Professional Documents
Culture Documents
~-..,
11
" 1 "
1
.•- J) . ---. '.
.. -'-~", ,
,',
•
,i.\ ~ ,
-';II'
..... ~ ~- -::... . '. ( '. \
-'"'/
I,
.' I
RULES
FOR SUBMARINE
.-
J PIPELINE SYSTEMS
'r' I '
J
\,"1
'.1 1981
..... "
t i J
')
J '
"1
j
"1
, "J
: "1
j DETNORSKE
VERITAS
'I \
1
i
I i
,1
RULES
FOR SUBMARINE ,
PIPELINE SYSTEMS
"'
I
1981
This edition replaces
j
J
)
1
I
PREFACE
VERITAS has published Rules for offshore structures, off-
shore loading systems. process equipment. submarine pipeli-
nes etc.. and is prepared to issue a Certificate of Approval for
such instaIlations when found to be designed and constructed
in accordance with the appropriate Rules.
.+o~~
. ,'71-
;,
1 i
'l'
J
ODet norske Veritas 1981.
,
\-.- ,,'..I
~'.'
Printed by
De! norske Veritas, Oslo.
r
,j
I
IJ
5-
CONTENTS
Section 1 2.3.4 Waves 15
General regulations 2.3.5 Current 15
1.1 2.3.6 Corrosiviry 15
Symbols 9 2.3.7 Ice '. 15
1.2 Technical terms 10 2.3.8 Air and sea temperatures 15
1.3 2.3.9 Marine growth 15
Definitions : 10
1.1.1 Pipeline system 10 2.4 Internal pipe conditions IS
1.3.2 Submarine pipeline 10 2.4.1 Installation conditions 15
1.3.3 Riser system 10 2.4.2 Operational conditions 15
1.3.4 Pipeline riser 11
1.3.5 2.5 Design temperature 16
External riser 11 2.5.1 General 16
1.3.6 Internal riser II
1.3.7 2.5.2 Differentiated design temperatures 16
Riser support II
1.3.8 Piping components ~. 11
1.3.9 Splash zone II
1.3.10 Section 3
Submerged zone II Loads
1.3.11 Atmospheric zone II
1.3-.12 Platform II
1.3.13 3.1 Loading conditions and design conditions 17
Zone 1....•.•....•....•.....•....•..... II 3.I.I General 17
1.3.14 Zone 2......•..•....................... 11
1.3.15 3.1.2 Loading conditions ,. . . . . . . . 17
Surveillance II 3. I.3 Design conditions . . . . . . . . . .. . . . . . . . . . . . . . 17
1.3.16 Inspection II
-"1
1.3.17 To survey 11 3.2 Functional loads 17
r 1.3.18 A survey II 3.2.1 General 17
1 1.3.19 Surveyor - II 3.2.2 Functional loads during operation 17
1.3.20 Liquid hydrocarbons II 3.2.3 Functional loads during installation 17
1.3.21 Gaseous hydrocarbons II
1.3.22 3.3 Environmental loads 17
Fluid II 3.3.1 General 17
1.4 The Rules II 3.3.2 Wind loads ~ 18
1.4.1 Application II 3.3.3 Hydrodynamic loads. general. .._ 18
1.4.2 Amendments II 3.3.4 Wave loads 18
1.4.3 Alternative methods and procedures II 3.3.5 Current loads 1.8
1.4.4 Assumptions II 3.3.6 «Indirect» environmental loads : 19
3.3.7 Ice loads - 19
1.5 Certificate of Approval 12 3.3.8 Accidental loads _ 19
1.5.1 Issuance of the Certificate I2
1.5.2 Recommendations 12
1.5.3 Memoranda to Owner 12
1.5.4 Section 4
Withdrawal of Certificate 12 Strength and inplace stability
1.6 Concept evaluation 12
1.6.1 General '" 12 4.1 General __ 20
1.7 4.1.1 Design analyses 20
Instrumentation for monitoring of the 4.1.2 Design criteria 20
pipeline system . . . . . . . . . . . . . . . . . . . . . . . . . . 12 4.1.3 Design conditions _ 20
1.1.1 General 12
1.8 4.2 Pipeline/ riser during operation 20
Documentation I3 4.2.1 General _ 20
1.8.1 Submission of documentation 13
1.8.2 4.2.2 Yielding 20
Design phase 13 4.2.3 Buckling 21
1.8.3 Fabrication phase 13
1.8.4 4.2.4 Fatigue _ 21
Installation phase 13 4.2.5 On-bottom stability 22
1.8.5 Filing of documentation 13
1 4.2.6 Propagating ductil~ fractures 23
J 4.2.7
4.2.8
Riser supports
Spans
_ 2J
23
II 10.4.2
10.4.3
10.4.4
Ultrasonic procedure specification
Ultrasonic procedure qualification
Calibration of equipment
53
53
53
C6
e.6.1
Surface defects in base material
General ,
10
70
CIO.2
0.2.2 Acceptable standards for coaung properties
CIO.) Inspection and testing of qualification test welds 73
and test methods referring to generic type .... 84
CIOA Welder qualification ..... 73
Application and inspecuon of coaungs,
0 •••••••••••• 0 •••
0.2.3
C.IO.S Welding operator qualification for
general standards 85
73
00
0.1.2 Design basis ..0 ••• 0 0 •••• 0 •• 0 ••••• 0 •• 0 •• 0 82 E.6 Hydrostatic test report .. 0 0 0 0 •• 0 ••• 0 ••••••• 88
j
9
SECTION 1
GENERAL REGULATIONS
1.1 Symbols (n)p = permissible value of n,
A = cross sectional area of pipe. also: p = pressure. difference between two absolute pres-
A = exposed area of anode sures. external over-pressure
a = parameter used in wave analyses. (Defined in Fig. Per = criticai external over-pressure
A2). also: p. = external pressure
a = acceleration Pi = internal pressure
a, = relative acceleration ppr = propagation pressure
B = buoyant force per unit length of pipe. also: = initiation pressure
B = width of reference block ~T) = frequency distribution of average apparent wave
I>t = parameter used in wave analyses. (Given in Table periods
AI) Q = shear force nominal to pipe axis. also:
c = shape (drag) coefficient used in wind force formula Q = probability level
Co = drag coefficient q = lateral force per unit length of pipe
Ct = lift coefficient qw = wind force per unit length ofpipe
Cm = mass Iinertial coefficient R = reduction factor on number of waves
Cs = slamming coefficient R. = Reynold's number
d = water depth. also: r = reference value of n
d = diameter S = safety factor in on-bottom stability analysis. also:
D = nominaloutsidediameterof pipe S = Strouhal's number
o, = total outside diameter of pipe (including coating) S~ = Miner's sum
E = modulus of elasticity. also: =
(SM)p permissible value ofMiner's sum
E = consumption rate of anode s = number of stress blocks
"F h = total horizontal Ilateratl force per unit length of a pi- T = thickness of reference block. also:
pe due to drag and inertia T = average zero-upcrossing period
Fo = drag force T1 = pipe material temperature at time of installation
Fl = lift force T2 = pipe material temperature under considered condi-
F'm = mass Iinertial force tion
Fs = wave slamming force = «visual» wave period
Fy = total vertical force per unit length of a pipe due to = nominal wall thickness of pipe
drag and inertia = flow velocity for anodes
,f = coefficient of friction. also: u = utilization factor. also:
f = vortex shedding frequency u = liquid particle velocity nomal to pipe axis
fe = natural frequency for cross-flow excitation lui= absolute (positive) value of u
f; = natural frequency for inIine excitation = current velocity
H = clearance between pipe and fixed boundary. also: = resulting «design» velocity due to wave and current
H = wave height . = maximum orbital particle velocity
.1 HIll = significant wave height = particle velocity due to «design» wave
Hy = '(visual wave height» = flow velocity for anodes
Hn = the most probable largest wave height out of IOn = relative water particle velocity
waves encountered = component of wind velocity normal to pipe axis
Hr
I '
= =
reference value ofH n • i.e. for n r = weight per unit length of pipe in air. including pipe
= meancurrentrequirement per anode contents and water absorbed by the coating. also:
K = diameter factor. also: w = section modulus ofpipe cross section. also:
K = slope ofthe SoNcurve w = net weight of anodes
Kc = Keulegan-carpenter number x = longitudinal position of a point on a pipe .
Ks = stability parameterJ y = circumferential position of a point on a pipe. also:
k = roughness y = modeshape
k, = parameter in wave analyses (Table A I) a = linear coefficient ofthermal expansion. also:
k. = temperature derating factor a = symbol used in buckling formula
L = length ofreference block. also: 11 = logarithmic decrement ofstructural damping
L
I ..
= effective life ofanode = usage factor
= suspended length. span width = usage factor for equivalent stress
M = bending moment in pipe = usage factor for hoop stress
Mer = critical bending moment = permissible usage factor
MT = torsional moment in pipe = permissible usage factor when (1xis acting alone
m = parameter used in wave analyses. (Defined in Fig. = permissible usage factor when l1yis acting alone
A.2) = angular position of a point on a pipe relative to a
= effective mass per unit length of pipe defined radius 8 = 0
= -axial force in a pipe. also: r = mode shape parameter
= number of years in a probability consideration y = Poisson's ratio. also:
= critical axial force in a pipe = kinematic viscocity of a liquid
= «equivalem» axial force in a pipe subjected to inter- = mass density. also:
nal andlor external pressure = resistivity
I Nj = number of constant amplitude stress cycles «,.)) to = element stress due to net buoyancy force
J failure = critical one' dimensional compressive stress for com-
= critical number of stress cycles pletely elastic buckling (O',E or ~'EJ
= exponent when number of waves is expressed as a = equivalent stress according to von Mises
I power of 10 = permissible equivalent stress
J = actual number of stress cycles of a given stress ran-
ge(~),
= specified Inorrunall yield strength
= stress range
= number of waves within bJockj = Stress range for stress blOCK» no i
(C
10
1
0", = element stress due to vertical wave force Maximum operating pressure = maximum pressure to
°sJam = element stress due to net buoyancy force which a piping system will be subjected In operation. which
0, = longitudinal stress '7 should include static pressure and pressure required toE·
aa.el = criucal longitudinal (compressive) stress r~~ friction. (
oM Cv~ ~ _ ~~\~~~
= longitudinal stress due to pipe bending. defined as __ ...:.-...... r~\O o~~·a..
• M/v,,' ~pressure = total pressure caused by a change in ve-
1 . ---,--
ON
t = longitudinal stress due to axial force =
N/ A locity of flow within a pipeline system. _ -..
a ~~r = .. I h '1' . I
cnuca a; w en ,. IS acting a one Test pressure = Co-..-..~~\cv.......(.....,o
pressure specifie to be applied to a vessel.
'"
a KCf =
=
critical o. when N is acting alone pipe. component. etc.. on 0 letio of manufactureand/ or
o .p perrnissible c, on ~ of construction. It may also be the pressure
oe, = longitudinal stress due to shell bending specified to be applied to a vessel. etc.. after appropriate per'
Oy = hoop stress iods in operation.
a yer = critical compressive hoop stress
Oyp = permissible hoop stress lin tension> Strength test pressure =
pressure of a higher magnitude than
OyE = critical compressive hoop stress for completely elast- test pressure and with ~hon,duration.
ic buckling when Ov is acting alone ~-l-"f'"- ...:.~~{-,e, " c," - " ~ •
Tx~' = tangential shear stress Leak est pressure =pressu~e normally of a lower magrn-
·Xl = radial shear stress tu e than test pressure and WIth at least the same duration.
()
/
~Radial shear stress =
shear stress which in a cross section of Understrained lines = pipelines without substential axial res-
the pipe acts in the radial direction. traint l~1aximum one fixed support and no substential fric-
tion>.
-Pipe bending moment = bending moment (Ml in the pipe
.....cross section as a,,~hore) ~~ r c..=' ..... f~e i:. Suspended length =
length of a pipeline without contact
with the sea bottom or other supports (= unsupported
\ Shell bending moment = bending moment Im.or my) in the length).
I.£ipe wall per unit length.
Laying parameters = essential parameters affecting the stres-
Pipe bending stresses = longitudinal stresses due to pipe ses in a pipeline during laying. such as applied tension. stin-
bending moment. ger curvature. etc.
Shell bending stresses
rnent,
= stresses due to shell bending 010- Nominal .....all thickness =
the pipe wall thickness that is spe-
cified for supply of pipes.
1.4.1 Application
limit by assuming 35% below LAT.
1.4.1.1 These Rules apply to submarine pipeline systems as
1.3.10 Submerged zone defined in L3.1 intended for the transportation or transport-
ing liquid and gaseous hydrocarbons as defined in 1.3.20 and
By the submerged zone is meant the region below the splash 1.3.21. The Rules may also be applied. wholly or in part. to
zone including sea water. sea bottom. and buried or, mud zo- pipeline systems carrying other products, This is to be decid-
ne. ed by Veritas in each separate case.
. .J 1.3.11 Atmospheric zone 1.4.2 Amendments
By the atmospheric zone is meant the region above the splash 1.4.2.1 Amendments to the Rules may be' undertaken at
zone. any time and may also be applicable for pipelines or risers
which have already been approved by Veritas,
1.3.12 Platform
By a platform is meant a fixed or permanently anchored off- Unless otherwise decided. the a~dments are to come intO
, shore installation onto which the riser is mounted. force 6 months after the date o~uran~ ~ ...... :.o,-~.
104 ~ ..; II is assumed in these \{ ules that external rrsers on I.S.~ Withdrawal of Certificate
platforms and similar structures <Ire adequately protected
trorn impac S om vessels and similar accidental mechanical I .s 4.1 Veritas reserves the ril;hl 10 withdra w the Ccrtifi-
mflucncc Hence II IS assumed that the prorccung structu«.. call' of Approval if the Owner fails 10 cornplv with the direr-
and not the nscr. IS designed for such loads lives of operaunp the system withm the specified limits.
1.5.1.3 The Certificate of Approval will be issued after Ve- 1.5.4.4 The withdrawal may be made conditional. in that it
ritas' consideration of all relevant documents and declarations will be executed onlv if the Owner has failed to earn' out his
of survey concerning the pipeline system in question. The obligations within a ·stipulated time period. .
Certificate will contain.
a description of the pipeline system and its function. 1.5.4.5 If the situation leading to withdrawal of the Certifi-
a specification of the operational limitations for the pipeli- cate of Approval no longer exists. the Certificate may be
ne system. remstated . As a condition hereto. Veritas can require that the
a specification of the geographical location of the pipeline pipeline system will be subjected to certain specified surveys
system. tests or improvements.
a statement that the pipeline system is designed and con-
structed in accordance with these Rules and under the
surveillance of Veritas.
I
l 1.8 Documentation 1.8.2.6 Materials and fabrication of pipes and components
The following is to be submrtted for approval:
1.8.1 Submission of documentation Maleria s ecifications for pipes. i m components~
1.8.1.1 This section outlines the documentation required in ports. olts. nuts nd welding consumable. "O~,S'"
order to obtain a Certificate of Approval. Detailed require- Fabricatidfi pl..'Clficalion of pipes. piping components am
ments to the documentation is described in the respective supports. ~\.o
main sections.
1.8.2.7 Corrosion protection. The following information i:
1.8.1.2 Documentation essential for the understanding of to be submitted for approval:
the pipeline system and necessary to prove its safety is to be Specification for coating and coating application. includ
submitted Veritas, ing field joint coating
1.8.2 Design phase
"'-
- ' 'S.o-I)<:>"t""'V\.E:..
Specification for anodes
Specification of cathodic protection system including de-
1.8.2.1 The Owner is normally to~ to Veritas the de- sign calculations
sign documentation before fabrication and installation ~ Description of anode location
'l men~_ G» ~- e-~00.A......,
/ ENVIRONMENT
.....:..'--'\.~\,h~'-e.~""\ 4l.
I
I 2.1.1 Environmental phenomena
2.1 General ~c~"w""ff~~
~
'ec
The intended pipeline route is to be surveyed for
and obstructions down to a depth exceedrng that
reac ed by the pipeline during installation. burial or opera-
c- ::'lu>€fo
2.1.2.3 The various environmental factors are to be describ- 2.2.4 Seabed properties
ed by characteristic parameters based on statistical data or 2.2.4.1 All the geotechnical properties necessary for
long term observations. If sufficient data directly applicable evaluating the effects of relevant loading conditions are to be
for location in question are not available. reasonablyconserv- determined for the subfloor deposits. This should include
ative estimates based on relevant data for other relevant loca- possible unstable deposits in the vicinity of the pipeline.
tions may be used.
2.2.4.2 The geotechnical properties may be obtained
2.1.2.4 Statistical data are to be utilized in describing en- through. a com.oination ?f seismic survey.eii'l~in sit~ tests
vironmental parameters of a random nature (e.g. waves. and borings wlth€mllmg ) . e~Qrv..~t'lQ
windl. .Proper care is to be exercised in deriving such par-
ameters in a statistically vali(fuann§:;)nd generally accepted
~ e---v--r..Q
methods are to be used. C . cal surveys. sea bottom topographical surveys. visual sur-
. ~e:..-... ..... ~ veys. biological investigations. chemical examinations and la-
boratory testing on samples from borings.
2.2.2.3 The accuracy needed may vary along the proposed 2.3.2.2 The assumed maximum tide is to include both as-
route. A higher degree of accuracy is required in areas where tronomical tide and storm surge. Minimum tide estimates
other activities. obstructions or highly varied seabed topogra- should be base on the astronomical tide and possible nega-
phy or subsurface conditions may dictate more detailed in-
vestigations.
tive storm surge.
_0.
0 .......~J4;L
2.3.5.5 For risers and for pipelines during laying reasonable 2.4.2.2 Limits of temperatures and pressures. and allowed
assumptions should be made as to current velocity distribu- concentrations of corrosive components for the product LO be
uon.over the depth. For risers this is normally to be the same transported are to be specified, Of special concern is the con-
as used for the platform. . tent of:
J
tern the follow109 properties. with seasonal variauons 0; the oxygen
sea water and soil along the route are 10 be considered: carbon dioxide
- temperature hydrogen sulphide.
II.
@
~ ' 2 '3 '2 If the buoyancy of the pipe is included in the term
«weight». the longitudinal force due to press!.lG.is to be add-
'.J. 3.2 Functional loads . ed. If weight in air is used together with the actual pressure
normal to the surface. the effect of pressure on the longitudi-
3.2.1 General nal force is automatically included in the result.
J.J.I .J The environmental loads during norm' o eration a = liquid particle acceleration normal to the pipe axis
are not to be taken less than the most probabl sever~oad (wave induced particle acceleration)
in a time period of 100 years. ~. ~" ..... - . .ar = relative acceleration between water particle and pi-
-t .;>l!.-.).....,.,.... pe normal to the pipe axis
3.3.1.4 For temporary ~ the design period is to be ta- Cn. = added mass coefficient. In general em is a function
ken as three times the expected duration of the phase. but not L of Reynolds number. Keulegan-Carpenter number.
less than 3 months. Sec also 3.3. I .5. ... pipe roughness. and the distance between the pipe
~~'5 and a fixed boundary. This boundary may f.inst. be
J.3.1.5 The environmental parameters for determination of ...e.,"~ the seabouom for a pipeline on or close to the sea-
environmental loads in temporary phases lasting 5 davs or io'!tl ...,..;,... bottom. or the caisson wall for the outside riser on a
less. and which can be interrupted on a 48 hours Earnini) ; r1: .
gravity structure. Proposed values of C m given in
can be based on reliable weather forecasts. ~v· 5.0 'i!> {.r·....y.e.Appendix A may be used.
c..~~\i;:"""S'. Dr =
total outside diameter of the pipe (including coating.
J 3.3.2 Wind Joads
3.3.2.1 Wind loads. based on given wind data. may be de-
marine growth etc.J, .
= the inertia force per unit length acting normal to the 3.3.5 Current loads
pipe axis. ).J.5.1 The current induced drag and lift forces on a pipeli-
= the mass density of the surrounding water. ne or riser are to be determined m combination with the wa-
1!111!11I1111.1I111111111.11 • • • • •, ---------------------~--~~ ••:"
1
19
SoC::: ~o f e":'e.-LS ~
ve forces. This may be done by a vector additon of the wave Weight of the ice. /
and current induced water particle velocities. If available. Impact forces due to~f the ice.
computations of the total particle velocities and accelerations, Forces due to expansion of the ice.
based on more exact theories of wave - current interaction. Increased wind- and wave-forces due to increased expos-
will be preferred. ed area or volume.
3.3.5.2 Special attention is to be paid to possible current in- 3.3.7.3 Forces from floating ice are to be calculated accord-
duced vibrations. of exposed risers and free spans of pipelines ing to the best available theory. Due attention is to be paid to
due to vortex shedding or other instability phenomena. the mechanical properties of the ice. contact area. shape of
For guidance see Appendix A. structure. direction of ice movements etc. The oscillating na-
ture of the ice forces (build-up of lateral force and fracture of
3.3.6 ..Indlrect» environmental loads moving ice> is to be taken into account in the structural ana-
3.3.6.1 For a riser during operation possible significant soil lysis. When forces due to lateral ice motion will govern struc-
deformation. displacement of the platform due to soil de- tural dimensions. model testing of the ice-structure interac-
formation. and significant platform deformation are to be ta- tion may be required.
ken into account. Some portion of the connected pipeline
may also be considered for such effect.
"1
I
'1
, \O
-;..'o,,,O"v-'-Q-.....
cc-R-.o-., J:;. c"'O-'\.:'("\
cJ.-.."'.. . . ~ "''" "'"
:!o /_1> cc\.,'-~\..~ ~v:l~ l.~\~,-"-A..) 1
SECTldl\\
4
STRENGTH AND. INPLACE STABILITY
4.1 General ·U 32'., I n these: Rules two main design conditions arc de-
fined '.
4.1.1 Design analyses
4.1.1.1 The design analyses are to be based on accepted
-,
Pipeline-systems during operation
principles of statics. dynamics. strength of materials. and soil PIpeline sY$tems during mstallation
mechanics. and are to be in accordance with these Rules. See
also 4-.1.2.3.
~
..l r;.,.. J _
4.2.1.4 In zone 2 and where ound ecessary pipelines are
to be protected against unaccepta e mechanical influence.
Protection may be achieved by one or a combination of the
For design against corrosion. see Section 6. following means:
Concrete coating
4.1.2.2 These Rules do not specify any limitations regard- Burial
ing elastic deformations or vibrations. provided the effect of Backfilling - ......... ~~~--e._\. ~€.~ $;.,..'./<)
large deformations and the effect of dynamic behavior. in- Other mechanical protection.
cluding fatigue effect of vibrations. are taken into account in
the strength analyses.
Table 4.1 US3Ke factor is not to exceed the permissible value a or given below.
4.2.2.2 If not a more accurate mel hod is used. the tensile !1F and k(are defined in 4.2.2.1.
hoop stress. to be compared with a yp of 4.2.2.1. is to be deter-
mined by the following formula: 4.2.2.9 For suspended spans in axially restrained lines the
axial force developed due to the sag may be taken into ac-
'1 y = (Pi-PC>' lto count. If this effect will stop the bending strain (or flattening}
within the limit given in 4.2.2.5 and 4.2.2.6. the value of a.
Pi = Internal pressure to be inserted in the formula of 4.2.2.8 mav be determined as
p, = external pressure if the span acts as a cable. In such a case stresses due to ther-
D = nominal outside diameter of pipe mal expansion will only be those corresponding to the chan-
......~(a-
t = nominal wall thickness of pipe ge in sag caused by the thermal expansion.
4.2.3 Buckling
The possibility of buckling is to be considered. De-
4.2.3.1
pending upon the load and support conditions of the pipe.
one or more of the following three buckling modes may be
possible:
'.1 4.2.2.4 . For pipeliners and risers the permissible longitudi-
Local buckling of the pipe wall. due to external pressure.
axial force and bending moment. See 4.2.3.2 through
nal stress (a,) and shear stress C,x) depend on the consequen- 4.2.3.4.
ces of 'ieldin. n Cases where possible strain (displacement) Propagation buckling due to external pressure - when
does not exceed the permissible strain (see 4.2.2.5>' stresses~ first a local buckle or similar damage has occured. See
need not to be used as a criterion for safety against excessive e
4.2.3.5.
Buckling of the pipe as a~ compression, See 4.~.6 .
• yielding.l In cases where possible strain exceeds the perrnissi- f :P ""~t-A--~. d...&t~_ .....
ble strain (d~spl.acemenu. the equivalent stress ("c> is to be us- ~ e..A~-I!'"D ......:. ;:."'.......~'-
ed as the cntenon. see 4.2.2.8. . l 4.2.3.2 The pipeline is to have adequate safety against local
" lq~~~'Z.. buckling under the most unfavourable combination of ex-
4.2.2.5 The permissible strain depends on thefducility of the ternal overpressure. axial force and bending moment. The
material and on previously experienced plastic/strain. The pi- applied combination of stresses is to be compared with the
peline or riser is to have acceptabel fracture toughn after critical combinations. The critical combinations mav be de-
the deformation. For Olt ratios above a certain va ue. arten- termined from available relevant test results. The empirical
ing may govern. see 4.2.2.6:~ formulas. methods and corresponding criteria given in A~
pendix B may be used.
,."1 4.2.2.6..--T!:l~Ulattening due to bending together with the~t
J of roundness toleranc from fabrication of the pipe see 4.2.3.3 Bending moment due to a curvature which cannot
" ..2.. IS not to exceed 2 /i) : \o~og,~':l>..J"\ . ~ change. e.g, a riser in a J-tute needs not be taken into ac-
G .....~.~.~ .. ,'" /2/: . .~ count in the buckling analysis.
•. ~.. " - ' 0'0 ., ovQ..l(.".... ""'-_,
C "11._;.. ....... 2 m.. - min < --- -e """~"""'t.
..' <:.) 0ma.... 0min 100 4.2.3.4 The effect ofweight coating on pipe wall buckling
may be taken into account if satisfactory analytical or ex-
·n.2? The requirements of 4.2.2.5 and 4.2.2.6 apply to perimental documentation is provided.
conditions of permanent strain. such as the permanent curva- ~4.\. e-~
!ure of a buried pipeline. They also apply to exposed pipelines 4.2.3.5 ~ropagation buckling cannot be initiated be-
I~ (al.mostJ continuous contact with the bottom. For .exposed fore a local buckle has occured. no additional safetv azainst
pipelines not in continuous contact with the bottom the re- propagation buckling is required. For guidance see Appendix
quirernents of 4.2.2.5 and 4.2.2.6 will apply provided yield- B. r~e./~"""'t. ... '~·. c;;l • .J_~. o; ~h.'':~O c\..: ...."'_T"'.......
mg would lead to such contact that the strain would be
stopped before exceeding the permissible value. 4.2.3.6 ~has
to be documented either that the safety
against!'5irouckling is not less than what IS normally accept-
4.2.2.8 Normally for risers and in cases where possible ed or. 'irbarbuckling is unavoidable. that the pipeline! riser
strain exceeds the permissible strain. e.g. suspended spans will not suffer any dama~he postbuckled mode. For a _
where new contact with the bottom is not obtained before nonburried pipeline such ~will normally not be requir- (
the permissible strain is exceeded. the equivalent stress. defin- ed. .... "
ed as (lO-J .... - Q r"U:l.J..... J..,... ='
4.2.4 Fatigue
42.4.1 All stress fluctuations of magnitude and number
large enough to have a significant fatigue effect on the pipeli· consisung of a convenient number of constant amplitude J
ne system are to be investigated. stress range blocks (0r'j and a number of repetitions nj' The
fatigue criteria then reads:
4.2.4.2 Typical causes of stress fluctuations in a pipeline
system are. s n
Direct action of waves. r -7 <I}
Vibrations of the pipeline system. e.g, due to vortex ,=1 1',
shedding caused by current. waves. or wind.
Platform movements (displacements or deformations). where
Fluctuations in operating pressure and temperature.
= number of stress blocks
The above phenomena. together with possible other causes of = number of stress cycles in stress block i
stress fluctuations. are to be considered to the extent relevant = number of cycles to failure at constant stress range
in each case. (a~
1] = usage factor
4.2.4.3 Fatigue analyses are in particular to be made for
constructional details likely to cause stress consentrations. The number of stress blocks. s. is to be large enough to ensu-
se.-po TheJiIDi):>ffatigue design is to ensure adequate safety against re reasonalbe numerical accuracy. f'" ~"~6~t.:r",-'. ~ f.""
"",""\.",,~,,.:t e....."" "\,,0 """"-. .....
---fatigue failures within. the planned life of the structure. The
specific criteria will depend on method of analysis. of which The limit damage ration 1] will depend on th~ntaina~
two different categories exist: i.e, possibility for inspection and repair.
Recommended values of 1] are given in Table 4.3.
a> Methods based on fracture mechanics. See 4.2.4.4.
Methods. other than Miner's rule. for accessing cumulative
b) Methods based on fatigue tests. See 4.2.4.5.
damage will be considered in each separate case.
4.2.4.4 Where appropriate. a calculation procedure based
on fracture mechanics may be used. The specific criteria will T a ble 4 3 U sage f actor
be considered in each separate case. ""\
Access for inspection No access Access
4.2.4.5 The methods based on fatigue tests consists general-
ly of the following three main steps: Usage factor I"\. = 0.1 0.3
Determination of long term distribution of stress range.
I see 4.2.4.6.
4.2.5 On-bottom stability !
• - - Selection of appropriate SoN curve Icharacteristic resist- I
ance). see 4.2.4.7. 4.2.5.1 The pipeline is to be supported. anchored or buried
Determination of the accumulated damage. see 4.2.4.8. in such a way that under the assumed conditions it will not
move from its as-installed position. apart from movements
4.2.4.6 All stress fluctuations imposed during the entire life. corresponding to permissible deformation, thermal expan-
included the installation phase of the pipeline system which sion. and a limited amount of settlement after installation.
have magnitude and number large enough to cause fatigue
effects are to be taken into account when determining the Criteria which wi11limit permissible deformations are:
long term distribution of stress range. yielding.' buc~;nd fatigue Of. pipe
deterioration wear oLcoating .. ...JS4=
As most of the loads which contribute to fatigue are of ran- geometrical limitations of supports
dom nature statistical considerations will normally be requir- distance to other pipelines. structures or obstacles
ed for determination of the long term distribution of fatigue
loading effects. Deterministic or spectral analysis may be us- The requirement to permissible deformation may ~ary
ed. The method of analysis used is subject to acceptance. along the pipeline.
,D. ............."" ~
. <= !> ='
The effect of dynamic response are to be p~~ accounted 4.2.5.2 If the pipeline at any location along its route is on or
for when determining the stress ranges n1 it can be near~ the risk of slope failure is to be analysed. Regard-
shown that the dynamic effects are negligible. Special care is in&"precautions against slides. reference is made to 8.2.3.
I
to be taken to determine the stress ranges adequately in pipe-. L ~---o>le.~:t-_ ..... If-~~
I; lines or risers excited in the resonance range. The amount of"'
~'-assumed in the analysis is to be conservatively esti-
4.2.5.3 Buried lines are to be checked for possible ~
or floatation. For both liquid and gas lines sinking is to be
I'
I
rna .. ... .........~o...o considered assuming the pipe is waterfilled, and floatation is
to be considered assuming the pipe is gas- or air-filled.
: 4.2.4.7 Characteristic resistances are normally given as SoN
I curves. i.e, stress versus number of cycles to failure. 4.2.5.4 Llf
the specific W~!~!1t_9fthe waterftlledpipe is less
I than that orthe__s.Q1lJIii"~uc1iJ!g water coriten"tST.·no Tiiffiier
The SoN curve used is to be applicable for the material. con- ana:ryse$areniieded to document the safety against sinking.
struction detail and state of stress considered as well as to the For lines to be placed in soils having low shear strength. a
surrounding environment. "" consideration of soil stresses may be required. If the soil is. or
/~ likely to be liquefied. it is to be shown that the depth ~f
The SoN curve is normally to be based on a 9596 confidence' 'sinking will be satisfactorily limited. either by the depth ~f li-
limit. . ); g"uefaction or by build-up of resistance during sinking.
~.-..,. -
In Appendix B failure modes for some typical construction 4.2.5.5 If the specific weight of the gas- or air-filled pipe is
details are classified in relation to a family of SoN curves. less than that of the soil. it is to be proven that the shear
strength of the soil is sufficient to prevent floatation. Con-
4.2.4.8 In the general case where stress fluctuations occur sequently. in soils which are or may be liquefied. the specific
with varying amplitude in random order. the linear damage weight of the gas- or air-filled pipe is not to be less that that
hypothesis (Miner's rule) may be used. ' of the soil (if burial is required>.
Application of Miner's rule implies that the long term dis-
tribution of stress range is replaced by a stress histogram.
4.2.5.6 Exposed lines resting directly on the bottom with-
out any special supporting elements or anchoring devices. ex- J
111111111111111_. . . .11111'
cept possible weight coating. are to be checked for sinking in Fatigue (due to possible vortex shedding) see 4.2.4.
the same manner as ecplained above for buried lines. Furt- Interference with human activiteis e.g. fishing
her. such lines are to have the<Ee1OWJ required safety against
being lifted off the bottom ~horizontallY. Free spans are not acceptable if they may lead to failure of
' - - . ~~oO f.Ho ~ the pipeline or put restrictions to human activities.
4.2.5.7 Liquid lines as well as as lines a;:;-in~h~ air- or
gas-tilled condition. to have a-ific gravtt higher than that
[ of sea water. (<<Negative buoyancy)) . Ired minimum va- 4.3 Pipeline! riser durIng Installation
lues will depend on pipe size.
4.3.1 General
4.2.5.8 Horizontal (transverse> stability is to be checked for 4.J. I.I Strength considerations for the pipeline! risers dur-
wave and current conditions accordingto 3.3.1.3 and 3.3.1.4.
ing installation are to be made in order to determine how the
pipeline! riser may be installed without suffering any damage
The most unfavourable combination of simultaneously acting which may impair the function or the safety of the completed
vertical and horizontal forces on the pipeline is to be consid- line. or which may involve hazardous installation or repair
ered. When determining this unfavourable combination. it
work. See also Section 8.
may be taken into account e.g. that the forces will vary along
the line. and directional distribution of waves and currents.
. ,'j C·<:A-.c.· . . .'" (,,~.
-.p
. 4.2 .5.9 . If the rnotio
o..lt"\.a...\l V'\.s,Q
4.3.1.2 If the installation analyses for a proposed pipeline!
riser show that an acceptable set of installation parameters
f the pipeline is to be restrained eith- cannot be obtained with the installation equipment to be us-
er by friction force tween the pipe and the sea bottom or
by forces ;rnobirr:Zea hrough lastic deformation of the sup- ed. the pipeline/ riser is to be modified.
porting sou.aractor 0 ety of minimum 1.1 is to be includ-
4.3.1.3 The requirements of 4.3 apply also. as far as applic-
ed when establishing the restraining force.
able. to repair operations.
4.2.5.10 The coefficient of friction may vary (within a wide
range> with bottom material and surface roughness of the pi- 4.3.1.4 Only those sections under 4.3.2. 4.3.3 and 4.3.4
peline. The applied values are to be based on relevant in- found pertinent to the various installation techniques/ phases
formation from the actual location. should be considered.
4.2.5.11 Axial Ilongitudinal) stability should be checked. ·U.1.5 Any installation phase/ technique is to be checked.
Especially near platforms and/ or places where the pipeline Such phases and techniques are: .
changes direction. sufficient flexibility and space for expan- Start of laying operation
sion should be allowed fo . The expansion calculation should Normal continous laying
be based 0 conservative valu or the axial friction between Pipe abandon and retrieval
pipeline and so . .b,Q.,. ~~ Termination of laying operation
m~.\ +
- ~ mID
mIM
<; 120~
/'
'V' ,,'-4.0..)( oD I :0>",
pipe during laying. namely the change 111 direction 01
the Pipe axis in the horizontal plane near the lilt-off
points. is to be specially considered,
4.3.2.5 The requirement of 4.3.2.1 ctPPly to the assumed
most unfavourable condition during installation. i.e. assumed 4.3.3 Buckling
maximum wind. waves and current acting. (Loading condi- 4.J.3.1 Local buckling og the pipe wall is to be considered
tion b). see 3.1.2.1 and 3.3.1.4). This requirement applies also in accordance with the applicable clauses form 4.2.3.
to portions of the pipeline where the strains are completely Guidelines is found in Appendix B.
controlled and cannot change. e.g. where the curvature is
controlled by the curvature of a rigid ramp. whether or not Fati~ue
environmental loads are acting.
;;"-(~.j
4.3.4.1 When checking the fatigue life according to 4.2.4.
Z . 4.3.2.6
Instead of a direct consideration of residual strain as
~.x.Plain~d in 4.3.2.1 and 4.3.2.5. the following criterion may
~apPlled: .
possible fatigue effects in the installation phases are to be add-
ed.
(N + M);
~ b.g5~ )~ + 4.3.4.2 When the bottom tow. bottom pull or the floatation
2 0.85..
;--V A -: \\' . (1 Y - A ~ '7} -1](1F methode is used for installation of a pipeline. fatigue is con-
I . . sidered to be a major effect and this effect should be paid
where the usage factor I] is 0.72 for loading condition a) and special attention both through theoretical calculation and
0.96 for the condition mentioned in 4.3.2.5. tests.
Other symbols: 4.3.4.3 Wind induced cyclic loads on risers during con-
/
stru~nd transportation is to be considered and taken in-
( N
A
= axial force (including effect of water pressure>.
= cross sectional area of pipe.
to~ when found relevant.
M = bending moment I
! W
t1y
= section modulus of pipe.
= hoop stress. 4.4 Piping components and accessories .1
t1F = specified minimum yield strength.
,I It is to be noted that if ~1 is determined on the basis of a gi- 4.4.1 General
ven curvature. the nonlinear relationship between moment 4.4.1.1 All pressure-containing piping ctponents and acces-
and curvature is to be taken into account. sories are generally to represent the same safety as that re-
quired above for plain. straight pipe.
4.3.2.7 For installation methodes involving a J or S shaped
curve of the pipeline Nand M are to be determined by an ap- 4.4.1.1 For all components. for which detailed design pro-
propriate method. suitable for the. water depth. pipestiffness cedures and criteria are not given in these Rules. sufficient
and weight in quesiio].... -Since"the"effect ofthe"e'nvrroclmental strength is to be documented in at least one of the following
loacis""is diffici£lt-to "determine. the minimum required ana- ways:
lyses are as follows: Equal or similar components have been proven satisfac-
A) Loading condition a> is to be analyzed in detail. and the tory by previous successful performance under compar-
'. '[?r':.~U..~~.9Y:j.2.O'is to be applied with a usage factor I] able conditions.
o malClmur!1lf.T1:" By proof tests.
B) Loading condft1Onb) is to be considered by evaluating By experimental stress analyses.
the increase of M due to environmental loads on the By engineering calculations.
basis of the assumed environmental conditions. the rel-
evant characteristics of the installation equipment (par- 4.4.1.3 If components designed according to a recognized
ticularly the laying vessel). and all available relevant Code or Standard has proven satisfactory performance.de-
experience. If there is reason to expect that the increase sign according to that Code or Standard may be generally ac-
of M will exceed 3l%. the assumed maximum M is to cepted.
r
j
25
SECTION 5
MATERIAL REQUIREl\1ENTS
FOR PIPES AND PIPING COl\tlPONENTS
5.1 General 5.2.2 Supply condition 'fe'-"'~1-~
5.1.1 Validity 5.2.2.1 The uppl condition is to be specified taking into
account possible verse effects as a result o~ weld-
5.1.1.1 This section specifies requirements to characteristic ing and heat treatment operations. which will occur during
material properties for design and quality control of steel line- fabrication and installation.
pipes and piping components. The requirements are applica-
ble to C-Mn steels, C-~'ln-fine grain treated steels and low al- 5.:!.2.2 Steel to be used' for general service may be supplied
loyed steels having a specified minimum yield strength up to as rolled. controlled rolled. thermomechanical treated. nor-
500 Mpa.and consumables for welding. malized. quenched and tempered or subcritical age-hardened.
Steels of higher strength. other alloys and other materials 5.2.3 Heat treatment
may be used subject to special approval.
5.:U.I Steel castings and forgings are to be normalized.
5.1.1.2 \1aterials for corrosion protection and weight coat- normalized and tempered or quenched and tempered.
ing are covered bySection 6.
f>" .Q.,.~"l..~ ....,fi::- 5.2.3.2 Rolled steel for low temperature service Ii.e. mini-
5.1.1.3 The 'iiiiiiUlacrtml is to be capable of producing ma- mum design temperature below O°CJ is either to be normal-
terials of required quality. Relevant documentation is to be ized. quenched and tempered or therrnomechancically treat-
J made available on request. ed,
5.1.4 Documentation and identification 5.2.4.5 The elements listed in Table 5.1 are to be determin-
ed and reported. Other remaining elements added on purpose
...,,1 5.1.4.1 All materials are to be delivered with test certificates to control the material properties are also to be checked. and
stating the heat number. manufacturing methods. test results. to be reported.
identification etc. Material test certificates for pressurized
parts are normally to b~ndor~ by Veritas, Procedures for chemical analyses are described in Appendix
Q.. f' F"'l<:>,)~~ C.
5.1.4.2 All materials are to be traceable and suitably mark-
ed for easy identification of manufacturer. grade. heat num- 5.2.4.6 The chemical composition of low-alloy and alloyed
ber.size and application. steels will be considered in each case.
5.104.3 Materials of uncertain ongin or uncertain quality 5.2.4.7 The impurity level and inclusion contents are to be
are .to be rejected. or a special identification and test pro- kept specially low in steel to be used in pipeline systems de-
gramme is to be agreed upon. signed to transport com . ies which under unfavourable
conditions Olav cause listenng. also called stepwise crack-
ing. (See also 5.2.11 and6.4. -I"- ~E'e...
5.2 Steel for line-pipes
5.2.4,8 The chemical composition is to be specially consid-
5.2.1 Steel making ,fc ....ole.-\...t... ered for steel to be used in pipelines where underwater weld-
ing is planned for tie-in operations or should be anticipated in
5.2.1.1 The steel is to processed and€Dn a manner ensur- case of repair situations.
109 uniform composition. properties and soundness. Irnpunt-
ies and residual elements are to be kept at a level consistent 5.2.5 :\-fechaniclil testing
with specified property and service requirements. '-
s.e....-....e.c... ~-" \J ~ r;,. 5.2.5.1 The following mechanical properties are essenual
5.2.1.2 The steel is normally to be ully kille -Steels for li- and are to be determined and reported as part of the quality
1 quid pipelines may. however. be semi- I e when the specif- control:
....J ied minimum yield strength is less than 300 ~IPa . - Yield strength
26
C Mn Si P S Cu Ni Mo Cr Al Others Carbon
Analysis 96 % % % % % 96 90 % (totaO % equivalent-'
max. max. max. max. max. max. max. max. max. % max.
Ladle 0.18 1.60 0.55 0.025 0.020 0.J5 0.40 0.25 0.20 0.08 J) 0.40
Check 0.20 1.70 0.60 0.030 0.025 0.35 0.40 0.25 0.20 0.08 J} 0.43
II
27
high upper shelf Charpy V-energyl, the notch toughness re- limit for SSC resistance. when the accumulated plastic strain
5.2.9 Supplementary fracture toughness testing 5.2.13 Resistance against chloride stress corrosion crack-
5.2.9.1 Fracture toughness tests other than the Charpy ing
V-test. may in special cases be allowed or required to assess 5.2.13.1 Materials which are to be used' In seawater en-
.i.l the resistance to unstable fractures and/ or determine defect
tolerances in materials and welds.
vironment are to be resistant against chloride stress corrosion
crackning.
Such tests could be Drop Weight Tear Test (DWTT). Crack 5.2.13.2 Application of alloyed steels and/or extra high
J Opening Displacements Test (COOl. Compact Tension Tests
(CTl. Drop Weight test (0\1,/) or full scale type tests. Pro-
strength steels (specified min yield strength above 500 MPaJ
is to be specially considered when the pipeline will be operat-
cedures. extent of testing. conditions and interpretation of re- ing at higher temperature (above 70°C). or the oil and gas
I sults are to be agreed in each case. contain significant amounts of chloride components. Verifi-
cation by relevant experience or suitable laboratory tests may
I 5.2.10 Resistance against hydrogen induced cracking in be required.
welded joints.
5.3.1 General
exceed 325 H\'5 at any pan of the weld unless otherwise re-
quired (see 5.2.12). 5.3. I .1 The material is to be free from any defects which
may make the material unsuitable for intended service.
5.2.11 Resistance against environmental induced blister- Cracks. notches. gouges and tears are not acceptable. Over-
ing. laps. slivers. impressed mill scale etc. are to be removed by
grinding unless proved to be of a superficial nature (see
5.2.11.1 Steel for pipelines designed' to transport commodit-
7.2.6.13'.
ies which may cause blistering (also often called hydrogen in-
duced pressure cracking or stepwise cracking) is to be made 5.3. I .2 The material is to be free from gross laminations.
in a manner making the steel reasonably resistant. Verifica- gross inclusions. segregations. shrinkages and porosity. The
tion by relevant experience or suitable laboratory tests may soundness of rolled. forged and cast material is to be verified
be required for the base material. (See 5.2 and 6.4) by non-destructive testing according to agreed procedures
and standards (see 7.2.7.3).
5.2.12 Resistance against sulphide stress corrosion crack-
ing (SSC) - .
5.2.12.1 Materials and welding consumables for use in pi-
peline systems required designed against sulphide stress cor- 5.4 Steel for piping components
rosion cracking (see 6.4). are to have a chemical composition
5.2.12.3 Suitable heat treatment may be required for high 5.5.1 General
strength steels and welds to ensure adequate resistance
against SSe. S.5.1 .1 Welding consumables are to be suitable for the in-
tended applicauon giving :.I weld with required properties.
5.2.12.4 Cold formed C-~ln and e-~ln fine grain treated soundness and corrosion resistance in the finally installed
steels are to be heat treated and meet the applicable hardness condition.
2S
5.5.1.2 \\1" elding consumables are tn have classification ac- 5.6 Holt 3<;semblies
cording to recognized classiflcauon schemes. Low hydrogen
ccnsumablcs are normally to be used for welding of hil;:h 5.6.1 General
strength steels.
Cellulosic electrodes may. however. be used provided it is es- 5.6.1.1 Bolts and nuts arc to be made of steel having chemi-
tablished special welding procedures preventing hydrogen in- cal composition and mechanical properties in accordance
duced cracking. with. and arc to be manufactured and tested to relevant. re-
cognized standards.
5.5.1.:; Hydrogen controlled consumables are to give a dif-
fusible hydrogen content of max 5 mil I00 s; weld metal 5.6.1.2 Bolts to be exposed to or immersed in sea water arc
(when determined with the glycerin method). and are to be to be of property class 8.8 (ISO R898) or of a equivalent
type approved. strength level. The strength level is not to exceed property
class 10.9 for bolts to be installed above the splash zone.
5.5.2 Chemical compositon
5.6.1.3 When bolt assemblies are to be used in low tempe-
5.5.2.1 The chemical composition of the weld deposit is to rature service. or having large diameters. fracture toughness
be compatible with the base metal to prevent general and lo- testing may be required.
calized corrosion. Content of alloying elements is to be kept
ara safe level consistent with documented experience. Pre- 5.6.1.4 Bolts. nuts and other fastening elements are to be'
cipitation effects due to intended heat treatments are to be protected against corrosion - by suitable. durable coatings.
considered. When bolts assemblies are pan of or will join components
which are required designed against stress corrosion crack-
5.5.3 Mechanical properties ing. the applicable conditions to materials. manufacturing
5.5.3. I The meehaniamca I pro,..~
........
••les 0 f the we Id meta I are to - 5"
and 12testing
) would also apply. to these connections, (See
meet the base material requirements. Exessively overmatch- ._..
ing yield and tensile strengths are. however. to be avoided.
5.7 Materials for support structures
5.5.3.2 Impairment of tensile and toughness properties due
to intended heat treatments is to be considered.
5.7.1 General
5.5.4 Handling and storage of welding consumables 5.7.1.1 When support structures are welded directly to. or
act as a pressurized pan of the pipeline system. the material
5.5.4.1 Welding consumables are to be treated with care to requirement for the pipeline pan in question are to be met.
avoid contamination. moisture pick-Up and rusting. and are
to be stored under dry conditions. 5.7.1.2 Support structures which are not directly welded to
pressurized parts are considered as structural members. The
5.5.4.2 The relative humidity is to be kept at max 4090 in material requirements specified for primary structural merne-
stores for low hydrogen consumables unless supporting evid- bers according to Dnv «Rules for the design. contruction and
ence confirm a somewhat higher humidity to be tolerable. inspection of offshore structures» - latest issue will normal-
5.5.4.3 Table 5.4 shows generally' recommended storage ly apply.
and handling routines. Recycling and rebaking is to be strict-
ly in accordance with the manufacturers' instructions. .
Covered electrodes
- low hydrogen
type 20-JO°CII 150°C 700Cll
- cellulosic type 20-30°Cu 20-30°C 11
Flux lor submerg-
ed arc welding 20-30°CIl 70°C 31
Notes:
II The temperalUre should exceed ambient by + SoC.
2) When withdrawn for use. low hydrogen eonsumabtes are to be kept in
heated containet$ and normally to be used Iwithin 4 hours.
3) To be 'handled ~rdinB to good workshop practice.
~~-
, I
, 29
I
!~:
I
SECTION 6
/1 .~ CORROSION PROTECTION AND \VEIGHT COATING
/,r~ \".I..e~'a.....a.... .
I 6.1 Corrosion protection, general Stray currents may be avoided by means of a metallic con'
-----'" I,..".t~ ductor connected to the return (negative) side of the stray cur·
f 6.1.1 Validity rent source. Counteraction ofthe effect of stray current rna}
f be obtained by means of cathodic protection or removal relo-
;i'! ! 6.1.1.1 Pipeline systems are to be adequately protected cation of the stray current source.
':' 1 from corrosion. 6.1 through 6.5 cover minimum require-
, ' ' ' '1 ments to corrosion protection systems. 6.6 covers the require-
~I ments to weight coating.
~ J 6.2 External coating
iLl
~ ...•...
6.1.1.2 Requirements to pipe materials and welds with res-
pect to environmentally induced cracking such as hydrogen 6.2.1 General
-1', i induced pressure cracking (hydrogen blistering) and SUlphide 6.2.1.1 The external coating is to provide adequate corro-
\ ~Si'lV stress corrosion cracking are given in Section 5. sion protection in the actual environment.
I r
;, ~,~~(; .....A.-
6.1.2 Definitions 6.2.1.2 Different parts of the pipeline system such as
<=r" lA'\'\
6.1 .2.1 Splash zone: The splash zone is defined as the as-
I.1 t
tronomical tidal ra~ge Ius the wave height having a proba-
pipe coating
field joint coating
"'.1.. " -bilit.y o~eedance o. 0.0. The upper limit of the splash zo-
J
coating of supports
'/ he is determJ'iie'Cr ass ng 65 % of this wave height above
• LJ:lo.T HAT and the lower limit by assuming 35% below LAT.
are to be adequately covered by the coatings specifications.
j,~t~/'\,,,.l.e- 6.1.2.2. Submerged zone: The sU.bmer~ed zone is defined as 6.2.2 Coating materials
.if f.€ the region below the splash zone including sea water and sea
Of special importance is proper roundin f the welding sys- 6.2.2.4 In add ilion to the properties given in 6.2.:U the
tem for barge welding during pipelaying, coaling specificauon IS 10 include information on
A - ... >s.~
,-. I.· -.. ,.....
30
generic type and composition and approval. If an impressed current system is to be used.
coating thickness due consideration IS to be paid to avoid overprotection and to
primer design a system with sufficient mechanical strength.
binder
reinforcement 6.3.1.2 Cathodic protection by sacrificial anodes is to be
fillers designed to provide adequate protection during the design life
of the pipeline system.
6.2.3 Coating application
The design may be based on a shorter period if reinstallation
6.2.3.1 The external coating is to be applied according to an
approved procedure. The procedure is normally to include: of anodes is arranged for.
6.2:4 Field joint coating At temperatures other than ambient the potential given in
6.2.4.1 Field joint coating should be applied according to an
approved procedure of similar nature as described in 6.2.3.
table 6.1 may not apply. Protective potentials which are
I mV 1°C more negative may be used for steel surfaces ope-
rating at temperatures between 25 and 100°C.
l
The field joint- coating should be compatible with the pipe
coating. 6.3.2 Design of system
Criteria for acceptance. repair and rejection of coating before 6.3.2.1 The cathodic protection system is to be designed so
final submersion of pipe are to be stated. Repair methods for that it is able to deliver sufficient current and distribute this
damaged coating under field conditions are to be described in current so that the criteria for cathodic protection is obtained
the procedure for field joint coating. (Table 6.)).
The current density requirement is to be selected on the basis
6.2.4.2 Surface preparation by power tool brushing to a of the environmental conditions either by experience from si-
uniform near-white metal finish may be accepted for asphalt milar conditions or from direct measurements along the rou-
or coal tar based field joint coating. te.
6.2.4.3 When mastic is used for field joint coating. it is of Guidance on the design of cathodic protection systems is gi-
special importance to keep the temperature of the mastic ven in Appendix D.
within acceptable limits.
6.3.2.2 Cathodic protection design specification should in-
The mastic should be adequately cooled by continuous wa- clude:
tercooling before the pipes passes over the stinger during lay-
ing operations. calculation of area to be protected
influence onl from electrically connected systems
current density requirement
6.3 Cathodic protection coating breakdown criterion
anode material and manufacturer
6.3.1 General anode weight. design. distribution and total number
calculation of the effectiveness of the system.
6.3.1.1 The cathodic protection system is normally to be
based on sacrificial anodes. 6.3.2.3 The anode core is to be designed to support the an-
ode during all constructional and operational phases. e.g.
Impressed current may be used upon special consideration transportation. installation etc.
31
6.~.3 Anode materials and fabrication The test welds are to be sectioned and examined for bonding
6.3.3.1 Sacrifical anodes may be alloys of aluminium or' and possible excessive Cu-penetrauon using a microscope
zinc. with magnification of at least 100x. The Cu-penetration is
normally to be less than 0.3 mm for procedures to be used on
The driving potential and electrochemical efficiency of the risers. while maximum 0.8 mm for procedures to be used on
anode alloy are to be documented by appropriate tests. The pipelines.
testing should be based on long term freerunning tests under
relevant -conditions, The hardness in the heat affected zone is to be determined on
the macrosections and is to be within the normal limit specif-
6.3.3.2 The anode core should be hot-dip galvanized for ied for the pipeline system.
zinc or blastcleaned to Sa 2.5 according to SIS 055955 prior
to casting of the anodes. 6.3.4.7 The welds and electrical connection between anode
and pipe is to be checked before pipe installation. Pipes with
6.3,).3 Manufacturers may be required to prove their capa- metallic connection between 'anode and reinforcement in
6.4.1 General
6.3.4 Installation of anodes 6.4.1.1 Internal corrosion control is to be provided for pi-
OJ' peline systems transporting corrosive hydrocarbons.
6.3.4.1 The anode arrangements is to be in compliance
j with the approved design specification. The anodes are to be Internal corrosion control may be achieved by one or more
mounted in a manner such as to avoid mechanical damage of the following methods:
during handling and installation of pipes. It is advisable that
anodes have a smaller diameter than the weight coating. Application of corrosion inhibitors
Corrosion allowance
6.3.4.2 Anode bracelets are to be fastened securelv on the Internal coating
pipe. The two segments may be welded together ~ith steel Application oi corrosion resistant alloys or linings
strips in order to ensure satisfactory mechanical connection Drying
and proper positioning. Each anode is to be electrically con-
nected to the pipe by at least two attachments. 6.4.1.2 The following properties of the commodity to be
transported should be taken intO account in the establishment
6.3A.J Electrical connection between anode and pipe is of a program for internal corrosion control:
normally to be made by manual welding or thermite weld-
ing. Attachment welding are to be placed at least 150 mm off Oil/ gas/ water ratios
other welds. Salinity. bacteria content. pH of water phase
Content ofcorrosive gases such as CO~. H ~S and O 2
J Manual welds for electrical connections are to be made on an
attachment plate. Attachment plates welded directly onto the
pipeline/ riser are to be orientated circumferentially. and per-
Solids content and flow characteristics
Temperature and pressure
formed .with qualified welding procedure. See 8.7. Regarding
material requirements see 5.7. Expected time dependance and variations due to. operational
conditions should be indicated. The possibility of changing
6.3.4.4 If thermite welding is used for attachment of anode conditions by seawater injection (secondary recovery) should
cables. welding procedure is to include: be considered at the design Stage.
Brand and designation of powder 6.4.1.3 Internal corrosion control is normally required
Size of mold. charge and cable when the commodity is containing water or has a relative
Preparation of surface humidity of more than 50't. and when the partial pressure of
corrosive gases is above the following limits:
Prior to thermite welding the surface is to be dry. clean and
bright. oxygen : 0.001 ~IPa (0.014 psi
6.3.·.. 5 Attachments of electrical connections by therrnite hydrogen sulphide :001 \1Pa 1I A psi)
'-"1
I welding are to be made with a qualified procedure proved to carbon dioxide . : 0.01 \1Pa (I A psi)
give sufficient bonding and negligible Cu-penetration along
grain boundaries. The size and shape of the mold is to sua the Combination of these corrosive gases may be more agressive.
diameter of the pipe and the anode cable size. especially the combination of H~S and O~. The corrosivity
will also generally increase by increasing temperature.
6.34,6 Qualification of the thermae welding procedure is
to be based on VIsual examination and mechanical testing of 6.4, 1.4 The H,5 values listed In 6.4.1 .3 are to be considered
three test welds. for general corrosion. Regarcrng limits of hydrogen sulphide
32
If the coating is applied before the pipeline is installed. due temperatures of hydrocarbons
~~nsideration should be given to internal coating of field intermittent wetting and drying
JOints. wave forces
resistance to ageing by seawater and sunlight
6.4.3.2 Internal coating which only is applied to increase ease of repair and maintenance
the capacity of the pipeline system is not subject to approval. compability of different materials when such are combin-
Due consideration is to be given to the possibilities of increas- ed.
ed localized corrosion at imperfections in the internal coating.
6.5.1.2 The riser is to have a Corrosion allowance in addi-
tion to other means of corrosion protection as described in
6;4.4 Internal corrosion control by corrosion resistant al- 6.5.1.3. .
loys
The corrosion allowance is to provide protection for 2 years.
6.4.4.1 Corrosion resistant alloys may be used for corrosion
control. The aJloy may be used as solid pipe or as a lining in- Table 6.2 gives guidelines on determination of the corrosion
side the pipeline. allowance as function of operating temperatures of the riser.
6.4.4.2 The corrosion resistance of the alloy should be doc- Table 6.2 Corrosion allowance of risers as function of
u~ented ~y reference to previous successful application in si- operating temperature
~ar envtr?ments or laboratory testing. The laboratory test-
Ternperature.Pfl Corrosion allowance. mm
109 should include tests for resistance against stress corrosion
cracking. pitting. crevice corrosion and erosion corrosion. < 20 2
20 - 40 4
6.4.5 lllterna} corrosion IIlltnitorln'g
40 - 60 6
60 - 80 8
6.4.5.1 Internal corrosion monitoring is normally to in- 80 - 100 10
elude di1Ten:nt procedures such as thickness measurements
fluid analysU. e1ectrochemicaJ probes. electrical resistance 6.5.1 .3 Acceptable means of corrosion protection in the
probes and different types of weight loss coupons. The pro- splash zone are application of a corrosion resistant metallic
gramme should be based on the following: shearing or vulcanised rubber.
JJ
6.5.1.4 If metallic sheaung is used. the aHoy should have caused by the contact between the bottom and the pipeline
adequate corrosion resistance and sufficient thickness and. during the towing operation. This is normally to be proved
strength to withstand the loads during installation and opera- through tests. Such tests should be carried OUI with relevant
tion. The welding is to be carried out to a qualilied pro- diameters. submerged weight. concrete quality. jointing
cedure. All welds are to be examined 100 per cent by suitable methods and along a similar route as the actual towing.
NDT-methods. A sacrilicial anode is to be located below the
cathodic protection system should be specially considered. 6.6.3.5 Admixtures. Admixtures are to meet requirements
of a recongnized standard and are normally to be verified by
.J 6.5.3 Protection of risers in in ternal transition zones trial mixes.
6.5.3.1 Protection of risers in internal transition zones (airi
seawater) for instance in shafts of concrete structures may be 6.6.4 Properties of concrete
suitable coating and corrosion allowance. Acceptablecorro-
sion allowance may be as given in Table 6.2. 6.6.4.1 General. Concrete for weight coating is to have suf·
ficient strength and durability.
Due consideration should be given to the possibilities of in-
spection and' repair for transition zones. 6.6.4.2 Strength. The concrete is to have a minimum char-
acteristic strength of 30 Nt mm- found from 150 x 300 mm
6.5.4 Pipeline shore-approach. cylindrical specirnents tested in accordance with A5n1 C39.
6.5.4.1 The pipeline shore approach are to be specially When test specimens of different shape or dimensions are us-
considered in the design of the corrosion protection system. ed. an appropriate correction factor is to be applied to convert
In the tidal area the pipeline may be treated as risers corrosi- the compressive strength determined to the standard cylinder
on-wise. strength.
6.6.5.2 Types: Reinforcement may be in the form of steel plan for testing. inspection. reporting of results etc. at coal in!!
wire fabric or welded cages fabricated of plain or deformed .yard is subject 10 acceptance.
bars. The type and amount of reinforcement is to be selected
in due account of the anticipated pipeline loading and service 6.6.7.2 Concrete constituems. Tesunz of the individual mil'
conditions and so as to control the crack pattern of the con- terials is to be carried out at regular i~tcrvals during concrete
crete coating. production. The frequency of testing is to be determined tak-
ing the quality and uniformity oD material supply into ac-
6.6.5.3 Splices: Reinforcement type and application method count. 't
are to insure continuity of the hoop reinforcement.
6.6.7.:1 . Concrete. Prior to start of concreting the mix pro-
6.6.5.4 Placing: Reinforcing steel is to be accurately placed portions. concrete strength and weight are to be documented
and adequately supported. by tests.
Reinforcing steel is not to make electrical contact with the pi- During production concrete is to be tested regularly for thick-
pe or anodes. ness. strength and density. The frequency is to be minimum
one sample per 15 pipes coated and minimum one per shift,
6.6.6 Application and curing of concrete coating
In addition to molded test specimens the strength IesIS are 10
6.6'.6.1 Application. Concrete is to be applied to pipe joint
be supplemented by control of the in-place strength measured
using suitable equipment and procedures that will result in on drilled-out cores. The minimum diameter of the core is to
adequately consolidate concrete coating of uniform thickness. be at least 3 times the nominal maximum aggregate size. and
density and strength. The concrete is to be placed as soon as the length to diameter ratio is to be not less than 1.0. Sampl-
possible after mixing and in any case well before the initial ing. storing and testing are to be in accordance with
set. ASTM-C42 or equivalent. The core strength is to be convert-
ed to the strength of standard cylinders 150 x 300 rnrn in ac-
6.6.6.2 Curing. The selected method of curing and its dura- cordance with AST~f-C42. The strength requirement is con-
tion is to be such as to ensure satisfactory strength and dura- sidered satisfied provided the mean converted strength of
.bilfry of concrete. and to prevent undue cracking of concrete
three cores is at least 85'\, of the specified minimum char-
coating. acteristic strength and no single core.is below 75 %.
'1l'
Documentation of the adequacy' of the proposed cunng
method may be required. particularly ~or adverse climatic 6.6.7.4 Electrical insulation measurements by approved
conditions. procedure to prove no contact between weight coating rein-
forcement and pipeline steel are to be carried out.
6.6.7.Testing and inspection. /: ..:::..
6.6.7.1 General. Methods for testing of materi s are to be
in accordance with a recognized standard. The organization
I
'Ii j
_-----_-e.~_
---_/
35
SECTION 7
FABRICATION OF PIPES AND PIPING CO~IPONENTS
1 ypc and numbcr of tests to be madc for each pipe arc given 7.2.4.3 Failure of a lest specimen due to defective prepara-
in Table 7.1. tion may be disregarded and is to be replaced bv a new res:
specimen.
Dimensions of test specimens and testing procedure arc given
in Appendix C. 7.2.5 Hydrostatic testing
7.2.4.2 The qualification of the fabrication procedure is to 7.2.5.1 Every pipe is to be hydrostatically tested and with-
stand without any sign of leakage or sweats a test pressure (p!
be based on the following requirements:
determined by the following formula for at least I0 seconds.
Hydrostatic testing to the specified test pressure (see
7.2.5).
Dimensional tolerances and workmanship to the specified p::: 0.9 '~r.K ~)t (~lPal
limits (see 7.2.6>-
Soundness of base material and welds within the specif- !1F ::: specified minimum yield strength (MPa).
ied acceptance limits (see 7.2.6 and 7.2.7). t = nominal wall thickness Imrnl,
Check analyses within the specified composition limits D = nominal outside diameter trnm).
(see 5.2.4). K = factor determined by pipe diameter.
Tensile properties of base material at least equal to the
specified minimum values (sec 5.2.6).
Notch toughness of base material at least equal to the Outside diameter K
minimum specified values for resistance against brittle (norninall
fracture. and propagating ductile fractures when so re-
quired (see 5.2.7 and 5.2.8). 00 <200 0.75
Transverse weld tensile strength at least equalto the spe- 200 < 00<:500 0.85.
cified minimum tensile strength. 00> 500 0.90
Bending ductility to specified deformation without ap-
pearance of any defect greater than 3 rnrn. however. For hydrostatic tester's equipped with end sealing devices. the
max. 6 mm at the specimen edges. applied sealing force for endsealing resulting in an additional
Brittle fracture resistance of weld metal and heat affected longitudinal stress has to be considered. Supporting calculai-
zone at least equal to the required average and minimum tons to achieve the required stress intensity for computing of
single values (see 5.2.7>- tests pressure is to be submitted by the pipe manufacture.
Macrosections with a sound weld merging smoothly into
the pipe. Acceptance criteria as per Table 10.1. 7.2.5.2 Pressure test records showing test pressure and du-
Maximum hardness equal to or below the specified limit ration are to be available for each pipe.
(see 5.2.10 and 5.2.12).
7.2.5.3 Pipes which have failed on pressure testing. are to
be rejected.
Table 7.1
Qualification of pipe fabrication procedure
Type and number of tests for each pipe
Each heat Each 50 pipe. Each 50 pipe. mini- Each pipe Each pipe Each pipe
minimum mum once each heat (Ace. to 7.2.5) (Ace. to 7.2.6) (Ace. to 7.2.7)
1 once a heat lAce. to Table 7 J)
Noles:
I. Check analysis is not required if this has already been performed during an intermediate stage.
J 2. If [here are more than SO pipes manufactured from each 50 tons. mechanical tesung IS only required for each SO tons.
l Table 7.3
Number and type of mechanical tests on pipe production tests
,
Pipe material tests Weld tests
Pipe size Tensile tesr!' CharpyZIJ) Tensile" test Guided!' Charpy'" Macro-
outer dia- V-notch transverse to bend test V-notch section/
meter (mw Longi- Trans- toughness weld toughness hardness
tudinal verse
Seamless
00<300 I I sample
00> 300 I I sample
,J Welded
00<300 I I sample I 2 2 samples I
00> 300 I I sample I 2 2 samples I
:-';oles:
I. Yield strength. ultimate tensile strength and e!ongauon to be determined.
2. Brittle fracture resistance to be determined by Charpy \'-nOtch testing at the specified testing temperature (see 5.~71.
J. When pipe material is required.to be resistant against propagating dUCIIle fractures, production tests are also to include the specified type and number of
tests.
4. Ultimate t("nsile strength of the weld to be determined.
5. Bend test 10 be either I face T I root bend. or 2 side bend specimens for thickness less and greater than 11.5 mm respectively.
6. Charpy \. -notch of weld metal and heat a/Tected lone. :-':otching of HAZ to be periormed at the position giving lowest average energy absorption during
qualification testing.
j
Table 7.4
Mechanical testing of weld repair procedures
Non-destructive tests Tensile test transverse Guided bend test-' Charpy v'-ncrch Macro-section/ hard-
to weld!' toughness" ness
J
Ace. to 7.2.7.8 2 4 ~ I
lIiotes:
.1 \. Tensile test to record ultimate tensile strength of the joint
2. Either two root bends pius two face bends. or four side bends for thickness less and greater than I ~5 mm respectively.
J.lmpa.:t testing to be carried out with the notch positioned in centre of weld. fusion line. 2 mm from f.l. and 5 mm from f.l. This testing may. be exempted
from surface repair procedure provided same welding consumable. size and heat input is applied.
7.2.6 Dimensions and workmanship 7.2.6.3 The inside diameter at the ends is to be measured
I over a length of 100 mm from the end and isto comply with
7.2.6.1 Tolerances on dimensions and workmanship for li-
J ne-pipes are given in 7.2.6.2 through 7.2.6.12. When pipes the following limits:
are cut back. the pipe ends are to be rechecked. Tighter toler-
ance limits may be required if installation welding is to be Inside diameter tnorninall Tolerances
performed with welding equipment demanding narrow line- ID <;;300 mm + 1.6 mm
up tolerances. -0.4 mm
ID> .100 mm .,. 2.4 mm
7.2.6.2 The outside diameter of the pipe body is to comply - 0.8 mm
with the following limits:
Outside diameter (nominal) Tolerances 7.2.6.4 The out-of-roundness is to be limned and measured
00<500 mm ±(}.75 percent
J 00> 500 mm ±l per cent
JII
inside pipe over a length 100 mm from each end. IS to comp- NDT'record~ of each pipe are to be identified and traceable
ly with the following limits: (sec 8.6.1.3).
t<12.5 rom Max. 1.5 mm Circumferential welds are to be radiographed full length. Ul-
t> 12.5 mm 12.5 per cent. trasonic testing may also be required in special cases.
max. 3 mm
Weld repairs are to be radiographed full length.
7.2.6.8 The straightness of the pice measured as the gap be-
tween the straight line between the ends and the lowest point Non-destructive testing is to be in accordance with Section
of the pipe surface is to be maximum 2.0 mm per meter 10. Weld seams are to meet the acceptance limits of Table
length. 10.1.
7.2.6.9 The pipe is to contain no dents deeper than 6 rnm, 7.2.8 Production testing
being measured as the gap between the prolongation of the
original contour of the pipe and the lowest point of the dent. 7.2.8.1 Production testing is to be carried out to verify that
The length of a dent in any direction is not to exceed half the the pipes are fabricated to the composition. mechanical pro-
pipe diameter. perties. soundness and dimensions specified. Production tests
are to be performed as directed in Tables 7.2 and 7.3.
.Any cold formed gouges and notches in dented areas are to
Testing is to be witnessed by Veritas or an inspection agency
be removed by grinding (see also 7.2.9.3).
recognized by Veritas.
7.2.6. 10 The reinforcement of the weld seam is to be kept 7.2.8.2 If any of the selected test specimens do not fulfil the
within the following limits:
requirements. the corresponding pipe is to be rejected. In or-
der that the remaining pipes from the same batch of maxi-
Wall thickness Reinforcement of weld mum 50 pipes (or 50 tons. see note in Table 7.2) may be ac-
Inominall Inside pipe Outside pipe cepted. two similar tests are to be repeated on two different
Max. Min. Max. Min. pipes. and both tests are to be satisfactory. Should one of the-
t<12.5 mm 2 rom 0 3 mm 0 se tests fail. individual testing of the remaining pipes of the
t> 12.5 mm 3 rom 0 4 mm 0 batch is to be carried out.
The weld seam inside the pipe is to be ground flush over a 7.2.8.3 Failure of a test specimen due to defective prepara-
length of 100 rom from each end. tion may be disregarded and replaced by a new test speci-
men.
7.2.6. I I The weld is to have an even surface finish and 7.2.8.4 If the failure rate exceeds 5 per cent. the quality
merge smoothly into the base materia\. Minor undercutting control program is to be increased to an appropriate level and
maybe tolerable without repairs provided the depth and maintained until the failure cause is identified and eliminated.
length comply with Table 10. I. Retesting of supplied material and requalification of the fabri-
cation procedure may also be required.
7.2.6.1 2 The pipe surface is to be free from any defects
which may make the pipe unsuitable for intended service. 7.2.8.5 When pipes have failed by mechanical testing. and
Cracks. arc burns. notches and gouges are not acceptable. acceptable properties are intended restored by a controlled
Overlaps. slivers. impressed mill scale etc. which do not heat treatment. individual retesting is to be performed.
comply with a workmanlike finish are to be removed. Lami-
nations and inclusions extending to the surface or the bevel 1.2.9 Repairs
face and having a transverse dimension above 6 mm are to
be removed by grinding (see also 5.3 and 7.2.9.3). 7.2.9.1 Pipes containing defects may be repaired. or the de-
fective sections CUl off. Weld deposits having unacceptable
mechanical properties are to be completely removed before
rewelding.
1.2.1 Visual examination and Don-destructive testing
7.2.7.1 Each pipe is to be visually examined and non-des- 7.2.9,2 Surface defects in pipe material inside the pipe. on
tructive tested after pressure testing. If a pipe is cut back. the the outside of the pipe and less than 100 mm from the pipe
new pipe end is also to be inspected. end are to be repaired by grmding only.
,~
39
In other areas. surface defects may be weld repaired once. 7.3.1.4 When cold forming of pipes to bends or other com-
provided the depth of the defect is maximum 1/3 of the wall ponents introduces a permanent deformation more than 3 per
thickness. The length of that part of a defect which has depth cent. the mechanical properties of C·M nand C-Mn fine grain
more than 1/& of wall thickness is to be no longer than 1/4 treated steel are to be retested in the affected region. When
of the outside pipe diameter. such materials are cold deformed more than 5 %. stress re-
lieving is to be performed. When the deformation exceeds
7.2.9.3 Where defects are eliminated by grinding. the re- 10%. hot forming is normally to be performed followed by a
"j maining wall thickness is to be within the minimum specified controlled heat treatment. restoring a uniform microstructure
limit. Grinding is to be performed in a workmanlike manner. and mechanical properties (e.g, normalizing. quenching and
tempering).
·7 .2.9.4 Alocal weld repair is to be at least 100 mm long.
Weld repairs in pipe material are to be orientated circum- low alloy steels are normally to be suitably heat treated after
ferential if so is possible. Weld seams may be repaired full any cold and hot forming operation.
length. however. not more than twice in the same area. Weld
repairs are to be ground to merge smoothly into the original 7.3.2 Fabrication procedure specification
l pipe contour.
The thickness limit for post weld heal treatment of low alloy' If the steel has been quenched and tempered, the post weld
ed steels is to be considered in each case. heat treatment temperature is. however. nOI to be higher than
JO°C below the tempering temperature.
7.4.1.2 When post weld heat treatment is used to ensure
adequate resistance of welded joints against sulphide stress 7.4.) .4 Heating. soaking and cooling is to be performed in a
corrosion. this is normally to be performed for all thtcknes- controlled manner. The soaking time is to be 2 min/ mrn.
ses. however. minimum I hour. Where local heat treatment is
performed. the specified temperature' is to be maintained in' a
7.4.1 .J Post weld heat treatment is to be carried out at band extending at least J times the wall thickness on each
575-600°C for C-Mn and C-Mn fine grain treated steels. side of the weld. The temperature at the edge of the insula-
while low alloyed steels are to be post weld heat treated at tion bend is to be maximum half the soaking temperature.
600-625°C unless otherwise recommended by the steel ma- When the temperature at all pans has fallen to 300°C. the
ker. joint may be cooled freely.
"
I
I
J
41
SECTION 8
INSTALLATION
.
8.1.1 .3 Field coating procedure is to be specified as describ-
ed in 6.2.4.
8.1.1 .4 NOT
Section I .
• ~
e~o"" ""':'-i\-w...S,,-,-t... 'c..Sr\ .. *
rocedures are to be specified as described in
8.3.1 Qualification
8.3.1.1 Construction has to be carried out by means of
qualified personnel. procedures and equipment. The quali-
fications are to be proved prior to start of construction.
8.1.1.5 A detailed quality control system has to be specified 8.3.1.2 Welders and welding operators are to be qualified
for all installation activities. see 1.4.4.2. in accordance with 8.5.5.
8.1.1 .6 The installation specification is to give detailed in- 8.3.1 .3 Welding procedures are to be qualified in accord-
formation on parameters which have to be controlled in or- ance with 8.5.3 and 8.5.8.
der to obtain the correct configuration of and stress levels in
1 the affected portion of the pipeline. The range within which
the parameters are allowed to vary is to be clearly stated. see
4.3.
8.3.1.4 NOT procedures and operators are to be qualified in
accordance with Section 10.
.
+:~
brief description of the tension devices with information handled in a safe manner to prevent damage. and are to be
'.'1I~---'l.0l1..W:!.llin8 for~_e. holding force and~ueese>ressure
r
adequately supported and protected during storage and trans-
brief description of support and gui es on layvessel and portation.
"j stinger. including information on possible horizontal and
vertical adjustment 8.3.2'-2 Pipes. prefabricated sections and accessories are to
'°'1
brief decription of stinger including weight and buoyancy be inspected before installation. Damaged items are to be re-
distribution and procedures for obtaining correct con- paired to the satisfaction of the Surveyor or clearly marked
J./1.'1. ' figuration and deplaced. see 6.3.4 and 8.5.8.
brief description of other systems or equipment essential
for the installation operation. 8.3.2.3 Storing of pipes has to be carried out in such a way
j that the pipe is not being permanently deformed by its own
8.1.1.9 For a riser installation the specification should in- weight or the weight of above layers of pipes. Special care
elude information such as: should be taken for storing heavy coated anode joints.
description and general layout drawings of the riser
showing location of supports. bends. flanges. etc. 8.3.3 Installation operations
detail drawings of riser supports, bends. flanges. spoolpie-
ces. etc. 8.3.].1 The installation of the pipeline system is to be car-
description and drawings of corrosion protection system. ried out in accordance with approved procedures and in such
description and specification of equipment essential for a way that the pipe and coating will not be exposed to un-
the installation acceptable strainsl stresses or be damaged.
instrumentation systems used for measuring or controll-
ing essential parameters during the installation operation 8.3.].2 Mounting and application or riser supports are to be
procedure specification covering ail installation opera- carried out so as to obtain the support conditions upon which
tions. the design calculations have been based.
Non-destructive testing is.to be performed in accordance with ration. dilution and solidification panern. i.e. groove type
-.., Section 10 and the soundness of the test welds is to meet the (V. U. Y. X> angles. root gap and root face are to be spe-
I acceptance limits given in this section. cially considered.
I
~8.5.1.4 The type a ber of mechanical tests for each Welding process: Any change.
joint are given in able 8.1. arnpling of test specimens. di-
mensions and meth s ng are described in Appendix C. Welding consumables: Any change of type. classification.
diameter and brand as well as additions/ omissions of
The mechanical properties of the test welds are to meet the powders. hot and cold wires. .
following requirements:
Gas shielding: Any change of specified mixture. compo-
The ultimate tensile strength of the joint is to be at least sition and flow rate range.
equal to the specified ultimate tensile strength of the pipe
material. When different steel grades are joined. the ulti- Welding position: A change to a principal position not be-
mate tensile strength of the joint is to be at least equal to ing qualified according to Table 8.2.
l the minimum specified ultimate tensile strength of the lo-
wer grade. Welding direction: A change from vertical down to verti-
cal up or vice versa.
(- Theguided bend tests are to disclose no defects exceeding
1 rnm, Minor cracks. less than 6 mm. originating at the
specimen edges may be disregarded if not associated with
Currenu Any change beyond ± 15% and from AC to
DC.
i: obvious defects. 'o.t
e..J~ :-r-~
Polarity: Any change.
The fracture surfaces of the nick reak test specimens are
to show complete fusion enetration. Other defects Vollage: Any change beyond ± 10% except ± 5% for
~ exceeding the limits of able I . are not acceptable. gas metal arc welding.
,-'--- ---- «Fish eyes» may be d~!ar unless associated with
unacceptable amount o~ inclusions and porosity. Travel speed: Any change beyond ± 10%.
._-
r- >~~~
The average and single Charpy V-notch toughness at Time lapse between root pass and first filler pass: Any de-
each position is not to be less than specified according to lay significantly increasing the cold cracking risk.
5.2.7. When different steel grades are joined. a series of
impact tests is to be performed in the heat affected zone Preheating: Any decrease;
on each side of the weld. The weld metal is then to meet
·-T
the more -stringent energy requirement. Interpass temperature: Any significant change in the mi-
I nimum and maximum interpass temperature limits.
J The maximum hardness is not to exceed the limits given
in 5.2.10 and 5.2.12 as applicable. ...............'-"-~ . POSI weld hem treatment: Any change significantly affect-
. -f'" -""l!A.s.,. ing mechanical properties. the residual stress level. the
~uo
The macrosection is to show a sound weld = g corrosion resistance. i.e. the heating rate. cooling rate.
temperature level and period. heating band and insulation
J a e 10.
<he pipe without defec ts as pet the
urn ts of
width to be specially considered.
~
8.5.3.5 Failure of a test specimen due to defective prepara-
tion may be disregarded. and is to be replaced by a new test 8.5.5 Qualification of welders and welding operators
specimen. 8.5.5.1 Qualification of wei and welding operators art
generally to be as describ 1 1.2.3. or underwater welding
<', I
8.5.4 Essential parameters for weldIng procedures additional conditions apply. . .. 10. ~
J 8.5.4.1 A qualified welding procedure remains valid as
long as the essential parameters are kept within acceptable li- 8.5.5.2 Under special circumstances. qualification of weI·
mits and production tests are performed regularly. When one ders may be based on visual examination and mechanica
testing only. if so agreed by Veritas, In such cases bend test-
j or more variations outside the acceptable limits occur. the
welding procedure is to be considered invalid. and is to bere-
specified and qualified.
ing and nick-break testing are to be carried out in accordance
with Appendix C. Acceptance criteria for nick-breaks are
however. to be as follows:
8.5.4.2 The essential parameters and the acceptable limits of The fractured surface is to show complete penetration
L J [
variations are normally to be as described below. For special
welding system other essential parameters and acceptable
and fusion. There is to be maximum one - I - gas
pocket per cm-, being less than 1.5 rom in extension. On-
variation limits may have to be imposed. ~r~c1usions. with maximum depth 0.8 nun
]. .
Materials: A change from a lower strength grade to a
/ and with maximum length 3 mm spaced at least 12 rom .
I higher. and any change in type. composition and proces-
i may be accepted. «Fish eyes» may be disregarded unless
not associated with significant number of slag inclusions
I
I
sing significant for the weldability and the mechanical
and properties of the weld. The C-content. alloy content.
carbon equivalent and supply condition is to be specially
l and cluster porosity.
.... <:-<:>~
<;12.5
,300 2 -, .2 0 2 4 2
> 300 4 4 0 4 11 4 4 .2
,300 .2 0 0 4 .2 4 .2
> 12.5
> 300 4 0 0 8 4 4 .2
"'Oles:
I) Root and face bend tests ma)' be used instead of side bends.
2) Nick break teslS may be omitted for manual metal arc welding 10 be performed above water.
J I Impact lCSting is not required for t <S mm.
4) Each Charpy V·notch sample consists of J specimens.
S) Impact testing is to be carried out with the V'notch positioned in the weld metal. on the fusion line. 2 mm from the fusion line and S mm from the fusion
line.
6) When more welding processes or more welding consumabies are used. impact testing is normally to be carried out in the corresponding weld res:ions if the
resion tesIed cannot be considered representauve for the complete weld.
8.5.6.2 The bevelled pipe ends are to be free from con- pies are to be located in the weld metal. and in the heat affect-
tamination by moisture. oil. grease. rust etc. which might af- ed Zone at the position which showed the lowest average
fect the weld quality. energy absorption during the procedure qualification test. see
8.5.1. '>
.t~"'....
8.5.6.3 Internal or external line-up clamps are normally not
to ~oved before the first two passes are completed.
-...It.l~-Wnen~welds are necessary for alignment. these are only
8.5.8 Repair o~ •
to be made' e weld groove using a qualified welding pro- 8.5.8.1 Pipes and welds containing defects are to be repair-
ed as described in 8.5.8.2 through 8.5.8.9. ........,c..:.....,..'Lc-
--_oJ
cedure. efectiv tack welds are to be completely removed.
~ _+c.ii"oso
8.5.6.4 Welding is not to be discontinued before the joint 8.5.8.2 Defects outside the weld are to be repaired by~
~f"~
has sufficient strength to avoid plastic yielding and cracking ing only. If grinding reduces remaining wall thickness bero'W'
during pulling and handling. Prior to restarting after inter- the minimum specified thickness. the defective pipe section is
ruptions. preheating to the minimum specified preheating to be cut out. Grindung is to be performed in a workman-like
temperature is to be applied, manner. and with smooth transition into the pipe surface.
8.5.6.5 Supports. attachments. lifting devices etc. used for 8.5.8.3 Defects in the weld may be repaired by grinding or
welding. Repair welding specifications are to be prepared.
permanent positioning of risers and pipelines are normally to
be welded to a doubler ring. Doubler rings for temporary use and are to give the following information in addition to that
are to be clamped. relevant of 8.5.2.1.
Method for removal of defect.
S
~ Preparation of weld area.
8.5.6.6 Pe entdoubler rings are to be made as fully
. encircling leev nd of materials satisfying the requirements Non-destructive tests for conftrmation of defect removal.
?• _ for pressure parts. see 5.7. Longitudinal welds are to be made
with a backing strip. avoiding penetration into the main pipe.
Permissible minimum and maximum weld repair sizes.
The circumferential welds are to be continuous. and made in 8.5.8.4 The repair welding procedures are to be qualified.
a manner minimizing the risk of root cracking and lamellar The qualification tests are to be made in a realistic manner si-
~~\'tAft~ mulating repair situations likely to occur. e.g.
Through thickness repair: "')
Table 8.2 Qualified principal welding positions External repairs of undercuts with one stringer pass. .a:- (
Inside root repair with one pass only.
Test position Applicable welding positions Repeated weld repairs in same area.
IG IG
The repair tests welds are to be made in the overhead
2G IG.2G
through vertical position. using pipe with a chemical compo-
5G IG.5G
All sition in the upper range of the specification.
2G + 5G
or 6G All
8.5.8.5 The test weld covering through thickness repair is
to be visually inspected. non-destructive tested and mechani-
cal tested as required for the installation welding procedure.
8.5.7 Production test see 8.5.3. The single pass test welds are to be visually inspect-
8.5.7.1 Production tests may be required during installa- ed. magnetic particle examined and mechanical tested with
tion. The test is to be performed in a manner which. as far as two macro/ hardness tests provided there is used the same
possible. reproduces the actual welding. and is to cover weld- welding consumables and parameters as for the major re-
ing of a sufficiently large pipe sector in a relevant position. pairs.
When production testing is required. half the number of tests 8.5.8.6 Preheating is to be performed prior to repair weld-
specified in Table 8.1 are to be carried out. Impact test sam- ing. The minimum specified preheating! interpass tempera-
1111'!lImllllll
45
ture is to be maintained until the repair has been completed, Welded connection on the lay vessel and subsequent lo-
wering.
85.8.7 Long defects may require repair in several steps to Underwater welding.
avoid yielding and cracking. The maximum length of allowa-
ble repair step is to be calculated based on the maximum The choice of method is to be based on an evaluation of the
stresses in the joint during the repair operation. The repair conditions under which the tie-in is to be carried out and the
length is to be at least approximately 100 mm even if the de- service conditions under which the tie-in is to operate.
fect is of less extension.
8.7.1.2 The tie-in operation is to be carried out in accord,
8.5.8.8 Grinding is to be performed after arc air gouging to ance with an approved tie-in specification.
remove any carbon pick-up.
8.7.1 .3 Tie-in specification is to include:
J 8.5.8.9 A joint may be repair welded twice in the same
area. If the joint still contain defects. the complete joint is to
description and specification of components which will
be introduced as permanent parts of the pipeline.
be cut out unless special repair welding procedures simulat- calculation of stresses occurring during installation and
1
~2 Defects which exceed the acceptance limits in Table Other methods are subject to special approval.
_ .. ~~~ to be completel~ rem,?ved an.d repaired in accord-
. . .ance Wtth 8.5.8. Magnetic particle tesung IS normally to be 8.7.4.2 Sealing devices are to be of a proven design and ma-
used to ensure complete removal of defects prior to repair nufacture. Sealing@are to be pressure tested prior to in-
welding. stallation into the pipeline sections unless this has been carr-
ied out at an earlier stage.
8.6.3.3 Weld repairs are to be radiographed. This examina-
tion is to cover the repaired area and an additional length of 8.7.4.3 A detailed welding procedure specification is to be
50 mm at each end of the repair weld. established. and is in addition to that specified in 8.5.2.1 to
contain:
8.6.3.4 Magnetic panicle testing may replace radiography water depth.
when the defect is located at the outside of the pipe. and is re- pressure inside the chamber.
moved by grinding only. gas composition inside the chamber.
humidity level.
temperature fluctuations inside the chamber.
8.7 Tie-ins' g.7.4.4 Storage and handling routines of welding con-
I surnables on the suppon vessel and in the welding chamber
J 8.7.1 General as well as the sealing and the transfer procedures to the weld-
8.7.1.1 Tie-ins between different portions of a pipeline. or 109 chamber are to be specified.
between pipeline and riser. may be carried OUt by one of the
following methods. 8.74.5 The welding procedure IS to be qualified under re-
- Mechanical connectors. presentative conditions in a SUitable testing facility. The qua-
46
lification test is to consist of minimum one complete joint for Thickness of cover or depth of trench lif applicable) and
manual welding and minimum three joints for mechanized descnption of the stale of rest 'along the route
welding system. Verification that the condition of weight coaling or the
anchormg system which provides for on-bouom stability
The qualification program may be increased when the under- is in accordance with the approved specification
water welding will occur under conditions where previous Description of wreckage. ~or other ObJCCL<; which
experience is limited. or will be undertaken by a company may affect the cathodic protection system or otherwise
with limited experience in this field. impair the pipeline
Description and location of damages to the pipeline. its
8.7.4.6 The qualification test welds are to be inspected and coaling or cathodic protection system
tested as per 8.5 .3 and comply with the requirements specif-
ied for the pipeline section in question. 8.8.2.2 The final survey report of the installed riser is to
verify that the nser, including supports. clamps. anchors. pro-
,8.7.4.7 Preheating to a suitable temperature is to be applied tection devices te.g, fenders. casings. etc.J and corrosion pro-
~~.I;.. for<€oistu~removal and hydrogen diffusion. tection system. are Installed in accordance with approved
drawings and specifications.
8.7.4.8 The essential parameters for underwater welding
are those specified in 8.5.4.1 plus those given in 8.7.4.3. The 8.8.3 Survey of corrosion protection system
acceptable variation limits are normally those specified in
8.8.3.1 Inspection of the external coating of the pipeline
8.5.4 pius the following:
system is required. Special attention should be given to the ri-
ser in the splash zone.
Pressure inside chamber: any increase
Gas composition inside chamber: any change
8.8.3.2 Spot measurements of the polarization along the pi-
Humidity: any increase beyond
peline may be required in areas with damaged coating. Spe-
specified range may
cial attention is to be paid to areas far from sacrificiai anodes
be required
and areas with stress concentrations.
8.704.9 A confirmanon test weld may be required made on
8.8.3.3 In areas where measurements indicate that cathodic
location prior to starting the tie-in welding. The test weld is
protection has not been attained. some corrective action is to
to be made on pipe coupons in the habitat under actual con-
be arranged. e.g. mounting of additional sacrificial anodes.
ditions. The coupons are to cover welding from the 6 o'clock
increasing current output from rectifiers. or appiication of
to 9 o'clock region. Subject to acceptable visual inspection
protective coating.
and radiography in accordance with 8.6 the tie-in welding
may commence. Mechanical testing is to be performed as
8.8.3.4 The possibility of over-protection is to be investigat-
soon as possible. The number of mechanical tests is half that ed at locations where detrimental effects of over-protection
required for welding procedure qualification.
may be suspected.
When the same welding habitat. equipment and welding pro- 8.8.3.5 The possibility of stray currents are to be investigat-
cedure are used for consecutive tie-ins on the same pipeline ed by measurements and visual observations by qualified per-
under comparable conditions further confirmation test welds sonnel. Provisions according to 6.x.x.x and 6.x.x.x are to be
are not required. complied with where detrimental effects may be suspected.
8.7.4.10 The tie-in weld is to be non-destructive examined 8.8.4 Pressure test
full length. as per 8.6 and comply with tile applicable accept-
ance standard' in Section IO. 8.8.4.1 The pipeline system is to be pressure tested after in-
stallation. The testing is to be carried out in accordance with
8.7.4.11 Prior to qualification testing for underwater weld- an approved procedure. A pipleine system may be tested in
ing. the welder is to have passed a surface welding tests (see sections. e.g, between tOP of risers or between tOP of the riser
7.2.3) and have relevant training for welding under pressure. and shore. When a pipeline is to be buried or covered. the
pressure test is to be performed after such operation.
Qualification for underwater welding is to consist of at least
one test weld made in a-testing facility under representative 8.8.4.2 The test is normally to be carried out with liquic!(
test medium. ~
conditions in accordance with the qualified underwater weld-
ing procedure. The test weld is to be visual inspected .. radio-
graphed and mechanical tested. see 7.2.3 and Appendix C.. 8.8.4.3 The pressure test is to prove the strength and the
thightness of the tested section. The minimum test pressure is
to be 1.25 times the design pressure. Hoop stress in the pipe
during testing is normally not to exceed 90 per cent of the
minimum specified yield strength. Higher stresses will be
8.8 Final surveys and tests considered in each case.
8.8.1 General 8.8.4.4 During pressurizing. added test liquid versus pres-
8.8.1.1 A final survey of the installed pipeline system is to sure is to be recorded in order to evaluate the amount of resi-
be carried out in order to verify that the condition of the pi- dual air in the test section.
peline system satisfies the approved specification and the re-
quirements of these Rules. 8.8.4.5 After pressurizing sufficient time has to be allowed
for stabilization of the pressure in the pipe section.
8.8.1.2 If the pipeline is to be buried or covered by other
protection stabilization methods. surveys are normally requir- 8.8.4.6 The holding time for pipeline sections is normally to
ed both before and after burial <Covering) operations. be minimum 24 hours. after the pressure has stabilized. For
short lines and risers 8 hours holding time may be accepted.
8.8.2 Survey of Installed pipeline system For pipeseetion that can be 100 % visually inspected the hold-
ing period is normally to be at least 2 hours.
8.8.2.1 The final survey on the pipeline system is at least to
provide the following information: 8.8.4.7 Alternative pressure testing procedures may also be
- Detailed plot of the pipeline position accepted. For guidance see Appendix E.
~$t~..l~ rr: ~<.c 47
8.8.4.8 If the tested section ~r~the failure is to 8.8.6 Testing of alarm and shutdown systems
be corrected and the section retested.
8.8.6.1 It is the Owner's responsibility to protect the pipeli-
ne system against operational conditions for which the sys-
8.8.4.9 Pressure testing of tie-in welds between already test-
tem is not designed.
ed sections may in special cases be exempted provided the re-
gular radiographic examination is extended with ultrasonic
8.8.6.2 Instrumentation for the safe operation of the pipeli-
-1 examination of other suitable methods. Monitoring may be
required. The NDT procedures and operators are to be qualif-
ne system is to be tested according to generally recognized co-
J ied for this testing. see Section 10.
des and the manufacturer's recommendations prior to start of
operation.
'1' 8.8.5 Buckle detection
8.8.6.3 Emergency shutdown systems are to be tested ac-
j 8.8.5.1 Buckle detection is to be carried out by running a cording to generally recognized codes prior to start of opera-
gauge pig (caliper pig) through each pipeline section after in- tion.
stallation. When the pipeline is to be buried. the final buckle
detection is to be performed after trenching.
J'
,
J
48
SECTION 9
OPERATION AND MAINTENANCE
9.1 General 9.3 In-service inspection
9.1.1.2 The Owner is to retain files of the running inspec· 9.3.1.2 Veritas may have free access to
tion and the remedial measures taken and make these files
scrutinize in-service inspection reports
available upon request.
carry out survey in connection with in·service inspection
made by the Owner or his contractors
9.1.1 J The Owner is forthwith to notify Veritas if any of
carry out survey.
the events occur as given below. so that the need for surveys
can be determined: whenever found necessary in order to retain the Certificate of
Approval.
the pipeline system is damaged. or is suspected of having
been damaged. in a manner likely to impair its safety or
9.3.2 Start up inspection
strength
the pipeline system dernonstate signs of deterioration 9.3.2.1 The objective of the stan up inspection is to observe
likely to impair its safety or strength during and immediately after stan up any movements or be-
the pipeline system is subjected to any alteration. repair haviour of the pipeline system. This may include inspection
or replacement and measurement of the distance between the bend connect-
transportation of new fluids. ing the pipeline and the riser and the installation in order to
detect lateral or axial movement. If necessary these measure-
9.1.2 Retension of Certificate of Approval ments are to be continued until such movements have stabil-
ized.
9.1.2.1 The Certificate of Approval will be retained in the
operating phase provided the requirements in these Rules are
9.3.2.2 Mechanical couplings including flanges may require
satisfied. See also 1.5.2.
visual inspection during stan up. Leak detection is to be car-
ried out when found necessary.
pipeline and locate areas that may be subjected to close visual. 9.4.1 General
inspection and testing. This is to include detection and mapp-
9.4.1.1 All repairs are to be carried out by qualified per-
ing of:
sonnel in accordance with approved specifications and pro-
mechanical damages to the pipeline cedures. and up to the standard defined for the pipeline.
l coating damages
anode consumption and condition
condition of the seabed with respect to scouring or build-
9.4.1.2 Repairs of parts that are subject to certification' are
to be surveyed and approved by Veritas.
up of seabed substance
signs of lateral and axial movement 9.4.1.3 The Owner is to notify Veritas in advance of any
leaks such action and to submit the necessary plans and specifica-
tions for approval. The exact documentation that is to be sub-
9.3.5.3 Control of the performance of the corrosion protec- mitted for approval or information purposes is to be decided
tion system is to be carried out. If found necessary. potential in each particular case.
~l measurements are to be conducted at the discretion of the
Surveyor and in accordance with 8.8.3. 9.4.1.4 Pipeline systems with defects may be operated tem-
porarily at a reduced pressure until the defect has been re-
71 9~3.5.4 Inaccessible parts of the pipeline system are to be re- moved.
motely examined by suitable equipment.
J 9.4.2 Grooves. gouges and notches
9.3.5.5 Thickness measurements may be required where
9.4.2.1 Sharp defects like grooves. gouges and notches are
there is reason to believe that the pipe wall thickness may be
to be removed by grinding or by other approved repair meth-
reduced due to external! internal corrosion or erosion (e.g.
J od. The remaining wall thickness is to meet the minimum re-
the effect of sand content in the flow).
quired for the particular location. see 4.2.2. Deeper defects
are to be removed by cutting out the damaged portion of the
Other means for internal corrosion monitoring are also to be
pipe as a cylinder.
used. see 6.4.5.
9.4.3 Dents
9.4.3.1 A dent is defined as a depression which produces a
9.3.6 Extent of periodical inspection - riser gross disturbance in the curvature of the pipe wall.
9.3.6.1 Normally the below specified inspection is to be 9.4.3.2 A dent affecting the longitudinal or circumferential
carried out in addition to the inspection specified for the pi- weld is to be removed by cutting out the damaged portion of
peline. see 9.3.5. the pipe as a cylinder. or by installing a full encirclement
J 9.3.6.2 Close visual inspection of supports, bolts. flanges
welded split sleeve. see 9.4.5.9.4.6 and 9.4.7.
and couplings. 9.4.3.3 The acceptability of dents are to be evaluated in
each case. Factors to be taken into consideration are:
9.3.6.3 Thickness measurements at pre-selected reference size and shape of dent
J points are to be carried out on a regular basis. see 6.4.5.3. properties oi pipe material
The measurements are to be carried out according to an ap- oil or gas
proved procedure which should include information on: pressure
type of equipment possible consequences of pipe rupture
type of probe pigging possibilities
evaluation procedure
location of reference points 9.4.4 Leaks
9.4.4.1 Prior to permanent repair of any leak. the rnacha-
9.3.6.4 Potential readings are to be performed at a fair dist- nisms causing the leak are to be established.
ance from the adjacent anodes.
! 9.4.4.2 Permanent repair of a leak in pipe body or weld
9.3.6.5 Distance between the bend connection the pipeline
I and the rises and the structure is to be measured and record-
ed.
may be carried Out by cutting OUt the damaged portion of the
pipe as a cylinder or by installing a full encirclement welded
split sleeve. see 9.4.5. 9.4.6 and 9.4.7.
1 For low pressure oil lines repair by properly designed leak
.J clamps may be accepted.
9.3.7 Special inspection
9.3.7.1 If any events occur which impair the safety. 9.4.4.3 leaking flanges and couplings are to be sealed if
strength or stability of the pipeline system. the Owner is found satisfactory by torquing the bolts or by replacing at
forthwith to notify Veritas and a special inspection is to be least the sealing devices such as gaskets and seals.
carried 'out.
9.4.5 Repair by welding
Such events are:
the pipeline system is damaged or suspected of having be- 904.5.1 Repair welding procedures and welders are to be
en damaged qualified as described in 8.5.3 and 8.5.5.
the pipeline system demonstrates signs of deterioration
The pipeline system is subjected to alteration. repair or re- 9.4.5.2 Repair welding above water is to be carried out as
placement. described in 8.5.
9.J.7.2 Special inspections is normally to be carried out in 9.4.5.3 Underwater repair welding is to be carried out in a
the presence of a Surveyor. The Surveyor is 1O be provided dry habitat. see 8.7.4.
with the facilities needed for first hand evaluation of the
conditions necessitating the inspection. 9.4.5.4 Repair welding may in special cases be carried out
50
on pipelines under pressure. Acceptable repair conditions are 9.4.6 Temporary repairs
to depend on:
actual wall thickness 9.4.6.1 If not possible to take the pipeline OUI of operation.
pressure repairs may be made by installing properly designed leak
flow rate clamp over the defect. The strength of the sleeve is to be as
oil or gas required in 4.2.2.
welding procedure
safety procedures
j
11111 illlll 111I Illi III!IIIII_III::!I:
5\
SECTION 10
NON-DESTRUCTIVE TESTING
10.1 General Image quality indicator sensitivities in per cent of the wall
thickness based on source and film side indicators res-
10.1.1 Selection or method pectively.
10.1.1:1 Methods for non-destructive testing are to be cho- Density. (The density of the radiographs measured on the
sound weld metal image>. .
sen with due regards to the conditions influencing the sensivi-
ty of the methods. Film coverage.
Appropriate methods will be evaluated in each case. 10.2.2 Radiographic procedure qualification
10.2.2.1 Two radiographic exposures are to be made of a
welded joint using pipe of the same diameter and wall thick-
10.2 Radiographic examination of welds ness and of material equal to or similar to that which is to be
l 10.2.1 Radiographic procedure specification
used in the pipeline system.
I
I
I
I
iI I I I I T
I
I
I
1 i i ,
I
I
I ! I
........ I T' ! I
,
I i_0 i I
i
> ! I I
J I
I
-
I
I 1 :
5 10 15 20 25 35 40 45 50
Material thickness, mm
Note:
For production radiography; sensitivity
readings based on film side penetrarneters
are to be judged as per results from the
procedure qualification.
If the multiple exposure technique is used. at least two penet- The test pieces are to be available as reference during the in-
rameters are to be recorded on each film and located near spection work.
each end of the fllm.
10.3.3.2 The procedure qualification is to be performed on
For testing of the ends of longitudinal or spiral welded seams. a sample pipe containing artificial defects made as drilled ho-
one penetrameter may be used. les or machined notches. The defects are to be placed both on
the outside and inside of the sample. orientated parallel.
10.2.4.2 The maximum acceptable film lengths are limited transverse and through the weld and in base material. The
by a 6 per cent increase of the wall thickness in the beam di- defect dimensions and locations are subject to agreement.
rection.
10.2.4.3 All films are to be clearly marked to identify the 10.3.4 Calibration of equipment
proper weld and to locate any discontinuities quickly and ac-
curately. Veritas may specify the identification system. 10.3.4.1 Calibration of the Ultrasonic equipment is to be
carried out whenever it has been out of function for any rea-
Processing and storage is to be in a way that enables the films son including on/off. and whenever there is any doubt con-
to maintain their quality throughout the design life of the in· cerning proper functioning of the equipment.
stallation.
10.3.4.2 Calibration is to be performed with the sample pi-
pe described in 10.3.3.2. The equipment is to be set to pro-
10.2.S Evaluation of welds and standards of acceptability duce maximum signal amplitude from the artificial defects.
The trigger level is then to be reduced to an agreed level. Cali-
10.2.5.1 The radiographs are to be interpreted by qualified bration is to be performed at the production speed.
personnel. The report is to show if the weld quality meets the
requirements of Table 10.1. which defects have been judged
unacceptable. and the number of repairs made. 10.3.5 Qualifications of operators
10.2.5.2 Since radiography gives two dimensional results 10.3.5.1 The operators are upon request to be able to de-
only. welds which meet the acceptance criteria may be reject- monstrate the following capabilities:
ed if the density indicates the depth of the defect to be detri- Calibrating the equipment
mental to the integrity of the weld. Performing an operational test under production condi-
tions
10.2.5.3 The Surveyor is to have the right of being final Evaluating size and location of reflectors.
judge in assessment of weld quality.
10.3.6 Production ultrasonic examination
10.3.6.1 The contact surface is to be clean and smooth. i.e.
10.3 Ultrasonic: examination of welds with stationary free from dirt. scale. rust. welding spatter. etc. which may
equipment influence the results of the testing.
10.3.1 Eqilipment
10.3.1.1 The equipment is to 10.3.7 Evaluation of welds and standards of acceptability
be applicable for the pulse echo technique or the double- 10.3.7.1 For stationary equipment the purpose of jhe test-
probe technique ing is normally to detect defects which are to be further
use a frequency of 4 MHz unless otherwise agreed upon evaluated by radiography.
have a sufficient number of fixed, guided probes ensuring
examination of the complete seam for longitudinal and Indications giving signals below the agreed trigger level are
transverse defects and for detection of possible lamination acceptable.
interfering the testing
have a trigger system alerting indications of defects and a Indications grving signals above the trigger level are to be
system -alarrning malfunctioning of the equipment considered injurions unless further investigations by radio-
have a system automatically locating the defect area graphy show that the weld meets the acceptance criteria in
have a continuous monitoring of weld seam centering Table 10.1.
10.3.2 Ultrasonic procedure specification 10.3.7.2 The Surveyor is to have the right of being final
10.3.2.1 A procedure specification is to be established and judge in assessment of weld quality.
is at least to include the following information:
Material quality and dimensions
Welding process and groove geometry 10.4 Ultrasonic examination of welds with portable
Type of instrument equipment
Type(s) of transducers
Frequencies 10.4.1 Equipment
Calibration details 10.4.1.1 The equipment is to
53
be applicable for the pulse echo technique and for the The test pieces are to be available as reference during the in-
double-probe technique spection work.
cover as a minimum the frequency range from 2- 6
MHz 10.4.3.2 Reference blocks as described under 10.4.4 will
have a calibrated gain regulator with max. 2 dB per step normally be considered satisfactory as test pieces. Whenever
have a Oat screen accessible from the front for direct groove geometry. welding methods or other factors may cau-
plotting of reference curves se special problems in flaw detection. Veritas may require
allow echoes with amplitudes of 5 per cent of full screen special test pieces to be prepared.
height to be clearly detectable under test conditions
include straight beam transducers and angle beam trans-
ducers of 45.°. 70° and 80°. 10.4.4 Calibration of equipment
10.4.4.1 Calibration of the ultrasonic equipment is to be
carried out whenever it has been out of function for any rea-
r -PROBE CONTACT SURFACE son including on/off. and whenever there is any doubt con-
cerning proper functioning of the equipment.
l .l/r- DIAMETER D T
10.4.4.2 The IIW /ISO calibration block is to be used for
calibration of range and for angle determination. The \'2 cali-
bration block according to DIN 54122 may be used for cali-
I-p bration of range only.
.J T
L 10.4.4.3 For evaluation of flaw indications a reference
curvce is to be established. The curve is to be plotted on the
J instrument screen.
.J 10.4.4.4 A reference block is to be used for gain calibration
II B and construction of the reference curves. The reference block
/1 1 lll-lJO rTrn is normallv to be manufactured from the actual material and
.1 /·1 have dime;'sions according to Fig. 10.2.
111
·1 10.4.4.5 The sound path from the probe in postuon A to
'-'I the reflector. Fig. 10.3 is not to be less than 60 per cent of the
j nearfield length of the probe.
L = Length of reference block given by probe angle and
10.4.4.6 The echo height from position A is to be maxim-
material range to be covered.
T = Thickness of reference block. ized and the gain control regulated so that the echo height is
B = Width of reference block. minimum 40 rnm. 75 per cent of full screen height. This gain setting is called the
D = Diameter of drilled hole. primary gain and is to be recorded. Without altering this gain
P = Position of drilled hole. setting the maximized echo heights from point Band C are to
be plotted on the screen. The reference curve is now to be
drawn as a smooth line through the three points. Two curv-
.j Actual wall Thickness of Position of Diameter of es. 20 and 50 per cent of the reference curve are also to be
thickness ref. block drilled hole drilled hole constructed.
tin mm Tin mm Pin mm Din mm
10.4.4.7 The primary gain is to be corrected for difference
t<25 20 or t .. T/2 2.4 in surface character and attenuation between the reference
25 <t<50 38 or t T/4 3.2 block and the actual pipe by means of the double probe
SO < t<lOO 75 or t T/4 4.8 technique. Two Identical angle probes. facing each other one
skip distance apart as shown in Fig. 10.4. are to be used. The
primary gain is to be corrected accordingly and then becomes
Fig. 10.2 Reference block for construction of reference the corrected primary gain.
curve for portable equipment.
IIIIIII'P'
54
AQ CQ
REFERENCE ClJIV[ REFERENCE BLOCK,
100"10
\
\
75"10+-_ _-\
RECEIVEO ECHO
--.---REFERENCE CURVE
\
20·i.
-- .......
-...- FOR THICKNESSES
-10mm
I1ATERIAL TO BE TESTED,
. a ABC
REtEMD EOCI
100·/.
\
75·1. \
- - REFERENCE CURVE
FOR THICKNC:c;SC:S
BETWE<=N 10 ANQ 25mm
b A
,.2"-=-.=-_:""1:)
/ /
/
/ /
'"
,. ,."-
",, , T
~~"- ----
~~=f-~,
...
-+--+--<1 / ,- ---1-"
C
'- ---
,- ---j-i-'
,
'-- --- - .....
i_}
100"10
'- ---CJ I
75"1..-----,.
Fig. ] 0.5 Probe movement (or testing butt welds, portable
equipment.
FOR THICKNESSES - 25mm
li!111I111lI111
1
I 55
J 10.5.2 Magnetic particle procedure qualification
~'~I 10.5.2.1 No special procedure qualification test is required.
--/
10.5.3 Qualifications of operators
10.5.3.1 Operators performing magnetic particle examina-
I tion are to be capable of performing and operational test. 'us-
ing the test method and technique which is to be applied in
a production.
10.4.7 Evaluation of welds and standards of acceptability 10.504.5 Non-fluorescent wet or dry particles are to provide
adequate contrast with the background of the surface being
10.4.7.1 As ultrasonic examination is principle detects «re- examined.
flectors» in the material. all indications are to be considered
as the most dangerous type of defect until otherwise proven. 10.5.4.6 Examination with flourescent magnetic particles is
to be conducted in a darkened area using filtered ultraviolet
The report is to show if the weld quality meets the require- light with wave lengths within the range of 3200-3800 A.
ments. which defects have been judged unacceptable and the
number of repairs made. I 0.5 04.7 Magnetic particle examination is not to be per-
formed on parts with surface temeratures exceeding 300°C
10.4.7.2 In general all defect indications exceeding the re- (570°F) Between 60°C (140°F) and 300°C. only dry magnetic
ference curve are to be repaired and reexamined. particle examination is to be used.
"I
10.4.7.3 All defect indications with length ;oat exceeding 10.5 04.8 Care is to be taken to avoid local heating of the test
50 per cent of the reference curve are to be repaired and ree- surface. Prods tipped with lead. or «soft prods» are recom-
xamined. mended. Arc strikes and burn marks are to be ground out
and reinspected with a suitable method.
1004.7.4 All defects indications exceeding 20 per cent of the
reference curve are to be investigated to the extent that the 10.5.4.9 Demagnetization is required if the material due to
operator can evaluate the shape. identity and locaticn :in the magnetic particle testing has become permanently mag-
terms of the acceptance criteria in Table 10.1. netized and this may interfere with the servicability of the
part or installation.
..J"
10.4.7.5 If only one side of the weld is accessible for test-
ing. all defect indications exceeding 50 per cent of the refer-
, ence curve with length ;oa t and all defect indications exceed- 10.5.5 Evaluation of welds and standards of acceptability
I
ing 20 per cent of the reference curve with length ;oa 2t are to
J be repaired and reexamined. 10.5.5.1 The magnetic particle examination operators are to
report all surface defects detected. The report is to show if the
1004.7.6 The Surveyor is to have the right of being final weld quality meet the requirements of Table 10.1. and the
judge in assessment of weld quality. number of repairs made.
J 10.5.5.2 Surface which are shown to have defects exceed-
ing the limits given in Table 10.1 are to be repaired and re-
1 10.5 Magnetic particle examination of welds examined.
I 10.5.1 Magnetic particle procedure specification 10.5.5.3 The Surveyor is to have the right of being final
10.5.1.1 A procedure specification is to be established and judge in assessment of weld quality.
is at least to include the following information:
Material quality and dimensions
Welding process and groove geometry 10.6 Liquid penetrant examination of welds
Type of magnetization
Type of equipment 10.6.1 Liquid penetrant procedure specification
I
J
Surface preparation 10.6.1.1 A procedure specification is to be established and
Wet or dry method is at least to include the following information:
Make and type of magnetic particle and contrast paint Material quality and dimensions
I
I
\1 agnetic field strength
Dernagnetizauon
Welding process and groove geometry
Surface preparation
J
Description of examination technique Brand name and specific type (number of letter designa-
tion if available) of penetrant. remover emulsifier and I 0.6.3 Qualifications of operators
developer.
10.6.3.1 Operators performing liquid penetrant exarruna-
Details of the method of pre-examination cleaning and.
tion are to be capable of performing an operational test. using
drying. including cleaning materials used and time allow-
the test method or technique which is to be applied in pro-
ed for drying.
duction.
Details of the method of penetrant application; the length
of time that the penetrant remains on the surface. and the
10.6.4 Production liquid penetrant testing
temperature of the surface and penetrant during the ex-
amination if not within the 15°C- 35°C range 10.6.4.1 Liquid penetrant examination is only to be used on
Details of the method of removing excess penetrant from non ferromagnetic materials and materials with great vana-
the surface and of drying the surface before applying the tion in magnetic permeability.
developer.
Details of the method of applying the developer. and 10.6.5 Evaluation of welds and standards of acceptabllity
length of developing time before examination
10.6.5.1 The liquid penetrant examination operators are to
Method of postexarnination cleaning.
report all surface defects detected. The report is to show if the
surface meets the requirements of Table 10.1 and the number
10.6.2 Liquid penetrant procedure qualification
of repairs made.
10;6.2.1 When the temperature of the surface and the pe-
netrant is within 15°C-'- 35°C range. no special procedure 10.6.5.2 Surfaces which are shown to have defects exceed-
qualification test is required. The procedure is considered ing the limits given in in Table 10.1 are to be repaired and re-
qualified based on approval of the testing procedure specifi- examined.
cation.
10.6.5.3 The surveyor is to have the right of being final
Outside the temperature range 15°C - 35°C a suitable com- judge in assessment of weld quality.
parator block is to be used to compare indications from sur-
face defects examined within and outside the range.
I
I
SLAG INCLUSIONS Isolated slag: Length <.ti2. width <.tl4. max. 4 nun.
MISALIGl'.'MENT OF ADJOINING
PIPE ENDS <:0.15 t, max. 3 rnm. 3
,J --=---
DENTS Depth: Max. 6 mm. Length: Max. 00/2.
r,
COLD FORMED GOUGES.
J GROOVES. NOTCHES A1\TD
ARC BURNS Not acceptable. May be removed by grinding.
LACK OF FUSION OR
j INCOMPLETE PENETRATION Length <t 2.3.7
BURN THROUGH Max. dim. 6 mm of any single defect. total length max. 12 mm in
any 300 mm weld length. 3.4
Notes to tbe aceeplaocc limits: conunuous length of weld which <:quais live times the length ofthe defect
II See porosity chan Fig. 10.7. When the exu::nl of porosity or slag inclusi- area.
ons may mask for detecuon of other defects. supplementary radiographic S) Observeq cracks should initiau:: more extensive non-destrUCtive testing 01
or unrasomc examination is required. the joint and revision of the welding procedure.
~J If elongal.ed defects are snuated on line and the distance between them is oJ The depth 10 be measured by rnechanical means.
less man the length of the longest Indication. ine dc:fe<:lS are 10 be evaluat- 7) Severe corrosive envtronrnent may necessnate more stringent require-
ed as one conunuous defect. ments La be adopted.
.ol Any accumulauons OJ slag mclusions. mcornptete penetration. rmsalign- 8) The LOla! length of hollow beac In any conunuous 300 mm length 01
ment, hollow bead, burn thrOullh or undercut arc LO be Judged as the weld metal shall nO( exceed SO mm. Indrvicual adjacent hollow bead dIS'
mosr serious OJ (he defects In quesuon. conunuiues, each exceeding 6 mm in length. are 10 be separated by at
~I :-:01 more lIIan one urne the detect lirnus as per notes 2 :lIld 3 Within any lasL 50 mm of sound mew.
58
POROSITY:
Definition:
Voids due to entrapped gas.
Radiographic characterization:
Sharply defined dark shadows of rounded or elongated sha-
pe.
-
11111 II'
HOLLOW BEAD: "/ 11/11"" J11~...
1111'
Definition: ~/l/ \\~"
,\~
t1
Elongated voids in the root pass. -;'tlo'II.·1 ;:
Radiographic characterization:
,,
'-----_............. ""
,..-------
Sharply defined dark shadows in line of elongated shape.
SLAG INCLUSIONS:
Definition:
Slag entrapped during welding.
Radiographic characterization:
Dark shadows of irregular shape.
SLAG LINES: -
Definition:
Elongated cavities containing slag.
Radiographic characterization:
Dark lines parallel to the weld edges.
LACK OF FUSION:
Definition:
-
Plane defect due to incomplete fusion between beads or be-
tween metal and parent metal.
Radiographic characterization.
Thin dark line with sharply defined edges. The line may tend
,....--~~
/1////1
--....~--~
',/ IlIfttlt/JI/II/I I/ 11
;11'
to be diffuse and wavy depending upon the orientation of the ' 1/ / /
.defect with respect to the x-ray beam. ~'III\II,I~
"i "
"I, ""
INCOMPLETE PENETRATION: "-------~ ~.,.:.;.----_.
Definition:
Gap left by incomplete ruling of the weld root with weld me-
tal. ~
" / 1 1 / \ 1 \ ''
Radiographic characterization: , /I II" II " .111/ III , I , ,'"
Dark continuous or intermittent line following the weld root. " 11I1
~/"/101\1I '1'\'
"
\\\
UNDERCUT:'
--
I/!!I/ilt 11/111111//I III' .111 \ \ \ \
'1
"I'~
!'"
~ 11'''1&'''\ ~ "
\ \1
"
, "
Definition:
'-------'''''','''"'' "
~..:.";.'-------
A groove in the surface of the pipe following the edge of the
weld.
Radiographic characterization:
Dark line along the edge. of the weld. The line may be more
or less diffuse dependent on the shape of the undercut.
5-9
l
I
lmm PORE DIAMETER
\0 PER CENT 3 PER CENT '\ PER CENT
• ••••••• • • • • • • •
• •••••••
•••••••• • • • •
• •••••••
•••• • •••
•••••••• • • • •
• ••••••• • • • • • • •
• •••••••
• ••••••• • • • •
•• •••••••
•••••••
• ••••••• • • • •
• ••••••• • • •
• ••• • • • • • • • •
• •••••••
• ••••••• • • • •
• • • • • • •
J
2mm PORE DIAMETER
1
j
10PER CENT 3 PER CENT
• • • • • •
J • • • • •
'""\ • • • • • •
J • • • •
• • • • •
l
' ,,' • • •
• • •
•
•
• •
'1
It • • • • •
• •
I
'. ),
>
I
• •
J Fig.tO.7
area.
Typical distribution of porosity by projected
61
APPENDICES
... I
I
i
IJ
111111111.111111111111111_ _-
"" ..........
ZCt S!!!W
63
.,
APPENDIX A
ENVIRONI\1ENTAL LOADS
A.l Wind loads A.I.3.2 In-line excitations may occur when
These forces are assumed to act normal to the pipe axis in V = wind velocity normal to the pipe axis
the plane defined by the pipe axis and the wind direction. fj = natural frequency of the pipe
See A.I.2. o = pipe diameter
1 Cyclic wind forces due to vortex shedding. Also these
forces ar~ assumed to act normal to the pipe axis. They
A.1.3.3 Cross-flow excitations may occur when 4.7
8.0. V r as defined in A.1.3 .2.
< v ;«
.
may act 10 two planes - "parallel» and «normal- to the
wind direction. See A.I.3. A.I.3.4 The amplitudes of the vortex shedding induced m0-
tions due to wind may be derived according to the simplified
approach for vortex shedding in steady current given in A.2.
substituting the mass density of the water with the mass
A.I.2 Static wind loads
density of the air.
A.I .2.1 The «static» wind force per unit length of the pipe
may be determined as:
-; .. )
where
A.2 Vortex shedding due to current
qw = Wind force per unit length of the pipe. acting normal
to pipe axis in Nt m A.2.1 Genera!
C = Shape coefficient according to A.I.2.2 A.2. Ll Fluid flow past a riser or a free span on a pipeline
Vn = Component of the wind velocity normal to the pipe
axIS 10 mt sec. .
may cause unsteady flow patterns due to VOrtex shedding.
This may lead to oscillations of the pipe normal to its axis.
01 = Total outer diameter of pipe. i.e, including coating
.J etc.. in metres. A.2.1.2 Normally two types of oscillations may be encoun-
tered: oscillations in line with the velocity vector (in-line mo-
A.I.2.2 The shape coefficient should. strictly speaking. de- tionl, and oscillations perpendicular to the velocity vector
pend on wind velocity. pipe diameter and surface roughness. [cross-flow motionS>. Such oscillations may be investigated
.J H~wever: in .~f more accurate data. the coef-
ficients given 1 II.A. y be used.
according to A.2.2 and A.2.3.
~ .,*/ . A.2.1.3 For certain critical flow velocities. the vortex shed-
A.I.2.3 As a guidance for the surface roughness used for de- ding frequency may coincide with or be a multiple of the na-
termination of the shape coefficient in Fig. A.I. the following tural frequency of the pipe. resulting in harmonic or sub-
values may be used:
harmonic excitations.
k Irnetersl A.2.1.4 The vortex shedding frequency may be obtained as:
'.J Steel. new uncoated: 5.10- 5
Steel. painted: 5.10- 6 51'\'
3.10- 3 f=--
Steel. highly rusted:
3·\0-3
o
Concrete:
,Marine growth: 5.10- 3-5.\0-1 where
A.L2.4 For several pipes (relatively) close together. group ef- f = vortex shedding frequency (Hz)
. fects may be taken into account. However. if no adequate SI = Strouhaf's number
documc:ntationof group effects for the specific case is avail- V = flow velocity normal to the pipe axis
able. the shape coefficients given in A.1.2.2 may be used for D = pipe diarnter
all the individual pipes in the group.
For pipes~~...~ber is a function of the Reynold's
A.I.2.5 For pipe sections which are sensinve to dynamic number. see,Fig. A.~ ~""'!!!!~::-~ _
wind loading during construction. transportation or opera-
tion. the dynamic behaviour of the wind is to be taken into A.2.1.5 For determination of the velocity ranges where vor-
account when determining the wind loads. This may' either tex shedding induced oscillations may occur. a parameter. V r
I :be done be use of recognized gust loading factors. or by use called the reduced velocity. is used. V r is defined as
J .of a stochastic approach for the wind loading.
\' r - \' .
-
[,·0
A.1.3 Vortex shedding due to wind
i where
:-\.1.3.1 Wind induced cyclic excitations of pipes may occur
In two planes. in-line with or perpendicular to the wind di- v = flow velocity normal to the pipe axis
rection. see A.1.1.1. For a closer descnpuon of the vortex 1", = natural frequency of the Pipe
shedding phenomena. see A.2. o = pipe diameter ..
!1I!11ii111
..
A.2.1.6 An other parameter controlling the motions is the A.J Recommended values of hydrodynamic coefficients
stability parameter. KJj • defined as
A.J.I General
A.J.1.l The proper hydrodynamic coefficients to use in each
. case will depend on the flow and pipe conditions character-
............... ~ . 60t -~':I. ized by
~ . . .\,:A._.. . -.:..(,,:~
= logarithmic decrement of structural tlamprng - Reynold's nurnber ifc,= U Dlv)
= mass density of surrounding water "'-..../' - Keulegan-Carpenter numbedKc =
L'm' TID)
= pipe diameter pipe roughness (kID)
distance between the pipe and a fixed boundary (HID)
= effective mass per unit length of the pipe. defined as
L where
Jm[Y(~
0
D
H
= clearance
pipe diameter
= wave period
between the pipe and a fixed boundary
me = T = roughness height
k = flow velocity
J [y(42 U
Um
= maximum orbital particle velocity
= kinematic viscosity of the water
0 1I =
where A.J.t.2 The hydrodynamic coefficients should preferably be
obtained from relevant model test. taking into account the ac-
m = mass per unit length. including structural mass. add- mal values of the different parameters specified in A.J.t. In
ed mass and the mass of any fluid contained within the following some proposed values of the hydrodynamic .
the pipe coe ffiIClents
. are . given. r-.c.t~·\04:i(D
.... '& Jl....c. 't.,-' .'\~~"';.
". L...,......
y (x)= mode shape of the actual pipe span T".1
~Q,,~t- ~ Co ... \1"1l..,c. ..') •. i:~
L = length of the pipe A.3.2 Added mass coefficient 4' It 'V
d =-submerged length of pipe . . .
r
A.3.2.1 The added mass coefficient for a Circular cylinder as
A.2.2 In-line oscillations . fU~!l..<L.Q.( the distance from a fixed boundary is given in
A .2..
2 I Resonant.tn-. line .vortex Sheddi109 10 d uced oscillauons ~ .€~-' . - ...._if-----
may occur when 1.0 < Y r < 3.5 and Ks < 1.8. For definition The figure may be used for both smooth and rough pipe sur'
ofVr and Ks. see A.2.I .6 andA.2.1.7. faces. For a pipe which is not influenced by any Iixed bound-
ary. the recommended added mass coefficient is t.0.
A.2.2.2 Depending on the flow velocity. the vortices will
either be shed symmetrically or alternatively from either side A.J.3 Drag coefficient
....;...
.'
of the pipe. . f 'I
A.3.3.1 The drag coefficient as function 0 the Keu egan-
~
, ~
For 1.0< v,
< 2.2. the shedding will be symmetrical. and ~rpenter numbe:. for smooth .and marine .gro~h ,:over.led
·the necessary flow velocity for onset of motion may bedeter-~for supercnucal Reynold s numbers IS given In. F g.
mined from Fig. A.3. ~ he figure is valid for free field flow without any influ-
ence of a fixed boundarY.' -
U
F or Yr > 2.2. the shedding will be symmetrical.
A.3.3.2 The drag coefficient for steady current is equal to the J
. A.2.2.J T.he maximum amplitude of the motions due to in- asymptotic value for Kc equal to infinity, For combined wa-
-
line vortex shedding may be determined from Fig. A.4. ve and current action the increase of Kc due to the current
may be taken into account.
A.2.3 Cross-flow oscUlations
A.3.3.3 To determine the drag coefficients for pipes close to a
II A.2.3.1 Cross-flow oscillations may occur for Ks < 16 and fixed boundary. the drag coefficients given in A.3.3~be
values ofYr as determined from Fig. A.5.
A.2.3.2 The max~um amplit~e cross-flow oscilla-
multiplied by a correction factor obtained fr~A.9. )
I I II I I! III! I
i
',1 A.4.1.2 The wave slamming force per unit length of the pipe The contribution to fatigue from each wave block is gi-
may be calculated as ven as:
n,
y=R..:.:J..
i=20
r (
- i)K
I Nj i=20-n; 20
?I. = number of waves within blockj
Fs = slamming force per unit length in the direction of the NI = critical number of stress cycles (from relevant
velocity SoN curve>associated with l:J. tlj
@
Cs
= mass density ofthe surrounding water
= slamming coefficient nj = number of stress ranges in excess of the limiting
stress range associated with the cut otT level of
D = member diameter the S-N curve
V = velocity of the water surface normal to the surface of R = reduction factor on number of waves. For a gi-
the pipe. Normally the vertical water surface velocity ven element only, waves within a sector of 10
will apply degrees to each side of the perpendicular to the
member have to be accounted for. In case of an
A.4.L3 The slamming coefficient C s may be determined us-
~
irectiO nal wave distribution. R equals 0_11_
ing theoretical and! or experimental methods. Eor smooth. K = 10 of the SoNcurve (in log-logscale>
circular cylinders the value of C s should not be taken less 1'......'-Ct..""'"~~
than 3.0. A.4.2.2 The calculated contribution to fatigue due to slamm-
ing has to be added to the fatigue contribution from other
A.4.1.4 As the slamming force is impulsive, dynamic amplifi- variable loads.
cation must be considered when calculating the response.
References to Appendix A
For a pipe section fixed at both ends. dynamic amplification
II factors of 1.5 and 2.0 are recommended for the end moments AI. BSI Code of Practice No.3. Chapter 5. Part 2: «Wind
i ) and the midspan moment. respectively. Loads». September 1972.
""'" ~ A2. CIRIA Underwater Engineering Group. Report
A.4.2 Fatigue due to wan slamming UR8: «Dynamics of Marine Structures». London. Ju-
If! ne 1977.
A.4.2..1 The fatigue damage due to wave slamming may be A3. Blevins. R.D.: "Flow-induced Vibration». Van Nos-
determined according to the following procedure: trand Reinhold Company. New York. 1977.
A4. Heideman. Olsen and Johansson. «Local Wave Force
Determine minimum wave height. Hm,n' which can cau- Coefficients». ASCE Civil Engineering in the Oceans
seslamming IV. September 1978. .
Divide the long term distribution of wave heights. in ex- AS. Sarpkaya, T.: «Vortex Shedding .and Resis~n~ in
cess of Hmin. into a reasonable number of blocks Harmonic Flow about Rough Circular Cylinders»,
For each block the stress range may be taken as: BOSS 76-conference. Trondheim, Norway. August
\,. [ ....------...(
)
l:J. O'j= 2 aO's/am-€: O'b + O'w J)1" 19-6
I • . C
,,,,,,,--------,, I . A6. Sarpkaya. T.: «In-line and Transverse Forces .on Y:
'____. O'sIam= stress in the element dueIOthe slam oad given linders near a Wall in Oscillatory Flow at High Re-
-- C!n A.4.1]) ynold's Numbers». OTC Paper No. OTC 2980. May
"'0= stress due to the~bu~ancy force on the ele- 1977.
ment ....t..U\o Ai. Sarpkaya, T.: «Hydrodynamic Drag o~ Bo~o~'
"'. . = Stress due to vertical wave forces on the element mounted Smooth and Rough Cylinder m Periodic
a = fae;Jor: accounting for dynamic amplifications. see Flow». OTC Paper No. OTC 3761. May 1979.
(C4·1.9--. ... ..:: A.~ 02.. A8. King. R.• Prosser. MJ.• John, OJ.: «On Vortex Ex-
- Each slam is associated with 20 approximate linear~0 citation of Model Piles in Water», Journal of Sound
~stress ranges . and Vibrations. Vol. 29. No.2. pp. 169-180. 1973.
Ql..e.~~e....~
J
J
0 . 2 0 , . . . - - - - - , - - - -.....- - - ' - - , - - _ - ,
------1t------··--- .._-
c +--------t----.---- ----'--"---1
!
,
,---- 1i10 = 1• ..: 0.15 +----3'<----1----+----j-----I
a .10+----~~~--+----r__---_1
0.5,+-----tfl~---_y'--17""7''-----:-_j
2.0 [
Fig. A.I. Shape coefficient for circular cylinders.
Ref. A.1.
Fig. A.4. Amplitude of in-line motion as a function of Ks
Ref. A.2.
,CRIn-
LAMINAR SUBCRlTICAl CAL! SUPER CRITICAL
0.4
-
I i I: b
I
6.0 +-----""""'====:------j~~j;(u:"'MiiW~
5
0.3
~
A~ v,
5.0.J------..b:=----+-=:::==~
0.2 I- I
I~I I
0.1 !/ I I
I I ,.O+--------r=::::--:::-=::::~:r--:;::=:======l
0.1
I
. 1.0 10 1()2 103 1()4
I
10"
3.0+.------1------+------1
0.0 +-....-'...............-.-...".f--...,...-.--.-......
10
4
1'os
.,..,.....-.r----.---,-....,...,~
I
10' 10
1
Re
Fig. A.2. StrouhalsDumber for circular cylinders as Fig. A.S. Flow speed for onset of cross flo'" metion, Ref. I
fUDdioD of reYDolds Dumber. Ref. A.8. A.2.
2. 5
I 1 I
FIRST INSTABILITY SECOND INSTAB
v, REGION REGION
l
z.z
2.0
t-- - - --7 i"""
I 1.2 CROSS FLOW
MOTION
I
MOTION
I
V ~
y·OIAM.
1.0~~----+_-----~----4
0.8
1.5
1.0
<;>
/ NO MOTION
.
0.6
0.'
0.2
,
o 0.5 1.0 1.5 2.0 2 6 8 10
Fig. A.J. Flow velocity for onset of In-line motion. Ref. Fig. A.6. Amplitude of erossflow motion as a funedon of Ks
A.2. . Ref. A.3.
il
J
67
..
INE"T1A COEFFICIENT, C .. - "ECOWWENoeO VALUES 0
3.0 \
\.
-,
~
~., 1\
~ /J
c. -,
-f f 10
,<:. , <,
----
l 2.29
fr
I r-,
----
'- Z.O
2.0 ~. Jc
.
I
(
: (\
~
1 tI ~ '.0
,
j
f ~"
l 1.0 I I I
Sc... C,,",.a\AL
..,j.~s.~ .. -",)"'~O""'''Jl.:'o - .... c..
c. e.o~'~~·::"G~S.C.-'A ....:'"',s.~
Fig. A.IO. Lift coefficient for a circular cyllnder at a fixed
boundary In oscillatory flow.
1. ICc
~c.. c~ "':..:. '=a",t:~
~
['
'. ., " "
1.0 10 15 , 1 . O+---~----!---+---io-~-I---i
I N
ii
~I
0.6+-+--+---i---t----i---;---;
_..1
I O. 4 +--+--+---i-~-+----+-----;--;
GROW~H
~,~/~RIHe
........
. ! UGH~ ESS
0.2 +----P""-:----;.---:~--;----+-___1
!\. "-~I I
<,
-
. ST EELR< UGHHE
I
s/ '"
! 1
~~
0. 70
0.0 +-__-+
0.0 0.2
i-_-~---+-----!-.J
0.4
1. 5 -t--".... ---i----;---~--__;---..:-.~
.
I
,.
I
i
I
I
0.0 02 0.4 0.6 0.8 1.0
.H/O
APPENDIX B
BUCKLING CALCULATIONS
B. I Local buckling where
B.I.I In the absence of more accurate information (or 'ha = permissible usage factor Ii.e. permissible value of
methods) the critical combination of longitudinal and hoop ...E.L) when a, = O.
stresses may be expressed as follows: (J xcr .
'hr = permissible usage factor (i.e. permissible value of
...EL) when c, = O.
a yer
(Compressive stress is positive in this formula.I
Other symbols are defined in B.I.I.
c. = (1.N + e. M
The usage factors should depend on whether the critical
(1N N stress is in the elastic or in the plastic range. Therefore nor'
(Compression positive)
• =
A rnally 1],p will be smaller than 'hp Recommended usage factor
(1M M are given in B.I.3.
• = (Compression positive>
\.V
B.I.3 A recommended dependence on the degree of plas-
N = axial force. ticity involved is given for risers during operation in Table
A = t: (D - t) t = cross sectional area. B.1. For pipelines during operation the factors in Table B.I
M = bending moment. may be multiplied by 1.1. For both pipelines and risers dur-
ing installation. the factors in Table B.I may be multiplied by
\.\' = ; (0 - t}2 t = (elastic) section modulus. maximum 1.44. However. no usage factor should exceed 1.0.
See also B.I.4.
D = nominal outer diameter of pipe.
t = nominal wall thickness of pipe.
Table B.I
Loading ~ <; I
condition 1<.2f......<J
aF (1F
~
considered as during "installation».
(1yc:r = (1yE = E ( D t Y 2
for (1yE <;"3 (1F
= (1yc:r= (1F[ I- t· (~ YJ 2
for (1yE > "3 (1F
B.2 Propagation buckling
B.2.1 Theoretically. the probability that a propagating buck-
B.I.2 The permissible combination of (1. and (1y should be le will be initiated is not higher (but may be lowed than the
defined by inserting permissible usage factors in the formula probability that a local buckle will occur. However. due to
of B.I.I for critical combination. The permissible combina- the great economic risk involved in propagation buckling. in-
tion may then be expressed as creased safety. or at least a closer investigation. may be ad·
viceable. For such investigation the available results from the
overpressure is less than the propagation pressure (pp) of the B.].3 ~or a pipe subjected to an axial force N in !he pipe it-
pipe. A simplified consideration of plastic work involved in self. an IOter~al pressur~ P, and an external pressure P•. the
total collapse gives «effective» axial force WIth respect to «bar buckling» is:
J
70
APPENDIX C
QUALITY CONTROL OF MATERIALS.
QUALIFICATION OF \VELDING PROCEDURES AND WELDING PERSONNEL
c.) General C.4.1.2 Wet analyses and spectrochemical analyses are to be
made on materials sampled by e.g. drilling or milling and be·
c.).) Scope representative for the material composition.
CI.I.I This appendix is a guidance to quality control of ma-
terials and defines methods for determination of chemical CA.l.3 Spectrographical analyses are to be made on a clean.
composition. mechanical testing of materials and welds and bright metal surface after grinding to a depth at least 2 mm
schemes for qualification of welding personnel. below the surface. Analyses of semi-killed steel are. however.
to be taken at approximately one quarter thickness position.
Other Standardized testing methods. test specimens and
combination of tests may be used subject to agreement. CA.I.4 Ladle analyses are to be taken prior to and during
steel casting to ensure a uniform composition of each heat.
C.).2 Definitions
CA.I.5 Check analyses are to be taken on the final products.
Cl.l.! Test sample: The part of the material (pipe. plate. sec- The check analyses may. however. optionally be determined
tion. east-on bar. piece cut from forgings etc.l which is select- at an intermediate stage. e.g. on plates. provided the results
ed for testing. are stated on the certificates.
C.I.2.2 Test specimen: The part of the test sample which is CA.I.6 Determination of chemical composition is to include
prepared by machining etc. for carrying out the various tests. all elements listed in Table 5.1 (RJ and other remaining ele-
ments intentionally added to control the material properties.
C.1.3 Testing equipment When the steel is made from scrap. the manufacturer is also
Testing equipment is to be of proven design with adequate to check the content of other residual elements which may
capacity and accuracy. The equipment is to be satisfactorily impair the quality of the product. e.g. Sn, As. Sb.
maintained and kept in accurate condition by regular calibra-
tion and check routines. Endorsed calibration records are to CA.1.7 The chemical composition is to be stated on the certi-
be kept available in the testing facility. ficate by the elements listed in Table 5.1 (R) and any other
elements intentionally added to control the material propert-
Only competent and trained personnel is to carry out testing. ies. Trace elements need. however. not be reported.
CA.I.8 Recheck analysis: Should a check analysis fail to meet
C.2 Steel making the specified composition limits. all other heats within the sa-
me batch are to be subject to a complete chemical analysis.
C.2.l General Only those heats which are within the specification. may be
accepted .
.C2.1.1 Steel may be made from pig iron. sponge iron or re-
cycled scrap. Residual elements are to be kept at a level C4.I.9 Requirements are given in S.2A (Rl.
which will not impair
C.3.1 General
C3.I.I Steel may be ingot cast. continuous cast or mould
cast. Sequence casting is subject to agreement. C.6 Surface defects in base material
C3.I.l The cast ingot. item or slab is to be inspected for sur- c'6.1 General
face defects. Defects are to be removed prior to subsequent
working. c'6.1.1 The steel manufacturer or any other works perform-
ing operations which may influence the surface finish of the
C3.I.3 Spun cast products are to be machined to a depth en- material. are to take precautions and make regular checks
suring removal of impurities and surface defects. with suitable equipment to ensure that the final surface finish
. is acceptable.
C.IO.I General
e.10.1.1 The purpose of qualification testing of welding per-
C.8 Sampling of test specimens sonnel is to verify that the welder or welding operator have
the necessary training. skill and understanding to produce
C.8.1 Seamless pipes sound welds according to a qualified welding procedure.
e.8.I.l Tensile test specimens (transverse and longitudinal)
and Charpy V-notch specimens (transverse) may be sampled e.10.1.2 In order to be qualified. welders and welding opera-
from any location within the pipe material. However. if the tors are to be at least 18 years of age. and are to have passed a
pipe has been spun cast. the test specimens are to be taken at relevant theoretical and practical training program.
the inside surface of the pipe.
C.10.1.3 The company responsible for the welding opera-
e.8.2 Welded pipe tions is prior to qualification testing. to confirm that each
welder and welding operator have obtained adequate under-
C.S.2.1 Pipe material: Tensile test specimens (transverse and standing of
longitudinall and Charpy V-notch specimens (transverse). are
to be sampled ISOo from the weld. fundamental welding techniques
significance of welding parameters
e.S.2.2 Weld seam: The test specimens are to be sampled relevant materials response to welding
transverse to the weld. with the weld deposit at the center. as operation of the welding equipment to be used
shown in Fig. e.6. The same applies for jointers which are welding procedure specifications
produced in the IG principal position (pipes horizontal while handling of welding consumables
rotating). relevant methods of non-destructive testing
relevant acceptance criteria for weld defects
C.8.3 Cold formed or forged bends
e.10.1.4 Welding personnel to make bunwelds and fil1et
e.S.3.1 The test specimens are to be cut from an overlength
welds is to have passed qualification testing for single side.
bend section having received the same deformation and heat
full section bunwelding of pipes in the principal positionis)
treatments as applied for the bends. Base material test speci-
required.
mens are to be sampled from the area of maximum tensional
deformation. The longitudinal axis of the specimen is to be
e.IO.).S Welding personnel satisfying the above general con-
orientated transverse to the direction of the principal wor-
ditions and having performed an acceptable test weld accord-
king/grain flow. When a bend contains longitudinal weld
ing to e.1 0.2 is thereby qualified.
seam<s>. test specimens are also to be selected as described for
welded pipe (C.S.2).
e.10.1.6 For underwater welding additional conditions will
apply. see C.I 004.
C.8.4 Forged seamless piping components other than bends
e.SA.1 The test specimens are to be taken from a portion of e.10.1.7 An endorsed qualification test record is to be issued
the forging which has received a deformation representative after completion of an acceptable test weld. The record is to
for the working ratio of the most highly stressed cross' sec- be of a suitable form containing information sufficient to
tion. For components with greatly varying working ratios describe applied welding procedure. testing set up. evaluation
and section thicknesses. more test samples may be necessary. methods and conclusions. scope of application and date of
testing.
Separately forged test blanks may be used when integrally
forged extension samples can not be reasonably provided. e.IO.I.S Where a qualification of recent date is allowed
transferred to a new project. the welding personnel is to be
e.SA.2 The test specimens are to be machined with their informed about particular project requirements for which
principal axis transverse to the direction of principle grain their welding performance will be specially important.
flow. and be at least 0.1 t from the as-forged surface. Where
transverse testing can not reasonably be performed due to the e.10.1.9 Requalification is to be performed if the welding
small size of the component. the test specimens may have personnel has not regularly performed qualified welding
longitudinal orientation. within a period of more than six months.
I ·1111!111I111111 111I1111111I11111.' _
73
C.IO.2 Test welding doubled. and both the new welds are to be acceptable. No
further retests are permitted until the welder/operator has
CIO.2'.1 Prior to starting the test welding. reasonable time is passed acceptable additional training.
to be permitted to adjust the welding equipment.
If a failure occurred due to conditions beyond the welder's/
C.10.1.2 If the welding procedure involves more than one operator's control. this failure may be disregarded. and a new
operation or more welding units. test welding is to include alI opportunity to qualify given.
l operations and units necessary to complete the weld. Con-
,j sequently the performance test may require welding with dif- C.IO.4 Welder qualtflcanon
ferent welding units and welding parameters.
C.l0.4.1 A welder is qualified for welding when the condi-
CI0.2.3 Two pipe nipples of sufficient length to introduce tions given in.CIO.l. C.l0.2 and CIO.3 have been fulfilled,
realistic restraint are to be joined according to the qualified Qualified welding positions are given in Table C.2.
welding procedure. The pipe diameter. wall thickness and the
principal positionlsl are to be selected in accordance with the c.I0.4.2 A welder qualification is valid within the limits of
range to be qualified. essential variables as described below. If any of the following
Type and number of mechanical tests are given in Table CI. is to be examined visually and by radiography. If interrupted
period exceeds 6 months. the performance test is to be as
CI0.6.5 The applicability of a welder's certificate is given in specified for initial qualification.
Table C2 as regards welding positions. Applicability for
welding at greater water depths or other pressure or diving For underwater welders who are on stand-by and without
modes will be decided in each case. necessarily doing regular underwater welding. the conditions
for maintenance of the qualification is to be specially agr~d
C.IO.6.6 For underwater welders any change of coated elec- upon.
trodes will normally require requalification.
C.IO.7 -Extracrdlnary requallfication of welding personnel
CIO.6.7 Renewal of the certificate for underwater welders CIO.7.1 Welding personnel maybe required to 'requalify in
may be required if welding has been interrupted for a period
case of negligence or questionable welding performance. In
of more than 3 months. The retest is then to consist of mak- such cases the welder/ operator in question shall present evid-
ing minimum one test coupon of length approximately
300-400 mm in an agreed welding position. and the coupon ence of further acceptable training. and are. to be requalified
as for initial qualification.
75
REDUCED SECTION
~ 6Omm-1
L---r-T--:-:i""").---.........J
APPROX
J&mm 11 t t
LENGT.. 25mmRmin.
SOmm.
I.. APPROXIMATELY225MM------~
WELD REINFORCEMENT SHO LD NOT BE
...L REMOVED ON EITHER SlOE OF SPECIMEN
T
Weld tensile test for field weld pr cce dure
Qualification test.
- - - - - - - - 2 0 0 m m (minimum)
*WELD
THICHNESS
I
WELD REINFORCEMENT IS TO BE REMOVED FROM BOTH FACES FLUSH WITH THE SURFACE OF THE SPECI-
MEN. SPECIMEN SHALL NOT BE FLATTENED PRIOR TO TESTING. CUT SURFACES SHALL BE SMOOTH AND
PARALLEL
I t-- THICKNESS
SPECIMENS MAY BE MACHINE CUT TO 12,5 MM WIDTH OR THEY MAY BE OXYGEN CUT TO APPROXIMA. E-
LY 20 MM WIDE AND THEN MACHINED OR GROUND SMOOTH TO 12,SMM WIDTH. CUT SURFACES SHALL
BE SMOOTH AND PARALLEL I
I
j
77
l.~---------~APPRox.225mm-----------+4
3mm
55
NOTCH POSITIONS. I
I
'5:2
2IT
5!
CENTER OF WELD
;1
~ I
I
----=..:.---~L.
1--.. 20
I
A
20
!
FUSION LINE It.Ll
I
Q
I
I"
40
2mm FROM f. I.
: s::g,!! I
2mm
i \J{ III
ROOT RADIUS 0,25
5mm FROM f.l. I
\ 5rrm
\
DE TAIL "A"
Charpy v- notch
specimen Inotch perpendicular
to rolled s ur t c e e .
~ 1 MM A.
I
I
.1
HARDNESS TESTING
Bun WELDS
I
J
~ ~
O.5mm
"
I DETAIL A MAGNIFIED I
t'V 1 MM
j
HARDNESS TESTING
HARDNESS TESTING
MULTIPLE PASS SINGLE BEAD REPAIR
INSIDE OR OUTSIDE
J
WELD REPAIR
J
Fig. C.S. Hardness testing welded joints - schematic.
J
I
J
79
W//~:ZWAo'fcfdiof~
. I g I Tensile test specimens. .
II I~::
I Q I
I
}. Bend test speci mens.
I
~}
IMPACT TESTING:
Center of weld metal
1 speci mens.
~}
Fusion li ne
I specimens.
S"J
61 A
A '~
J Smm from fu sian line
a1 A ) speci mens.
TOP OF PI PE
. - - - - - - - Hardness /macrosection
Face or side bend ~4---- Tensile
Root or side bend ~~-- Nick break
OO~ 300mm
--1--- . - Weld me 1al } ~
. . - Fusion line
- + - 2mm from f.!. Ec
iE
Nick break -----~~~ ~ 5mm from f.l_ - ;J)
Tensile -.....L.__~.§~'~--- Root or si de bend
, .
~---- Face or side bend
' - - - - - - - Hardness / macrosection
TOP OF PIPE
~/~--------Hardness/macrosec br
Root or side bend - - - - - - - - Sidebend
~ick break - - - - - - - - . - / 1 Tensile
~·AI'l-....._ - - - - -
Outer diameter
00 > 300mm
.. --i' \I
e
11
I CC
_\I
Note: The indicated locations of the test specimens are to be used for welding positions 2G. 5G and 6G
For qualification of welding in 1G position. sampling positions are optional.
TOP OF PIPE
Nic k break
Root bend or side bend
Root bend or side bend oJ
TOP OF PIPE
.Note: At the company's option, the locations may be rotated 45 degrees counterclockwise or they may
be equally spaced around the pipe except specimens shall not include the longitudinal weld. Also.
at the company's option. additional specimens may be taken.
t r
82
APPENDIX D
GUIDELINES ON CORROSION CONTROL
D.] Design of cathodic protection systems For coated pipeline systems. however. the current demand
D.l.1 General
may increase with time as the ~oating deter~Orates. . I
D.I.I.I The purpose of D. I is to provide some general guide- Table D. I presents a general guide for selection of design cur-
lines to the design of cathodic protection systems for sub- rent densities. Three minimum design current densities arc
marine pipeline systems. listed for some major offshore' areas and special enviro I
merits.
Veritas will be open to evaluate cathodic protection systems
based on alternative design methods, The initial current densitv is used to determine the necessary
current output capacity' of new anodes. The final curre "I
D.I.1.2 Cathodic protection for submarine pipelines and ri- density is used to determine the necessary current output c I
sers is generally by sacrificial anodes. pacity of anodes when the anodes are consumed to the utili-
zation factor. The mean current densitv is used to deterrmne
The cathodic protection system is generally applied in com- the weight of the a n o d e s . ' I'
bination with a suitable coating system. The coating will re- i
duce the initial current requirement and improve the current
distribution.
~
peline system.
Initial Mean Final
value value value
D.I.2.2 Environmental conditions: The following parameters
should be taken into account in the design of the cathodic North Sea (nonhem) 160 120 100
protection system: North Sea (southern) 130 100 90 I
Arabian Gulf 120 90 80
Temperature of pipeline system India ]20 90 80
Temperature of seawater/sea bed Australia 120 90 80
Oxygen content of seawater/sea bed Brazil 120 90 80 I
Chemical composition of seawater/sea bed Gulf of Mexico 100 80 70
Resistivity of seawater/sea bed West Africa 120 90 80
Current velocity of seawater Indonesia 100 80 70 I
Biological activity I
Pipelines (burial
specified> 50 40 30
I
If relevant parameters from the same area on these are not
available. measurements along the route may be required. Risers in shafts with
flowing seawater 180 140 120 I
The current output of anodes is dependent on the resistivity. Risers in shafts with
For seawater the resistivity in tropical waters It::::::: 25°C) may stagnant seawater 120 90 80
be taken as 20 ohmcm while in colder waters <t : : : : 5- 10°C)
it may be taken as 33 ohmcm. Sea bed (ambient I
temperature) 25 20 IS
The resistivity of the 1m upper layer of the sea bed may be ta-
ken as 100 ohmcm if no measurements have been carried
out.
0.1.3 Current demands For buried pipelines. higher values are used than for b:O?'f
D.I.3.1 The total current demand is given by the current steel in seabed. This is due to that a higher safety margir ~
density and the area of exposed steel surfaces. The following necessary and the fact that complete burial may not be 4 J-
areas should be considered: tained. '
areas in seawater D.I.3.2 The current density for a coated steel surface is hi: I-
areas below mudline Iy dependent on the quality of the coating materials and _.b
unprotected foreign structures in electrical contact with coating application.
the pipeline system I
Table D.2 gives guidelines on the selection of coating bre I·
The current density is determined by the environmental down criteria for coated structures. The coating breakdo .. h
conditions. The selection of design current densities may be criterion is defined as the ratio: •
based on experiences from similar pipeline systems in the sa-
me environment or measurements. Current density coated steel
·100%
Current density bare steel
The current density is normally not constant with time. For
bare steel surfaces in seawater the current density may dec-
rease due to the formation of calcareous deposit caused by
The presented values are based on satisfactory coating ap t
calion. If the coaling is particularly exposed to wear and J }
the cathodic current chanical damage. higher values must be used.
83
To establish the current density requirement for coated steel. D.1.4 Anode materials
the values in Table D.I should be multiplied by the percenta-
.....
0.1.4.1 Zinc anodes should conform to the following compo-
~
ges in Table 0.2. sition in order to reduce the susceptibility to intergranular
I
J corrosion.
Table D.2 Guide on coating breakdown criteria (,,) for
some coatings (expected lifetime 25 years) max % min %
I
,I Initial Mean Final Aluminium
Cadmium
0.2
0.06
0.1
0.03
Thick film pipeline Iron 0.002
coatings I 10 20 Copper 0.005
Vinyl systems 2 20 50 Silicon 0.125
Epoxy coal-tar 2 20 50 Lead 0.006
Epoxy {high-build> 2 20 50 Zinc remainder
0.1 .3.3 For pipeline systems in contact with the reinforce-
l ment of concrete structures, allowance should be made for
current drainage to the reinforcement. An average current
density of 0.5- I mA/m~ for the outer reinforcement layer is
0.1.4.2 The following electrochemical properties of alloys
other than given in D.1.4.1 should be documented by ap-
propriate tests:
normally sufficient. Initial values may be somewhat higher
and final values significantly lower. The area of the outer Driving potential (mY) to polarized steel. i.e. the differ-
I:.J reinforcement may be taken as the area of the concrete sur- ence between closed circuit anode potential and the po-
face. tentials given by Table 6.1.
Current capacity (ampere. hours/ kg).
0.1.3.4 The current density may be dependent on the tempe- Susceptibility to passivity.
rature. For pipelines and risers carrying hot oil or gas an in- Susceptibility to intergranular corrosion.
crease in the current density has been observed.
The testing of the above-mentioned properties may be carried
In the temperature range 25°C to 100°C an increase in the out by long term free-running Ii.e. without external power
current density in the order of I m.A../ m 2 per °C as compared source> laboratory testing, or field testing of full scale anodes.
to the values given in Table D.I may be used. The tempera-
ture to be considered is the temperature difference between Table 0.3 gives some guidelines on typical values for es-
'..,. I hydrocarbon and seawater! sea bed. sential parameters for some technical anodes alloys.
J
']
84
0.15.2 For bare steel surfaces the anode current output ca-
pacity should be calculated in the initial stase when the cur-
rent demand is greatest and at the end of the lifetime when D.2 Standards for coating
the anode is consumed to the utilization factor and the anode
has the lowest current output. D.2.] General
<,
0.2.1.1 Standards or recommendations for coating materials.
0.1.5.3 Installation of additional anodes with smaller dimen- application and testing are listed below. Most test methods
sions for the initial stage (for instance 3 years) to meet the will be found under the first group referring to the most com-
high initial current requirements may be more economical mon generic types of pipeline coatings. The second group
than to find a single anode shape which meets both initial contains more general guidelines for coating application and
and final current demand. inspection.
For coated structures where an increase in the current density D.2.2 Acceptable standards for coating properties and test
may be observed the current output capacity should be methods referring to generic type
checked at the end of the lifetime when the anode is consum-
ed to the utilization factor. 0.2.2.1 Coal tar based coatings:
The total current output capacity should be greater than the British Standard BS 4164. Specification for Coal Tar Based
total current demand. Hot Applied Coating Materials for Protection of Iron & Steel.
AWW A C 203. Standard for Coal Tar Protective Coatings All surface preparation of pipes for pipelines or risers is nor-
and Linings for Steel Water Pipelines - Enamel and Tape - mally to be in accordance with:
Hot - Applied.
Swedish Standard SIS 055900. Pictorial Surface Preparation
?"ACE Publication 2J 362. Specifications for Asbestos Pipeli- Standards Grade Sa 2 1/2. or better (Sa 3).
ne Felt.
The following standards for surface preparation are consider-
0.2.2.4 Epoxy coating: ed to be equivalent: .
British Gas Standard (preliminary). British Standard BS 4232. Surface Finish of Blast-Cleaned
Steel for Painting. Second Quality. or better (First Quality).
0.2.2,5 Vulcanized rubber coating:
u.s. Steel Structures Painting Council SSPC. Grade SSPC-SP
British Standard Code of Practice CP 3003: Pan I. Rubber. IO. Near- White Blast Cleaning. or better <GradeSSPC-SP 5).
To obtain good bonding the rubber coating should be applied NACE No. 2. Near-White Blast Cleaned Surface Finish. or
by extrusion of a continuous rubber stripe under controlled better (~·ACE :--:0. I).
tension to rotating pipe.
For field joint coating of weld areas on lay barge or similar.
for coal tar or asphalt based coatings. surface preparation by
wire brushing to remove all weld spatter rust dirt and dust
0.2.3 Application and inspection of coatings, general until a clean uniform grey-white metallic finish is obtained.
standards
0.2.3.3 Application and inspection of coating:
0.2.3.1 General:
NACE Standard RP-06-75. Recommended Practice. Control
Below are listed some recognized general standards for coat- of Corrosion on OITshore Steel Pipelines.
ing application including pipe metal surface preparation. in-
spection and testing of final coatings. For application of pipe- U.S. Steel Structure Painting Council SSPC. Steel Structures
line coatings. the standard listed under 0.2.2 are of primary Painting Manual.
interest. The below requirement to surface preparation of mi-
nimum SIS grade Sa 2.5 or equivalent should always be gov- British Standard BS 5493. Code of practice for protective
erning for yard coating of pipes. coating of iron and steel structures against corrosion.
0.2.;.2 Surface preparation of pipes: References is also made to the standards given in 0.2.2.
o ( 4·1 \
SLENDER ANODES . In--Ij
l·;7·i, r
Ra = .:«:
l·S
(0.3)
S = ~ b>2c
2
BRACELET ANODES
AND OTHER SHAPES
0.315 .~ (D.4)
yA
:\ = exposed surface area of anode
E.I GeDeral E.2.3 The minimum test pressure is to be at least 1.25 times
E.l.l This appendix covers Veritas' guidelines with respect to the design pressure. The hoop stress during pressure testing is
pressure testing of pipelines and pipeline sections. normally not to exceed 90 % of SMYS. Higher stresses will,
be considered in each case. During pressurizing, added test li-
The purpose of the pressure testing is to verify that the tested quid versus pressure should be recorded in order to evaluate
sections are leakproof and have the required structural the amount of residual air in the test section.
strength to withstand the design pressure with the anticipated
level of safety. E.2.4 After pressurizing sufficient time for stabilization must
be allowed having in mind that a temperature change during
It is assumed that the separate pipes have been individually the pressure test will greatly influence on the pressure. Signi-
pressure tested in the pipe mill. fieant temperature differences between added test liquid and
surrounding environment might lead to a long stabilization
time (several days). ' .
E.l.2 The Owner is to establish specifIcations for hydrostatic
testing describing procedures and equipment.
E.2.S The holding period should normally be 24 hours. If,
The procedure specification is to cover at least the following: however, a 100% visual inspection of the tested section is
carried out. the holding period could be limited to the time
necessary to carry out this inspection, but not less than 2
Pressure test specification designation and revision num- hours. For short sections as for instance risers 8 hours hold-
ber
Description of the sections to be tested (defining lengths, ing period may be acceptable. During the holding period the
elevations. in-line valves and connectors, branches, con-. pressure is to be recorded every 1/2 hours.
nection for test equipment. e.g. isometric drawings, flow-
sheets and alignment sheets>, ' ,
Test medium (including additives>
E.3 Pressure test method no. 2
Mixing of test medium and additives E.3.1 The testing sequence will be as follows:
Test pressures
Test holding time Caliper pigging (normally included>
Description of all testing equipment Filling of test liquid
Description of all testing instruments Stabilization <long sections>
Method for cleaning and removing of air from the test Pressurizing to strength test pressure
section Stabilization
Sequence of pressurizing Holding
Monitoring and recording of test pressure Reduction to leak test pressure
Depressurizing and discharge of test medium Stabilization
Holding
E.I.3 Instruments and equipment for measuring pressure. vo- Pressure release
lume and/ or temperature is to have an appropriate measur- Reporting
ing range with sufficient accuracy verified by a recognized
test laboratory. The verification should normally not be older E.3.2 With respect to filling of test liquid and stabilization, re-
than one year. ference is made to E.2.2 and E.2.4.
Pressure measuring equipment is to have an accuracy and re- E.3.3 The minimum strength, test pressure is 1.4 times the
peatability of ± 0.1 % . design pressure. The maximum equivalent stress during pres-
sure testing is normally not to exceed the von Mises equiva-
If temperatures are measured during the pressure test, the ac- lent stress during pressure testing in the pipe mill or 0.96
curacy of temperature testing equipment is to be 0.1aC. times SMYS, whatever is the largest. Higher stresses will be
considered in each case. The holding period for this strength
The volume measurement equipment, if used, is to have a test should not be shorter than I hour and not longer than 3
sensitivity of 0.1 % of the added volume of liquid necessary hours. The pressure is to be recorded every '10 minutes.
to produce a hoop stress equal to SMYS.
E.3.4 The leakproof test pressure is to be 1.1 times the design
E.1.4 Below are described two alternative methods of pres- pressure. For a leakproof test the holding period should nor-
sure testing. mally be 24 hours. For test sections where 100% visual in-
spection is carried out, the holding period could be limited to 1
E.2 Pressure test method DO. 1 the time necessary to carry out this inspection, but not less
than 2 hours. During this holding period, the pressure is to be I·
E.2.1 The testing sequence will be as follows: recorded every 1/2 hours. For shorter sections. for instance
risers, 8 hours holding period may be acceptable. I
Caliper pigging (normally included> ,
- Filling of test liquid
Stabilization (long sections>
Pressurizing to test pressure E.4 Acceptance criteria
Stabilization E.4.1 The test will be accepted if during the test all pressure
Holding containing components in the tested section maintain their in-
Pressure release tegrity and no leaks are found. Since it is difficult to judge if
Reporting certain small pressure changes could be caused by for inst-
ance temperature changes, a pressure change of ± 0.2 % of
E.2.2 Filling of test liquid should be carried out in due time the test pressure could be accepted, If greater pressure drops
prior to the actual pressure testing (several days). During fill- occur the test will not be accepted or the holding period
ing, steps should be taken to ensure that the volume of air re- should be extended until a 24 hour period with acceptable
maining in the test section is minimized. pressure change has occurred.
87
£.4.2 If the temperature is taken into account when interpret- cations along the section to be tested (e.g. one in eacH end of a
ing the test results. then the Owner has. prior to the test. to long section>.
present calculations clearly showing the effect on the pressure
from variations in the following variables: E.6 Hydrostatic test report
Temperature of test liquid when filling £.6.1 The Owner is to provide a test report for each section
tested.
- Temperature of environment
.- Restraints
The report is at least to comprise
During the actual test. the temperature of the environment
test report as per attached form
has to be recorded at several relevant positions along the line.
pressure time diagrams
The readings to be made every hour.
actual pressure volume diagrams plotted versus theoreti-
cal pressure volume diagram
E.5 Witnessing
- if relevant. all temperatures versus time is to be plotted
£.5.1 The pressure testing shall be witnessed by Veritas. If and included
found necessary. Veritas may have surveyors at relevant 10- certificate of pressure measuring equipment
,.,..
.:t..::
'4.-
~
", 88
{·f,:
" '
Owner.: ....................................................................•............. , .
Pipeline Description: " : .
Testing Contractor: '" ..............•...............'.. , '" " " '" '" ..'..
Construction Contractors. , " . ,i
I
Strength Test Pressure: bar Start of Test: bar End of Test: bar J
Leakproof Test Pressure: 0 • bar Start of Test: bar End of Test: bar
i
Time and Date Strength Test Started: 0 •••••••••••• 0 •••••••••••••••••• Ended: . 0 •••••••••••••••••••••••• , • J
Time and Date Leakproof Test Started: Ended: 0 ••• '" 1
Remarks: 0.· •• • ••••••••••••••••••••••••• 0 ••••••
; .
J
I
.J
~n'!' 1·111 I I