DATE 11 April 12 April 13 April 14 April 15 April 16 April 17 April 18 April 19 April 20 April 21 April
MOBILIZATION
SURVEY
PLANNING 383 766 1148 1148 1661 2174 2686 2686 2686
% PLANNING 14.25% 28.51% 42.74% 42.74% 61.83% 80.93% 100% 100% 100%
DATE 22 April 23 April 24 April 25 April 26 April 27 April 28 April 29 April 30 April 1 Mei 2 Mei
MOBILIZATION
SURVEY
PLANNING 2686 2686 2686 2686 2686 2686 2686 2686 2686
% PLANNING 100% 100% 100% 100% 100% 100% 100% 100% 100%
NOTE:
ACTUAL
PLANNING
ALREADY DONE
S CURVE ET PT RTU PLTU BABELAN
3000 120
2174
2000 80.94 80
TOTAL TUBE INSPECTED
% TUBE INSPECTED
1743
1661
64.89
61.84
1500 60
28.52
500 458 20
383 17.05
14.26
0 0 0 0 0
0 0 0 0 0
12-Apr 13-Apr 0 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr
12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr
Σ tube planning 0 383 766 1148 1148 1661 2174 2686 2686 2686 2686 2686 2686 2686
Σ tube actual 0 0 0 0 458 996 1148 1148 1148 1148 1148 1148 1743
% tube planning 0 14.26 28.52 42.74 42.74 61.84 80.94 100.00 100.00 100.00 100.00 100.00 100.00 100.00
% tube actual 0 0 0 0 17.05 37.08 42.67 42.67 42.67 42.67 42.67 42.67 64.89
LIST OF ITEM:
ITEM NAME QUANTITY SCHEDULE PLANNING REMARK
HP HEATER Inspected on Sunday-Tuesday (16 – 18
1148 TUBES 13-15 APRIL
April 2023)
Inspected on Monday-Wednesday (24-26
LP HEATER 1538 TUBES 17-19 APRIL
April 2023)
DAILY ACTIVITY
ET PT RTU (PLTU BABELAN)
• RFT on HPH
• 1148 Tubes of HPH already inspected
18 April 2023 • Survey for LPH cleaning -
• 1306 tubes of LPH already cleaned
progress