BOTT. RL 109.97
35
1:3 X
100
E-E
V
V
RCH-110 AD
E
V X
GR
KABL
4
4
RCH-118
E-F
E
KABL
CHB/MA/006 X
RL 115.44 AD T
WOR
RL 105.80 GR AR
TP
V
V
WOR
RL 113.15
D15
RCH-97
P
ES
NOT
X
I TO
0D
W DRAWING NO.
V OM
D
INE
IB
TOPOGRAPHICAL MAP
T 1
(-)4
55 X
(-)4
MB
R
PA
0
(-)3
(-)5
RCH-111
IC
V
5
ST
0
1:3
(-)3
X 2 FLOOR CONTOUR PLANS
0
EA
70
(-)2
V
N 213600 RCH-83 10
1:5
V
1:5
5
RL 110.40
(-)2
1:5
0
IB
(-)1
RL 113.87 F1
OT
5
T
V
75 OM
(-)1
RCH-99
0
10
(-)5
V
10
10
1:4
RCH-109
0
V
V 0
5
200
RCH-7 RL 137.93
V
10
RL 115.65 80
15
-F
RL 127.37 DE
20
(-)6
GR
V
25
(-)5
5
RCH-85 1:5
E-G
(-)6
(-)7
5
30
AD 0
0
GR
35
D 1:4
50
E-G
40
D
AD
RL 116.08
45
RCH-40
RCH-40A
+60 GR -F
DE
50
55
A
RL 103.05 GR
12
RL 102.68 RCH-8
12
60
V RCH-148
55
RL 116.98 V
70
SE
TH.1.50 RL 153.42
75
(-)6
AM
+40 F2 5
-I
80
CO
E-F 0
X
GRAD
.
N 213200 (-)5
+30 5
RCH-139 E-E (-)5
GRAD 0
X
(-)4
5
14
16
V
85
0
RL 123.25
GE
16
V
RCH-39 V (-)3 RCH-146
1:3 V 5
OL
X
RL 106.24 0
OG
ADE
F
X
20
RL 141.04 (-)2
ADE-
5
IC
20
V
GR
F2 QUARRY No. 2
V (-)2
A
GR
18
0
18
1:2
RCH-10
D
10 V
V (-)1
5
P
LB
DA
M
0
D
(-)1
0 I LO
25
RO (-)5 GR
NA RL 122.31 AD CK
30
LA E-F
0
1:4 GR
AD BO
35
RCH-90 E-G
40
UN
10
D
15
45
RCH-11 0D
DA
15
RL 127.83
GR
50
GR
A
20
RCH-117
55
RY
DE
RL 134.72
AD
RCH-138
60
D 20
-E
N 212800
65
E-F
RL 146.26
16
D
0D
70
QU
50
RL 120.73
V
(-)7
75
AR
16
D
5 (-)8
V
RY
(-)7 5
1:1
85
0
No
80
RCH-93 (-)6
.2
5
(-)6
A
(-)5 0
RL 126.56
1:5
RCH-87 5
(-)5
(-)4 0
RL 125.54 5
X (-)4
X 0
X (-)3
RCH-137 5
X X (-)3
0
F3 RL 109.77
G RCH-94 X
LIN (-)2
TT ND
SE PO 5
RL 112.42 (-)2 1:5
X 0 RCH-175
RL 161.38
X
TH.049
N 212400 RCH-95
X
RL 116.55
RCH-82
X
RL 138.09
X
X
X
RCH-102 SIMLON X X F3
G SOU
RL 111.67
TH EAS
T EXTEN
SION B
LOCK
RCH-126
RL 132.08
N 212000
PLATE No. 13
E 196200
E 196600
E 197400
E 197800
E 198200
E 195400
E 198600
E 199000
E 199400
SEAM I
1:4000
N 211600
CMPDI R 1 OCM 0 0 7 1 7 3
N 214800
SE 1 ROAD
TT
L ING
TA
NK PROPOSED CHUPERBHITA OCP
10
2
RCH-161
LE N
10
0
A
RL 99.64
T
EN
+130
SE
M
NK 98
HO
BA
2 RIVER / NALA
LD
EM
96
B OU
N 214400
+160
ND
AR
PRO
Y P.
NG
POS 3 PROPOSED BUILDUP
ER
O
ED
+1
DI
ED D
PR CHP
35
SI
96
AREA
OS
+130 UMP
AY
13 M
IV
NO-1
W
OP
. Cum 102
IL
IR
RA
PR
TO
98
AN
RCH-98
+165
100
4 PROPOSED EMBANKMENT
GU
RCH-80
104
102 RL 99.63
RCH-112 10
+135
2
RL 104.75 +135
10 106
4
RCH-79 DUMP
RCH-105 NO-3
N 214000 RCH-113
PROP. 108
8
5 O.B. DUMP
10
RL 105.65
PRO+165
6
AD RL 106.78
10
RL 108.60 110
CHP RO
10
POS
11 08
0
10
4
11
1
0
PW ED D
6
10
UMP
8
RCH-81
106 124
NO-2
10
RL 109.97
106
8
6 SURFACE CONTOUR 188
10
8
0 2
108 11 11 128 5 M. +165
PROPOSED 108 10
8 132
Cum
106
RCH-110
136
VILLAGE ROAD RCH-118 110 112
WORK-SHOP
108 CHB/MA/006 140
144 RL 115.44
(-)5
STORE 108
SCHOOL
110
RL 105.80
RCH-97
RL 113.15 148 130
132 134 7 FLOOR CONTOUR
+135
126 128
106
OFFICE
RL 110.29
108 124
Ge
+1
104
30
+1
olo
+125
20
+115
RCH-111
8 QUARRY BATTER
+1
00
+95
108
104 RCH-83
+70
gic
+7
N 213600 +45
5
106 RL 110.40
+5
110
0
+3
+25
al
+5
(-)
0
(-)
108 RL 113.87 +5
150
15
9 LEASEHOLD BOUNDARY
15
'C +115
'T 160
Blo
(-)
YP
10
110 112 RCH-99
(-)
E +95 170
RCH-109
5
'B
ck
0
'T +10
PROPOSED 110 YP O
E FF
RCH-7 RL 137.93 180
I CE RL 115.65 +80
EAST PART 182
112 +55
Bo
15
116 RL 127.37
184
CA
10
un
NT 186
REHABILITATION 112
5
EE RCH-85 +85
108 N 114 188
1. ALL DIMENTIONS ARE IN METERS.
100 RL 116.08
RLMAGAZINE
116.08 106
108 (-)5
da
55
.
SITE 110HOUSE 104
RCH-40
RCH-40A
+60
18
ry 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
50
EX 102 +55 0
IST
65
ING RL 103.05 RCH-8
DU 100 RL 102.68
60
MP RCH-148
17 190
102 100 RL 116.98 +45 0
200
LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
TH.1.50 RL 153.42 210
100
114
160
+1
+40
116
200
40
+1
106
25
210
+1
110
100
108
15
102
+9
0
220
104
10
+6
106
230
5
110
+4
108
0
N 213200
116
+1
+30 +40 240
5
RCH-139
+0
114
+95 250
RL 109.39 RCH-9
+75 260
RL 123.25
RCH-39 RCH-146 270
100 SL. NO. NAME DRAWING NO.
RCH-106 280
RL 106.24 RL 172.86
+105 RL 141.04
20
102 TOPOGRAPHICAL MAP
1
0
+150
104 +130 280
19
+45
0
106 RCH-10 2 FLOOR CONTOUR PLANS
18
0
108 RL 122.31
17
110 SEAM FOLIO PLANS
3
0
+1
50
270
+1
25
11
+1
RCH-90 10
0
+8
5
112
114
+6
0 260
120 RL 127.83 RCH-11 +4
0
250
116 +1
5 RCH-117
112 108 RL 134.72
RCH-138 +35 240
N 212800
RL 146.26
+160
116 RL 120.73 220
118 +45
20
0 210
118
116 112 116 RCH-93 +80
190
114 +75
+130
116 220
120 RL 126.56 RCH-87 180
120
118 114
RL 125.54 +75 170
118 220
122
116 1
112 1 14 +80
114 RCH-137 1112 210
0 +105 +75
RL 109.77
160
200
110 NG RCH-94
LI
TT ND
13
SE PO
12
+85
118
0
RL 112.42 +105
8
12
+120 RCH-175 190
12
4
11
120
0
114 110
6
118 118 RL 161.38
116
114 TH.049
8
120 112 11
110 120 146
RCH-95
N 212400 144
122
126 142
112
120 114
RL 116.55
T.3.39 146 RCH-82 150 DUMP 180
0
NO-3
14
118
116 120 142
RL 138.09 144 170
116
1 200
142 44
120
148
112
114 126
110 144 138 140
136 6 M. C 215 160
122 128
118 112
114
RCH-102
136
134
134
170 um
RL 111.67 140 2
T.5.47 13
120 118
116
130 140
114 132
128 190
130
112 126
124 128
Proposed
116
12
126 RCH-126
112 128 124
122
120
N 212000 11
120
126
122 12
2 RL 132.08
PLATE No. 16
4
12
116
6
0
12
118
126
116
114
4
11
124 118
P.R. FOR SIMLONG EXTENSION OCP ( 2 MTY)
6
11
122
124
120
122
118
STAGE END FOR EAST PART
116
N 211600 124126
1:4000
CMPDI
E 196800
E 195600
E 196000
E 196400
E 197200
E 198000
E 198400
E 197600
R 1 O CM 0 0 7 1 7 6
N 214800
SE
RCH-161
1 GARLAND DRAIN
RL 99.64
T
EN
KM
N
BA
EM
PR
OP
OS
ED
GA
RL
2 RIVER / NALA
AN
D
DR
AI
N
N 214400
R
ED
E
OS
IV
OP
3 QUARRY EDGE
IR
PR
RL 103.83
RL 106.57
M
GU
RCH-80
P.
RL 99.63
RCH-112
RL 104.75
4 PROPOSED BUILDUP
AREA
O
PR CHP
N 214000 RCH-79 RCH-113 RCH-105
CHP
5 PROPOSED EMBANKMENT
RCH-81
AREA
RL 109.97
PROPOSED RCH-110
WORK-SHOP
VILLAGE ROAD RCH-118
CHB/MA/006 RL 115.44 5 DIRVERSION OF ROAD
STORE RL 105.80
RCH-97
RL 113.15
RL 110.29
OFFICE
RCH-111
N 213600
RCH-83
RL 110.40
RL 113.87
PROPOSED RL 115.65
RCH-7 RL 137.93 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
RL 109.39 RCH-9
RL 123.25 2 FLOOR CONTOUR PLANS
RCH-39 RCH-146
RCH-106 RL 172.86
RL 106.24
3 SEAM FOLIO PLANS
RL 141.04
RCH-10
RL 122.31
RCH-90
RL 127.83 RCH-11
RL 134.72
RCH-117
N 212800 RCH-138
RL 146.26
RL 120.73
RCH-93
RL 126.56 RCH-87
RL 125.54
RCH-137
RL 109.77
NG RCH-94
LI
ETT ND
S PO
RL 112.42
RCH-175
RL 161.38
TH.049
N 212400 RCH-95
RL 116.55
RCH-82 Proposed DUMP
RL 138.09
Diversion Road NO-3
RCH-102
RL 111.67
RCH-126
RL 132.08
N 212000
PLATE No. 17
PLAN SHOWING
INFRASTRUCTURE
1:4000
CMPDI
E 196800
E 195600
E 196000
E 196400
E 197200
E 197600
E 198000
E 198400
E 198800
R 1 O CM 0 0 7 1 7 7
1 FOREST LAND
N 214800
LIM
EM
IT
PR
O PO
SE
N 214400
D 3 RIVER / NALA / DRAIN
LE
AS
EH PR
R
OP
D
OL
VE
OS
E
D
OS
BO ED
RI
OP
UN GA
WEST PART
PR
D AR RL
I
RCH-115 RCH-98
Y A ND
AN
RL 103.83
DR DUMP
RL 106.57
NO-3
M
AI 4 EXTERNAL O B DUMP
N
GU
RCH-80
RL 99.63
RCH-112
RL 104.75
CHP
AK
PU
R 5 VILLAGE
RCH-81
AR
DH
TO
D RL 109.97
OA
.R
.D
P.
W
HOSPITAL
RCH-110 JHAPANI
SIMLONG VILLAGE ROAD RCH-118
MA KALI CHB/MA/006 RL 115.44
6 PROPOSED EMBANKMENT
N.H.S RL 113.15
RCH-97
N.H.S
OFFICE
RL 110.29
WE
NHS
AREA
IG
H
RCH-111 BR
ID
GE
N 213600
PROPOSED RL 110.40
RCH-83
CO .-B
No
AL 3
WORK-SHOP RL 113.87
P
DE
HO
'C
GE
P
'T
OT
STORE
KS
YP RCH-99
E
O 7 EXISTING BUILDUP AREA N.H.S
OR
'B RCH-109
LO HOSPITAL
W
JHAPAN
'T CO
PROPOSED YP O No AL
.-B DE RCH-7 RL 137.93
E FF
IC RL 115.65 1 PO
T I VILLA GI
CA
NT
E
CO
No AL D
KA
RL 127.37
TC GE C AL
REHABILITATION
HA
EE RCH-85-B2 EPOT RO
N AD
BL
RLMAGAZINE
116.08
HOUSE RCH-40
EAST PART OC
K
SITE RCH-40A
EXISTING DUMP
RL 102.68 RL 103.05 RCH-8
JHAPAN BO
I VILLA
RCH-148
UN 8 PROPOSED PIT LIMIT
RL 116.98
TH.1.50 GE RL 153.42 DA BHEHA
RY RA VIL
LAGE
N 213200
RCH-139
9 LEASE HOLED BOUNDARY
RL 109.39 RCH-9
JHAPAN
RCH-39
RL 123.25
I RCH-146
RCH-106
JHAPAN
RL 106.24 RL 172.86
I RL 141.04
EXISTING OCP
RCH-10
RL 122.31
1. ALL DIMENTIONS ARE IN METERS.
BARA G
RCH-90
HAGHA
RL 127.83 RI
RCH-11 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
BARA G RCH-117
N 212800 RCH-138
RL 134.72
HAGH ARI LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
RL 146.26
RL 120.73
RCH-93
Ex
RL 126.56 RCH-87 is
tin
g
RL 125.54 vi
lla
ge
RCH-137 Ro
RL 109.77
ad
NG RCH-94
LI
TT ND
SE PO
RL 112.42
RCH-175
RL 161.38
TH.049
RL 132.08
N 212000
CHHOT
A GHAG
VILLAG HARI
E
CHHOT
A GHA
VILLAG GHARI
RCH-86
N 211600
EASTERN COALFIELDS LTD.
P.R. FOR SIMLONG EXTENSION OCP ( 2 MTY) 102177
E 196000
E 196400
E 197200
E 197600
E 198000
E 198400
E 199200
E 198800
R 1 OCM 0 0 7 1 7 8
PROPOSED CHUPERBHITA OCP
N 214800
1 ROAD
10
2
RCH-161
100
RL 99.64
+130 2 RIVER / NALA
98
96
N 214400
+160 3 PROPOSED BUILDUP
O P.
DUMP AREA
PR P
NO-1 CH
G
IN
D
R
96 +135
SI
+130
VE
AY
VOLU
W
ME 13 102
IL
RI
RA
T
Mcum
EN
TO
RCH-98
M
98 RCH-115
NI
RL 103.83
WE
MA
RL 106.57
EM
100
ST
RCH-80
ED
GU
104
OS
102 RL 99.63
OP
PA +135
108
RCH-112
104
10
106
PR
2
5 O.B. DUMP
RL 104.75
RT
10
4
+135
106
8
10
RL 105.65 RL 106.78 RL 108.60
+165
6
AD
10
CHP
10
RO
11 08
+40
6 QUARRY BATER
0
10
4
11
DUMP
1
0
PW
6
10
VOLU NO-2
8
RCH-81
ME 5
106
Mcum
10
RL 109.97
106
8
10
8
0 2 +165
11 11 128
108
PROPOSED 10
8 13
RCH-110
4
106
108 1362 18
RCH-118 110 112
VILLAGE WORK-SHOP 108 CHB/MA/006 140 RL 115.44 7 SURFACE CONTOUR
144
STORE 108
110
RL 105.80
RCH-97
RL 113.15 148 130
132 134
+135 136
106 RL 110.29 138
140
OFFICE
146
104 108
14
13 132
4
130 128 126
+125
8 VILLAGE
14 4 136 140
8 +115
RCH-111 142
+95
108 +70
144
N 213600 104 RCH-83 +45 146
106 RL 110.40
+
110
14
+25
+110 148
0
108 RL 113.87 +15
150
+115
160
110 112 RCH-99
RCH-109 +95 170
0
PROPOSED 110
RL 115.65 +80
RCH-7
+10
RL 137.93 180
182
1. ALL DIMENTIONS ARE IN METERS.
112 +55 +60
116 184
15
RL 127.37
10
186 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
REHABILITATION
5
112 RCH-85 +85
108 114 188
100102 108
(-
)5 LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
RL 116.08 106
55
. 110 RCH-40 +30
SITE 106 104 RCH-40A
+60
18
50
0
EXISTING 102 +55 +15
65
RL 102.68 RL 103.05 RCH-8
100
60
RCH-148
17
102
DUMP RL 116.98
0 190
200
TH.1.50 RL 153.42 210
100 100
20
114
+40 160
+
200
116
11
+
106
0
210
12
110
100
108
30
102
DRAWING NO.
5
+45 SL. NO. NAME
220
104
230
110
108
N 213200 .
116
+30 240
0
RCH-139
40
1 TOPOGRAPHICAL MAP
114
+95 250
RL 109.39 RCH-9
+75 260
RL 123.25 FLOOR CONTOUR PLANS
RCH-39 RCH-146 270 2
5
100
+
14
280
0
RCH-106 RL 172.86
RL 106.24
3 SEAM FOLIO PLANS
+100 RL 141.04
20
102
0
+150
104 +130 280
19
+45
0
+
12
106
+
RCH-10
5
11
0
18
0
108
+
RL 122.31
17
110
45
0
60
270
+
30
+
15
RCH-90
+
15
11
0
0
112
114 260
120 RL 127.83 RCH-11
250
116
RCH-117
112 108 RL 134.72
Ge
10
RCH-138 240
N 212800
116 +160
RL 146.26 olo
118
RL 120.73
20
220
gic
+
0
al
35
210
118
116 112 116 RCH-93 190 Bl
114 +130
+70
220 oc
116
120 RL 126.56 RCH-87 180 k
120
118 114 +15 Bo
118 RL 125.54 170 un
116
122 220
da
112 1
1112 ry
+85
114 RCH-137
+40
0 210
160
RL 109.77
200
110 RCH-94 +60
+85
13
12
118
0
RL 112.42 +105
8
12
+120 RCH-175 190
12
4
11
120
0
114 110
6
118 118 RL 161.38
116
114 TH.049
8
112 11
120 146
110 120 RCH-95
N 212400 144
122
126 142
112
120 114
RL 116.55
T.3.39 146 RCH-82 150 DUMP 180
0
NO-3
14
118
116 120 142
RL 138.09 144 170
116
1
142 44
120
148
112
114 126
110 144 138 140 VOLU
112 RCH-102
136
ME 6 160
122 128
118 114
RL 111.67 140
136
134
134
Mcum
2
T.5.47 13
120 118
116
130 140
114 132
128
130
112 126
124 128
CHHOTA GHAGHARI
116
12
122
2
112 128
126
124
RCH-126 VILLAGE
122
120
126
122
120
RL 132.08 PLATE No. 19
N 212000 11 4
12
116
6
0
126
114
116
114
124 118
6
11
122
124
120
118 10th YEAR STAGE PLAN
122
N 211600 124126
1:4000
CMPDI
E 196800
E 195600
E 196000
E 196400
E 197200
E 197600
E 198000
E 198400
R 1 OCM 007 1 9 9
N 214800
SE
TT
1 PROP.DIVERSION OF ROAD
LIN
TA G
NK
10
2
RCH-161
10
0
+102
T
RL 99.64
EN
M
+100
NK 98
BA
2 PROP.DIVERSION OF NALA
EM
96
+98
+130 +125
N 214400 +95
+60
+75 +90
3 PROPOSED BUILDUP P .
ER
O
D
PR CHP
SE
+65 +35
AREA
O
IV
OP
102
IR
PR
+130 +130
+35
AN
+99 +10
0
M
+8
+60
0
4 PROPOSED EMBANKMENT
GU
+35
+1
5
104
+100
102
+95 +95
106
DUMP
N 214000 RCH-105 NO-3
(-)
+9
0
15
RL 108.60
+6
CHP
10
5
10
4
+4
+2
0
6
0
10
+5
8
(-)
+65
15
+50
188
35
+35 6 SURFACE CONTOUR
(-)
PROPOSED
30
8
10
106
+80
(-)
108 +110
(-)
25
VILLAGE ROAD RCH-118
5
WORK-SHOP 25
(-)
108
20
RL 115.44
(-)
(-)5
(-)
STORE RL 105.80
15
SCHOOL
110
7 FLOOR CONTOUR
15
+5
15
(-)
+3
0
10
108
+140
(-)
5
106
OFFICE 5
+5
0
+1
104
3
+5
0
+1
0
20
+20
8 QUARRY BATTER
+1
+7
00
5
108
N 213600 104 +50
106
110
108 +80
'C
'T +140
+8
0 +110 9 LEASEHOLD BOUNDARY
110 112 YP RCH-99
E 170
'B
'T
PROPOSED 110 YP O
E FF
IC
RCH-7 +140 RL 137.93 180
182
112 E
RL 127.37
+11 184
CA 0
NT 186
REHABILITATION 11
108 2
EE
N
RCH-85
114
+165
188
1. ALL DIMENTIONS ARE IN METERS.
100 102 RL 116.08 108
RLMAGAZINE
116.08 106
110 HOUSE RCH-40
SITE EX
IST
ING
104
102
RCH-40A
RL 103.05
18
0 2. THIS PLAN HAS BEEN MADE TENTATIVELY AND SUBJECT TO CHANGE TO SUIT
DU 106 100 RL 102.68 RCH-8 +165
MP RCH-148
17 190
102 100 RL 116.98
0
200
LOCAL SITE CONDITION AND ACTUAL ESTIMATION.
TH.1.50 RL 153.42 210
114
160
116
200
106
210
110
100
108
102
220
104
230
110
108
N 213200
116
240
RCH-139
114
250
+1
RL 109.39
+170
40
RCH-9
260
RL 123.25
RCH-39 RCH-146 270
SL. NO. NAME DRAWING NO.
RCH-106 280
RL 106.24 RL 172.86
+165 +160
RL 141.04
20
1 TOPOGRAPHICAL MAP
0
104
19
0
106 RCH-10 2 FLOOR CONTOUR PLANS
DA
18
M
RO
0
RL 122.31
17
NA SEAM FOLIO PLANS
3
0
LA
RCH-90
+170 +165
120 RL 127.83 RCH-11
116
RCH-117
112 108 RL 134.72
RCH-138 +165
N 212800
RL 146.26
116 RL 120.73
118 20
0 210
116 RCH-93 190
13
SE PO
12
118
0
RL 112.42
8
12
RCH-175
12
4
11
120
0
6
118 RL 161.38
116
114 TH.049
8
112 11
110 120 146
RCH-95
N 212400 144
142
RL 116.55
T.3.39 146 RCH-82 150 EXT
0
ERN
14
142
RL 138.09 144
AL D
UMP
RCH-102
RL 111.67
T.5.47
Proposed
RCH-126
Diversion Road
N 212000
RL 132.08
PLATE No. 20
1:4000
CMPDI
E 196800
E 195600
E 196000
E 196400
E 197200
E 198000
E 198400
E 197600
R 1 O CM 0 0 7 2 0 0