You are on page 1of 30

Contract ID No. : #REF!

Project Name : #REF!

Location : #REF!

Contractor : #REF!

EFFECTIVITY : #REF!

ORIGINAL EXPIRY : #REF!

ORIGINAL DURATION : #REF!

INCLUSIVE DATES CUMMULATIVE


RESUME DAYS
TIME REVISED REVISED DAYS
ORDER DAYS USED SUSPENDED/ REASON
EXTENSION/SUSPENSION DURATION EXPIRY REMAINING WORK
DATE FROM TO EXTENDED TIME EXTENSIONS
SUSPENSION

PREVIOUS APPROVED REVISIONS

1 5/4/2020 3/23/2020 5/3/2020

PREVIOUS APPROVED REVISIONS


STRAIGTH LINE DIAGRAM 1 of 1
SHOWING CONTRACT EFFECTIVITY, CONTRACT EXPIRY DATE

Name of project : #REF!


Location : ### Effectivity of contract : #REF!
Station limits : n/a Expiry Date : #REF!
Contract Length : n/a Contract Duration : #REF!
Contractor : ### Approved Time Extension : #REF!
Orig. Contract Amt. : #REF! Approved Suspension Order : #REF!
Rev. Contract Amt. : #REF! Revised Expiry Date : #REF!

ORIGINAL DURATION
48 CALENDAR DAYS

March 1-31, 2020 April 1-30, 2020 May 1-31, 2020 June 1-30, 2020

WORK SUSPENSION NO.1

EFFECTIVITY DATE OF ORIGINAL EXPIRY DATE


EFFECTIVITY DATE
March 18, 2020 Work Suspension Order No.1
March 24, 2020 June 22, 2020

July 1-31, 2020 August 1-31, 2020 September 1-30, 2020 October 1-31, 2020

Republic of the Philippines LEGEND: Prepared by:


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X STRAIGTH LINE DIAGRAM SHOWING VITAL DATES ORIGINAL CONTRACT DURATION
BUKIDNON 2ND DISTRICT ENGINEERING CONTRACT TIME EXTENSION #REF!
Pinamaloy, Don Carlos, Bukidnon WORK SUSPENSION ORDER
#REF!
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND DISTRICT
ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon

#REF!

#REF!

Effectivity of the contract : #REF!

Original Contract Duration : #REF!

Original Expiry Date : #REF!

Revised Contract Revised Expiry


Contract Time Extension No. Duration
Duration Date

1 #REF! #REF! #REF!

PREPARED BY:

###
###

RECOMMENDING APPROVAL: APPROVED:

#REF! #REF!
#REF! #REF!

I hereby acknowledge receipt of this Contract Time Extension.


#REF!
DATE: _____________________ Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGION OFFICE X
Pinamaloy, Don Carlos, Bukidnon

Project ID : P00631269MN-CW1
Project Name : CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
Location : BARANGAY MASCARINAS, KIBAWE, BUKIDNON
Contractor : ZULAR-AZ CONSTRUCTION & SUPPLY, INC.

DETAILED QUANTITY CALCULATIONS


ITEM 803(1)a Structure Excavation (Common Soil)
Introduced Quantity : 67.53 Cu.m
Increased Quantity : 1.72 Cu.m
Revised Quantity : 69.25 Cu.m

# L W D
add stair 2 33.00 0.40 0.70 = 18.48
SLAB 1 30.00 2.00 0.10 = 6.26
less SLAB 1 6.00 18.50 0.10 = 11.10
SLAB 2 24.00 1.60 0.20 = 15.36
1.72 Cu.m

ITEM 804(1)b Embankment (From Borrow)


Introduced Quantity : 38.63 Cu.m
Increased Quantity : 56.37 Cu.m
Revised Quantity : 95.00 Cu.m

# L W D V
stair 2 6.00 0.30 0.20 = 0.72
2 6.00 0.30 0.40 = 1.44
1 6.00 0.30 0.60 = 1.08
slab 1 30.00 2.00 0.10 = 6.00
bleacher 1 1.20 1.00 6.00 = 6.60
1 1.00 0.80 6.00 = 5.40
1 0.40 0.20 6.00 = 1.80
1 0.20 0.00 6.00 = 0.60
1 0.95 0.90 6.00 = 5.55
1 0.90 0.80 6.00 = 5.10
1 0.60 0.40 6.00 = 3.00
1 0.40 0.60 6.00 = 3.00
44.01 Cu.m

ITEM 804(4) Gravel Fill


Introduced Quantity : 24.73 Cu.m
Decreased Quantity : 11.34 Cu.m
Revised Quantity : 13.39 Cu.m

# L W D
add stair 2 24.00 0.30 0.10 = 1.44
slab 1 30.00 2.00 0.10 = 6.00
less SLAB 1 6.00 18.50 0.10 = 11.10
SLAB 2 24.00 1.60 0.10 = 7.68
11.34 Cu.m

ITEM 900(2)c Structural Concrete (Class B, 28 days)


Introduced Quantity : 27.37 Cu.m
Decreased Quantity : 11.34 Cu.m
Revised Quantity : 16.03 Cu.m

# L W D
add stair 2 24.00 0.30 0.10 = 1.44
slab 1 30.00 2.00 0.10 = 6.00
less SLAB 1 6.00 18.50 0.10 = 11.10
SLAB 2 24.00 1.60 0.10 = 7.68
11.34 Cu.m
ITEM 902(1)a Reinforcing Steel (Deformed), Grade 40
Introduced Quantity : 2,596.95 kg
Decreased Quantity : 56.99 kg
Revised Quantity : 2,653.94 kg

# # OF BARS L factor
stair WF 12mm 1 165.00 0.30 0.89 44.06
stair WF 12mm 1 3.00 66.00 0.89 176.22
stair slab 10mm 1 3.00 48.00 0.62 89.28
slab 10mm 1 98.00 0.40 0.62 24.30
2m slab 10mm 1 5.00 30.00 0.62 93.00
slab 10mm 1 61.00 2.00 0.62 75.64
less CC 10mm 1 12.00 19.70 0.62 146.57
10mm 1 37.00 7.20 0.62 165.17
10mm 2 3.00 25.00 0.62 93.00
10mm 2 48.00 2.60 0.62 154.75
56.99 kg

ITEM 1000(1) Soil Poisoning


Introduced Quantity : 16.49 L
Decreased Quantity : 7.08 L
Revised Quantity : 9.41 L

No. L W area
add stair 2.00 6.00 1.80 = 21.60
slab 1.00 30.00 2.00 = 60.00
less slab 1.00 6.00 18.50 = 111.00
slab 2.00 24.00 1.60 = 76.80
7.08 L

ITEM 1046(2)a1 CHB Non-Load Bearing (including reinforcing Steel), 100mm


Introduced Quantity : 248.32 Sq.m
Increased Quantity : 51.51 Sq.m
Revised Quantity : 299.83 Sq.m

H L # area
bleacher 1.20 1.00 6.00 = 6.60
1.00 0.80 6.00 = 5.40
0.40 0.20 6.00 = 1.80
0.20 0.00 6.00 = 0.60
0.95 0.90 6.00 = 5.55
0.90 0.80 6.00 = 5.10
0.60 0.40 6.00 = 3.00
0.40 0.60 6.00 = 3.00
stair 0.20 6.00 2.00 = 2.40
0.40 6.00 2.00 = 4.80
0.60 6.00 1.00 = 3.60
0.20 1.50 4.00 = 1.20
0.40 1.50 4.00 = 2.40
0.60 1.50 2.00 = 1.80
0.80 1.50 2.00 = 2.40
51.51 Sq.m

ITEM 1027(1) Cement Plaster Finish


Introduced Quantity : 207.36 Sq.m
Increased Quantity : 51.51 Sq.m
Revised Quantity : 258.87 Sq.m

H L # area
bleacher 1.20 1.00 6.00 = 6.60
1.00 0.80 6.00 = 5.40
0.40 0.20 6.00 = 1.80
0.20 0.00 6.00 = 0.60
0.95 0.90 6.00 = 5.55
0.90 0.80 6.00 = 5.10
0.60 0.40 6.00 = 3.00
0.40 0.60 6.00 = 3.00
stair 0.20 6.00 2.00 = 2.40
0.40 6.00 2.00 = 4.80
0.60 6.00 1.00 = 3.60
0.20 1.50 4.00 = 1.20
0.40 1.50 4.00 = 2.40
0.60 1.50 2.00 = 1.80
0.80 1.50 2.00 = 2.40
51.51 Sq.m
ITEM 1051(1) Railings
Introduced Quantity : - m
Increased Quantity : 57.60 m
Revised Quantity : 57.60 m

L # L
2.70 16.00 = 43.20
V 0.90 16.00 = 14.40
57.60 m

ITEM 401(1)a2 Metal Railing - Grade 50 (Steel)


Introduced Quantity : - m
Increased Quantity : 49.60 m
Revised Quantity : 49.60 m

L # L
49.60 1.00 = 49.60
49.60 m

Prepared by:

AMELITO D. ARANQUEZ
Proprietor
ITEMIZED QUANTITIES AND COST OF VARIATION WORK ORDER
PROJECT CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON

LOCATION BARANGAY MASCARINAS, KIBAWE, BUKIDNON

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ZULAR-AZ CONSTRUCTION & SUPPLY, INC.
BUKIDNON SECOND
AS PER ORIGINAL CONTRACT COST AND QUANTITIES WITHIN LIMITS OF THIS QUANTITIES OF THIS VARIATION
DISTRICT ENGINEERING OFFICE
VARIATION/EXTRA WORK ORDER ORDER No.01
Pinamaloy, Don Carlos, Bukidnon REMARKS
ADDITIVE DEDUCTIVE
ITEM NO. DESCRIPTION UNIT UNIT COST QUANTITY AMOUNT QUANTITY TOTAL AMOUNT
QUANTITY AMOUNT QUANTITY AMOUNT
B.5 Project Billboard / Signboard each 3,780.00 2.00 7,560.00 - - 2.00 7,560.00 NO CHANGE
B.7(2) Occupational Safety and Health Program ls 133,560.00 1.00 133,560.00 - - 1.00 133,560.00 NO CHANGE
B.9 Mobilization / Demobilization ls 126,000.00 1.00 126,000.00 - - 1.00 126,000.00 NO CHANGE
803(1)a Structure Excavation (Common Soil) Cu.m 552.29 67.53 37,296.14 - 1.72 950.570 65.81 36,345.58 DECREASED
804(1)a Embankment (From roadway / structure excavation) Cu.m 143.30 67.53 9,677.05 - - 67.53 9,677.05 NO CHANGE
804(1)b Embankment (From Borrow) Cu.m 1,016.90 38.63 39,282.85 56.37 57,326.86 - 95.00 96,609.71 INCREASED
804(4) Gravel Fill Cu.m 1,024.10 24.73 25,325.99 - 11.34 11,613.290 13.39 13,712.70 DECREASED
900(1)c2 Structural Concrete (Footings) (Class A, 28 days) Cu.m 8,553.71 11.90 101,789.15 - - 11.90 101,789.15 NO CHANGE
900(1)c4 Structural Concrete (Columns) (Class A, 28 days) Cu.m 8,673.98 3.84 33,308.08 - - 3.84 33,308.08 NO CHANGE
900(2)c Structural Concrete (Class B, 28 days) Cu.m 7,694.88 27.37 210,608.87 - 11.34 87,259.940 16.03 123,348.93 DECREASED
902(1)a Reinforcing Steel (Deformed), Grade 40 kg 72.08 2,596.95 187,188.16 - 56.99 4,107.840 2,539.96 183,080.32 DECREASED
903(2) Formworks and Falseworks Sq.m 719.74 64.00 46,063.36 - - 64.00 46,063.36 NO CHANGE
1000(1) Soil Poisoning L 673.29 16.49 11,102.55 - 7.08 4,766.890 9.41 6,335.66 DECREASED
1003(11)a1 Fascia Board (Fiber Cement Board) M 795.55 183.74 146,174.36 - - 183.74 146,174.36 NO CHANGE
1046(2)a1 CHB Non-Load Bearing (including reinforcing Steel), 100mm Sq.m 924.74 248.32 229,631.44 51.51 47,633.36 - 299.83 277,264.79 INCREASED
1032(1)a Painting Works (Masonry / Concrete) Sq.m 374.02 238.24 89,106.52 - - 238.24 89,106.52 NO CHANGE
1032(1)c Painting Works (Steel) Sq.m 486.68 215.60 104,928.21 - - 215.60 104,928.21 NO CHANGE
1027(1) Cement Plaster Finish Sq.m 224.37 207.36 46,525.36 51.51 11,557.30 - 258.87 58,082.66 INCREASED
1021(1)a Cement Floor Finish (Plain) Sq.m 220.27 187.80 41,366.71 - 187.80 41,366.710 - - DELETED
1048(6) Glass Fiber Ls 252,000.00 1.00 252,000.00 - 1.00 252,000.000 - - DELETED
1014(1)b2 Prepainted Metal Sheets, above 0.427mm (Rib Type, Long span) Sq.m 1,209.22 162.30 196,256.41 - - 162.30 196,256.41 NO CHANGE
1013(2)a2 Fabricated Metal Roofing Accessory, gauge 26 (Flashings) Lm 352.12 54.92 19,338.43 - - 54.92 19,338.43 NO CHANGE
1013(2)b1 Fabricated Metal Roofing Accessory, gauge 26 (Gutters) Lm 480.52 129.84 62,390.72 - - 129.84 62,390.72 NO CHANGE
1001(9) Storm Drainage and Donwspout Ls 15,120.00 1.00 15,120.00 - - 1.00 15,120.00 NO CHANGE
1047(2)a Structural Steel (Trusses) kg 109.01 3,141.80 342,487.62 - - 3,141.80 342,487.62 NO CHANGE
1047(1) Structural Steel Ls 63,000.00 1.00 63,000.00 - - 1.00 63,000.00 NO CHANGE
1047(2)b Structural Steel (Purlins) kg 104.27 1,019.24 106,276.15 - - 1,019.24 106,276.15 NO CHANGE
1047(3)c Metal Structure Accessories (Turnbuckle) each 592.20 20.00 11,844.00 - - 20.00 11,844.00 NO CHANGE
1047(4) Metal Structure Accessories (Cross Bracing) kg 570.80 129.47 73,901.48 - - 129.47 73,901.48 NO CHANGE
1047(7)a Metal Structure Accessories (Bolts) kg 567.87 35.51 20,165.06 - - 35.51 20,165.06 NO CHANGE
1047(6) Metal Structure Accessories (Steel Plates) kg 117.73 633.02 74,525.44 - - 633.02 74,525.44 NO CHANGE
1047(7)b Metal Structure Accessories (Sagrods) kg 715.68 19.73 14,120.37 - - 19.73 14,120.37 NO CHANGE
1100(10) Conduits, Boxes & Fittings (Conduit Works / Conduit Rough-in) Ls 25,200.00 1.00 25,200.00 - - 1.00 25,200.00 NO CHANGE
1101(33) Wires and Wiring Devices Ls 31,500.00 1.00 31,500.00 - - 1.00 31,500.00 NO CHANGE
1102(1) Panelboard with Main & Branch Breakers Ls 12,600.00 1.00 12,600.00 - - 1.00 12,600.00 NO CHANGE
1103(1) Lighting Fixtures and Lamps Ls 18,900.76 1.00 18,900.76 - - 1.00 18,900.76 DELETED
NEW ITEM

1048(6) Glass Fiber Ls 57,235.89 - - 1.00 57,235.88 - 1.00 57,235.89 NEW ITEM
1103(1) Lighting Fixtures and Lamps (a) Ls 72,318.12 - - 1.00 72,318.12 - 1.00 72,318.12 NEW ITEM
401(1)a2 Metal Railing - Grade 50 (Steel) m 2,239.10 - - 49.60 111,059.17 - 49.60 111,059.17 NEW ITEM
1051(1) Railings m 847.45 - - 57.60 48,813.30 - 57.60 48,813.30 NEW ITEM
TOTAL COST: Php 2,966,121.24 Php 405,943.99 Php 402,065.24 Php 2,970,000.00
Concurred:
Original Sum Involve in this Revision (Php) 2,966,121.24
New Sum Involve in this Revision (Php) 2,970,000.00
AMELITO D. ARANQUEZ Difference Cost (Php) 3,878.76
Proprietor
Indangan, Davao City % CHANGE FROM ORIGINAL COST 0.13%

Prepared: Submitted: Checked: Reccomending Approval: Approved:

ISABELITA D. BALBA REYNALDO S. EMETERIO NORMA A. OGABANG MANUEL D. VARIAS, JR. MARIVEL FRANCES L. ONG, A.E.R.
Project Engineer II Chief, Construction Section Chief, Planning and Design Section OIC-Assistant District Engineer District Engineer
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS & HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon
CONTRCT ID NO. : 22KB0051
VARIATION ORDER : Variation Order 1
NAME OF PROJECT : CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
LOCATION : BARANGAY MASCARINAS, KIBAWE, BUKIDNON
CONTRACTOR : ZULAR-AZ CONSTRUCTION & SUPPLY, INC.

You are hereby directed to make herein changes from the plans, specification, or do the following work not in the plans and specification.

DESCRIPTION OF WORK TO BE DONE:

Item No. 803(1)a Structure Excavation (Common Soil), decreased from 67.53 Cu.m to 65.8088599687663 Cu.m
Item No. 804(1)b Embankment (From Borrow), increased from 38.63 Cu.m to 95.0041360999126 Cu.m
Item No. 804(4) Gravel Fill, decreased from 24.73 Cu.m to 13.39 Cu.m
Item No. 900(2)c Structural Concrete (Class B, 28 days), decreased from 27.37 Cu.m to 16.03 Cu.m
Item No. 902(1)a Reinforcing Steel (Deformed), Grade 40, decreased from 2596.95 kg to 2539.96 kg
Item No. 1000(1) Soil Poisoning, decreased from 16.49 L to 9.41 L
Item No. 1046(2)a1 CHB Non-Load Bearing (including reinforcing Steel), 100mm, increased from 248.32 Sq.m to 299.83 Sq.m
Item No. 1027(1) Cement Plaster Finish, increased from 207.36 Sq.m to 258.87 Sq.m
Item No. 1021(1)a Cement Floor Finish (Plain), Item Deleted
Item No. 1048(6) Glass Fiber, Item Deleted
Item No. 1103(1) Lighting Fixtures and Lamps, Item Deleted
Item No. 1048(6) Glass Fiber, New Item, 1 Ls
Item No. 1103(1) Lighting Fixtures and Lamps (a), New Item, 1 Ls
Item No. 401(1)a2 Metal Railing - Grade 50 (Steel), New Item, 49.6 m
Item No. 1051(1) Railings, New Item, 57.6 m

REASONS FOR REVISION:

Due to the change of building orientation to utilize the available proposed project site.

Work to be performed under this Variation/ Change Order, shall be based on the existing contract prices
ITEMIZED QUANTITIES AND COST OF REVISION ARE IN SEPARATE SHEET
I, the undersigned contractor has given careful consideration to the proposed Variation Order No. 01 of the Difference cost due to Variation Order #1 : (+) PhP 3,878.76
above named project, hereby agree, if this proposal approved, I will provide all equipments, and furnish all Original Sum Involve in this Revision : PhP 2,966,121.240
materials except on as may otherwise be noted above on the sheet specified. New Sum Involve in this Revision : PhP 2,970,000.000
Percentage of Variation : 0.13%

Prepared: Accepted by: Date Accepted:

ISABELITA D. BALBA AMELITO D. ARANQUEZ _____________________


Project Engineer II Proprietor
Indangan, Davao City

Submitted by: Checked: Recommending Approval : APPROVED:

REYNALDO S. EMETERIO NORMA A. OGABANG MANUEL D. VARIAS, JR. MARIVEL FRANCES L. ONG, A.E.R
Chief, Construction Section Chief, Planning and Design Section OIC-Assistant District Engineer District Engineer
CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
BARANGAY MASCARINAS, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1048(6) Glass Fiber
Unit of Measurement: ls
Output per hour - As Submitted: 1.000 LS
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 8.00 99.11 792.88
b. Skilled Labor 1 8.00 71.54 572.32
c. Unskilled Labor 2 8.00 55.26 884.16

Sub· Total for A.1 • As Submitted 2,249.36


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of Labor Cost) 224.94
Sub· Total for B.1 • As Submitted 224.94
B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 2,474.30
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 1.00
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 2,474.30
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
Fiber Glass Board with Ring and Net (Heavy Duty)
a. set 2.00 20,000.00 40,000.00
Movable Glass Fiber Board Frame
b. Angular Bar 25 x 25 x 4mm kg 18.900 60.00 1,134.00

Sub· Total for F.1 - As Submitted 41,134.00


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 43,608.30
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 6,541.24
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 4,360.83
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 2,725.52
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 57,235.89
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
BARANGAY MASCARINAS, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1103(1) Lighting Fixtures and Lamps
Unit of Measurement: ls
Output per hour - As Submitted: 1.000 LS
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 16.00 94.86 1,517.76
b. Skilled Labor 2 16.00 68.57 2,194.24
c. Unskilled Labor 4 16.00 52.93 3,387.52

Sub· Total for A.1 • As Submitted 7,099.52


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Sub· Total for B.1 • As Submitted
B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 7,099.52
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 1.00
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 7,099.52
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. High Bay Lamp, LED Light 200 watts piece 3.00 16,000.00 48,000.00
-

Sub· Total for F.1 - As Submitted 48,000.00


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 55,099.52
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 8,264.93
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 5,509.95
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 3,443.72
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 72,318.12
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
BARANGAY MASCARINAS, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1051(1) Railing
Unit of Measurement: m
Output per hour - As Submitted: 6.255 sq.m
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 1.00 94.48 94.48
b. Skilled Labor 1 1.00 68.29 68.29
c. Unskilled Labor 2 1.00 52.71 105.42

Sub· Total for A.1 • As Submitted 268.19


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
a. Welding Machine (Gas/Diesel Driven) 1 0.75 371.00 278.25
b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of Labor Cost) 26.82

Sub· Total for B.1 • As Submitted 316.43


B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 584.62
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 6.255
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 93.46
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. 38 mm diam. Stainless steel pipe pc 0.330 1,621.00 534.93
b. Welding Rod pc 0.015 80.00 1.20
c. Consumables (3% of material cost) 16.08

Sub· Total for F.1 - As Submitted 552.21


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 645.68
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 96.85
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 64.57
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 40.35
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 847.45
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION (COMPLETION) OF MULTI PURPOSE BUILDING, BARANGAY MASCARINAS, KIBAWE, BUKIDNON
BARANGAY MASCARINAS, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 401(1)a2 Metal Railing - Grade 50 (Steel)
Unit of Measurement: m
Output per hour - As Submitted: 6.255 m
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 1.00 94.48 94.48
b. Skilled Labor 1 1.00 68.29 68.29
c. Unskilled Labor 2 1.00 52.71 105.42

Sub· Total for A.1 • As Submitted 268.19


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
a. Welding Machine (Gas/Diesel Driven) 1 0.75 371.00 278.25
b. Cutting Outfit 1 0.25 45.45 11.36
Minor Tools (10% of Labor Cost) 26.82

Sub· Total for B.1 • As Submitted 316.43


B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 584.62
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 6.255
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 93.46
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. Structural Steel Tube (100 x 100 x 2) kg 2.887 70.00 202.08
Structural Steel Tube (50 x 50 x 1.5) kg 4.972 70.00 348.02
Structural Steel Angular Bar kg 3.560 70.00 249.23
b. Welding Rod kg 0.020 80.00 1.60
c. Wire Mesh pc 0.262 2,800.00 734.80
d. Consumables (5% of material cost) 76.79
Sub· Total for F.1 - As Submitted 1,612.51
F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 1,705.98
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 255.90
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 170.60
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 106.62
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 2,239.10
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION OF MULTI-PURPOSE BUILDING
BARANGAY BALINTAWAK, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1032(1)a Painting Works (Masonry/Concrete)
Unit of Measurement: sq.m
Output per hour - As Submitted: 2.100 sq.m
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 1.00 94.48 94.48
b. Skilled Labor 2 1.00 68.29 136.58
c. Unskilled Labor 1 1.00 52.71 52.71

Sub· Total for A.1 • As Submitted 283.77


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of Labor Cost) 28.38

Sub· Total for B.1 • As Submitted 28.38


B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 312.15
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 2.10
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 148.64
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. Concrete Neutralizer gal 0.020 180.00 3.60
b. Concrete Sealer/Primer gal 0.040 644.00 25.76
c. Patching Compound gal 0.050 550.00 27.50
d. Semi Gloss Latex (two coat only) gal 0.080 720.00 57.60
e. Consumables (5% of Materials Cost) 5.72

Sub· Total for F.1 - As Submitted 120.18


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 268.82
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 40.32
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 26.88
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 16.80
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 352.83
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION OF MULTI-PURPOSE BUILDING
BARANGAY BALINTAWAK, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1013(2)a2 Fabricated Metal Roofing Accessory, gauge 26 (Flashings)
Unit of Measurement: lm
Output per hour - As Submitted: 10.0 l.m
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 1.00 94.48 94.48
b. Skilled Labor 1 1.00 68.29 68.29
c. Unskilled Labor 1 1.00 52.71 52.71

Sub· Total for A.1 • As Submitted 215.48


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of Labor Cost) 21.55

Sub· Total for B.1 • As Submitted 21.55


B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 237.03
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 10.000 sq.m
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 23.70
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. Flashing (0.60 mm) sq.m 1.05 337.00 353.85
b. Blind Rivets pc 19 1.50 28.50
c. Consumables (3% of Material Cost) 11.47

Sub· Total for F.1 - As Submitted 393.82


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 417.52
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 62.63
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 41.75
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 26.10
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 548.00
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION OF MULTI-PURPOSE BUILDING
BARANGAY BALINTAWAK, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1004(2) Finishing Hardware
Unit of Measurement: ls
Output per hour - As Submitted: 1.000 ls
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor

Labor cost for these items are to be considered/included in the installation of doors, windows and other fabricated materials

Sub· Total for A.1 • As Submitted -


A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of Labor Cost) -

Sub· Total for B.1 • As Submitted -


B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted -
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 1.00
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted -
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. Lockset set 14.000 981.00 13,734.00

Sub· Total for F.1 - As Submitted 13,734.00


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 13,734.00
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 2,060.10
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 1,373.40
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 858.38
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 18,025.88
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
CONSTRUCTION OF MULTI-PURPOSE BUILDING
BARANGAY BALINTAWAK, KIBAWE, BUKIDNON
DETAILED UNIT PRICE ANALYSIS (DUPA)
FORM.POW·2015·01D-ll
Item No.1 Description: 1018(4) Synthetic Granite Tiles
Unit of Measurement: sq.m
Output per hour - As Submitted: 1.950 sq.m
Output per hour - As Evaluated:

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A.1 Labor
a. Construction Foreman 1 1.00 94.48 94.48
b. Skilled Labor 5 1.00 68.29 341.45
c. Unskilled Labor 5 1.00 52.71 263.55
Sub· Total for A.1 • As Submitted 699.48
A.2 Labor

Sub· Total for A.2. As Evaluated


Name and Capacity No. of Unlt/s No. of Hour/s Hourly Rate Amount (PhP)
B.1 Equipment
Minor Tools (10% of Labor Cost) 69.95

Sub· Total for B.1 • As Submitted 69.95


B.2 Equipment

Sub· Total for B.2· As Evaluated


C.1 Total (A.1 + B.1)· As Submitted 769.43
C.2 Total (A.2 + B.2)· As Evaluated
D.1 Output per hour· As Submitted 1.95
D.2 Output per hour· As Evaluated
E.1 Direct Unit Cost (C.1/D.1). As Submitted 394.58
E.2 Direct Unit Cost (C.2/D.2) • As Evaluated .
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F.1 Materials
a. Synthetic Granite Tiles sq.m 1.050 700.00 735.00
b. Cement bags 0.325 260.00 84.50
c. Sand cu.m 0.026 1,000.00 26.00
d. Tile Grout bags 0.125 250.00 31.25

Sub· Total for F.1 - As Submitted 876.75


F.2 Materials

Sub· Total for F.2 - As Evaluated


G.1 Direct Unit Cost (E.1 + F.1)·As Submitted 1,271.33
G.2 Direct Unit Cost (E.2 + F.2) • As Evaluated
H.1 Overhead, Contingencies & Miscellaneous (OCM)- As Submitted 15%/12%/10%/8% of G.1 15% 190.70
H.2 Overhead, Contingencies & Miscellaneous (OCM). As Evaluated 15%/12%/10%/8% of G.2 -
I.1 Contractor's Profit (CP) • As Submitted 10%/8% of G.1 10% 127.13
I.2 Contractor's profit (CP) • As Evaluated 10%/8% of G.2 -
J.1 Value Added Tax (VAT)· As Submitted 5% of (G.1 + H.1 + I.1) 5% 79.46
J.2 Value Added Tax (VAT) • As Evaluated 5% of (G.2 + H.2 + I.2)
K.1 Total Unit Cost· As Submitted (G.1 + H.1 + I.1 + J.1) 1,668.62
K.2 Total Unit Cost· As Evaluated (G.2 + H.2 + I.2 + J.2)

Prepared by: CheckedlRevlewed by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGION OFFICE X
Pinamaloy, Don Carlos, Bukidnon

Project ID : P00443910MN-CW1
Project Name : CONSTRUCTION OF MULTI-PURPOSE BUILDING
Location : BARANGAY POBLACION, DANGCAGAN BUKIDNON
Contractor : CARESYSTEM

DERIVATION OF TIME EXTENSION

Err:509
Err:509 Err:509 Err:509

Output Per hour: 20.00 cu.m.

Computation: Err:509 cu.m. / 20.000 cu.m.


Err:509 hrs.

Err:509
Err:509 Err:509 Err:509

Output Per hour: 1.200 cu.m.

Computation: Err:509 cu.m. / 1.200 cu.m.


Err:509 hrs.

Err:509
Err:509 Err:509 Err:509

Output Per hour: 0.270 cu.m.

Computation: Err:509 cu.m. / 0.270 cu.m.


Err:509 hrs.

Err:509
Err:509 Err:509 Err:509

Output Per hour: 143.438 kgs

Computation: Err:509 kgs. / 143.438 kgs


Err:509 hrs.

Err:509
Err:509 Err:509 Err:509

Output Per hour: 2.100 sq.m.

Computation: Err:509 sq.m. / 2.100 sq.m.


Err:509 hrs.

Err:509
Err:509 Err:509 Err:509

Output Per hour: 0.270 cu.m.

Computation: Err:509 cu.m. / 0.270 cu.m.


Err:509 hrs.

Total No. of Hours : Err:509 hrs.


So, Err:509 days.
say, 4 days

Prepared by: Checked by:

ISABELITA D. BALBA REYNALDO S. EMETERIO


Project Engineer II Chief, Construction Section
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND DISTRICT
ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon

#REF!

CHRONOLOGY OF EVENTS

DATE ACTIVITY
#REF! Issued of Notice to Proceed to the Contractor
#REF! Effectivity of the contract
Issuance of Proclamation Order No. 922 Declaring the State of
March 08, 2020 Public Health Emergency Throughout the Philippines due to
Covit-19 threat.

Receipt of Notice to Proceed of the Contractor and effectivity


#REF! date of the project

Issuance of Executive Order No. 13, Seiries of 2020 from the


Office of the Provincial Governor, "An Order Declaring A
March 17, 2020 General Community Quarantine in the Entire Province of
Bukidnon".
Construction Staff Meeting was conducted at DPWH-Buk. 2nd
DEO, Office of the Construction Chief to discussed the issue
March 23, 2020 about the General Community Quarantine in the Entire
Province of Bukidnon and granting of Work Suspension Order
to the contractor.

The contractor was requested for Work Suspension Order due


to the General Community Quarantine implemented in the
#REF! Entire Province of Bukidnon as part of preventive measure
against Coronavirus Disease (COVID-19)

Effectivity of the Work Suspension Order requested by the


#REF! Contractor.
Construction Staff Meeting was conducted at DPWH-Buk. 2nd
DEO, Office of the construction chief to discussed the issue
about the order prescribing new guidelines under general
#REF! community quarantine in the entire Province of Bukidnon as
per EO no. 21 s.2020 and granting of work resumption order
to the contractor.

The contractor requested for Work Resumption Order as per


EO no. 21 s.2020.
#REF!
Effectivity of the Work Resumption Order no. 1.

The contractor requested for Contract Time Extension in lieu


of WSO no. 1.
#REF!
Effectivity of the Contract Time Extension in lieu of WSO no. 1.

#REF! Original Expiry of the contract

#REF! Revised Expiry due to CTE no. 1 in lieu of WSO no. 1.

#REF!
#REF!
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND DISTRICT
ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon

#REF!

Present:
REYNALDO S. EMETERIO - Chief, Construction Section - DPWH
#REF! - Project Engineer - DPWH
CARLITO G. MAGONCIA - Project Engineer - DPWH
LUZMINDA C. VIRTUDAZO - Project Engineer - DPWH
JONALIE S. ABENOJA-BAYANBAN - Project Engineer - DPWH
JOAN M. ESTIGOY-FEROLINO - Project Engineer - DPWH
AMELIA T. GONZALES - Project Inspector - DPWH
WALDO RAE C. BOLONOS - Project Inspector - DPWH

Highlights of the Meeting:

ISSUES/CONCERNS ACTION/S TO BE TAKEN

Has been issued by this office as per request by the


contractor since an order prescribing new guidelines
under general community quarantine in the province
Work Resumption Order No. 1
of Bukidnon has been issued per Executive Order No.
21, Series of 2020 stating that the construction
industry may resume its operations.

To be issued to the contractor to cope with the delay


Contract Time Extension no. 1 in lieu of Work Suspension incurred to the construction schedule affected by the
Order no. 1 State of Public Health Emergency caused by the
Coronavirus Disease (COVID-19) pandemic.

There being no other issues/concerns to be taken up, the meeting was adjourned at 10:30 in the
morning.
I hereby certify to the correctness of the above statements.

#REF!
#REF!

Attested:

#REF! #REF!
#REF! #REF!
CONTRACT ID : ###
PROJECT NAME : #REF!

LOCATION : ###
STATION LIMIT : n/a
CONTRACTOR : ###

CONSTRUCTION MEETING

Submitted by:

###
###
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
BUKIDNON SECOND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE X
Pinamaloy, Don Carlos, Bukidnon

#REF!

FOR : LIBERATO S. TAN, JR


District Engineer

SUBJECT : COMMENTS/RECOMMENDATION
#REF!

#REF!

1. CONTRACTUAL DATA
a. Original Contract Amount -- #REF!
b. Revised Contract Amount -- #REF!
c. Effectivity of Contract -- #REF!
d. Original Expiry Date -- #REF!
e. Revised Contract Expiry -- #REF!
#REF!

h. Contractor -- #REF!

2. #REF!

3. #REF!

4. #REF!

5. #REF!

###
###

###
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X
BUKIDNON 2ND DISTRICT ENGINEERING
Pinamaloy, Don Carlos, Bukidnon

Contract ID No. : #REF!


Project Name : #REF!
Location : #REF!
Contractor : #REF!

PROJECT ENGINEER'S REPORT


#REF!

#REF!

#REF!

#REF!

Certified by:

###
###
Sheet Content: Prepared by: Submitted by: Recommending Approval: Approved by:
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X
BUKIDNON 2ND DISTRICT ENGINEERING
Pinamaloy, Don Carlos, Bukidnon
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGION - X
BUKIDNON 2ND DISTRICT ENGINEERING #REF! REYNALDO S. EMETERIO MANUEL D. VARIAS, JR. LIBERATO S. TAN, JR.
Pinamaloy, Don Carlos, Bukidnon
#REF! Chief, Construction Section OIC-Asst. District Engineer District Engineer

You might also like