Professional Documents
Culture Documents
LNG EPC
(Amendment to GPO-EN-SPE-42103)
Code Description
A Proceed - No comment
B Proceed - With comment
C Do Not Proceed - Revise & Resubmit
D Cancelled
E Received as information
Signature:
B05 Approved for Use A.Gofar 29 Dec 2016 H. Ogiso 29 Dec 2016 T.Shimizu 29 Dec 2016
B04 Issued for Approval of Revision A.Gofar 14 Dec 2016 H. Ogiso 14 Dec 2016 T.Shimizu 15 Dec 2016
B03 Issued for Approval of Revision A. Gofar 07 Nov.2016 H. Ogiso 07 Nov.2016 T. Shimizu 07 Nov.2016
B02 Issued for Review of Revision A. Gofar 5 Oct.2016 H. Ogiso 5 Oct.2016 T. Shimizu 5 Oct.2016
B01 Approved for Design T. Shimizu 25 Sep. T. Ito 25 Sep. 2015 T. Hino 25 Sep. 2015
2015
A01 Issue for Review T. Shimizu 30 June T. Ito 30 June 2015 T. Hino 30 June 2015
2015
Rev Reason for Issue Author Date Checked Date Approved Date
BP Document Number Contractor Document Number
870310-PTS-900-MAE-SPC-
TEP-900-SPE-MM-BP4-0003
! This document is copyright and shall not be 85003
reproduced without the permission of BP BP Original Specification Number Document Class
GPO-EN-SPE-42103 2
Tangguh Expansion Project – LNG EPC
Project Specification for Fabrication, Assembly, Erection, and Inspection of Pipework (Amendment to GPO-EN-
SPE-42103)
Table of Contents
1 Introduction .................................................................................................. 6
1.1 Project Background................................................................................................ 6
1.2 Document Purpose ................................................................................................ 6
1.3 Numbering of Original COMPANY Specifications .................................................. 6
2 Specification Amendments ............................................................................ 7
Introduction 7
Chapter I Scope and definitions................................................................................ 7
300 General statements ...................................................................................................... 7
300.4 Status of appendices .................................................................................................... 7
Chapter V Fabrication, assembly and erection ........................................................... 7
327 General ......................................................................................................................... 7
327.1 Control of welding and fabrication ................................................................................. 7
327.1.1 Initial documentation .................................................................................................... 7
327.3 Material control and storage.......................................................................................... 7
327.4 Pipe work marking ..................................................................................................... 8
328 Welding and brazing ..................................................................................................... 8
328.2 Welding and brazing qualification .................................................................................. 8
328.2.1 Standard welding procedure specifications ................................................................... 8
328.2.3 Performance qualification by others .............................................................................. 9
328.5 Welding requirement .................................................................................................... 9
328.5.1 General ......................................................................................................................... 9
331 Heat treatment ............................................................................................................. 9
331.1 General ....................................................................................................................... 9
331.1.7 Hardness tests ........................................................................................................... 9
334 Cleaning after fabrication ............................................................................................ 10
335 Assembly and erection ............................................................................................... 10
335.2 Flanged joints ........................................................................................................... 10
Chapter VI Inspection, examination and testing .................................................... 11
341 Examination ................................................................................................................ 11
341.4 Extent of required examination.................................................................................. 11
344 Types of examination ................................................................................................. 13
344.5 Radiographic examination ........................................................................................... 13
344.5.1 Method....................................................................................................................... 13
345 Testing ...................................................................................................................... 14
345.2 General requirement for leak test................................................................................ 14
345.2.3 Special provision for testing ........................................................................................ 14
Appendix E Reference standards............................................................................... 15
Appendix AA Requirements for carbon steels, low alloy steels and martensitic stainless
steels 15
AA.2 Welding ...................................................................................................................... 15
AA.2.2 Filler metal ............................................................................................................... 15
AA.3 Welding procedure qualification .................................................................................. 15
AA.3.1 Essential variables ................................................................................................... 15
AA3.2 Charpy V- notch impact testing ................................................................................... 15
AA3.3 Hardness determination .............................................................................................. 16
AA.5 Post–weld heat treatment........................................................................................... 16
Appendix BB Requirements for 300 series austenitic and high alloy austenitic stainless
steels, 6%Mo alloys, nickel base alloys, and cupro nickel ............................................... 17
BB.2 Welding ...................................................................................................................... 17
BB.2.2 Filler metal ............................................................................................................... 17
BB.3 Welding procedure qualification .................................................................................. 17
BB3.1 Charpy V-notch impact testing ................................................................................. 17
BB3.2 Hardness Determination ............................................................................................ 17
Appendix CC Requirements for 22 Cr duplex and 25 Cr super duplex stainless steel
materials 17
CC.2 Welding ...................................................................................................................... 17
CC.2.2 Filler Metal............................................................................................................... 17
CC.3 Welding procedure qualification .................................................................................. 18
CC.3.5 Hardness determination ........................................................................................... 18
CC.3.7 Corrosion testing ..................................................................................................... 18
CC.4 Welder qualification .................................................................................................... 18
Appendix FF Requirements for Closure Weld (Golden Weld) ...................................... 18
FF.1 General ....................................................................................................................... 18
FF.2 Procedure ................................................................................................................... 18
Appendix 1 - Original Base COMPANY Specification ............................................ 20
Revision History
Amendment Revision Amender Amendment
Date Number Initials
Related Documents
Document Number Document Name Description of Content
GPO-EN-SPE-42103 GPO-EN-SPE-42103 Specification for
Fabrication, Assembly, Erection and
Inspection of Pipework (ASME B31.3)
TEP-900-SPE-MT-BP4- Project Specification for Positive Materials
0001 Identification (PMI) for Pressure Vessels,
Piping, and Other Components
(Amendment to GPO-EN-SPE-36103)
Stakeholders
Stakeholders will be agreed with the Approver during small group review.
Holds
Hold Section Short description of hold
No Number
1 Introduction
1.1 Project Background
The Tangguh Expansion Project will consist of new offshore facilities, including wellhead platforms
and pipelines, and onshore development on the existing Tangguh brownfield site in West Papua,
Indonesia. The new onshore facilities will include one additional natural gas liquefaction train of a
similar design and capacity to the existing trains, an onshore receiving facility (ORF), new LNG and
condensate loading berth, additional boil off gas (BOG) recovery, condensate storage tank, utilities,
flares and the infrastructure to support logistics and the associated increase in the temporary and
permanent workforce.
- GIS AA-BBB
- A specific example would be - (GIS 12-201 - Specification for Low Voltage Induction Motors
(IEC))
Many of these Original Specifications also contain a cover page with the following numbering:
- GPO-EN-SPE-AABBB
- Using the same example as above - (GPO-EN-SPE-12201 - Specification for Low Voltage
Induction Motors (IEC))
These two numbering systems refer to the same base document and for the purposes of this Project
Specification we refer to the GPO-EN-SPE-AABB format.
2 Specification Amendments
This section lists any amendments to the original base COMPANY Specification which this document
relates to. Amendments are listed by the relative section from the original base COMPANY
specification.
Introduction
Add
f. This specification is based on ASME B31.3, 2012 edition. And ASME B31.3, 2012 Edition
shall be applied for TEP project.
327 General
(2) For SS316L weld, PQR requires hardness survey with max.
248Hv10 for process piping including fuel gas piping (exceptions are
utility piping, chemical injection, etc)
For 22% DSS weld, PQR requires hardness survey with max. 28
HRC.
For 25% DSS weld, PQR requires hardness survey with max. 32
HRC.
For other materials, hardness survey on PQR is not required unless specifically
required.
328.5.1 General
Modify to read (h) (1)
(1) For TEP applications, Table 328.5.1H shall be used.
And also refer to 328.2.1 (3).
331.1 General
Add
335.2.6 Equipment Flange Connections
1. Flange covers shall be retained on all flange connections to all equipment
including PV, pumps, compressors, turbines and similar mechanical equipment until
ready to connect the mating piping.And at the opening, all equipment flanges shall be
inspected for any damage.
2. Flanges connecting to strain sensitive mechanical equipment e.g., pumps,
compressors, turbines, inline instruments etc., shall be fitted up in close parallel and
lateral alignment prior to tightening the bolting. To achieve this true alignment full
advantage shall be taken of the ‘cut to fit’ allowances and loose flanges provided.
3. Flange connections to strain sensitive equipment shall be the last connection
made on completion of a line or interconnecting system of lines complete with
permanent supports. Final connections shall be witnessed by Contractor’s
Representative to ensure undue nozzle loading is not imposed on the strain sensitive
equipment.
Add
335.12 Installation of Pipework
335.12.1 General
1. Pipework shall be installed in accordance with the codes and standards and the
Contractor’s 3D model, isometric drawings and specifications.
2. Piping shall be erected and supported as indicated on Contractor’s documents, in a
manner that will not put undue strain on pumps, vessels, or equipment. All equipment,
prefabricated piping, and appurtenances shall be fitted and assembled strain-free. The
Fabricator shall be prepared to demonstrate, by disassembly of the spool, the strain-free
state of all fabricated piping.
335.12.2 Pipework Erection
1. All pipes shall be inspected before erection to ensure that they have been adequately
cleaned and are free of any debris or contaminants that might affect the subsequent
welding, testing, or operation of the pipework.
2. Pipework shall be erected on permanent supports designated for the line.
3. During erection of pipework suitable temporary supports are to be provided to ensure
that no undue stresses are imposed on the pipe or equipment to which it is connected.
4. Fabricator shall avoid undue strain being placed on equipment by unsupported
lengths of piping.
5. It should be noted that vessel flanges generally are not set sufficiently true to
permit prefabrication of the mating pipe flanges without prior physical dimensional
checks being made.
341 Examination
Legend
A: 5% Random RT, i.e. entire circumference of one weld out of every 20 welds shall be examined.
(Applicable to circumferential butt welds)
B: 10% Random RT, i.e. entire circumference of one weld out of every ten welds shall be examined.
(Applicable to circumferential butt welds)
C: 100% RT for all circumferential butt welds
D: 100% MT or PT for all branch connection welds (cover pass)
E: 100% MT or PT for all branch connection welds (root & cover pass)
F: 10% MT or PT for pressure retaining fillet welds other than branch connection welds, i.e.,
socket and other fillet welds.
G: 100% MT or PT for all pressure retaining fillet welds other than branch connection welds,
i.e., socket and other fillet welds
H: 100% MT or PT for all circumferential butt welds (in addition to RT)
1. All pressure retaining welds and attachment welds shall be 100% visually inspected
regardless of piping service class in addition to the required NDT in this Table.
2. For Category “D” fluid service of ASME B 31.3, RT is not required. This Table does not
apply to Category “D” fluid service except for 100% visual check.
3. For random radiography, at least one weld of each welder for every material grouping he
welds and weld process he uses shall be radiographed. When random radiography reveals
a defect, Progressive Examination shall be applied in accordance with Para. 341.3.4 of
ASME B 31.3.
4. UT may be applied in lieu of RT subject to specific approval by Company.
5. Either of MT or PT may be applied to P-1 welds. PT shall be applied to P-8 & P-10H welds.
6. Weld acceptance criteria shall be ASME B31.3,”Normal Fluid Service” unless otherwise
specified.
7. In case P-4, 5A and 5B Cr-Mo low alloy welds, if applied, NDT class shall be B+C+G for all
pressure rating. NDT requirements for other materials, if any, will be specified by
Company.
8. For ASME B 31.1 piping, this Table does not apply. All ASME B 31.1 piping shall be
nondestructively examined as per B 31.1 Code requirements unless otherwise specified.
9. When pneumatic test is applied, the following additional inspection to this Table shall be
required, as a minimum:
(a) For all Pressure Class
100% RT for all butt welds and 100% MT or PT for all other pressure retaining welds
regardless of piping service class.
(b) Exception
The above additional requirements do not apply to the piping for instrument air, plant
air, and nitrogen.
10. Other NDT
(a) PMI: PMI shall be in accordance with TEP-900-SPE-MT-BP4-0001.
(b) Ferrite Check of DSS weld: 10% of DSS weld shall be Ferrite checked by Fischer
Ferrite Scope with the acceptance criteria of 35%-65%.
11. Welder Performance Control
The above NDT requirements are based on proper welder performance control of
Contractor/ piping contractor(s). In case RT rejection rate of individual welder is high,
Company has a right to disqualify/re-training and/or increase RT rate to 100% until stay-
back to an acceptable range.
In order to minimize RT rejection ratio/ re-work and to keep overall RT rejection ratio
below 3% (film base) as a target, Contractor shall establish the welder performance
control procedure at site for Company’s review. This procedure shall include welder’s
performance evaluation by an initial evaluation (RT of first production welds, min. 5 joints
of each welder) and subsequent periodical evaluation (based on progressive examination
result for 2 additional welds in case of repair as per ASME B31.3 and RT rejection ratio for
each certain period, such as semi-monthly) of each welder.
For piping pre-fabrication in Indonesia outside the TEP site by piping subcontractor's shop,
the same requirements shall be applied and the subcontractor welder control procedure
shall be agreed with Contractor/ Company.
344.5.1 Method
Modify to read (f) (1) (2)
(f) Branch to run-pipe connections including set-on branch fitting connection and pipe to
pipe connections RT shall be substituted by the following inspection;
(1) Visual inspection shall be carried out on all prepared joints prior to welding (fit-up) and
after completion of welds including weld root penetration. The examination shall be
recorded for each branch connections. For the purpose of visual inspection of root
penetration of branch connection weld, access shall be kept considering the
fabrication sequence, if necessary.
(2) 100% PT or MT shall be made on all branch connection welds regardless of piping
class except for Category D fluid piping. In addition, in-process PT or MT shall be
required after root pass weld for critical piping as specified in Table 341.1.4A.
345 Testing
(a) Qualification of weldments in P1 materials and low alloy steels down to -46°C shall be in
accordance with ASME B31.3 including impact test exemption curve.
(b) In case impact test of base/weldments is required as per ASME B31.3 for carbon steel
for service at MDT down to -29°C (-20°F), the required impact values at MDT shall be in
accordance with the requirements of ASME B31.3. For other low alloy steels, if any, to
follow Table AA3.2. In case base metal impact test is exempted for P1 carbon steel as
per ASME B31.3, weld qualification impact test is not required provided that AWS
impact test certified weld consumable at -29°C or below with. Min 27J is used, such as
AWS E7016/7018.
(c) Impact value for low temperature carbon steel piping down to -46°C shall be in
accordance with the requirements of ASME B31.3.
(c) Pressure retaining dissimilar welds between duplex stainless steel and C-Mn or
low alloy steels shall be avoided. If required, it shall be made using Nb free nickel
based consumables (e.g, E/ERNiCrMo-10, E/ERNiCrMo-13 or E/ERNiCrMo-14).
FF.2 Procedure
a) Piping subcontractor shall prepare a method statement for closure welds based on the
following requirements and obtain Contractor/Company approval prior to use.
b) Each specific closure weld shall be approved by Company via TQ or designated Closure
weld request form before any work is started.
c) An experienced welder who has a low weld repair rate (target below 1.5% with the
evidence of welder performance record) shall perform the closure weld. Irrespectively
to the piping class or material type, closure weld shall be monitored with special
attention to all stages of fit up, welding and inspection, and recorded.
d) PMI testing, confirmation of correct usage of base material and weld consumables shall
be completed prior to fit up preparation.
e) MT or PT shall be performed on beveled edges.
f) Fit up and alignment shall be performed without inducing any abnormal stress and strain
in the weld point. If tack welds, other than bridge type are used, it shall be feathered
both ends of each tack, visually inspected.
g) A qualified inspector being present throughout the welding operation to confirm the
visual condition of the weld at all stages till completion.
h) All welding shall be performed using approved WPS and all of the parameters specified
shall be complied with.
i) After root pass completion, VT and PT shall be required.
j) After completion of weld, VT and MT or PT shall be required.
k) After VT and MT/PT is passed, 100% RT shall be applied. RT acceptance criteria for
closure welds shall be “severe cyclic service” as per ASME B31.3, Table 341.3.2
regardless of piping class.
l) If PWHT is required on closure weld, PWHT shall be carried out in accordance with the
approved procedure. NDT shall be repeated before and after PWHT.
GPO-EN-SPE-42103-
SUPPLIERCOPY.pdf