Professional Documents
Culture Documents
1
Performance Bond
An undertaking or guarantee
Given by a bank, insurance company or
other financial institution (Bondsman)
On behalf of its customer (Account Party)
To a third party (Beneficiary)
To indemnify the third party
Up to a specified amount
In the event of the customer’s failure to
perform his obligation under the contract
with third party
2
Performance Bond
5
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
York claimed 10% of the purchase price
due upon the expiry of the DLP and
costs of repairs.
These claims were referred to
arbitration.
Voltas requested that the PG be
extended. York refused to extend the
PG’s validity.
Volta then proceeded to make a
demand under the PG.
6
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
The terms of the PG:
In the event of York failing to fulfill any
of the terms and conditions of the said
Purchase Agreement, we shall indemnify
Voltas against all losses, damages, costs,
expenses or otherwise [sic] sustained by
Voltas thereby up to the sum of
S$523,000.00 (the guaranteed sum) upon
receiving your written notice of claim for
payment made pursuant to Clause 4
hereof. 7
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
This was further reinforced by Para 5 of
PG which stated as follows:
We shall be obliged to effect payment
required under such a claim within 30
business days of our receipt thereof. We
shall be under no duty to inquire into the
reasons, circumstances or authenticity of
the grounds for such claim or direction
and shall be entitled to rely upon any
written notice thereof received by us
(within the period specified in clause 4 8
hereof) as final and conclusive.
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
The Court found that the wording of the
PG was ambiguous and ultimately
concluded that the PG was conditional in
nature.
Consequently, a breach of the underlying
contract leading to loss was required
before Voltas could make a demand on
the PG.
Voltas could only make a demand on the
PG if and when York was found liable in
the arbitration proceedings between
Voltas and York arising from the 9
underlying contract.
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
In reaching its conclusion, the Court
considered the underlying contract as
extrinsic evidence to assist in the
interpretation of the terms of the PG.
The Court also considered the discussions
between the parties.
10
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
The rationale for the Court’s decision that the
PG was conditional was as follows:
Clause 26 of Appendix 2 of the Purchase
Agreement explicitly states that the PG
shall be unconditional.
However, the word “unconditional” is
nowhere to be found in the terms of the
PG.
The omission of the word “unconditional”
here is an even stronger indicator that the
PG is conditional in nature.
11
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
This is also fortified by the parties
having had the discussion on the terms
of the PG, and the defendant having
had the opportunity to vet the terms
of the PG and suggest changes which
were subsequently adopted.
The defendant did not suggest the
retention of the stipulation in Clause
26 that the PG was to be
unconditional.
12
York International Pte Ltd v
Voltas Ltd [2013] SGHC1
The demand made by Voltas was also
defective in that it had failed to state that it
had suffered loss.
This would have constituted an additional
ground on which am injunction would have
been granted.
The Court emphasized that the doctrine of
strict compliance applied to PG.
An appeal was filed by Voltas against this
decision. There has as yet been no published
decision by the Court of Appeal.
13
Conditional Bond
22
Seek injunction to restrain
the Beneficiary from making
call
Potton Homes v Coleman Contractors (Overseas)
[1984] 28 BLR 19
Dicta of Eveleigh LJ: If the contractor were
unable to perform because the employer failed to
provide the finance (advance payment), it would
seem wrong to me if the court was not entitled to
have regard to the terms of the underlying
contract and could be prevented from considering
the question whether or not to restrain the
employer by the mere assertion that a
performance bond is like a letter of credit……The
23
27
Current Position
28
Current Position
29
Current Position
Fraud Exception
The position remains that there are few if
any reported cases in England or the
commonwealth where enforcement of an
unconditional performance bond in a
construction contract has been prevented on
the ground of “the fraud exception” despite
the frequently expressed acknowledgment
of the principle of such an exception by the
courts. (Hudson’s “Bldg & Engg Contracts”)
30
Current position
Unconscionability
Even after Bocotra, there was still some
uncertainty as to whether the Court of Appeal
had intended unconscionability as a separate
limb or whether it was used interchangeably
with fraud. There were conflicting High Court
decisions on this point.
The debate has now been laid to rest in a
recent pronouncement of the CA in GHL Pte
Ltd v Unitrack Building Construction Pte Ltd.
31
Current Position
32
Current Position
GHL Pte Ltd v Unitrack Building Construction Pte
Ltd [1999] 4SLR 604
On 30 Apr 1998, Unitrack and GHL executed a
variation of the MC. They agreed that NSC
would receive payment directly from GHL and
contract sum revised downwards to $1.96m.
A dispute subsequently arose.
GHL purported to call on PB for $578k.
Unitrack commenced action against AGF &
GHL, claiming injunction restraining GHL from
seeking payment from AGF on PB on the basis
that in light of revision of contract sum, such
action would be unconscionable on the part of
GHL.
33
Current Position
GHL Pte Ltd v Unitrack Building Construction
Pte Ltd [1999] 4SLR 604
Interim injunction applied and granted.
Appellants appealed.
Appeal dismissed. CA held that
unconscionability was a separate ground
apart from fraud for restraining a
beneficiary of PB from enforcing it. CA also
found on the facts of the case that GHL’s
call on PB was unconscionable.
34
Current Position
GHL Pte Ltd v Unitrack Building Construction Pte Ltd
[1999] 4SLR 604
In particularly, they considered the fact that there
was a drastic revision of contract sum downwards by
65% and that after the revision the NSC works were
taken out of the contract and GHL entered into
direct contracts with the NSCs.
Under the MC, GHL was only entitled to a PB of an
amount equal to 10% of the contract sum, and 10% of
the contract sum as revised was only $196k. By
calling on the PB for the full amount of $578k, GHL
was effectively seeking to obtain a sum which
represented about 30% of the revised contract
35 sum.
Current Position
GHL Pte Ltd v Unitrack Building Construction Pte Ltd [1999] 4SLR
604
L P Thean JA: “We are concerned with abusive calls on the
PB. It should not be forgotten that a PB can operate as an
oppressive instrument, and in the event that a beneficiary
calls on the bond in circumstances, where there is prima
facie evidence of fraud or unconscionability, the court should
step in to intervene at the interlocutory stage until the
whole of the circumstances of the case has been investigated
…a temporary restraining order does not prejudice or
adversely affect the security; it merely postpones the
realisation of the security until the party concerned is given
an opportunity to prove his case.”
36
Standard of Proof Required
Bocotra Case
To warrant injunctive relief, fraud or
unconscionability must be clearly
established.
“To allay these concerns, we need only to
note that dispensing with the consideration
of the balance of convenience test does not
make an injunction any easier to obtain.
Indeed, a higher degree of strictness applies,
as the appellant will be required to establish
a clear case of fraud or unconscionability in
interlocutory proceedings. It is clear that
mere allegations are insufficient.” 37
Cases After Bocotra
San International Pte Ltd v Keppel Engineering
Pte Ltd [1996]
D were main contractor for warehouse
project
P was sub-contractor to D
P had to procure PB for 10% of contract sum
Disputes surfaced and P’s subcontract was
terminated
D made a call on PB
P sought to restrain the call. One of the
grounds was D had acted unconscionably.
P sought to adduce evident that D held some
$3m belonging to P comprising certified and
uncertified sums of work done and retention
38
monies.
Cases After Bocotra
San International Pte Ltd v Keppel
Engineering Pte Ltd [1996]
At first instance, injunction was refused.
Whilst P were entitled to require D to set
off certified sums due to them, the other
amounts in their hands were at best
uncertified claims which have yet to be
substantiated.
It was not possible on the untested
affidavit evidence to find that D’s claim
was lacking in bona fides.
P’s appeal was dismissed by CA.
39
Cases After Bocotra
Four Seas Construction Co Pte Ltd v The Tai Ping
Insurance Company [1997]
P contracted with YHS to build factory &
office
Due to P’s financial problems, YHS agreed to
advance monies to P to pay their DSC.
Loan made by YHS amounted to $5.98m
Direct payment to DSC totalled $9.7m
YHS made demand on PB issued by D for
$3.2m to cover loan made by YHS to P
P applied for & obtained interim injunction
restraining payment out on bond. P alleged
demand made on bond was dishonest as YHS
knew that it was not made with regards to
the loan agreement. 40
Cases After Bocotra
Four Seas Construction Co Pte Ltd v The Tai Ping
Insurance Company [1997]
Interim injunction set aside by Tay Yong Kwang
JC
On the affidavit evidence before him, there
was at best a commercial dispute between
parties
Allegation by P concerning under-valuation and
under-certification were nothing extraordinary
Unless P could demonstrate that YHS’s
assessment was so absurd or their documents
in support were concocted or so irrationally
done that no reasonable person could honestly
believe them, P were not even at the starting
gates of establishing a prima facie case of
fraud or unconscionability. 41
BS Mount Sophia Pte Ltd v
Join-Aim Pte Ltd[2012]3SLR3
Facts
A contractor had furnished an on-
demand PB issued by an insurance
company to a property developer
under a building contract.
The developer made a partial call on
the PB as “it allegedly believe that it
was entitled to LD from the contractor
for delay in the completion works
allegedly caused by the contractor.
42
BS Mount Sophia Pte Ltd v
Join-Aim Pte Ltd[2012]3SLR3
Decision
The CA considered the entire chronology of
events leading up to the beneficiary’s call and
found, inter alia, that the call was unjustified
because the beneficiary had not, before the call,
made any “complaints or allegations, whether in
writing or otherwise, of any delay” by the
obligor. Also, based on the evidence, it seemed
to the CA that the beneficiary “did not genuinely
believe that the [obligor] was responsible for the
delay”. 43
BS Mount Sophia Pte Ltd v
Join-Aim Pte Ltd[2012]3SLR352
49
Ban on use of PB?
The calls for abolition of on-demand bonds are
more applicable in UK context where UK Courts
have shown marked reluctance to venture beyond
fraud exception.
Singapore’s judiciary has taken a more robust
approach in enforcement of bond and judicial
vigilance can be counted on to check abuse by the
unscrupulous.
By insisting on strict standard of proof whilst
preserving the latitude to intervene where there
is fraud or unconscionability, Singapore courts
have preserved the commercial efficacy of PB
without detracting from their duty to do justice in
deserving cases. 50
Accounting for surplus monies
Where a beneficiary has successfully made a call
under bond and amount received was in excess of
actual loss, Question arises as to whether he can
keep it or can Contractor recover overpayment.
English court in Cargill International SA and
Another v Bangladesh Sugar and Food Industries
Corp held that in the absence of clear words,
there would at some stage in the future be an
accounting between the parties. What has not
been clear is when accounting should be carried
out and completed. 51