REV # 02, DOR Concrete Works Only Workmanship
REV # 02, DOR Concrete Works Only Workmanship
REV-02
20/02/2023
SCOPE : CONCRETE WORKS ONLY WORKMANSHIP
MATERIAL WORK-
S/N ITEM DESCRIPTION SERVICES
SUPPLY MANSHIP
A Preliminaries
A.1 Electricity Supply ZAMIL
A.2 Temporary empty Port-cabin related to Subcon Supervision staff ZAMIL ZAMIL
A.3 Temporary furniture to Subcon Port-cabins/ Temporary offices SUBCON SUBCON
Temporary Toilets, washing facilities, Resting Area / Mess Hall / Smoking
A.4 ZAMIL ZAMIL
shelter / prayer area
A.5 Temporary car parking for subcon staff SUBCON SUBCON
A.6 Containers / Warehouse for storing materials ZAMIL SUBCON
A.7 Shifting Subcontractors' Materials from Laydown to workplace SUBCON
Subcontractor's Manpower's Accommodation, Transportation, Catering, &
A.8 SUBCON
Insurance
A.9 Personnel Protective Equipment (PPE) as per specs SUBCON
A.10 Safety signs/materials at Site ZAMIL SUBCON
A.12 Empty Yard for Temporary offices, car parking, workshops, etc... ZAMIL