Professional Documents
Culture Documents
The project should not be undertaken because the NPV is negative. This implies that the present value
of the benefits is less than that of costs. The project has more cost than benefits therefore it is not
economically viable to undertake such a project.
1|Page
Question 2
1. Inflation is not considered
year 1 2 3 4 5 6
Net of 40000 40000 40000 40000 40000 40000
PV Factor 0.909 0.826 0.751 0.683 0.621 0.564
PV 36360 33040 30040 27320 24840 22560
Total Present value 174160
Initial Investment -72000
NPV K102,160
2. Inflation considered
year 1 2 3 4 5 6
Net of 40000 40000 40000 40000 40000 40000
PV Factor 0.954 0.910 0.869 0.829 0.791 0.755
PV 38160 36400 34760 33160 31640 30200
Total PV 204320
Initial Investment -72000
NPV K132 320
2|Page