SCHEME COMMISSIONING PLAN AND PROGRESS

Sr. No. Item Discription Engineer Scheme status DG Shifting status


1 Noorpur Gautam Pump lowering done Shifted
2 Jamunamau Pranav Pump lowering done Shifted
3 Rasid patti Bibhakar Pump lowering done Shifted
4 Rahimganj Asif Pump lowering done Shifted
5 Lakhauri Abhay Pump lowering done Shifted
6 Hunhuna Gautam Pump lowering done
7 Pastamaphi Gautam Pump lowering done Shifted
8 BABHANIYAVAN SOHAWAL Y.Verma Pump lowering done Shifted
9 LAHRA PUR, PRANAPUR Sohawal Abhay Pump lowering done
10 MAHMUD MAU Rudauli K Mishra Pump lowering done Shifted
11 AKHTIYAR PUR Rudauli Asif Pump lowering done Shifted
12 HARIHARPUR BALIYA Rudauli Pranav Pump lowering done Shifted
13 TALAGAON Rudauli Bibhakar Pump lowering done Shifted
14 PHELSANDA, SHAHBAZ PUR Rudauli Asif Pump lowering done Shifted
15 FIROZPUR MAKHDOOMI Rudauli Ali Afjal Pump lowering done Shifted
16 CHANDRAMAU MANGA Mavai Bibhakar Pump lowering done Shifted
17 HARIBHANDHANPUR SOHAWAL Abhay Pump lowering done
18 DAKHIN PARA, TANDWA Sohawal Abhay Pump lowering done
19 Saitalohani Sohawal Abhay P1
20 LOHATI SARAIYAN Rudauli Ali Afjal P1
21 KALAFARPUR SOHAWAL Abhay P1
22 TEEKAR RUDAULI Ravi P1
23 FATTAPUR KHURD Rudauli Ravi op run
24 KOPAKANP, NEOTI Rudauli Ratan OP&Comp
25 Bartara Mavai Guatam OP&Com
26 Dilwal Mavai Guatam OP&Com
27 Kushahari Mavai Guatam comp run
28 Sultanpur Mavai Guatam op run 40% LP
29 Dashrath mau Rudauli Ravi 10% Laying Pend
30 Betauli Rudauli Ratan 25% Laying Pending
ESS
Connection from DG to pump
Done
Done
Done
Done
Done

Done

From electricity

Done
Done
Done
Done