Professional Documents
Culture Documents
Attachment 6
May 2016
NOVA Gas Transmission Ltd.
Section 58 Application Attachment 6
Boulder Creek South Lateral HDD Feasibility Report
May 2016
NOVA Gas Transmission Ltd.
Section 58 Application Attachment 6
Boulder Creek South Lateral HDD Feasibility Report
TABLE OF CONTENTS
1 Introduction ........................................................................................................................... 3
2 HDD Crossings ...................................................................................................................... 3
3 Design Parameters ................................................................................................................ 3
4 Tributary to Simonette River Crossing ............................................................................... 4
4.1 Watercourse Description .......................................................................................... 4
4.2 Horizontal Directional Drill Alignment ..................................................................... 4
4.3 Laydown Area ............................................................................................................ 4
4.4 Geotechnical Review ................................................................................................ 4
4.5 Design Summary ....................................................................................................... 5
4.6 Specific Construction Risks ..................................................................................... 6
4.7 Contingency Crossing Method ................................................................................ 8
5 Ante Creek Watercourse Crossing ...................................................................................... 9
5.1 Watercourse Description .......................................................................................... 9
5.2 Horizontal Directional Drill Alignment ..................................................................... 9
5.3 Laydown Area ............................................................................................................ 9
5.4 Geotechnical Review ................................................................................................ 9
5.5 Design Summary ..................................................................................................... 10
5.6 Specific Construction Risks ................................................................................... 11
5.7 Contingency Crossing Method .............................................................................. 13
6 Summary of HDD Risk Assessments ................................................................................ 14
7 Summary of the HDD Schedules ....................................................................................... 14
8 Drilling Fluid Disposal ........................................................................................................ 14
9 Water Supply ....................................................................................................................... 15
10 Recommendations .............................................................................................................. 15
11 Conclusions ......................................................................................................................... 16
12 Reference Documents – HDD Design Drawings .............................................................. 17
Appendix A – Stress Summary ...................................................................................................... 18
Appendix B – Annular Pressure Charts ........................................................................................ 20
1 INTRODUCTION
NOVA Gas Transmission Ltd. (NGTL), a wholly owned subsidiary of TransCanada Pipelines
Limited, is proposing to construct, own and operate the Boulder Creek South Lateral Pipeline
Project to safely delivery natural gas to the existing NGTL system in Alberta.
The Project, located approximately 119 km south east of Grande Prairie, Alberta, consists of
approximately 21 km of 219.1 mm (NPS 8), 168.3 mm (NPS 6), and 114.3 mm (NPS 4) outside
diameter pipe. The pipeline will be constructed in two new sections (Southern and Northern
sections) which will tie-in to and utilize the existing NPS 6 Sturgeon Lake South Lateral to
transport gas between the two sections.
The Southern Section of the Project will begin from a tie-in point on the existing NPS 36
Western Alberta System Mainline Extension (WASME) in SE 27-66-25 W5M and will consist of
NPS 8 pipe for approximately 4 km, then reduce to NPS 6 pipe to continue for approximately 11
km and tie-in to the SLSL in NE 19-67-23 W5M.
The Northern Section will branch off the Sturgeon Lake South Lateral in SE 28-68-22 W5M with
NPS 6 pipe for approximately 6 km to tie-in to NPS 8 Boulder Creek Lateral (BCL) in SE 09-69-
22 W5M, and continue for approximately 100 m of NPS 4 pipe to tie-in to NPS 4 Calais
Extension in NE 09-69-22 W5M. Construction for the two sections of the pipeline will be
concurrent.
Within the scope of the Project, two watercourses have been determined where NGTL is
proposing to utilize the Horizontal Directional Drill (HDD) methodology for the pipeline
installations. This report is provided as a feasibility assessment of site conditions, incorporating
the provided draft geotechnical information and a geometric review of the proposed HDD
alignment and design.
The proposed HDD design drawings and this feasibility report will be reviewed and revised upon
receipt of the final geotechnical report.
2 HDD CROSSINGS
This report will assess the feasibility of the following HDD installations:
Tributary to Simonette River Watercourse Crossing (SW ¼ 26-66-25-W5M) – NPS 8
Pipe installation
Ante Creek Watercourse Crossing (SW ¼ 4-67-24-W5M) – NPS 6 Pipe installation
3 DESIGN PARAMETERS
The HDD crossings are designed to incorporate the geotechnical information provided,
Pipeline Research Council International (PRCI) PR-227-03110 guidelines, access
specifications, above ground/buried facilities in the area, watercourse geometric
parameters and space limitations.
The geotechnical conditions at the site were considered in an effort to design the drill for
progression primarily through formations that are favorable for horizontal directional
drills, methodology of construction, industry practices, environmental risks, and
engineering tolerances.
beyond the 8 m depth of investigation. A 1.3 m thick zone within the clay (till) contained frequent
coal pieces/ rafts, at a depth of 6.3 m.
Similar stratigraphy was reported at the location of BH03, with a thin layer of topsoil, 0.7 m of
sand and 2 m of clay overlying clay (till), which extended to the 20.2 m depth of investigation. A
0.5 m thick gravel deposit was reported within the clay (till) at a depth of 9.8 m.
At the location of BH04, near the planned exit area on the northeast approach, 5 m of clay (till)
was underlain by sand, which extended beyond the 12.7 m depth of investigation.
The near-surface clay overlying the clay (till) in BH02 was described as firm, low plastic (high
plastic below 1.4 m depth), sandy, with trace gravel below 4.5 m depth. The near-surface clay
in BH03 was described as firm to stiff, low to high plastic, with sand. The clay (till) was generally
described as low to high plastic and firm to very stiff, with trace amounts of gravel, sand and
bedrock fragments. The sand, encountered at depth in BH04 was reported to be poorly graded
and compact to dense.
carried out by CCI indicate that a wall thickness of 8.2 mm and Gr. 359 steel is suitable for this
crossing, based upon the operating conditions supplied. A summary of the stress analysis
calculations is attached in Appendix A.
The following is a summary of the design of the Tributary to Simonette River HDD crossing:
Zone 2: 70 – 360 m MD
Risk: The drill path passes below the depth of geotechnical investigation. Formation
properties may be different from what was encountered in the geotechnical
investigation.
Mitigation: Continuous monitoring of drill performance, including annular pressure and
cuttings return, should be maintained. The Contractor shall attempt to complete
the crossing by utilizing the mud motor downhole tooling to mitigate any possible
bedrock conditions.
Risk: Fracture to waterbody.
Mitigation: The drill path has been designed to minimize the risk of fracture to waterbody.
The contractor shall closely monitor the annular pressure to ensure it remains
within the designed pressure curve. If the annular pressure exceeds the
theoretical model, the contractor shall trip out the drill string to reduce the
pressure and ensure no fractures occur.
Zone 4: Pull-back
Risk: The possible presence of gravel and cobbles along with the unknown
geotechnical condition suggests that the pipeline may become damaged during
pull-back.
Mitigation: The pipe coating for this crossing will be Fusion Bond Epoxy (FBE) System 2B. It
is expected to provide suitable protection from corrosion, moisture, abrasion and
impact damage. Extra care should be taken to ensure a clean and open hole
prior to pull-back. The borehole should be proven with a wiper trip prior to pipe
pull. Additional wiper passes may be required.
interbedded clay and sand layers encountered at depth in BH08 underlying the clay (till) were
stiff to hard and compact to dense, respectively.
It is important to note that an artesian groundwater condition encountered at approximately 36
m depth, at the BH08 location. An artesian head pressure of 1.5 to 1.8 m was observed by the
field personnel. The head pressure of the artesian conditions is less than entry elevation and is
not expected to flow to surface.
squeezing can block off the hole around the drill stem causing poor cutting
clearance and annular pressure spikes.
Mitigation: A proper drilling fluid management plan by the HDD contractor should be utilized
to minimize the formation of mud rings. If issues are still experienced, mechanical
swabbing may be required.
Risk: It is expected that the HDD borehole will penetrate through clay (till). Although no
cobbles were observed during testing, clay (till), by definition, comprises a
heterogeneous mixture of all soil types including a random distribution of cobbles
and boulders. The possible presence of cobble and/or boulder sized material
along any drill path through the clay (till) should be expected.
Mitigation: Properly sized equipment should be used to help minimize deflection while
drilling the pilot hole.
Mitigation: A proper drilling fluid management plan by the HDD contractor should be utilized
to minimize the formation of mud rings. If issues still arise, mechanical swabbing
may be required.
Zone 5: Pull-back
Risk: The possible presence of gravel and cobbles along with the unknown
geotechnical condition suggests that the pipeline may become damaged during
pull-back.
Mitigation: The pipe coating for this crossing will be Fusion Bond Epoxy (FBE) System 2B. It
is expected to provide suitable protection from corrosion, moisture, abrasion and
impact damage. Extra care should be taken to ensure a clean and open hole
prior to pull-back. The borehole should be proven with a wiper trip prior to pipe
pull. Additional wiper passes may be required.
Detailed risk assessments of the Tributary to Simonette River Watercourse and Ante Creek
crossings have been completed, summarizing the possible construction issues that may be
encountered. As discussed in sections 4.6 and 5.6, risks and mitigations have been identified
for these HDD installations and, if mitigated properly, the risks are manageable.
Overall Schedule
Task
Tributary Ante Creek
Mob./Rig In 1 Day 1 Day
Pilot Hole 4 Days 6 Days
Swab and Pullback 1 Day 1 Day
Demob./Rig Out 1 Day 1 Day
Total 7 Days 9 Days
Assumptions:
The schedule is based on 7 working days a week.
The schedule is based on working 24 hours per day (2 shifts per day).
Standard production rates with minimal fractures.
Drill and pull methodology.
Tributary to Simonette
120 53
River
Assumptions:
The contractor provides adequate recycling systems.
Assumes minimal loss of circulation to provide a conservative disposal estimate.
Drill and pull methodology.
9 WATER SUPPLY
It may be possible that water for drilling purposes may be withdrawn from the watercourses.
Alternate sources, such as nearby municipalities, should be investigated and Temporary
Diversion Licenses obtained prior to commencement of construction.
Tributary to Simonette
163
River
The volume is based on the estimated initial water requirements, dilution rates, HDD
schedule, and the final borehole size.
The water required for the pretest of the pipe sections has not been included in these
estimates.
10 RECOMMENDATIONS
The following recommendations outline the main action items that should be completed in order
to ensure a smooth progression of the project into the construction phase:
a) The HDD design shall be reviewed and incorporate any new data from the final
geotechnical report, once received.
Tributary to
HDD 1559-EG-01-A 1 of 1
Simonette River
The pipe section installated stresses are modelled in 5 sections (exit tangent (5), exit arc (4), bottom tangent (3),
entry arc (2), entry tangent (1)) incorporating effects of buoyancy, soil friction, curvature, fluidic drag and pipe weight.
The calculated stresses are evaluated using the AGA method (PRCI). Operating stresses incorporate hoop, bending,
tensile, and thermal expansion.
Variable Definitions:
SMYS - Specified Minimum Yield Strength
D - Outer Diameter of Product Pipe
E - Young's Modulus (Steel)
t - Wall Thickness of Product Pipe
0
Tensile Stress: Allowable Tensile Stress % of Allowable
5 9.5 MPa F(t) = (0.9)* SMYS 2.9%
4 11.6 MPa F(t) = 323.1 MPa 3.6%
3 11.6 MPa 3.6%
2 13.3 MPa 4.1%
1 13.2 MPa 4.1%
The pipe section installated stresses are modelled in 5 sections (exit tangent (5), exit arc (4), bottom tangent (3),
entry arc (2), entry tangent (1)) incorporating effects of buoyancy, soil friction, curvature, fluidic drag and pipe weight.
The calculated stresses are evaluated using the AGA method (PRCI). Operating stresses incorporate hoop, bending,
tensile, and thermal expansion.
Variable Definitions:
SMYS - Specified Minimum Yield Strength
D - Outer Diameter of Product Pipe
E - Young's Modulus (Steel)
t - Wall Thickness of Product Pipe
0
Tensile Stress: Allowable Tensile Stress % of Allowable
5 19.5 MPa F(t) = (0.9)* SMYS 6.0%
4 21.4 MPa F(t) = 323.1 MPa 6.6%
3 21.3 MPa 6.6%
2 23.1 MPa 7.1%
1 22.1 MPa 6.8%