Date W/C What you should be working on…

6th March Pitch/start research/Build Weebly/Statement of Aims


13th March Statement Of Aims due to upload/continue research and planning
20th March RAG project proposals/ Research/Development
27th March Research/Development
EASTER 2 WEEKS
17th April Research/Development
24th April Development/Production
1st May Production/Reflection
8th May Production/Reflection
15th May Production/Reflection / designing and submission of exhibition posters
(template available on Moodle)
22nd May Complete practical element final evaluation for own project/ preparing
for audience feedback (QR code, Forms survey)/ Planning for NR
Exhibition
HALF TERM 1 WEEK
5th June Exhibition at NR/Write up of audience feedback
12th June Planning for LANSDOWNE Exhibition/ Marks to UAL
19th June Exhibition at LANSDOWNE