B-1
Item Description Quantity Unit Unit Cost Total Cost
1 16 mm Bar 16 pcs 275 4400
2 RSB Labor 31.56323872964 Kg 4 126.253
3 Cement 34 Bag 220 7480
4 Gravel 1.4065 Cubic Meter 1000 1406.5
5 Sand 1.1252 Cubic Meter 600 675.12
6 Labor Cost 1.4065 Cubic Meter 1200 1687.8
Total 15775.67
G-1 // to B1
Item Description Quantity Unit Unit Cost Total Cost
1 16 mm Bar 30 pcs 275 8250
2 RSB Labor 39.45404841206 Kg 4 157.8162
3 Cement 65 Bag 220 14300
4 Gravel 5.3955 Cubic Meter 1000 5395.5
5 Sand 4.3164 Cubic Meter 600 2589.84
6 Labor Cost 5.3955 Cubic Meter 1200 6474.6
Total 37167.76
Item Cost
B-1 15775.67295492
G-1 // to B1 37167.75619365
G-1 not // to B1 57205.28343238
C-1 33335.16495574
C-2 37613.35611512
C-3 13385.04646742
194482.2801192
G-1 // to B1 Pieces Area Length Volume Unit WeighWeight(Kg)
Rebar 5 0.00020106193 5 0.005027 77000 39.45405
Cement 0.17985 5 0.89925 1440 1294.92
Gravel 0.17985 5 0.89925 1520 1366.86
Sand 0.7194 1540 1107.876
G-1 not // to B1
Item Description Quantity Unit Unit Cost Total Cost
1 16 mm Bar 40 pcs 275 11000
2 RSB Labor 47.3448580945 Kg 4 189.3794
3 Cement 104 Bag 220 22880
4 Gravel 8.6328 Cubic Meter 1000 8632.8
5 Sand 6.90624 Cubic Meter 600 4143.744
6 Labor Cost 8.6328 Cubic Meter 1200 10359.36
Total 57205.28
C-1
Item Description Quantity Unit Unit Cost Total Cost
1 20mm Bar 24 pcs 429.69 10312.56
2 RSB Labor 0.04523893421 Kg 4 0.180956
3 Cement 52 Bag 220 11440
4 Gravel 4.3218 Cubic Meter 1000 4321.8
5 Sand 3.45744 Cubic Meter 600 2074.464
6 Labor Cost 4.3218 Cubic Meter 1200 5186.16
Total 33335.16
Bag G-1 not // to BPieces Area Length Volume Unit WeighWeight(Kg)Bag
Rebar 5 0.000201 6 0.006032 77000 47.34486
64.746 Cement 0.17985 6 1.0791 1440 1553.904 103.5936
Gravel 0.17985 6 1.0791 1520 1640.232
Sand 0.86328 1540 1329.451
C-2
Item Description Quantity Unit Unit Cost Total Cost
1 20mm Bar 24 pcs 429.69 10312.56
2 12 mm Bar 4 pcs 154.69 618.76
3 RSB Labor 365.739 Kg 4 1462.956
4 Cement 57 Bag 220 12540
5 Gravel 4.731 Cubic Mete 1000 4731
6 Sand 3.7848 Cubic Mete 600 2270.88
7 Labor Cost 4.731 Cubic Mete 1200 5677.2
Total 37613.36
C-3
Item Description Quantity Unit Unit Cost Total Cost
1 20mm Bar 8 pcs 429.69 3437.52
2 16mm bar 2 pcs 154.69 309.38
3 RSB Labor 127.8311 Kg 4 511.3245
4 Cement 21 Bag 220 4620
5 Gravel 1.68165 Cubic Mete 1000 1681.65
6 Sand 1.34532 Cubic Mete 600 807.192
7 Labor Cost 1.68165 Cubic Mete 1200 2017.98
Total 13385.05
C-1 Pieces Area Length Volume Unit WeighWeight(Kg)Bag
Rebar 8 0.000314 6 0.01508 77000 118.3621
Cement 0.2401 6 1.4406 1440 2074.464 51.8616
Gravel 0.2401 6 1.4406 1520 2189.712
Sand 1.15248 1540 1774.819