Professional Documents
Culture Documents
Location : #REF!
Contractor : #REF!
EFFECTIVITY : #REF!
ORIGINAL DURATION
48 CALENDAR DAYS
March 1-31, 2020 April 1-30, 2020 May 1-31, 2020 June 1-30, 2020
July 1-31, 2020 August 1-31, 2020 September 1-30, 2020 October 1-31, 2020
#REF!
#REF!
PREPARED BY:
###
###
#REF! #REF!
#REF! #REF!
Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGION OFFICE X
Pinamaloy, Don Carlos, Bukidnon
Project ID : P00631269MN-CW1
Project Name : CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
Location : BARANGAY MASCARINAS, KIBAWE, BUKIDNON
Contractor : ZULAR-AZ CONSTRUCTION & SUPPLY, INC.
# L W D
add stair 2 33.00 0.40 0.70 = 18.48
SLAB 1 30.00 2.00 0.10 = 6.26
less SLAB 1 6.00 18.50 0.10 = 11.10
SLAB 2 24.00 1.60 0.20 = 15.36
1.72 Cu.m
# L W D V
stair 2 6.00 0.30 0.20 = 0.72
2 6.00 0.30 0.40 = 1.44
1 6.00 0.30 0.60 = 1.08
slab 1 30.00 2.00 0.10 = 6.00
bleacher 1 1.20 1.00 6.00 = 6.60
1 1.00 0.80 6.00 = 5.40
1 0.40 0.20 6.00 = 1.80
1 0.20 0.00 6.00 = 0.60
1 0.95 0.90 6.00 = 5.55
1 0.90 0.80 6.00 = 5.10
1 0.60 0.40 6.00 = 3.00
1 0.40 0.60 6.00 = 3.00
44.01 Cu.m
# L W D
add stair 2 24.00 0.30 0.10 = 1.44
slab 1 30.00 2.00 0.10 = 6.00
less SLAB 1 6.00 18.50 0.10 = 11.10
SLAB 2 24.00 1.60 0.10 = 7.68
11.34 Cu.m
# L W D
add stair 2 24.00 0.30 0.10 = 1.44
slab 1 30.00 2.00 0.10 = 6.00
less SLAB 1 6.00 18.50 0.10 = 11.10
SLAB 2 24.00 1.60 0.10 = 7.68
11.34 Cu.m
ITEM 902(1)a Reinforcing Steel (Deformed), Grade 40
Introduced Quantity : 2,596.95 kg
Decreased Quantity : 56.99 kg
Revised Quantity : 2,653.94 kg
# # OF BARS L factor
stair WF 12mm 1 165.00 0.30 0.89 44.06
stair WF 12mm 1 3.00 66.00 0.89 176.22
stair slab 10mm 1 3.00 48.00 0.62 89.28
slab 10mm 1 98.00 0.40 0.62 24.30
2m slab 10mm 1 5.00 30.00 0.62 93.00
slab 10mm 1 61.00 2.00 0.62 75.64
less CC 10mm 1 12.00 19.70 0.62 146.57
10mm 1 37.00 7.20 0.62 165.17
10mm 2 3.00 25.00 0.62 93.00
10mm 2 48.00 2.60 0.62 154.75
56.99 kg
No. L W area
add stair 2.00 6.00 1.80 = 21.60
slab 1.00 30.00 2.00 = 60.00
less slab 1.00 6.00 18.50 = 111.00
slab 2.00 24.00 1.60 = 76.80
7.08 L
H L # area
bleacher 1.20 1.00 6.00 = 6.60
1.00 0.80 6.00 = 5.40
0.40 0.20 6.00 = 1.80
0.20 0.00 6.00 = 0.60
0.95 0.90 6.00 = 5.55
0.90 0.80 6.00 = 5.10
0.60 0.40 6.00 = 3.00
0.40 0.60 6.00 = 3.00
stair 0.20 6.00 2.00 = 2.40
0.40 6.00 2.00 = 4.80
0.60 6.00 1.00 = 3.60
0.20 1.50 4.00 = 1.20
0.40 1.50 4.00 = 2.40
0.60 1.50 2.00 = 1.80
0.80 1.50 2.00 = 2.40
51.51 Sq.m
H L # area
bleacher 1.20 1.00 6.00 = 6.60
1.00 0.80 6.00 = 5.40
0.40 0.20 6.00 = 1.80
0.20 0.00 6.00 = 0.60
0.95 0.90 6.00 = 5.55
0.90 0.80 6.00 = 5.10
0.60 0.40 6.00 = 3.00
0.40 0.60 6.00 = 3.00
stair 0.20 6.00 2.00 = 2.40
0.40 6.00 2.00 = 4.80
0.60 6.00 1.00 = 3.60
0.20 1.50 4.00 = 1.20
0.40 1.50 4.00 = 2.40
0.60 1.50 2.00 = 1.80
0.80 1.50 2.00 = 2.40
51.51 Sq.m
ITEM 1051(1) Railings
Introduced Quantity : - m
Increased Quantity : 57.60 m
Revised Quantity : 57.60 m
L # L
2.70 16.00 = 43.20
V 0.90 16.00 = 14.40
57.60 m
L # L
49.60 1.00 = 49.60
49.60 m
Prepared by:
AMELITO D. ARANQUEZ
Proprietor
ITEMIZED QUANTITIES AND COST OF VARIATION WORK ORDER
PROJECT CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ZULAR-AZ CONSTRUCTION & SUPPLY, INC.
BUKIDNON SECOND
AS PER ORIGINAL CONTRACT COST AND QUANTITIES WITHIN LIMITS OF THIS QUANTITIES OF THIS VARIATION
DISTRICT ENGINEERING OFFICE
VARIATION/EXTRA WORK ORDER ORDER No.01
Pinamaloy, Don Carlos, Bukidnon REMARKS
ADDITIVE DEDUCTIVE
ITEM NO. DESCRIPTION UNIT UNIT COST QUANTITY AMOUNT QUANTITY TOTAL AMOUNT
QUANTITY AMOUNT QUANTITY AMOUNT
B.5 Project Billboard / Signboard each 3,780.00 2.00 7,560.00 - - 2.00 7,560.00 NO CHANGE
B.7(2) Occupational Safety and Health Program ls 133,560.00 1.00 133,560.00 - - 1.00 133,560.00 NO CHANGE
B.9 Mobilization / Demobilization ls 126,000.00 1.00 126,000.00 - - 1.00 126,000.00 NO CHANGE
803(1)a Structure Excavation (Common Soil) Cu.m 552.29 67.53 37,296.14 - 1.72 950.570 65.81 36,345.58 DECREASED
804(1)a Embankment (From roadway / structure excavation) Cu.m 143.30 67.53 9,677.05 - - 67.53 9,677.05 NO CHANGE
804(1)b Embankment (From Borrow) Cu.m 1,016.90 38.63 39,282.85 56.37 57,326.86 - 95.00 96,609.71 INCREASED
804(4) Gravel Fill Cu.m 1,024.10 24.73 25,325.99 - 11.34 11,613.290 13.39 13,712.70 DECREASED
900(1)c2 Structural Concrete (Footings) (Class A, 28 days) Cu.m 8,553.71 11.90 101,789.15 - - 11.90 101,789.15 NO CHANGE
900(1)c4 Structural Concrete (Columns) (Class A, 28 days) Cu.m 8,673.98 3.84 33,308.08 - - 3.84 33,308.08 NO CHANGE
900(2)c Structural Concrete (Class B, 28 days) Cu.m 7,694.88 27.37 210,608.87 - 11.34 87,259.940 16.03 123,348.93 DECREASED
902(1)a Reinforcing Steel (Deformed), Grade 40 kg 72.08 2,596.95 187,188.16 - 56.99 4,107.840 2,539.96 183,080.32 DECREASED
903(2) Formworks and Falseworks Sq.m 719.74 64.00 46,063.36 - - 64.00 46,063.36 NO CHANGE
1000(1) Soil Poisoning L 673.29 16.49 11,102.55 - 7.08 4,766.890 9.41 6,335.66 DECREASED
1003(11)a1 Fascia Board (Fiber Cement Board) M 795.55 183.74 146,174.36 - - 183.74 146,174.36 NO CHANGE
1046(2)a1 CHB Non-Load Bearing (including reinforcing Steel), 100mm Sq.m 924.74 248.32 229,631.44 51.51 47,633.36 - 299.83 277,264.79 INCREASED
1032(1)a Painting Works (Masonry / Concrete) Sq.m 374.02 238.24 89,106.52 - - 238.24 89,106.52 NO CHANGE
1032(1)c Painting Works (Steel) Sq.m 486.68 215.60 104,928.21 - - 215.60 104,928.21 NO CHANGE
1027(1) Cement Plaster Finish Sq.m 224.37 207.36 46,525.36 51.51 11,557.30 - 258.87 58,082.66 INCREASED
1021(1)a Cement Floor Finish (Plain) Sq.m 220.27 187.80 41,366.71 - 187.80 41,366.710 - - DELETED
1048(6) Glass Fiber Ls 252,000.00 1.00 252,000.00 - 1.00 252,000.000 - - DELETED
1014(1)b2 Prepainted Metal Sheets, above 0.427mm (Rib Type, Long span) Sq.m 1,209.22 162.30 196,256.41 - - 162.30 196,256.41 NO CHANGE
1013(2)a2 Fabricated Metal Roofing Accessory, gauge 26 (Flashings) Lm 352.12 54.92 19,338.43 - - 54.92 19,338.43 NO CHANGE
1013(2)b1 Fabricated Metal Roofing Accessory, gauge 26 (Gutters) Lm 480.52 129.84 62,390.72 - - 129.84 62,390.72 NO CHANGE
1001(9) Storm Drainage and Donwspout Ls 15,120.00 1.00 15,120.00 - - 1.00 15,120.00 NO CHANGE
1047(2)a Structural Steel (Trusses) kg 109.01 3,141.80 342,487.62 - - 3,141.80 342,487.62 NO CHANGE
1047(1) Structural Steel Ls 63,000.00 1.00 63,000.00 - - 1.00 63,000.00 NO CHANGE
1047(2)b Structural Steel (Purlins) kg 104.27 1,019.24 106,276.15 - - 1,019.24 106,276.15 NO CHANGE
1047(3)c Metal Structure Accessories (Turnbuckle) each 592.20 20.00 11,844.00 - - 20.00 11,844.00 NO CHANGE
1047(4) Metal Structure Accessories (Cross Bracing) kg 570.80 129.47 73,901.48 - - 129.47 73,901.48 NO CHANGE
1047(7)a Metal Structure Accessories (Bolts) kg 567.87 35.51 20,165.06 - - 35.51 20,165.06 NO CHANGE
1047(6) Metal Structure Accessories (Steel Plates) kg 117.73 633.02 74,525.44 - - 633.02 74,525.44 NO CHANGE
1047(7)b Metal Structure Accessories (Sagrods) kg 715.68 19.73 14,120.37 - - 19.73 14,120.37 NO CHANGE
1100(10) Conduits, Boxes & Fittings (Conduit Works / Conduit Rough-in) Ls 25,200.00 1.00 25,200.00 - - 1.00 25,200.00 NO CHANGE
1101(33) Wires and Wiring Devices Ls 31,500.00 1.00 31,500.00 - - 1.00 31,500.00 NO CHANGE
1102(1) Panelboard with Main & Branch Breakers Ls 12,600.00 1.00 12,600.00 - - 1.00 12,600.00 NO CHANGE
1103(1) Lighting Fixtures and Lamps Ls 18,900.76 1.00 18,900.76 - - 1.00 18,900.76 DELETED
NEW ITEM
1048(6) Glass Fiber Ls 57,235.89 - - 1.00 57,235.88 - 1.00 57,235.89 NEW ITEM
1103(1) Lighting Fixtures and Lamps (a) Ls 72,318.12 - - 1.00 72,318.12 - 1.00 72,318.12 NEW ITEM
401(1)a2 Metal Railing - Grade 50 (Steel) m 2,239.10 - - 49.60 111,059.17 - 49.60 111,059.17 NEW ITEM
1051(1) Railings m 847.45 - - 57.60 48,813.30 - 57.60 48,813.30 NEW ITEM
TOTAL COST: Php 2,966,121.24 Php 405,943.99 Php 402,065.24 Php 2,970,000.00
Concurred:
Original Sum Involve in this Revision (Php) 2,966,121.24
New Sum Involve in this Revision (Php) 2,970,000.00
AMELITO D. ARANQUEZ Difference Cost (Php) 3,878.76
Proprietor
Indangan, Davao City % CHANGE FROM ORIGINAL COST 0.13%
ISABELITA D. BALBA REYNALDO S. EMETERIO NORMA A. OGABANG MANUEL D. VARIAS, JR. MARIVEL FRANCES L. ONG, A.E.R.
Project Engineer II Chief, Construction Section Chief, Planning and Design Section OIC-Assistant District Engineer District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon
CONTRCT ID NO. : 22KB0051
VARIATION ORDER : Variation Order 1
NAME OF PROJECT : CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
LOCATION : BARANGAY MASCARINAS, KIBAWE, BUKIDNON
CONTRACTOR : ZULAR-AZ CONSTRUCTION & SUPPLY, INC.
You are hereby directed to make herein changes from the plans, specification, or do the following work not in the plans and specification.
Item No. 803(1)a Structure Excavation (Common Soil), decreased from 67.53 Cu.m to 65.8088599687663 Cu.m
Item No. 804(1)b Embankment (From Borrow), increased from 38.63 Cu.m to 95.0041360999126 Cu.m
Item No. 804(4) Gravel Fill, decreased from 24.73 Cu.m to 13.39 Cu.m
Item No. 900(2)c Structural Concrete (Class B, 28 days), decreased from 27.37 Cu.m to 16.03 Cu.m
Item No. 902(1)a Reinforcing Steel (Deformed), Grade 40, decreased from 2596.95 kg to 2539.96 kg
Item No. 1000(1) Soil Poisoning, decreased from 16.49 L to 9.41 L
Item No. 1046(2)a1 CHB Non-Load Bearing (including reinforcing Steel), 100mm, increased from 248.32 Sq.m to 299.83 Sq.m
Item No. 1027(1) Cement Plaster Finish, increased from 207.36 Sq.m to 258.87 Sq.m
Item No. 1021(1)a Cement Floor Finish (Plain), Item Deleted
Item No. 1048(6) Glass Fiber, Item Deleted
Item No. 1103(1) Lighting Fixtures and Lamps, Item Deleted
Item No. 1048(6) Glass Fiber, New Item, 1 Ls
Item No. 1103(1) Lighting Fixtures and Lamps (a), New Item, 1 Ls
Item No. 401(1)a2 Metal Railing - Grade 50 (Steel), New Item, 49.6 m
Item No. 1051(1) Railings, New Item, 57.6 m
Due to the change of building orientation to utilize the available proposed project site.
Work to be performed under this Variation/ Change Order, shall be based on the existing contract prices
ITEMIZED QUANTITIES AND COST OF REVISION ARE IN SEPARATE SHEET
I, the undersigned contractor has given careful consideration to the proposed Variation Order No. 01 of the Difference cost due to Variation Order #1 : (+) PhP 3,878.76
above named project, hereby agree, if this proposal approved, I will provide all equipments, and furnish all Original Sum Involve in this Revision : PhP 2,966,121.240
materials except on as may otherwise be noted above on the sheet specified. New Sum Involve in this Revision : PhP 2,970,000.000
Percentage of Variation : 0.13%
REYNALDO S. EMETERIO NORMA A. OGABANG MANUEL D. VARIAS, JR. MARIVEL FRANCES L. ONG, A.E.R
Chief, Construction Section Chief, Planning and Design Section OIC-Assistant District Engineer District Engineer
CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
BARANGAY MASCARINAS, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1048(6) Glass Fiber
Unit of Measurement: ls
Output per hour - As Submitted: 1.000 LS
Output per hour - As Evaluated:
Labor cost for these items are to be considered/included in the installation of doors, windows and other fabricated materials
Project ID : P00443910MN-CW1
Project Name : CONSTRUCTION OF MULTI-PURPOSE BUILDING
Location : BARANGAY POBLACION, DANGCAGAN BUKIDNON
Contractor : CARESYSTEM
Err:509
Err:509 Err:509 Err:509
Err:509
Err:509 Err:509 Err:509
Err:509
Err:509 Err:509 Err:509
Err:509
Err:509 Err:509 Err:509
Err:509
Err:509 Err:509 Err:509
Err:509
Err:509 Err:509 Err:509
#REF!
CHRONOLOGY OF EVENTS
DATE ACTIVITY
#REF! Issued of Notice to Proceed to the Contractor
#REF! Effectivity of the contract
Issuance of Proclamation Order No. 922 Declaring the State of
March 08, 2020 Public Health Emergency Throughout the Philippines due to
Covit-19 threat.
#REF!
#REF!
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND DISTRICT
ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon
#REF!
Present:
REYNALDO S. EMETERIO - Chief, Construction Section - DPWH
#REF! - Project Engineer - DPWH
CARLITO G. MAGONCIA - Project Engineer - DPWH
LUZMINDA C. VIRTUDAZO - Project Engineer - DPWH
JONALIE S. ABENOJA-BAYANBAN - Project Engineer - DPWH
JOAN M. ESTIGOY-FEROLINO - Project Engineer - DPWH
AMELIA T. GONZALES - Project Inspector - DPWH
WALDO RAE C. BOLONOS - Project Inspector - DPWH
There being no other issues/concerns to be taken up, the meeting was adjourned at 10:30 in the
morning.
I hereby certify to the correctness of the above statements.
#REF!
#REF!
Attested:
#REF! #REF!
#REF! #REF!
CONTRACT ID : ###
PROJECT NAME : #REF!
LOCATION : ###
STATION LIMIT : n/a
CONTRACTOR : ###
CONSTRUCTION MEETING
Submitted by:
###
###
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon
#REF!
SUBJECT : COMMENTS/RECOMMENDATION
#REF!
#REF!
1. CONTRACTUAL DATA
a. Original Contract Amount -- #REF!
b. Revised Contract Amount -- #REF!
c. Effectivity of Contract -- #REF!
d. Original Expiry Date -- #REF!
e. Revised Contract Expiry -- #REF!
#REF!
h. Contractor -- #REF!
2. #REF!
3. #REF!
4. #REF!
5. #REF!
###
###
###
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X
BUKIDNON 2ND DISTRICT ENGINEERING
Pinamaloy, Don Carlos, Bukidnon
#REF!
#REF!
#REF!
Certified by:
###
###
Sheet Content: Prepared by: Submitted by: Recommending Approval: Approved by:
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X
BUKIDNON 2ND DISTRICT ENGINEERING
Pinamaloy, Don Carlos, Bukidnon
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X
BUKIDNON 2ND DISTRICT ENGINEERING #REF! REYNALDO S. EMETERIO MANUEL D. VARIAS, JR. LIBERATO S. TAN, JR.
Pinamaloy, Don Carlos, Bukidnon
#REF! Chief, Construction Section OIC-Asst. District Engineer District Engineer