You are on page 1of 54

EMPLOYER CONSULTANT

JSC "TOSHKENT ISSIQLIKELEKTRMARKAZI

CONTRACTOR
ENGINEERING SUBCON.

ÇALIK ENERJİ SAN.VE TİC. A. Ş

PROJECT

Construction of Two Gas Turbine Units (GTU) with a capacity of 32 MW each


at Tashkent HPP

REVISION HISTORY

A 03.06.2022 For Review GVLB UBC AKC

REV. DATE DESCRIPTION PREPARED CHECKED APPROVED

DOCUMENT TITLE/SUBJECT:

PROJECT TAGGING GUIDELINES – KKS SYSTEM

PROJECT DOCUMENT NO: THPE-00-***-**-TCE-00*


Type
Doc.
Disc

Project Unit System Orig. Serial No Rev. A


Detailed Information

THPE 00 Y KM TCE 001 Size A-4

VENDOR DOCUMENT NO: ** if applicable


Lang. Eng.

Total
53
Sheet
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 2 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

TABLE OF CONTENTS

1. INTRODUCTION .......................................................................................................................................................................... 3

2. REQUIREMENTS TO BE MET BY THE KKS IDENTIFICATION SYSTEM ........................................................... 3

3. STRUCTURE & APPLICATION OF THE POWER PLANT KKS IDENTIFICATION SYSTEM ....................... 3

4. BREAKDOWN, STRUCTURE AND CONTENTS OF THE IDENTIFICATION ...................................................... 7

5. FUNCTION KEY (FUNCTION IDENTIFICATION) ........................................................................................................... 9

6. EQUIPMENT UNIT KEY ......................................................................................................................................................... 10

7. COMPONENT IDENTIFICATION ........................................................................................................................................ 11

8. BREAKDOWNS, CONTENTS OF KKS DATA CHARACTER .................................................................................. 12

9. PROJECT RELATED RULES, AGREEMENTS AND PROCEDURES .................................................................. 13

10. KKS FUNCTION CODE (System Code) .......................................................................................................................... 17

11. KKS EQUIPMENT UNIT CODE ........................................................................................................................................... 43

12. KKS COMPONENT CODE .................................................................................................................................................... 48

13. KKS CODE APPLICATION FOR LEVEL 3 ..................................................................................................................... 51

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 3 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

1. INTRODUCTION

1.1 This document describes the structured steps of KKS tagging procedure to be followed for
Construction of Two Gas Turbine Units (GTU) with a capacity of 32MW each at Tashkent HPP. This
procedure applies to all engineering systems covered in this project. The Power plant
identification system is applied to clearly identify plants, systems, parts and components of their
purpose, type and location. The contents are based on the “Identification Systems for Power Plant
(KKS)” published by VGB- Technical Association of Large Power Plant Operators.

2. REQUIREMENTS TO BE MET BY THE KKS IDENTIFICATION SYSTEM

2.1 In order to perform the set tasks the identification system must be capable of satisfying the
following requirements:

a) Determination of all installations and sub-systems,


b) An adequate number of reserve codes must be available for future developments in power plant
engineering,

c) The classification of installations and sub-systems must be generally applicable to all types of power
plant; all individual circuits and arrangements must, however, be clearly identifiable,

d) Clear identification of all sub-systems,


e) An identification used in a power plant must be non-recurring,
f) Subdivision with graded details and a fixed meaning for the data characters,
g) Variable identification length depending upon the detail requirements of the various areas of
application,

h) Independent identification of various systems must be possible,


i) Ease of recognition ensured by clarity and an acceptable length for the identification, (k)
Plausibility check facility, especially for data processing,
j) Existing standards, guidelines and recommendations must be taken into account.

3. STRUCTURE & APPLICATION OF THE POWER PLANT KKS IDENTIFICATION SYSTEM

3.1 The KKS consists of three types of identification:

a) The process-related identification identifies installations and equipment according to their


assigned task in the power plant process,
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 4 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

b) The point of installation identification identifies the points of installation within an installation
unit (e.g. cubicles, consoles, panels),

c) The location identification identifies the rooms and floors, or other installation sites, for installations
and equipment in building structures.

d) A uniform identification structure, with a maximum of four breakdown levels, was created for
all three types; the units referred to becoming smaller from left to right.

Fig. 1 shows the breakdown levels, referring to a process-related identification as an example.

Serial no. of breakdown level 0 1 2 3


Title of breakdown level Total plant Function Equipment unit component
Example Unit System Pump unit Pump

[Fig. 1. Breakdown levels, referring to Process-related identification]

3.2 Process-Related identification


In this type of identification the entire system is subdivided according to the function or process,
since, whether for mechanical, electrical, control of civil engineering, the equipment units and
components must be identifiable in relation to the process.

The process-related identification is for many applications the most important identification, since it
permits, for example, locations of electrical and control equipment, rooms, signals

and the identification in circuit diagrams related to particular functions.


This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 5 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

In the electrical and instrumentation control engineering sectors, the equipment for auxiliary
services, power supply, open-loop-control, instrumentation, etc,. is treated as a process
engineering function. The same applies to structures in civil engineering work.

The process-related identification corresponds to the identification block “Plant” in DIN


40719, part 2. This block has the prefix sign “=”. According to the standard, the prefix sign can
be omitted provided that the identification remains unambiguous.

3.3 Point of installation identification


As with the Process-related Identification, the KKS is also used to identify locations, principally
of electrical and instrumentation and control equipment, but also of mechanical equipment.
Locations, for example, coordinates, racks and positions in cubicles etc. are identified in the
breakdown level EQUIPMENT UNIT.

The identification letters now used for the Point of installation identification in the
breakdown level FUNCTION are the same as those for the process-related identification. This
improves recognition of the identification in the overall system.

In order to prevent possible confusion between Process-related identification and Point of


installation identification the prefix sign “+” must be added to the point of installation Code
(according to DIN 40719, part 2). Resp. the breakdown symbol “full stop” between breakdown
Level 1 and 2 must be added. This prefix sign is omitted when there is absolutely no ambiguity
in layout documents.

3.4 Location identification


In order to clearly identify the position of plant, subsystems and equipment in the power plant,
the building structure and floor is entered at the breakdown level FUNCTION, and the rooms
on the various floors of the building structure at the breakdown level EQUIPMENT UNIT. The
breakdown level COMPONENT is omitted in such cases. Fire protection sections are identified
according to the room identification.

3.5 Breakdown Level Structure


Serial no. of Breakdown
0 1 2 3
level
Overall
Number of breakdown level Function Equipment Unit Component
plant
Designation of Data
G F0 F1 F2 F3 FN A1 A2 AN A3 B1 B2 BN
character

Type of data Character (A) or (N) (N) A A AN N AAN N NA AAN N

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 6 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

A = Alphabetical symbols (letters, special symbols


N = Numerical symbols (digits)
( ) = The data characters may be omitted
3.6 Title and contents of the breakdown levels

0 1 2 3

Breakdown levels Total Plant Function Equipment unit Component

Process-related code

Total Plant System code Equipment unit code Component code

Mechanical Unit System Pump unit (Pump)


Unit Structure, floor Rolling door (Motor)
Civil
Unit Structure, floor Fan unit (Fan)
Unit System Measuring circuit
C&I
Unit System Open-loop control
Unit Switchgear
Electrical
Unit Transformer Fan unit

Point of Installation
Total Plant Installation unit code Installation space
code
Unit Switchgear Tier/Space
Unit Electrical equipment Tier/Space
Electrical and C&I
cabinet
Unit Control console Coordinate

Location Code
Total Plant Structure code Room code
Unit Structure, floor Room / coordinates
Civil
Unit Outdoor area Coordinates

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 7 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

4. BREAKDOWN, STRUCTURE AND CONTENTS OF THE IDENTIFICATION

4.1 The KKS is divided into different BREAKDOWN LEVELS and codes from right to left in
diminishing order of the units of a complete power plant.

The breakdown levels have the following structures:

0 1 2 3
Overall plant Function Equipment unit Component

G F0 F1 F2 F3 FN A1 A2 AN A3 B1 B2 BN

A or N (N) AAA N N AA N N N (A) AA NN

Function code Note 1) Note 1)


(Chapter 10.0)

Equipment unit code


(Chapter 11.0)

Component code
(Chapter 12.0)

For ex: For Closed cycle cooling water pumps

0 1 2 3
Overall plant Function code Equipment unit Component
code code
00 PGB 11 AP 001

Note: 1) Rules on AN numbering for piping and in-pipe-components

Serial No.
Valves (AA AN) Pipes (BR AN) Instrumentation (C AN)
AN

Valves in main pipes Sensing element


001-100 Main pipes
Valves, General (vibration, temperature,
Control Valves / Dampers flow, etc)
101-190 (For break up refer table
below)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 8 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

Suction and pressure relief Transmitter (flow,


191-199 Safety valves
lines on safety valves level, pressure,
temperature,
Switch (flow, level,
201-299 Not used Not used pressure,
vibration, analyzer)
temperature)
Serial No.
Valves (AA AN) Pipes (BR AN) Instrumentation (C AN)
AN

Pressure lines for


301-399 Instrument Isolation Not Used
Instruments
Drain, flushing pipes,
Valves in drains and
401-499 pressure suppression Tests points
flushing pipes
pipes

Local gauges (flow,


501-599 Valves for venting Venting level, pressure,
temperature)
Valves for sampling and
601-699 Dosing Sampling and Dosing pipes Not Used

701-799 Valves for internal controls For Internal Controls Blocked

801-899 Not used Not used Not Used

901-999 Not used Not used Not Used

Break up serial no. table for Control Valves / Dampers

101-130 Manual Dampers


131-140 Motor operated valves / Dampers (On/off, inching type)
141-150 Motor operated valves / Dampers (Modulating type)
151-160 Pneumatic operated valves / Dampers (On/off type)
161-170 Pneumatic operated valves / Dampers and Regulators (Modulating type)
171-180 Hydraulic operated valves / Dampers (On/off, inching type)
181-190 Hydraulic operated valves / Dampers (Modulating type)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 9 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

5. FUNCTION KEY (FUNCTION IDENTIFICATION)

Serial No. of breakdown level 1


Name of the breakdown level
Identification data character Function
Type of character F0 F1 F2 F3 FN

N AAA NN

Main groups F1
Groups F1F2
Subgroups F1F2F3
Function Key, Main Groups F1

Code Identification
A Grid and distribution systems
B Power transmission and auxiliary power supply
C Instrumentation and control equipment (Identification on a priority basis
according to main, instrumentation and control function also acceptable in
composite structure hardware packaging systems.)
E Conventional fuel supply and residues disposal
G Water supply and disposal
H Conventional heat generation
L Steam, water, gas cycles
M Main machine sets
P Cooling water systems
Q Auxiliary systems
S Ancillary systems
U Structures
W Renewable energy plants
X Heavy machinery (not main machine sets)
Z Workshop and office equipment

For complete function code list including system limits of function groups F1F2 and function sub-
groups F1F2F3 see function code (Chapter 10.0)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 10 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

6. EQUIPMENT UNIT KEY

2
Equipment unit identification

Serial No. breakdown level Equipment unit

Name of the breakdown level A1 A2 AN A3

Identification of data AA N N N A character


Type of data character

Main groups A1

Subgroups A1A2

Equipment Unit Key, group A1:

Code Identification

A Mechanical equipment

B Mechanical equipment

C Direct measuring circuits

D Closed-loop control circuits

E Analog and binary signal conditioning

F Indirect measuring circuits

G Electrical equipment

H Sub-assemblies of main and heavy machinery

For complete equipment units of the subgroups A1A2, see equipment unit code (Chapter 11.0)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 11 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

7. COMPONENT IDENTIFICATION

Serial No. breakdown level 3


Name of the breakdown level Component code
Identification of data character
B1 B2 BN
Type of data character
AA N N N

Main groups B1
Subgroups B1B2

Component code main groups B1:

Code Identification
- Electrical components
K Mechanical components
M Mechanical components
Q Instrumentation and control components (non-electrical)
X Signal origins
Y Signal applications

For complete components of the subgroups B1B2, see component code (Chapter 12.0). In
P&I diagrams breakdown level 3 is NOT used.
In other document it may be used according to separate agreements

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 12 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

8. BREAKDOWNS, CONTENTS OF KKS DATA CHARACTER

2 3
Serial No. of 0 1 Equipment unit Component
breakdown Overall
Name of plant Function A B
breakdown AN A3 B2 BN
F1 F2 A21 1
Identification of G F0 FN N N
data F3 AA A AA N N
N N
Type of data (A or N) N AAA
character N

Identification of
power station units and
unit independent plants

Prefix No. of the function code


Counting of similar systems and plants

System-classifying
Classifying sub-division of system
and plants of unit

System-counting
Counting sub-division of systems and plants
into system sections and sub-systems

Equipment-classifying
Classifying sub-division of mechanical
equipment, open loop-control

Equipment-counting
Counting of similar mechanical equipment, electrical and
control & instrumentation equipment

Additional identification of breakdown level 2


Identification of pilot valves, multiple drives/elec. loads,
measuring points with multiple output/operating points

Component-classifying
Classifying sub-division of components

Component-counting
Counting of components or signals

The data character marked ( ) and the prefix sign can be omitted of the identification is
unequivocal

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 13 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

9. PROJECT RELATED RULES, AGREEMENTS AND PROCEDURES

9.1 GENERAL RULES ON PROCESS-RELATED IDENTIFICATION

a. Piping & Instrument Diagrams (P&ID) and Single Line Diagram (SLD) are the basic documents
(origins) for a project related KKS coding.
b. Single line diagrams are the basic documents (origins) for a project related KKS
coding in electrical engineering.
c. For other engineering activities (e.g. layout planning, component engineering), KKS code must
always be taken from the above mentioned basic documents.
d. In basic KKS documents (P & IDs and SLD), the breakdown level 3 (Component code) shall not be
applied.
e. Special rules on point of installation identification and location identification have to be established
within the relevant engineering disciplines (Electrical, I&C and Civil engineering). The basis is the
KKS-Application Commentaries, Part B2, B3, and B4 by VGB.

9.2 RULES ON MODIFICATIONS AND CANCELLATIONS OF KKS NUMBERS

a. It is not allowed to change allocated KKS numbers for a project, if these numbers have been released
for the project.
b. The original KKS number is still kept, even when another kind of equipment is used providing that the
function according to the KKS equipment unit code is not changed (e.g. substitution of a gate valve
by a globe valve).
c. If in a project hardware component is no longer used, it is not allowed to re- allocate its KKS number
for another component in the same project.

9.3 AGREEMENT ON NUMBERING SYSTEM FOR BREAKDOWN LEVEL “0” G

Total Plant
Contents
G

n N = 1, 2, 3,………,9 for Unit n

0 For Plant common & hooking up to existing facility

Note : n = 2 & 3 for GTG unit #2 & 3 will be used for the proposed power plant except for Plant common
& hooking up to existing facility systems

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 14 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

9.4 AGREEMENT ON NUMBERING SYSTEM FOR BREAKDOWN LEVEL “1” F0

These two data character fields (also known as the prefix number fields) serve to number similar
systems or facilities. They constitute a valid component of the overall identifier only if followed by a
key (alphabetical characters) with which a text-designated system or facility has been encoded.
Combined-cycle power plants are generally constructed from modules which are combined to form
process units, and ultimately the combined-cycle power plant itself. The prefix number should be
allocated in accordance with the requirements of optimum computer-aided project processing
(based on modules and/or process units), such that a repeatedly recurring system or facility need
be encoded only once; it may later be duplicated by provision of the prefix number.

Function Prefix No.


Contents
F0

0 Common covering BOP systems

1 Unit 1 (GTG-1/HRSG-1)

2 Unit 2 (GTG-2/HRSG-2)

3 Unit 3 (GTG-3/HRSG-3)

G & F0 Data Character Fields (Prefix Number)


System/Facility

Unit10 Unit20 Unit30

10 20 30
Systems or facilities which occur once
within a process unit as super
ordinate
(single) items only, e.g.

Gas turbine 11MBA 22MBA 33MBA

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 15 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

• (Building) Structures HRSG 11UHA 22UHA 33UHA

Systems or facilities which occur as


super ordinate items in the overall 00
plant
for Plant common & hooking up to

existing facility
00UGY
Eg., Existing Piping & Cable bridge

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 16 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

9.5 GENERAL RULES ON OTHER NUMBERING CODE ELEMENTS (Fn, An, Bn)

Numbering starts a new when one of the preceding code elements changes. Numbering may be
consecutive or grouping.

a) Numbering starts a new when one of the preceding code element changes
b) Numbering may be consecutive or grouping.
c) Numbering may need not to be continuous.
d) Numbering conventions, once established, may not be altered, not even in the event of changes made
in the progress of planning.
e) Redundant zeros must be written.
f) An application-specific scheme of numbering may be established. However, such schemes may not
have the effect of reserving numbers in other applications, not even within the same engineering
discipline.
g) Management systems (e.g. computer checking programs, allocation sheets) have to assure, that no
double KKS numbers occur in the project.
h) If necessary, subdivisions of number ranges in Fn and An according to the division of work could be
made. They have to be written down directly in the Function key code and must be respected by the
partners.

9.6 GENERAL RULES REGARDING DIRECTION OF NUMBERING

a. Standard designations have priority in all cases.


b. Numbers are increased in media or process flow direction.
c. Project counting directives refereed to local layouts are related to breakdown level
“0”, and prefix number for system code “F1” and structures (F1=U) only.
d. The counting is related to any geographical direction. (eg.,South to North or East to west etc.,) This
shall be as per Owner’s requirement mentioned in “Part 4 Technical requirements, Section 2, Sub
section 2.8”.

9.7 WRITING MODUS OF KKS CODE

Following structures of the KKS code are allowed:


a. F o r p u m p s i n p a r a l l e l ; In one line with space between Function Level, Equipment
Unit Level (and Component Level).
(eg. 30QHE10AP001 for first drain pump and 30QHE20AP001 for second drain pump of
HRSG#30 blowdown tank
b. F o r p u m p s i n s e r i e s ; In one line with space between Function Level, Equipment Unit
Level (and Component Level).
(eg. 30QHE10AP001 for first drain pump and 30QHE10AP002 for second drain pump of
HRSG#30 blowdown tank)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 17 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

10. KKS FUNCTION CODE (System Code)

A GRID AND DISTRIBUTION SYSTEMS


AE 110 kV systems
AEA 110 kV systems
AEB 110 kV cable terminal
AEC 110 kV cable earthing and lightning protection system
AK Medium voltage (10 kV) systems
AKA Medium voltage main dist. board (free for use up to AKD)
AKE Medium voltage sub-dist. board (free for use up to AKN)
AN Low voltage ( < 1 kV) systems
ANA Low voltage main dist. board (free for use up to AND)
ANE Low voltage sub-dist. board (free for use up to ANN)
AP Control consoles
APA Control panel (free for use up to APD)
APE Interposing relay panel (free for use up to APN)
AQ Measuring and metering equipment
AQA Metering panel
AQB Summation panel
AR Protection equipment
ARA Protection relay panel (free for use up to ARZ)
AS Decentralized panels and cabinets
ASA Circuit breaker appurtenance
ASB Multiplication, conversion, decoupling
ASC Transducer appurtenance
ASD Compressed air, hydraulics
ASJ Automated controls, closed-loop control
ASL Grid simulation, voltage group selection
ASM Measuring equipment
ASN Auxiliary power supply
AT Transformer equipment
ATA Transformer equipment (free for use up to ATZ)
AU Open-loop control, check back and auxiliary equipment
AUA Open-loop control, check back and auxiliary equipment (free for use up to
AV AUZ)
Marshalling racks
AVA Marshalling racks (free for use up to AVZ)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 18 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

AW Instrument panels
AWA Instrument panels (free for use up to AWZ)
AX Central equipment
AXA Central equipment (free for use up to AXZ)
AY Communication equipment
AYA Control console telephone system
AYC Alarm system
AYE Fire alarm system
AYG Remote terminal unit
AYJ Remote metering system
B POWER TRANSMISSION AND AUXILIARY POWER SUPPLY
BA Power transmission
BAA Generator leads
from excl. generator bushings, incl. Current and voltage transformers,
cooling and ventilation systems to excl. generator transformer low side
bushings or to excl. auxiliary power transformer high side bushing test
BAB Foundation cabinets
BAC Generator circuit breaker, also communicating pole circuit breaker, incl. cooling
System
BAD Isolated Phase Bus ducts
BAS Auto voltage regulation system
BAT Generator transformers, including cooling system
BAU Earthing and lightning protection systems
BAW Earthing and lightning protection systems
BAX Control air supply system
BAY Control and protection equipment
BB Medium-voltage distribution boards and transformers, normal system
BBA Medium-voltage distribution boards, normal system (free for use up to BBO)
BBP Segregated phase bus ducts
BBS Neutral earthing resistor
BBT Medium-voltage auxiliary power transformers
BBX Fluid supply system for control and protection equipment
BBY Control and protection equipment
BC Medium voltage distribution boards and transformers, general-purpose
BCA Medium voltage start-up distribution boards, general-purpose (free for use up
to
BCT BCS)
Start-up, offsite, general-purpose transformers
BCX Fluid supply system for control and protection equipment
BCY Control and protection equipment
BD Medium voltage emergency distribution boards and transformers,
(diesel) emergency power system 1
BDA Medium voltage emergency distribution board (free for use up to BDS)
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 19 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

BDT Medium voltage transformer


BDX Fluid supply system for control and protection equipment
BDY Control and protection equipment
BF Low voltage main distribution boards and transformers, normal system
BFA Low voltage main distribution boards (free for use up to BFS)
BFT Low voltage auxiliary power transformer (free for use up to BFW)
BFY Control and protection equipment
BH Low voltage main distribution boards and transformers, general-purpose
BHA Low voltage main distribution boards
BHC Low voltage distribution boards
BHD Low voltage distribution boards / Motor Control Center (free for use up to
BHP BHO)voltage distribution boards
Low
BHT Low voltage auxiliary power transformer (free for use up to BHW)
BHY Control and protection equipment
BJ Low voltage sub-distribution boards and transformers, normal system
BJA Low voltage sub-distribution boards (free for use up to BJS)
BJT Low voltage auxiliary power transformers
BJY Control and protection equipment
BL Low voltage sub-distribution boards and transformers, general-purpose
BLA Low voltage sub-distribution boards (free for use up to BLS)
BLT Low voltage auxiliary power transformers
BLY Control and protection equipment
BM Low voltage distribution boards and transformers, (diesel) emergency power
system
BMA 1 voltage emergency distribution boards (free for use up to BMS)
Low
BMT Low voltage auxiliary power transformers (free for use according to voltage
level up
BMY to BMW)
Control and protection equipment
BP Power installations for variable-speed drives
BPA Power installations for variable-speed drives (free for use up to BPZ)
BR Low voltage distribution boards, uninterruptible (converter) power supply
BRA Low voltage distribution boards (free for use up to BRS)
BRT Converter (rotary)
BRU converter (static), inverter
BRV Emergency power generating equipment (if not under “X” = Heavy Machinery)
BRY Control and protection equipment
BT Battery systems
BTA Batteries (free for use up to BTK)
BTL Rectifiers, battery charger (free for use up to BTV)
BTW Common equipment (free for use up to BTZ)
BU DC distribution boards, normal system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 20 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

BUA DC distribution board (free for use up to BUS)


BUY Control and protection equipment
BV DC distribution boards, emergency power system 1
BVA DC distribution boards (free for use up to BVS)
BVY Control and protection equipment
BX Fluid supply system for control and protection equipment
BXA Fluid supply system for control and protection equipment (free for use up to
BXY BXX)
Control and protection equipment
BY Control and protection equipment
BYA Control and protection equipment (free for use up to BYZ)
C Instrumentation and control equipment
CA Protective interlocks
CB Functional group control, subloop control
CC Binary signal conditioning, drive control interface
CD Drive control interface
CE Annunciation
CF Measurement, recording
CFA Cabinet for measurement
CFB Cabinet for measurement
CFC Cabinet for measurement
CFD Cabinet for measurement
CFE Cabinet for measurement
CFF Cabinet for measurement
CFQ Cabinet for recording (meters, pen recorders)
CG Closed-loop control (excl. Power section)
CH Protection
CHA Cabinet for generator and transformer protection
CHB Cabinet for generator and transformer protection
CHC Cabinet for generator and transformer protection
CHD Cabinet for generator and transformer protection
CHY Cabinet for protection
CJ Unit coordination level, Overall block automation
CJA Unit control system (including cabinets)
CJC Instrumentation and control for water, steam cycle (incl. cabinets)
CJD Start-up control, set point control(unit)(including cabinets)
CJF Boiler control system (incl. cabinets)
CJJ Instrumentation and control cabinet for steam turbine set
CJK Instrumentation and control cabinet for steam turbine set
CJN Generator voltage regulator
CJP Instrumentation and control cabinet for set
CJQ Instrumentation and control cabinet for gas turbine set
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 21 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

CJR Instrumentation and control cabinet for gas turbine set


CK Process computer system
CKA Online supervisory and diagnostic computer
CKB Online supervisory and diagnostic computer
CKC Online supervisory and diagnostic computer
CKD Online supervisory and diagnostic computer
CKE Online supervisory and diagnostic computer
CKF Online supervisory and diagnostic computer
CKG Online supervisory and diagnostic computer
CKH Online supervisory and diagnostic computer
CKJ Access control computer
CKK Access control computer
CKL Access control computer
CKM Access control computer
CR Process control systems
CRA Automation system, non-fail-safe
CRB Automation system, non-fail-safe
CRC Automation system, non-fail-safe
CRD Automation system, non-fail-safe
CRE Automation system, non-fail-safe
CRF Automation system, non-fail-safe
CRG Automation system, non-fail-safe
CRH Automation system, non-fail-safe
CRJ Automation system, fail-safe
CRK Automation system, high-availability
CRL Enclosure (e.g. cabinet)
CRM Enclosure (e.g. local box)
CRN Process control system
CRP Process control system
CRQ Process control system
CRQ Process control system
CRR Communication (e.g. terminal bus)
CRS Communication (e.g. plant bus)
CRT Communication (e.g. field bus)
CRU Operation and monitoring
CRV Engineering
CRW Control system diagnostics
CRX Process optimization
CRY Process control system
CRZ Process control system
CS DCS cabinets I/O cabinets
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 22 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

CU Closed-loop control (power section)


CUA Cabinet for power adjuster 400V AC, e.g. function unit 1
CUB Cabinet for power adjuster 400V AC, e.g. function unit 2
CUC Cabinet for power adjuster 400V AC, e.g. function unit 3
CUD Cabinet for power adjuster 400V AC, e.g. function unit 4
CUE Cabinet for power adjuster 400V AC, e.g. function unit 5
CUF Cabinet for power adjuster 400V AC, e.g. function unit 6
CUG Cabinet for power adjuster 400V AC, e.g. function unit 7
CUL Cabinet for interposing relays for 24 V DC solenoid valves
CUM Cabinet for power supply of hardwired control room
CUN Cabinet for 24 V direct voltage fuses
CUP Cabinet for 230 V direct voltage fuses
CV Marshalling racks
CVA Logic Marshalling boxes and cubicles
CVB Marshalling racks
CW Control rooms
CWA Main control console
CWD Main control console
CWF Main control panel
CWN Main control panel
CWP Main control panel
CWQ Printers
CWR Printer console
CX Local control stations
CXA Local control station
CXB Local control station
CXC Local control station
CXD Local control station
CY Communication and information systems
CYA Telephone system (PABX)
CYB Loud speaker system
CYC Alarm system (acoustic)
CYD Data communication systems
CYE Fire alarm system
CYF Clock system
CYG Remote control system
CYH Telemetry system
CYJ Remote metering system
CYK HF carrier telephone system
CYL Staff paging system
CYN -Inter phone
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 23 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

CYP Optical monitoring system


CYQ Gas detection system
CYR Pneumatic tube conveyor
CYS Radiotelephone system
CYT Intrusion detection system
CYU Access control system
CYV Plant and production management system
CYY Telephone system for commissioning
E Fuel supply and residues disposal
EG Supply of liquid fuels (light fuel oil)
EGA Receiving equipment incl. pipeline
EGB Tank farm
EGC Pump system
EGD Piping system
EGE Mechanical cleaning, scrubbing
EGF Temporary storage system
EGG Preheating
EGR Residues removal system
EGT Heating medium system
EGU Billing meter station
EGX Fluid supply system for control and protection equipment
EGY Control and protection equipment
EH Chemical treatment of liquid fuels incl. residues removal (light and heavy fuel
EHC oil)
Additive dosing system
EHG Chemical treatment of light fuel oil
EHN Chemical treatment of heavy fuel oil
EHT Heating medium system
EHX Fluid supply system for control and protection equipment
EHY Control and protection equipment
EK Supply of gaseous fuels
EKA Receiving equipment incl. pipeline
EKB Scrubber system
EKC Heating system
EKD Main reducing station, expansion turbine
EKE Mechanical cleaning, scrubbing
EKF Storage system
EKG Piping system
EKH Main pressure boosting system
EKR Residues removal system
EKT Fuel gas preheating system
EKU Billing meter station
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 24 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

EKX Fluid supply system for control and protection equipment


EKY Control and protection equipment
EL Chemical treatment of gaseous fuels incl. residues removal
EN Supply of other fuels (heavy fuel oil or crude oil)
ENA Receiving equipment incl. pipeline
ENB Tank farm
ENC Pump system
END Piping system
ENR Residues removal system
ENT Heating medium system
ENX Fluid supply system for control and protection equipment
ENY Control and protection equipment
EP Treatment of other fuels (as main fuel)
EPC Pump system
EPG Physical treatment of light fuel oil
EPN Physical treatment of heavy fuel oil
EPT Heating medium system
EPX Fluid supply system for control and protection equipment
EPY Control and protection equipment
EQ Conversion of other fuels
G Water supply and disposal
GA Raw water supply
GAA Extraction, mechanical cleaning
GAC Piping and channel system
GAD Storage system
GAF Pump system
GAV Lubricant supply system
GAX Fluid supply system for control and protection equipment
GAY Control and protection equipment
GB Treatment system (carbonate hardness removal) incl. cooling tower make-up
water
GBB treatment system
Filtering, mechanical cleaning system
GBC Aeration, gas injection system
GBD Precipitation system (e.g. for carbonate hardness removal)
GBE Acid proportioning system (e.g. for carbonate hardness removal)
GBF Ion exchange, reverse osmosis system (e.g. for carbonate hardness removal)
GBG Evaporation system (e.g. for carbonate hardness removal)
GBH Deaeration
GBJ Preheating, cooling system
GBK Piping system, temporary storage system, pump system for main fluid
GBL Storage system outside fluid treatment system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 25 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

GBN Chemicals supply system


GBP Regeneration, flushing equipment
GBQ Injection system for main fluid
GBR Flushing water and residues removal system incl. neutralization
GBS Sludge thickening system
GBT Heating, cooling and flushing fluid distribution system
GBX Fluid supply system for control and protection equipment
GBY Control and protection equipment
GC Treatment system (demineralization)
GCB Filtering, mechanical cleaning system
GCC Aeration, gas injection system
GCD Precipitation system (e.g. for carbonate hardness removal)
GCE Acid proportioning system (e.g. for carbonate hardness removal)
GCF Ion exchange based demineralization
GCG Thermal Evaporation based Desalination
GCH Deaeration
GCJ Preheating, cooling system
GCK Piping system, temporary storage system, pump system for main fluid
GCL Storage system outside fluid treatment system
GCN Chemicals supply system
GCP Regeneration, flushing equipment
GCQ Injection system for main fluid
GCR Flushing water and residues removal system incl. neutralization
GCS Sludge thickening system
GCT Heating, cooling and flushing fluid distribution system
GCX Fluid supply system for control and protection equipment
GCY Control and protection equipment
GD Treatment system (others), blowdown demineralizing system
GDB Filtering, mechanical cleaning system
GDC Aearation, gas injection system
GDD Precipitation system (e.g. for carbonate hardness removal)
GDE Acid proportioning system (e.g. for carbonate hardness removal)
GDF Ion exchange, reverse osmosis system (e.g. for demineralization)
GDG Evaporation system (e.g. for demineralization)
GDH Deaeration
GDJ Preheating, cooling system
GDK Piping system, temporary storage system, pump system for main fluid
GDL Storage system outside fluid treatment system
GDN Chemicals supply system
GDP Regeneration, flushing equipment
GDQ Remineralisation system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 26 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

GDR Flushing water and residues removal system incl. neutralization


GDS Sludge thickening system
GDT Heating, cooling and flushing fluid distribution system
GDX Fluid supply system for control and protection equipment
GDY Control and protection equipment
GH Distribution systems (not drinking water)
GHB Distribution system after treatment (carbonate hardness removal)
GHC Demineralized water distribution system
GHD Raw water distribution system
GK Drinking water supply
GKA Drinking water treatment system
GKB Drinking water distribution system
GM Process drainage system
GMA Central disposal system
GMD Process drainage system for switchgear building *UBA*
GMF Process drainage system for steam generator building *UHA*
GMG Process drainage system for structure for raw water supply *UGA*
GMM Process drainage system for steam turbine building *UMA*
GMQ Process drainage system for workshop and stores building *UST*
GMS Process drainage system for fire pump house *USG*
GN Sanitary & Waste water treatment system
GNB Filtering, mechanical cleaning system
GNC Aeration, gas injection system
GND Precipitation system (e.g. for carbonate hardness removal)
GNE Acid proportioning system (e.g. for carbonate hardness removal)
GNF Ion exchange system (e.g. for demineralization)
GNG Evaporation system (e.g. for demineralization)
GNH Deaeration
GNJ Preheating, cooling system
GNK Piping system, temporary storage system, pump system for main fluid
GNL Storage system outside fluid treatment system
GNN Chemicals supply system
GNP Regeneration, flushing equipment
GNQ Injection system for main fluid
GNR Flushing water and residues removal system incl. neutralization
GNS Sludge thickening system
GNT Heating, cooling and flushing fluid distribution system
GNX Fluid supply system for control and protection equipment
GNY Control and protection equipment
GQ Domestic waste water collection and drainage systems
GQA Central disposal system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 27 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

GQB Storage system


GQF Plant drainage system for steam generator building *UHA*
GQM Plant drainage system for steam turbine building *UMA*
GQV Plant drainage system for office and staff amenities building *UYA*
GR Domestic waste water treatment system
GRB Filtering, mechanical cleaning system
GRC Aeration, gas injection system
GRD Precipitation system (e.g. for carbonate hardness removal)
GRE Acid proportioning system (e.g. for carbonate hardness removal)
GRF Ion exchange system (e.g. for demineralization)
GRG Evaporation system (e.g. for demineralization)
GRH Deaeration
GRJ Preheating, cooling system
GRK Piping system, temporary storage system, pump system for main fluid
GRL Storage system outside fluid treatment system
GRN Chemicals supply system
GRP Regeneration, flushing equipment
GRQ Injection system for main fluid
GRR Flushing water and residues removal system incl. neutralization
GRS Sludge thickening system
GRT Heating, cooling and flushing fluid distribution system
GRX Fluid supply system for control and protection equipment
GRY Control and protection equipment
GU Rainwater collection and drainage systems incl. treatment system
GUA Central disposal system
GUB Storage system
GUF Plant drainage system for steam generator building *UHA*
GUM Plant drainage system for steam turbine building *UMA*
GUT Plant drainage system for waste pit *UEB*
GUV Plant drainage system for office and staff amenities building *UYA*
GUX Plant drainage system for gate house *UYE*
H Heat generation
HA Heat recovery steam generation (HRSG) system
HAA LP part-flow feed heating system (flue-gas-heated)
HAB HP part-flow feed heating system (flue-gas-heated)
HAC Economizer system
Intermediate pressure: HAC20 - 49
High pressure:
HAC50 - 99. High
HAD Evaporator system-
pressure: HAC50
Low
99. pressure: HAD01 - 19
Intermediate pressure HAD20 - 49
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 28 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

High pressure: HAD50 - 99.


HAG Circulation system
HAH HP superheater system
Low pressure: HAH01 - 19
Intermediate pressure: HAH20 - 49
High pressure: HAH50 - 99.
HAJ Reheat system
HAK Secondary reheat system
HAM Triflux system
HAN Pressure system drainage and venting system
Low pressure: HAN01 - 49
High pressure: HAN50 - 99.
HAX Fluid supply system for control and protection equipment
HAY Control and protection equipment
HB Support structure, enclosure, steam generator interior
HBA Frame incl. foundation
HBB Enclosure
HBC Brick lining incl. insulating brickwork
HBD Platform, stairway
HBE Pressure vessel (supercharged boiler)
HBK Steam generator interior
HC Fireside heat transfer surface cleaning equipment
HCA Air soot blowing system
HCB Steam soot blowing system
HCC Water soot blowing system
HCD Flushing equipment
HCE Rapping gear
HCF Shot cleaning system
HCW Sealing fluid supply system
HCY Control and protection equipment
HM Gas heating system (for closed cycle)
HMA Primary heater (primary convection section)
HMB Radiation section
HMC Secondary heater (second convection section)
HMD Reheat system
HMY Control and protection equipment
HN Flue gas exhaust (without flue gas treatment)
HNA Ducting system
HNC Induced-draught fan system
HNE Smoke stack system (chimney)
HNF Flue gas recirculation system
HNU Flue gas pressure relief system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 29 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

HNX Fluid supply system for control and protection equipment


HNY Control and protection equipment
L Steam, water, gas cycles
LA Feed water system
LAA Storage, deaeration
LAB Feed water piping system
Low pressure: LAB01 - 19
Intermediate pressure: LAB20 - 49
High pressure: LAB50 - 99.
LAC Feed water pump system
Low pressure: LAC01 - 19
Intermediate pressure: LAC20 - 49
High pressure: LAC50 - 99.
LAD HP feed water heating system
LAE HP desuperheating spray system
LAF IP desuperheating spray system
LAH Start-up and shutdown piping system
LAJ Start-up and shutdown pump system
LAW Feed water sealing water system
LAX Fluid supply system for control and protection equipment
LAY Control and protection equipment
LB Steam system
LBA Main steam piping system
Low pressure: LBA01 - 19
Intermediate pressure: LBA20 - 49
High pressure: LBA50 - 99.
LBB Hot reheat piping system
Low pressure: LBA01 - 19
Intermediate pressure: LBA20 - 49
High pressure: LBA50 - 99.
LBC Cold reheat piping system
LBD Extraction piping system
LBE Back-pressure piping system
LBF Overpressure suppression and safety device incl. injection and hydraulic
station for
LBG safety function
Auxiliary steam piping system
LBH Start-up steam system, shutdown steam system
Low pressure: LBH01 - 19
Intermediate pressure: LBH20 - 49
High pressure: LBH50 - 99.
LBJ Moisture separator/reheater (MSR)
LBQ Extraction steam piping system for HP feed water heating
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 30 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

LBR
LBS Extraction steam piping system for LP feed water heating (main condensate)
LBT Emergency condensing system
LBU Common dump line
LBW Sealing steam system
LBX Fluid supply system for control and protection equipment
LBY Control and protection equipment
LC Condensate system
LCA Main condensate piping system
LCB Main condensate pump system
LCC Main condensate heating system
LCE Condensate desuperheating spray system
LCF Branch turbine condensate piping system
LCG Branch turbine condensate pump system
LCH HP heater drains system
LCJ LP heater drains system
LCL Steam generator drains system
LCM Clean drains system (collecting and return system)
LCN Auxiliary steam condensate system (collecting and return system)
LCQ Steam generator blowdown system
LCW Sealing and cooling drains system
LCX Fluid supply system for control and protection equipment
LCY Control and protection equipment
LF Common installations for steam, water, gas cycles
LFC Common drain/vent system
LFG Secondary-side steam generator tube sheet lancing system
LFJ Steam generator layup system
LFN Proportioning system for feed water, condensate system, incl. proportioning in
boiler

LY and turbine
Control and area
protection equipment
LYA Control and protection equipment
M Main machine sets
MA Steam turbine plant
MAA HP turbine
MAB IP turbine
MAC LP turbine
MAD Bearings
MAG Condensing system
MAH Motive water system
MAJ Air removal system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 31 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

MAK Transmission gear between prime mover and driven machine, incl. turning
MAL gear
Drain and vent system
MAM Leak-off steam system
MAN Turbine bypass station, incl. desuperheating spray system
Low pressure: MAN01 - 49
High pressure: MAN50 - 99.
MAP LP turbine bypass
MAQ Vent system
MAV Lubricant supply system
MAW Sealing, heating and cooling steam system
MAX Non-electric control and protection equipment, incl. fluid supply system
MAY Electrical control and protection equipment
MB Gas turbine plant
MBA Turbine, compressor rotor with common casing
MBB Turbine casing and rotor
MBC Compressor casing and rotor
MBD Bearings
MBH Cooling and sealing gas system
MBJ Start-up unit
MBK Transmission gear between prime mover and driven machine, incl. turning
gear, bar
MBL ring gear
Intake air, cold gas system incl. intake air preheating
MBM Combustion chamber (gas heating, combustion)
MBN Fuel supply system (liquid)
MBP Fuel supply system (gaseous)
MBQ Ignition fuel supply system
MBR Exhaust gas system (open cycle)
MBS Storage system
MBT Motive gas generator unit, incl. combustion chamber
MBU Additive system
MBV Lubricant supply system
MBW Sealing oil supply system
MBX Non-electric control and protection equipment, incl. fluid supply system
MBY Electrical control and protection equipment
MBZ Lubricant and control fluid treatment system
MK Generator plant
MKA Generator, complete, incl. stator, rotor and all integral cooling equipment
MKC Generator exciter set, including set with electrical breaking system, complete
(10 auxilliary excitation, 20 main excitation unit)
MKD Bearings
MKF Stator/rotor liquid cooling system, incl. coolant supply system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 32 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

MKG Stator/rotor hydrogen (H2) cooling system, incl. coolant supply system
MKH Stator/rotor nitrogen (N2)/carbon dioxide (CO2) cooling system, incl. coolant
supply
MKJ system
Stator/rotor air cooling system, incl. coolant supply system
MKQ Exhaust gas system
MKU Stator/rotor cooling oil cooling system, incl. coolant supply system
MKV Lubricant supply system
MKW Sealing oil system, incl. supply and treatment
MKY Control and protection equipment
MP Common installations for main machine sets
MPA Foundation
MPB Sheathing
MPG Frame, support structure
MPR Forced cooling system
MPS Drying and layup system
MY Control and protection equipment
MYA Control and protection equipment
N Process energy/fluid supply for external users
NA Process steam system (incl. condensate return)
NAA Piping system (steam)
NAB Piping system (condensate)
NAD Process heat transmission system
NAX Fluid supply system for control and protection equipment
NAY Control and protection equipment
ND Process hot water system
NDA Piping system (forward)
NDB Piping system (return)
NDC Process hot water pump system
NDD Process heat transfer
NDE Hot water storage system
NDF Distribution system
NDG Distribution system
NDH Distribution system
NDJ Distribution system
NDK Pressurizing system
NDX Fluid supply system for control and protection equipment
NDY Control and protection equipment
NE Process chilled water system
NEA Piping system (forward)
NEB Piping system (return)
NEC Process chilled water pump system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 33 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

NEE Process chilled water storage system


NEF Distribution system
NEG Distribution system
NEH Distribution system
NEJ Distribution system
NEK Pressurizing system
NEX Fluid supply system for control and protection equipment
NEY Control and protection equipment
PA Circulating water system
PAA Extraction, mechanical cleaning for direct cooling
PAB Circulating water piping and culvert system
PAC Circulating water pump system
PAD Cooling tower
PAE Cooling tower pump system
PAH Condenser cleaning system, incl. all appurtenances
PAR Make-up water piping system
PAS Make-up water pump system
PAV Lubricant supply system
PAX Fluid supply system for control and protection equipment
PAY Control and protection equipment
PB Circulating water treatment system
PBA Discharge from fluid treatment system
PBB Filtering, mechanical cleaning system
PBC Aeration, gas injection system
PBD Precipitation system (e.g. for carbonate hardness removal)
PBE Hardness stabilization system for circulating water
PBF Ion exchange system (e.g. for demineralization)
PBG Evaporation system (e.g. for demineralisation)
PBH Deaeration
PBJ Preheating, cooling system
PBK Piping system, temporary storage system, pump system for main fluid
PBL Storage system outside fluid treatment system
PBN Chemicals supply system incl. proportioning system
PBP Service water for circulating water treatment
PBQ Injection system for circulating water treatment system
PBR Flushing water and residues removal system
PBS Sludge thickening system
PBT Heating, cooling and flushing fluid distribution system
PBX Fluid supply system for control and protection equipment
PBY Control and protection equipment
PC Service water system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 34 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

PCA Extraction, mechanical cleaning for direct cooling


PCB Service water piping and culvert system
PCC Pump system
PCD Recirculation cooling system, outfall cooling system
PCH Heat exchanger cleaning system
PCM Service water system for generator, motor generator cooling
PCX Fluid supply system for control and protection equipment
PCY Control and protection equipment
PD Service water treatment system
PG Closed cooling water systems
PGB Closed cooling water system
PS Cooling tower blowdown system
PSB Cooling tower blowdown system
PU Common equipment for cooling water systems
PUE Air removal system
PUK Dosing system for sodium bisulfate
PUN Electro-chlorination System
PUP Fish barrier
PUQ Biocide treatment system (Cl2 gas)
PUR Impressed current cathodic protection for mechanical equipment within the
cooling
PUS water
Biocidesystem
generation system
PY Control and protection equipment
PYA Control and protection equipment
Q Auxiliary systems
QC Central chemicals supply
QCA Hydrazine supply and distribution system
QCB Corrosion inhibitor dosing system for open component cooling systems
QCC Phosphate supply and distribution system
QCD Ammonia supply and distribution system
QCH Sodium hydroxide supply and distribution system
QCL Oxygen dosing system (incl. H2O2 dosing)
QCY Control and protection equipment
QEA Central compressed air and carrier air generation system
QEB Central compressed air and carrier air distribution system
QF General control air supply
QFA Central control air generation system
QFB Central control air distribution system
QH Auxiliary steam generating system
QHA Pressure system
QHB Support structure, enclosure, steam generator interior
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 35 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

QHC Fireside heat transfer surface cleaning equipment


QHE Blowdown system, flash drain system
QHF Bunker, feeder and pulverizing system
QHG Boiler water circulation system (also for electrode steam boiler)
QHH Main firing system (electric powered as well)
QHJ Ignition firing equipment
QHL Combustion air system (primary air, secondary air)
QHN Flue gas exhaust (without flue gas treatment)
QJ Central gas supply, also inert gas
QJA Gas supply and distribution system
QJY Control and protection equipment
QK Chilled water systems
QKA Central water chiller
QKM Chilled water system for steam turbine building *UMA*
QL Feed water, steam, condensate cycle of auxiliary steam generating and
distribution
QLA system
Feed water system
QLB Steam system
QLC Condensate system
QLD Condensate polishing plant
QLF Common equipment for auxiliary steam generation and distribution systems
QLY Control and protection equipment
QU Sampling systems
QUA Sampling system for feed water system (*LA*)
QUB Sampling system for steam system (*LB*)
QUC Sampling system for condensate system (*LC*)
QUD Sampling system for auxiliary steam generating system (*QH*, *QL*)
QUE Sampling system for heating and cooling medium system (*SB*, *QK*)
QUG Sampling system for demineralized water system (*GH*)
QUH Sampling system for steam generating system (*HA*)
QUP Sampling system for cooling water system (*P*)
QUS Sampling system for HVAC system (*SA*)
QUW Sampling system for liquid waste (*GM* and similar)
S Ancillary systems
SA Heating, ventilation, air-conditioning (HVAC) systems
SAF HVAC system for steam generator building *UHA*
SAG HVAC system for structure for raw water supply *UGA*
SAH HVAC system for boiler house (*UHA*)
SAM HVAC system for steam turbine building *UMA* and gas turbine building
SAQ *UMB*
HVAC system for workshop and stores building *UST*
SAR HVAC system for flue gas treatment building *UVG*
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 36 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

SAS HVAC system for fire pump house *USG*


SAV HVAC system for office and staff amenities building *UYA*
SAY Heating, ventilation, air-conditioning (HVAC) systems for auxiliary building
SAZ Heating, ventilation, air-conditioning (HVAC) systems for ancillary building
SAX HVAC system for gate house *UYE*
SB Space heating systems
SBA Central heating plant
SBM Space heating system for steam turbine building *UMA*
SBQ Space heating system for workshop and stores building *UST*
SBR Space heating system for flue gas treatment building *UVG*
SBV Space heating system for office and staff amenities building *UYA*
SC Stationary compressed air supplies
SCA Compressed air generation system
SCB Compressed air distribution system
SD Cleaning systems
SDA Cleaning system
SDB Cleaning system
SDC Cleaning system
SDD Cleaning system
SDE Cleaning system
SDF Cleaning system
SDG Cleaning system
SDH Cleaning system
SDJ Cleaning system
SDK Cleaning system
SDL Cleaning system
SDM Cleaning system
SDN Cleaning system
SDP Cleaning system
SDQ Cleaning system
SDR Cleaning system
SDS Cleaning system
SDT Cleaning system
SDU Cleaning system
SG Stationary fire protection systems
SGA Fire water system
SGC Spray deluge system
SGE Sprinkler system
SGF Foam fire-fighting system
SGG Tank roof, tank shell cooling system
SGJ CO2 fire-fighting system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 37 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

SGL Powder fire-fighting system


SGM Inergen fire-fighting system
SGX Fluid supply system for control and protection equipment
SGY Control and protection equipment
SM Cranes, stationary hoists and conveying appliances
SMA Central equipment
SMM Crane in steam turbine building *UMA* and gas turbine building *UMB*
SN Elevators
SNM Elevator in steam turbine building *UMA*
ST Workshop, stores, laboratory equipment and staff amenities
STA Workshop equipment
STC Maintenance area
STE Stores and filling station equipment
STG Laboratory equipment
STP Staff amenities
UA Structures for grid and distribution systems
UAA Switchyard structure
UAB Grid systems switchgear building
UAC Grid systems control building
UAE Structure for pneumatic control system
UAG Structure for transformer
UAH Structure for supports and equipment
UAS Shaft structure (shaft)
UAY Bridge structure
UAZ Ducting structure
UB Structures for power transmission and auxiliary power supply
UBA Foundation for Power Control Center (switchgear building)
UBB Foundation for Power Control Center for HRSG
UBC Structure for offsite system transformers
UBD Structure for low voltage auxiliary power transformers
UBE Structure for medium voltage auxiliary power transformers
UBF Structure for generator transformers
UBG Structure for start-up transformers
UBH Structure for oil collecting pits
UBN Structure for emergency power generating sets (without central water chiller)
UBS Shaft structure (shaft)
UBX Special structure (plant-specific)
UBY Bridge structure
UBZ Ducting structure
UC Structures for instrumentation and control
UCA Unit control room building
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 38 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

UCL Structure for measuring equipment


UCP Cooling water monitoring structure
UCS Shaft structure (shaft)
UCY Bridge structure
UCZ Ducting structure
UE Structures for fuel supply and residues disposal
UEH Structure for unloading and reception of liquid fuels
UEJ Structure for storage of liquid fuels
UEL Structure for forwarding of liquid fuels (e.g. pump house)
UEM Structure for treatment and handling of liquid fuels
UEN Structure for transfer, conversion, storage of gaseous fuels
UER Structure for forwarding of gaseous fuels
UES Shaft structure (shaft)
UEX Special structure (plant-specific)
UEY Bridge structure
UEZ Ducting structure
UG Structures for water supply and disposal
UGA Structure for raw water supply
UGC Structure for demineralized water supply
UGD Structure for demineralization system
UGE Structure for neutralization system
UGF Structure for fire water supply
UGG Structure for drinking water supply
UGH Structure for rainwater
UGJ Structure for cooling tower make-up water treatment
UGK Flocculant mixing chamber
UGL Flocculator structure, flocculator
UGN Treated water basin
UGP Sludge thickener
UGQ Sludge dewatering building
UGR Sludge storage structure
UGS Shaft structure (shaft)
UGU Structure for effluent disposal
UGV Structure for sewerage plant
UGX Special structure (plant-specific)
UGY Piping and cable bridge
UGZ Piping and cable duct
UH Structures for heat generation
UHA Heat recovery steam generator (HRSG)
UHB Auxiliary boiler
UHS Shaft structure (shaft)
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 39 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

UHU Structure for flue gas reheating system


UHV Structure for combustion air circulation (e.g. for forced draft fan)
UHW Boiler blowdown structure
UHY Pipe and cable racks and bridges
UHY Bridge structure
UHZ Ducting structure
UL Structures for steam, water, gas cycles
ULA Feed water pump house
ULC Structure for condensate system
ULD Structure for condensate polishing plant
ULE Structure for emergency supply systems
ULR Structure for steam, water, gas cycle
ULS Shaft structure (shaft)
ULY Bridge structure
ULZ Ducting structure
UM Structures for main machine sets
UMA Steam turbine building
UMB Gas turbine building
UMC Gas and steam turbine building (single-shaft unit)
UMD Combined gas and steam turbine building with HRSG and auxiliary equipment
UMS Shaft structure (shaft)
UMY Piping and cable bridge
UMZ Ducting structure
UP Structures for circulating water systems (e.g. circulating water intake)
UPA Circulating water intake culvert
UPB Service water intake culvert
UPC Circulating water intake structure
UPD Service water intake structure
UPH Circulating water treatment structure
UPJ Service water treatment structure
UPN Circulating water inlet culvert
UPP Service water inlet culvert
UPQ Biocide treatment building
UPR Debris trough
UPS Cooling water measuring / compensator chamber
UPS Shaft structure (shaft)
UPT Screen wash water cleaning structure
UPX Acid proportioning station
UPX Special structure (plant-specific)
UPY Bridge structure
UPZ Ducting structure
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 40 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

UQ Structures for circulating (cooling) water systems (e.g. circulating water pumps
and
UQA outfall)
Circulating water pump building
UQB Service water pump building
UQF Circulating water storage pit
UQG Circulating water overflow structure, surge tank
UQH Screen wash water discharge culvert
UQJ Circulating water seal pit, incl. circulating water aeration structure
UQK Circulating water venting structure
UQL Service water surge pond
UQM Service water collecting pond
UQN Circulating water outfall culvert
UQP Service water outfall culvert
UQQ Circulating water outfall structure
UQR Service water outfall structure
UQS Shaft structure (shaft)
UQT Service (secondary cooling) water discharge culvert
UQU Circulating water spillway structure, incl. circulating water aeration structure
UQV Structure for artificial circulating water aeration
UQW Routing structure for circulating water discharge
UQX Special structure (plant-specific)
UQY Bridge structure
UQZ Ducting structure
UR Structures for circulating (cooling) water systems (e.g. recirculation cooling)
URA Cooling tower structure (circulating water)
URB Cooling tower structure (service water)
URC Structure for air cooled condenser
URD Cooling tower pump building (circulating water)
URE Cooling tower pump building (service water)
URG Cooling tower connecting structure
URH Cooling tower outlet structure
URJ Cooling tower outfall culvert
URK Cooling tower return structure
URL Cooling tower return culvert
URM Circulating water distribution building
URN Cooling tower bypass structure
URP Cooling tower blowdown structure
URQ Cooling tower blowdown culvert
URS Shaft structure (shaft)
URX Special structure (plant-specific)
URY Bridge structure
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 41 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

URZ Ducting structure


US Structures for ancillary systems
USA Structure for heating, ventilation, air-conditioning (HVAC) systems
USB Structure for space heating systems
USC Structure for stationary compressed air supply system
USG Fire pump house
USR Structure for waste treatment
USS Shaft structure (shaft)
UST Workshop/stores building
USU Consumables storage building
USV Laboratory building
USX Foam station
USY Bridge structure
USZ Ducting structure
UT Structures for auxiliary systems
UTA Supply systems building
UTB Central water chiller building
UTF Compressed air system building
UTG Central gas supply systems building (no fuel supply)
UTH Auxiliary steam generator building
UTK Fuel oil pump house
UTR Chemical storage tank pit
UTS Shaft structure (shaft)
UTX Special structure (plant-specific)
UTY Bridge structure
UTZ Ducting structure
UX Structures for external systems (power plant-specific)
UXA Structure for seawater desalination plant
UY General service structures
UYA Office and staff amenities building
UYB Staff amenities building
UYC Administration building
UYD Canteen
UYE Gate house
UYF Security gate house
UYG Information center
UYP Fire station
UYQ Garage
UYR Automobile workshop
UYS Shaft structure (shaft)
UYT Filling station
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 42 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

UYY Bridge structure


UYZ Ducting structure
UZ Structures for transport, traffic, fencing, gardens and other purposes
UZA Road
UZA Works roadway, path (incl. associated structures)
UZD Parking area (incl. associated structures)
UZJ Fencing and gate
UZP Structure for bank/shoreline stabilization
UZR Jetty, quay
UZS Shaft structure (shaft)
UZT Piping/cable route in outdoor area
UZU Site security structure
UZW Residential building, residential area
UZX Special structure (plant-specific)
UZY Bridge structure
UZZ Ducting structure
XJ Diesel engine plant
XJA Engine
XJB Turbocharger, blower
XJG Liquid cooling system
XJH Air intercooling system
XJK Transmission gear between prime mover and driven machine
XJN Fuel system
XJP Start-up unit (incl. flywheel)
XJQ Air intake system
XJR Exhaust gas system
XJV Lubricant supply system
XJX Fluid supply system for control and protection equipment
XJY Control and protection equipment
XK Generator plant
XKA Generator casing, incl. stator, rotor and all integral cooling equipment
XKC Generator exciter set, including set with electrical braking system
XKW Sealing oil system, incl. supply and treatment
XKY Control and protection equipment
XKY Control and protection equipment
XP Common installations for heavy machinery
XPA Foundation
XPB Sheathing
XPG Frame, support structure
XJR Exhaust gas system
XJV Lubricant supply system
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 43 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

XJX Fluid supply system for control and protection equipment


XJY Control and protection equipment
XK Generator plant
XKA Generator casing, incl. stator, rotor and all integral cooling equipment
XKC Generator exciter set, including set with electrical braking system
XKW Sealing oil system, incl. supply and treatment
XKY Control and protection equipment
XKY Control and protection equipment
XP Common installations for heavy machinery
XPA Foundation
XPB Sheathing
XPG Frame, support structure
XPR Forced cooling system
XPS Drying and layup system
XY Control and protection equipment
XYA Control and protection equipment
ZA Equipment for administration building (*UYC*)
ZB Equipment for kitchen (*UYD*)
ZC Equipment for canteen (*UYD*)
ZD Equipment for gate house (*UYE*)
ZE Equipment for information center (*UYG*)
ZF Equipment for training facilities (*UYH*)
ZG Equipment for medical center (*UYJ*)
ZH Equipment for fire station (*UYP*)
ZJ Equipment for automobile workshop (*UYR*)
ZK Equipment for special structures (*UYX*)
ZL Equipment for residential buildings (*UZW*)
ZM Equipment for control room
ZT Temporary workshop and office equipment for erection and commissioning
ZTA Temporary acid cleaning system
ZTB Temporary steam blowing system
ZTD Temporary demineralized water supply

11. KKS EQUIPMENT UNIT CODE

A Mechanical equipment
AA Valves, dampers, etc., incl. actuators, also manual; Rupture disk equipment
AB Isolating elements, airlocks

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 44 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

AC Heat exchangers, heat transfer surfaces


AE Turning, driving, lifting and slewing gear (also manipulators)

AF Continuous conveyors, feeders (escalators)


AG Generator units
AH Heating, cooling and air conditioning units
AJ Size reduction equipment, only as part of process
AK Compacting and packaging equipment, only as part of process
AM Mixers, agitators
AN Compressor units, fans
AP Pump units
Adjusting and tensioning equipment for non-electrical variables (to be applied
AS
only, if the actuator forms itself a constructive unit with another equipment unit)
AT Cleaning drying, filtering and separating equipment, excl. *BT*
AU Braking, gearbox, coupling equipment, non-electrical converters
AV Combustion equipment
AW Stationary tooling, treatment equipment
AX Test and monitoring equipment for plant maintenance

B Mechanical equipment
BB Storage equipment (tanks)
BE Shafts (for erection and maintenance only)
BF Foundations
BN Jet pumps, ejectors, injectors
BP Flow restrictors, limiters, orifices (not metering orifices)
BQ Hangers, supports, racks, piping penetrations
BR Piping, ductwork, chutes
BS Silencers
BT Flue gas catalytic converter modules
BU Insulation, sheathing

C Direct measuring circuits


CD Density
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 45 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

CE Electrical variables (e.g. current, voltage, power, electric, frequency)


Flow, rate (Flow transmitter, Flow meter, Flow switch, Flow orifice, Flow venturi,
CF Flow valve, Flow controller, Flow glass)
CG Distance, length, position, direction of rotation, wind direction

CH Manual input as manually operated sensor (e.g. fire detector)


CK Time
CL Level (also for dividing line)
CM Moisture, humidity
CP Pressure
CQ Quality variables (analysis, material properties), other than *CD*, *CM*,*CV*
CS Velocity, speed, frequency (mechanical), acceleration
CT Temperature
CU Combined and other variables
CV Viscosity
CW Weight, mass
CY Vibration, expansion

D Closed loop control circuits


DD Density
DE Electrical variables (e.g. current, voltage, power, electric, frequency)
DF Flow, rate
DG Distance, length, position, direction of rotation
DK Time
DL Level (also for dividing line)
DM Moisture, humidity
DP Pressure
DQ Quality variables (analysis, material properties), other than *DD*, *DM*,*DV*
DS Velocity, speed, frequency (mechanical), acceleration
DT Temperature
DU Combined and other variables
DV Viscosity

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 46 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

DW Weight, mass
DY Vibration, expansion

E Analog and binary signal conditioning


EA Open loop control

EB Group control

EC Subgroup control
EE Subloop control, equipment unit changeover
EG Alarm, annunciation (Alarm for danger )
EH Alarm, annunciation (Prealarm)
EJ Visualization of operation and monitoring displays
EK Alarm logics
EM Process computer
EN State-display computer, criterion display
EP Supervisory computer
EQ Internal automation (signal processing)
ES Internal automation (signal conditioning)
EU Combined analog and binary signal conditioning
EV Signal transmission, bus coupling
EW Protection
EY Protective logics, priority, non-equipment-unit-related
EZ Super-ordinate equipment unit protection

F Indirect measuring circuits


FD Density
FE Electrical variables (e.g. electr. Efficiency, power)
FF Flow, rate
FG Distance, length, position, direction of rotation
FK Time
FL Level (also for dividing line)
FM Moisture, humidity
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 47 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

FP Pressure
FQ Quality variables (analysis, material properties), other than *DD*, *DM*,*DV*
FS Velocity, speed, frequency (mechanical), acceleration
FT Temperature
FU Combined and other variables
FV Viscosity
FW Weight, mass
FY Vibration, expansion

G Electrical equipment
GA Junction boxes and cable
GB Cable/busbar penetrations
Electrical and instrumentation and control installation units identified as per
GH
process system (e.g. cubicles, boxes)
Information display and operator control equipment for process computers and
GK automation systems
GM Junction boxes for light-current systems of national telecommunication services
GP Sub distribution / junction boxes for lighting
GQ Sub distribution / junction boxes for power sockets
GR DC generating equipment, batteries
GS Switchgear equipment if not identified under process equipment
GT Transformer equipment
GU Converter equipment
GV Structure-related earthing and lightning protection equipment, surge arrestors
GW Cabinet power supply equipment
GX Actuating equipment for electrical variables
Junction boxes for light-current systems (not of national telecommunication
GY
services)
Hangers, supports and racks for electrical and instrumentation and control
GZ
equipment

Subassemblies of main and heavy machinery (only to be used in


H conjunction with *M*=Main machine sets and *X*=Heavy machinery)
HA Machine stationary assembly
This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 48 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

HB Machine rotating assembly


HD Bearing assembly

12. KKS COMPONENT CODE

This document is intended to be an identification aid only

If contains no binding information about scope of supply

- Electrical components
-A Assemblies and subassemblies
-B Transducers for non-electrical to electrical variables and vice-versa

-C Capacitors
-D Binary elements, delay devices, memory devices
-E Special components
-F Protective devices
-G Generators, power supplies
-H Signaling devices
-K Relays, contactors
-L Inductors
-M Motors
-N Amplifiers, controllers
-P Measuring instruments, testing equipment
-Q Power switchgear
-R Resistors
-S Switches, selectors
-T Transformers
-U Modulators, convertors from electrical to other electrical variables
-V Tubes, semiconductors
-W Transmission paths, waveguides, aerials
-X Terminals, plugs, sockets
-Y Electrical positioners, e.g. solenoids (not motors)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 49 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

-Z Terminators, balancing equipment, filters, limiters, cable terminations

K Mechanical components
KA Gate valves, globe valves, dampers, cocks, rupture disks, orifices
KB Gates, doors, dam boards
KC Heat exchangers, coolers
KD Vessels/tanks, pools, surge tanks (fluid systems)
KE Turning, driving, lifting and slewing gear
KF Continuous conveyors, feeders
KJ Size reduction machines
KK Compacting, packaging machines
KM Mixers, agitators
KN Compressors, blowers, fans

KP Pumps
KT Cleaning machines, dryers, separators, filters
KV Burners, grates
KW Stationary tooling and treatment machines for maintenance

M Mechanical components
MB Brakes
MF Foundations
MG Gearboxes
MK Clutches, couplings
MM Engines, not electrical
MR Piping components, ductwork components
MS Positioners, not electrical
MT Turbines
Transmission gear, non electrical, converters and boosters other than couplings
MU and gearboxes

Q Instrumentation and Control Components (non-electrical)

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 50 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

QA Enclosures (for I & C component protection only)


QB Sensors if not structurally integral with “QP”, metering orifices
QH Signaling devices
QN Controllers, fly bolt governor
QP Measuring instruments, testing equipment
QR Instrument piping
QS Condensation chambers (datum reservoir) in measuring circuits
QT Thermowells and pockets for protection of sensors

X Signal Origins
XA Functional group control / subgroup control
XB Control interfaces
XC Closed loop control
XD Reactor protection, signals in binary signal processing section
XE Reactor protection, signals in analog and binary sections

XF Priority control
XG Binary process signals conditioned by binary signal conditioning modules
XH Binary limit signals derived from analog process signals
XK Equipment unit / component protection
Control room and control stations, signals not assigned to specific control
XL
systems (e.g. control interface tiles)
XM Alarm signals
XN Status display computer / criterion display
XP Supervisory computer (process computer)
XQ Analog signals
Priority control and limitation function (control other than “XC” and “XT”, “YC” and
XR
“YT”)
XS Functional group control step signals
XT Turbine generator I & C, binary signals
XU Non-floating dynamic alarm signals
XW Hardwired alarm annunciation system

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 51 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

Y Signal Applications
YA Functional group control / subgroup control
YB Control interfaces
YC Closed loop control
YD Reactor protection, signals in binary signal processing section
YE Reactor protection, signals in analog and binary sections
YF Priority control
YJ Signal from non-standard areas (e.g. black box, dedicated I & C)
Control room and control stations, signals not assigned to specific control
YL systems (e.g. control interface tiles)
YN Status display computer / criterion display
YP Supervisory computer (process computer)
YQ Analog signals
Priority control and limitation function (control other than “XC” and “XT”, “YC” and
YR
“YT”)
YT Turbine generator I & C, binary signals
YV Signal gating (protective logic, alarm logic, etc)
YW Hardwired alarm annunciation system

13. KKS CODE APPLICATION FOR LEVEL 3

A. MCC for PUMPS


1) STATUS FEED BACK
- RUNNING nnaaannaannnXB01
- STOPED nnaaannaannnXB02
- DISTURBED(FAULT) nnaaannaannnXB48

2) COMMAND
- START / ON (or Start/Stop, On/Off) nnaaannaannnYB01
- STOP / OFF nnaaannaannnYB02
LCS(LOCAL SELECT) nnaaannaannnYB05

B. SWICHGEAR for Pump

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 52 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

1) STATUS FEED BACK


- RUNNING nnaaannaannnXB01
- STOPPED nnaaannaannnXB02
- ELECTRICAL FAULT nnaaannaannnXB48
- TEST POSITION nnaaannaannnXB82
- SWITCHGEAR AVAILABLE nnaaannaannnXB03
- MASTER TRIP RELAY OPERATED nnaaannaannnXB04
- LOCAL EMERGENCY PB OPERATED nnaaannaannnXB42
- REMOTE SLECTED nnaaannaannnXB43
- TRIP ON OVERLOAD nnaaannaannnXB47
- CURRENT nnaaannaannnXQ11
2) COMMAND
- START/ON nnaaannaannnYB01
- STOP/OFF nnaaannaannnYB02

C. MOTOR OPERATED VALVE (ON/OFF)


1) STATUS FEED BACK
OPENED LIMIT SWITCH nnaaannaannnXB01
CLOSED LIMIT SWITCH nnaaannaannnXB02
OPENED TORQUE SWITCH nnaaannaannnXB05
CLOSED TORQUE SWITCH nnaaannaannnXB06
REMOTE SLECTED nnaaannaannnXB43
FAULT(DISTURBED) nnaaannaannnXB48
POSITION TRANSMITTER(INCHING MOV only) nnaaannaannnXQ12
2) COMMAND TO DRIVE(MOV)
- OPEN COMMAND nnaaannaannnYB01
- CLOSE COMMAND nnaaannaannnYB02

D. MOV (INCHING)
1) STATUS FEED BACK
- POSITION TRANSMITTER nnaaannaannnXQ12
- REMOTE SELECTED nnaaannaannnXB43

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 53 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

- FAULT(DISTURBED) nnaaannaannnXB48
OPENED LIMIT SWITCH nnaaannaannnXB01
CLOSED LIMIT SWITCH nnaaannaannnXB02
OPENED TORQUE SWITCH nnaaannaannnXB05
CLOSED TORQUE SWITCH nnaaannaannnXB06
2) COMMAND TO DRIVE(MOV)
- ANALOG OUTPUT COMMAND nnaaannaannnYQ12

E. PNEUMATIC CONTROL VALVE AND DAMPER (MODULATING)


1) STATUS FEED BACK
- POSITION TRANSMITTER nnaaannaannnXQ12
2) COMMAND TO DRIVE
- ANALOG OUTPUT COMMAND nnaaannaannnYQ12

F. PNEUMATIC SHUT-OFF VALVE (SINGLE SOLENOID)


1) STATUS FEED BACK
- OPEN POSITION nnaaannaannnXB01
- CLOSE POSITIION nnaaannaannnXB02
- FAULT nnaaannaannnXB48

2) COMMAND TO DRIVE
- ENERZIGE/DE-ENERZIGE nnaaannaannnYB01

G. PNEUMATIC SHUT-OFF VALVE (DUAL SOLENOID)


1) STATUS FEED BACK
- OPENED STATUS nnaaannaannnXG01
- CLOSED STATUS nnaaannaannnXG02
- FAULT nnaaannaannnXG48
2) COMMAND TO DRIVE
- OPEN COMMAND nnaaannaannnYB01
- CLOSE COMMAND nnaaannaannnYB02

H. MANUAL VALVE.OTHERS POSITIONS


This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.
Doc. No. : THPE-00-Y-KM-TCE-001
PROJECT TAGGING GUIDELINES Page : 54 OF 54
– KKS SYSTEM Date : 03.06.2022
Revision :A

1) STATUS FEED BACK


- POSITION TRANSMITTER nnaaannaannnXQ12
- POSITION OPEN STATUS nnaaannaannnXG01
- POSITION CLOSE STATUS nnaaannaannnXG02

I. HIGH ENERGY IGNITOR SPARK/ SOOT BLOWERS


1) STATUS FEED BACK
- EXTENDED nnaaannaannnXB01
- RETRACTED nnaaannaannnXB02
- ENERZIGED/DE-ENERZIGED nnaaannaannnXB03
- FAULT/DISTURBED nnaaannaannnXB48
2) COMMAND TO DRIVE
- EXTEND nnaaannaannnYB01
- RETRACT nnaaannaannnYB02
- ENERZIGE/DE-ENERZIGE nnaaannaannnYB03

J. FIELD INSTRUMENTS
1) TRANSMITTERS
- TRANSMITTERS (4-20 mA) nnaaannaannnXQ01
- Temperature Element (T/C, RTD, Thermisters
nnaaannaannnXQ02
etc.,)
- Other analogue signal from the same instrument nnaaannaannnXQ03~09

2) SWITCHES
1. SPDT(FROM PROCESS ELEMENT)
- SWITCH HIGH(NO) nnaaannaannnXG01
- SWITCH LOW(NO) nnaaannaannnXG02
- SWITCH HIGH-HIGH(NO) nnaaannaannnXG03
- SWITCH LOW-LOW(NO) nnaaannaannnXG04
- SWITCH HIGH(NC) nnaaannaannnXG51
- SWITCH LOW(NC) nnaaannaannnXG52
- SWITCH LOW-LOW(NC) nnaaannaannnXG54
- SWITCH HIGH-HIGH(NC) nnaaannaannnXG53

This document is the property of ÇALIK Enerji Sanayi ve Ticaret A.Ş and may not be copied, used, reprinted or distributed by others.