ET PT RTU (PLTU BABELAN)

DATE 11 April 12 April 13 April 14 April 15 April 16 April 17 April 18 April 19 April 20 April 21 April

MOBILIZATION

SURVEY

PLANNING 383 766 1148 1148 1661 2174 2686 2686 2686

ACTUAL 0 0 0 458 996 1148 1148 1148 1148

% PLANNING 14.25% 28.51% 42.74% 42.74% 61.83% 80.93% 100% 100% 100%

% ACTUAL 0 0 0 17.05% 37.08% 42.67% 42.67% 42.67% 42.67%

REPORTING & CLOSING


DOCUMENT

DATE 22 April 23 April 24 April 25 April 26 April 27 April 28 April 29 April 30 April 1 Mei 2 Mei

MOBILIZATION

SURVEY

PLANNING 2686 2686 2686 2686 2686 2686 2686 2686 2686

ACTUAL 1148 1148 1743

% PLANNING 100% 100% 100% 100% 100% 100% 100% 100% 100%

% ACTUAL 42.67% 42.67% 64,89%

REPORTING & CLOSING


DOCUMENT

NOTE:
ACTUAL
PLANNING
ALREADY DONE
S CURVE ET PT RTU PLTU BABELAN
3000 120

2686 2686 2686 2686 2686 2686 2686

2500 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100

2174

2000 80.94 80
TOTAL TUBE INSPECTED

% TUBE INSPECTED
1743
1661
64.89
61.84
1500 60

1148 1148 1148 1148 1148 1148 1148 1148

42.74 42.74 996 42.67 42.67 42.67 42.67 42.67 42.67


1000 40
37.08
766

28.52

500 458 20
383 17.05
14.26

0 0 0 0 0
0 0 0 0 0
12-Apr 13-Apr 0 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr
12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr
Σ tube planning 0 383 766 1148 1148 1661 2174 2686 2686 2686 2686 2686 2686 2686
Σ tube actual 0 0 0 0 458 996 1148 1148 1148 1148 1148 1148 1743
% tube planning 0 14.26 28.52 42.74 42.74 61.84 80.94 100.00 100.00 100.00 100.00 100.00 100.00 100.00
% tube actual 0 0 0 0 17.05 37.08 42.67 42.67 42.67 42.67 42.67 42.67 64.89

LIST OF ITEM:
ITEM NAME QUANTITY SCHEDULE PLANNING REMARK
HP HEATER Inspected on Sunday-Tuesday (16 – 18
1148 TUBES 13-15 APRIL
April 2023)
Inspected on Monday-Wednesday (24-26
LP HEATER 1538 TUBES 17-19 APRIL
April 2023)
DAILY ACTIVITY
ET PT RTU (PLTU BABELAN)

Date Activity Result Constrain Documentation


11 April 2023 Mobilization - - -

• HPH: Cleaning on progress, already done at 05.00 pm.


12 April 2023 • Initial Survey -
Waiting for blowing.

• Stand by (waiting for • Cleaning result rejected by


13 April 2023 -
cleaning HPH) Mr Adi CL

• Stand by (waiting for • The cleaning process of HPH


14 April 2023 -
cleaning HPH) haven’t finished yet

• Cleaning result rejected by


• Stand by (waiting for Mr Adi CL for the second
15 April 2023 -
cleaning HPH) time (at 11.00 am) and
requested to be re-cleaned
16 April 2023 • RFT on HPH 458 tubes already inspected -

538 tubes already inspected. Then, the total tubes


17 April 2023 • RFT on HPH -
inspected is 996 tubes

• RFT on HPH
• 1148 Tubes of HPH already inspected
18 April 2023 • Survey for LPH cleaning -
• 1306 tubes of LPH already cleaned
progress

• Survey for LPH cleaning Cleaning result rejected by


19 April 2023 -
progress Mr Adi CL

• Standby (Waiting for


20 April 2023 - - -
LPH cleaning)
• Standby (Waiting for
21 April 2023 - - -
LPH cleaning)
• Standby (Waiting for
22 April 2023 - -
LPH cleaning) -

• Stand by (Waiting for


23 April 2023 - -
LPH cleaning-)

24 April 2023 • ECT on LPH 595 tubes of LPH already inspected