Professional Documents
Culture Documents
Author:
Mohamed Desa, Mohamed Nor
Publication Date:
1986
DOI:
https://doi.org/10.26190/unsworks/5039
License:
https://creativecommons.org/licenses/by-nc-nd/3.0/au/
Link to license to see what you are allowed to do with this resource.
NSW,2093
M. N. xMOHAMED DESA
M. ENG. SC. PROJECT
1986
WA
TER REFERENC
E
LIBRARY
rcpy
W'XTFR RF'^TARr.H lAnORMORY //' WATER
UBUMV'
¿¿"sTrS! manly VAi.L, NSW,.
M. N. MOHAMED DESA
M. ENG. SC. PROJECT
1986
WATíí! LAHORATriRV
•'" ;! (vrw V ' r- : »,i re
l l )
5iTUDI:N'rS DECLARATION
.. _ . . ^ ^ £ T /y)OHA/)nEÙ ^OR. fnOHAnr^BO OBSÑ
A) D u s is to certify that I
being a candidate for the degree of Master of Engineering Science
am fully aware of the policy of the University relating to the
retention and use of higher degree projects namely that the
University retains the copies of any thesis submitted for examin-
ation, "and is free to alloW the thesis to be consulted or
borrowed. Subject to the provisions of the Copyright Act (1968)
the University may issue thè thesis in whole or in part, in
pKotostat or microfilm or other copying medium".
I also authorize the publication by University Microfilms of a
600 word abstract in Dissertation Abstracts International (D.A.I.)»
B) I hereby declare that none of the work in this project has been
submitted to any other institution for the award of a higher
degree.
Signature
SUPhRVISORS CERTIMCATION
Sigikature
(i)
TABLE OF CONTENTS
Page
Table of Contents (i)
List of Tables (iii)
Acknowledgements (iv)
Abstract (V)
Page
2.2.5.4 Hydraulic Data Base 34
2.2.5.5 Minor Drainage System - Design
Procedure 41
2.2.6 Australian Rainfall and Runoff
- 1986 46
2.2.6.1 Introduction 46
2.2.6.2 Hydrologie Models 46
2.2.6.3 Hydraulic Models 46
2.2.6.4 Steps in Design and Analysis 47
REFERENCES
APPENDIX
(iii)
LIST OF TABLES
ACKNOWLEDGMENTS
ABSTRACT
1 .1 Introduction
CAUSES EFFECTS
Intensely developed
business, commercial and
industrial areas and ^^ ,Op
areas where flooding
would cause serious
damage or inconvenience.
Other business, commercial
and industrial areas and
intensely developed resi- 10 to 25
dential areas.
Sparsely developed resi-
dential areas and areas such 1 to 10
as parks and playing fields.
2.1 Introduction
There are several mathematical models by which a drainage
system can be designed. The degree of complexity depends
upon the nature of the problem to be analysed. A clear
distinction must be drawn between design methods
and simulation methods. The former is able to calculate
the pipe sizes required for a new drainage system, given
the design storm, the layout of the network and other
descriptors of the catchment, whereas the latter analyses
the performance of an existing system or an initial
design produced by applying another method.
Among those models, four of them will be reviewed in
this chapter. Two recent design procedures (manual methods)
will also be reviewed and applied in a case study with
the objective of assessing their simplicity and applica-
bility as a general method for urban drainage designers.
q(T) = (2.2)
10
where:
q(T) = peak runoff rate per unit area
T = the recurrence interval, in years
t = rainfall intensity averaging time
a
Equation (2.2) implicity emphasizes that the design
peak runoff rate is expected to occur with the same
frequency as the rainfall intensity used in the computa-
tion. Schaake, et al, (1967) made the most thorough
modern examination of the Rational Formula as a statis-
tical model in which he said the equation (2.2) is
approximately correct. The value of C in the above
equation was determined from a frequency analysis of
rainfall and runoff. In Schaake's work on urban catchment
C was then related by regression analysis to the imper-
vious area and slope as the independent variables.
In a survey conducted by Cordery and Pilgrim (1979)
of the use of Rational Method they found that the
estimates of peak rate of runoffs are generally low
compared with the derived values. The principal sources
of error they said are the computation of runoff coeff-
icient, C and the calculation of time of concentration,
t .
c
For drainage systems in which the contributing area
does not increase uniformly with time, the highest peak
of runoff rate may be produced by design storm whose
duration is less than the time of concentration. This
is known as partial effect. The occurrence of this
anomaly is illustrated in Figure 2.1.
Application of equation (2.1) to both areas yields the
following ratios of design discharges :
Q1/Q2 = iixAi/i2XA2
=(Ai/A2)(il/i2) (2.3)
where :
Cy = FFyXC^o (2.4)
where:
FFy = Frequency factor for particular
recurrence interval.
14
t^ = (min) (2.5)
where:
where:
L= length of reach (m )
n= Mannings roughness coefficien t
S= surface slop e
P= rainfall excess (m/h )
General Specifications
Type—specific purpose
Catchment size—less than 5 square miles
Computer language—Fortran IV
Parameter representai.ion—lumped
Processes Represented
Land Svirfaces
Impervious areas lUinoff considered solely from directly connected impervi-
ous areas
Flow routing By time-area diagram based on flow times obtained from
Manning formula
Subsurfaces
None
Channels
Basin configuration Subdivided into reaches of contributing paved areas and
channel sections
Flow routing Continuity equation and Manning flow formula assuming
uniform flow conditions
Time interval of calculation Variable option, specified b y the user
Applications Civil engineering design—urban storm drainage network
design or redesign of existing networks
Limited to basins with predominant paved area for
design storms of 2 to 20-year frequency
Input/oiutput Design storm hydrographs of rainfall and runoff for
smallest time interval available, output of observed
rainfall and runoff, together with computed runoff for
storm periods—output is printed and plotted
Calibration No calibration is involved; input is physically based
20
Theory.
The Illinois Urban Drainage Area Simulator is a single
event model adapted from the British Road Research Labo-
ratory storm sewer design model. It has the capacity to
route runoff flows through a sewer network and it treats
the paved and grassed areas seperately, as depicted in
the flow chart of Figure 2.3 (Kibler,1982).
The model was developed to overcome some of the
shortcomings found in the TRRL model. It allows for
runoff from three types of surfaces on each sub-area:
READ B A S I C DATA
AND D E S I G N STORM
READ CARDS
FOR NEXT REACH
COMPUTE PAVED
A R E A . HYDROGRAPH
COMPUTE GRASSED
AREA S U P P L Y RATE
COMPUTE TWE
GRASSED AREA
HYDROGRAPH
C O r a i N E OTHER HYDROGRAPHS
T R I B U T A R Y TO T H I S P O I N T
STORMWATtR MANAGEMENT
MODEL (SWMM)
NJ
Evaporotion
Figure 2.5ryiuc;il Urban nriiinaj'c System Model Tor SWMM - Diay rainnui t i c
28
/ V
30
2.2.5.1 Introduction
This method is the outcome of Australian Road Research
Board project ( F.S. 1 093) which was initiated in 1979
entitled "Urban Stormwater Collection Systems". The aim
of the project were:
1) To identify those practices about which
there is general concensus among practitioners
and for which there exists a satisfactory data
base.
2) To identify new procedures to replace existing
practices where such new procedures are considered
necessary and/or appropriate.
3) To indicate directions for new (or continuing)
research to improve and/or expand existing data
base to a generally satisfactory level.
In 1981 , Argue produced a report covering many facets
of urban stormwater drainage design, in particular the
great variability of practices which exist across Australia
for reasons of climate, topography, different types of
development, local custom, maintenance difficulties,
availabilitiy of materials, etc. Eventually a draft on
urban surface drainage design handbook was prepared.
The scope of the handbook is limited to systems of
surface drainage lines and underground pipes whose area
is limited to around 20 ha. The Rational Method is used to
estimate design flows. The design aspects covered in the
handbook are as follows:
1) major/minor drainage design philosophy
2) influence of modern roadway construction
techniques on gutter inlet geometry
3) stormwater conservation and public safety
consideration
4) economic consideration.
The following sections will review briefly some of
the more important chapters of the handbook in which
other detail can be referred to.
31
FULL-AREA
TIME
Where:
C = weighted runoff coefficient
w
A = sub-area (ha)
and
(2.8)
(EIA)part = • + Cp.Ap (ha)
tc
Where:
C^ = runoff coefficient for imper-
vious or paved area
32
Where:
i = design storm average rainfall
intensity (mm/h)
Roof-to-gutter flow:
residential roofs = 5 minutes
commercial/residential
roofs = 10 minutes
= 3.0XRD-5.0 (2.10)
where;
RD = residential density (excludes roadway
reserves, nature strips, etc.). Valid
only for RD<20 residences/ha.
1) Mannings formula
(m/s) (2.11)
and
2) Izzards formula (modified)
(L.S"'') (2.12)
where:
V = flow average velocity
n = Mannings "n"
R = hydraulic radius
SQ= channel bed slope (m/m)
F = shape correction factor = 0.9
Z = reciprocal of channel cross-slope
d = maximum flow depth (m)
spread,w
K
Q, °t-OF
Manning "n" = nB
Manning n = n.
1/2 (L.S ^)
Qp = 375.F ^A - ^B
(2.13)
8/3 ^ 8/3
= 375.F - dg ] +[ZB/nB] So,1/2
(L. '' )
(L.S
(2.15)
where :
Reynolds number
K
= Vq-DO/v
Figure 2.8.
39
Table 2.4 (Australia n Road Research Board, 1985 )
GUIDELINES FOR MANAGEMENT OF UNDERGROUND-MOVING FLOWSIN DEVELOPED CATCHMENTS
DEFINITION OF TERMS:
" Mdin drain pipeline (or "mainline") conveys flow between sub-area node pits of network
' l^^t^iJj'jri^jil i conveys flow collected from, nonnally, more than one inlet to junction pit located onr
r^in
oraJnpipenne
" Cross;Connection pipes convey flow from, normally, single inlets to junction pits located on main drain or lateral
pipelines. Cross-connectio n pipes are usually shorter than 10 m.
PART1
minor roads (carriageways less maniu m): the y should connecib ucv-c
eu.i
.-^y uLic/- w.ie; v^^i H
side-entry and grated inlet types) located along the drainage path. Th e alignment should favour
the carriageway "high side"in dual channel roads and streets. "Lo w side" inlets on dual channel
mino»- roads should be connected to the line either by inter-inlet cross-connections or by.deviating
the alignmentif necessary. Th e alignment should be just within the carriageway where inlets are
grated and just outside where side-entry inlets are used.
The alignment in single-channel minor roads should be on the "low side" of the street.
major roads (carriageways 10m or greater): mai n drain or lateral pipelines should be located
within carriageways between 1.5m and 2.6m from the "high side" kerb. Gutte r inlet pits should
be cross-connected to on-line junctions.
The alignment in single-channel major roads should be on the "low side" of the street.
Guideline2 Every effort should be made, including the use of angled cross-connections where otherwise
unavoidable, to space on-line junction pits as far apart as possible.
Guideline3 Inspection pits spaced at intervals of not more than 100 m'should be includedin all long,
uninterrupted pipelines of diameter 1050 mm and smaller.
Guideline4 In all gutter inlet pits and junction pits, design water levels assigned to pits should be not
higher than:
Guideline5 Regardless of the provisions of Guideline 4, design water levels assigned to consecutive pairs
of pits on main drain or lateral pipelines should differ by not less than 0.10m in the direction
of flow.
Guideline6 A 3-poin t priority sequence should be followed in assigning pit design water levelsin accordance
with Guidelines4 and5 :
priority1 : junction pits along lateral oipelines including the pits where thesepipelir.ei join
with main drain pipelines
priority2 : junction pits along main pipeline branches, where these are present
In each priority, assignment of pit design water levels should commence at the uostrear.e
xtr
e^.
iity
in1 and2 an d at the downstream extremityin priority 3.
^priontteii
Guideline7 A minimum pipe size ofD = 300n un should be usedin the design
Guideline8 Asa practical design rule, pipe sizes (diameters) snould not decreasein the directior. of flow.
Guideline9 In order to reduce the likelihood of blockage asa result of sedimentation, flow velocitiesir. pipes
operating under design conditions should be not less than 0.5 ms'^. Flow s which leadto violations
of this limit should normally be excluded from the underground network.
Guideline 10 Diameters of cross-connections may be selected from EITHER the table below OR may be set equalto the
diameter of the pipe conveying flow from the connected mainline or lateral pipeline junction pit,
whicheveris smaller.
Guideline 12 Pit floor levels in mainline or lateral pipeline junction pits receiving flow from cross-connected
entries must allow for slope of not less than 0.01 in cross-connection pipes. Pit floor level
should coincide with the invert of pipe D^.
Guideline 13 Where concrete pipes are specified for the underground network, class selections should be i
r^d
e
as follows :
More detailed information is contained in the graph below, supplied by the Concrete Pipe Association
of Australia.
\
S
-5
1
1 71 1
50 2:
A/<;?
4
-5
7-
\
40 r
1 j
TfP^ rnc T/^
3
-5 !
\
i
1
3
-0
'1
r'''
—
¡3 2-5
cc
: X
I
—
LJ Y AF-p-}^
£20 X ! 1
T
1
bJ
a. 1
i
^ 1-5
\ i '
cc
\
>
o >r ' TR r/^
OB
\
>
o 07
\
!
/
0
-6
0
-5
T
- N
\
V \
<•
1
k
0
-3
»A in o
<vj r— a
V9 CO o
^u ^ iO 23
AWL
' '
'"'
HTG
rLT— -
- BWL
'^o'Qo
D.
where :
tr
ifi-d
lj iitic
t.io
n pit(s ini
ji l
e) systems: Figure (a) INLET/JUNCTION PITS WITH GUTTER FLOW
'rjtcsontsa gciu'ral,s TiDple junctTon pit layout with
itrcair, Idterdl dnd grating inflows, Qy, Q, and Qq 1
respectively. B y assigning values to these parameters, CODE DLSCKIPTION <
"G" w
oil possible simple junction pit configurations can
be uc-scrlbed. Fiaur e (b)isan elevation section
•.ri
ruuyh tne pit taken along the alignment of its
I-l Inlet pit with outflow pipe - -
\ 4.0
L'l^chorge pipe. Th e value s listed are based on the Inlet on through pipeline
findingsof Sanyster etal (195S) known as "Missouri
Charts". I-2A - 2.0
I-2B
° "u^O o % s
ofa
e 0.5
j J-3
B ° offse
t laterals 2.0
1
43
]
. JUNCT
ION PIT WITH SINGLE ENTRY/EXIT PIPES
int¿«'sexiiOív
Case 1 situations :
point
PLAK rectangular pits, K = 2.0; circular pits, K = 1.5
w w
Case 2 situations :
Case 2 ;Entry pipe centreline intersecting side
wall of pit rectangular pits, K^ = 2.5; circular pits, K^ = 2.0
Case2 : K =2.5 (with or without gutter flow) (i) in situations where the risk of property inundation
w
is highly sensitive to uncertainty in pit loss
Kcbearch suggests that hydraulic shaping of pits to estimates, values for K^ should be obtained from
assist the passage of flow from entry to exit can be hydraulic models of pipe/pit installations tested
effective. under design conditions; and
(ii) in all other situations use IC = 3.0, with or without
Pit dimensions : Small pits, generally, result in gutter flow.
swller hea'Hlosses than large pits.
cír^idí^^u. • research by 4. NiCH
OI,S-WATTS FOmHAE
íTG.íTácT e n
-:T.L. Pingott o f Queensland Institute
of Technology, when compared with the results of An unpublished report by Nichols, Watts and Associates,
hare (1983), show marginally improved performance Consulting Engineers of Liverpool N.S.U., proposes a set
of formulae which enable headlosses to be determined for
for circular pits in situations which would
any arrangement of pipes and full-barrel flows included
otherwise, i.e. using rectangular pits, fall into
in Tables 7.3 and 7.4. Values determined by the formulae
Cases'1 and 2 above.
show close agreement with results obtained by Hare (1983)
Internal shaping : "Benching" of pits to provide a but are less satisfactory in their reproduction of head-
curved channel DQ/Z deep between entry and exit pipes losses for the cases investigated by Sangster et al
(see sketch) can reduce values obtained in Case 2 (1958, 1959). It i s considered that the Nichols-Watts
situations from 2.5 to about 1.5 (Archer et al, 1978). formulae underestimate significantly headloss i n the more
It appears to make no significant improvement in '-omplex pipe/pit and multi-pipe geometry cases.
Case 1 situations.
44
G
TABLE.6
STELP FIGURE GAv FIGURE. 6& FIGURE 6 C
1 \
STtP
sUB-cATCH^^t^rT
FLOW
COR.R.LSPOKDIMG
COiAPlLATtON
7
OlSTRl&UTlOM FOB. OTHE R
n&URL A & TKbLt1
SU&-CATCHfAENTS
FIGURE.7
STEP G L\HtS
STEP Table.-
GllKES
Z
- 7-2-
3 - G'hne
-1-tar:
C
TABLL
STtP
4
\
I
—I
5TEP STEP
1=3 TA&Lt4
riGUR^ 4 A
FlOURl 4 B 10 LOA
$TAGLZ F
IGURE l
O FlGUfLE, \0 A
!r
i'—
I KYDR-OLOGIC/VL
,
—' J
i1)
J
DitP /AOD£L PlMAL DESIGK -
T=l tZ D STA.GE1 COMSTR.UCHON
-0
I\
STEP DRAW\HGS
a l = ]
FIGURLS N
46
2.2.6.1 Introduction
3c>
- y — ^
m .
v-
£7-1 OZ <7-3
10(7
iZl«
^ilkiilii
¡itili
PÌÌpEÌI
Figure 2.10 Gutter Flow Design Charts for ^50 mm Width Gutter
(Australian Rainfall and Runoff, 1986)
49
use Mannings
equation, -
Q = 1/n A.Rr-^s'/^
calculate I for
assumed total time
calculate,
Q = C.I.A/0.36 (L.S ^)
where •
calculate.
^design = Q .(0.6+0.4P )
end con
(L.S"'')
calculate.
flew velocity and gutter
time of travel (mins.)
>f
calculate,
= t n + gutter rime of
^overland overland ^^^^^
1t
YES
3.1 Introduction
The Australian Road Research Board, 1985 and the
Australian Rainfall and Runoff, 1986 methods of urban
drainage design described in chapter 2 were applied to
a case study area in Maroubra. Although the two methods
are not yet in final form, it is hoped that the results
of this case study will provide a comparison between
each methods in terms of their generalities and ease of
use. Each step of the two procedures is followed closely
so that the merits of each method may be determined.
Figure 3.1 shows the case study area (26.22 ha) which
is considered to be an "isolated" urban catchment. The
top part of the area is steep and the remaining area being
relatively flat. The existing land use in the catchment
is residential with a density of about 15 residences per
ha. The area is in ultimate urbanised condition.
The first analysis uses the Australian Road Research
Board, 1985 design procedure of urban drainage systems.
Both major and minor systems were designed for the sub-
area B within the study catchment. Figure 3.1 shows the
sub-area B boundaries.
A major system design with Average Recurrence Interval
(ARI) equals 100 years was used in conjunction with a
minor system with ARI equals 5 years. This combination
led to a "gap flow" design ARI equals 50 years for the
surface-moving system by assuming that partial blockage
of 50% occured in the associated underground pipe.
In this case study using the Australian Road Research
Board, 1985 design procedure, it was assumed that major/
minor drainage systems have not been so far designed.
This would give opportunity to apply the design procedure
from the begining.
51
riyxi
' iZ-
t v ' i r J u ' r-.-, \i L,
(^krt-i
i vr'i l,/ini
ilili-J -
/•ii! f.o 1:1-rc;-; , fi' - "i k at V ^
iv /A4--'' i
c: i
^ y T i
!
1
L..
L • -
Node point 1
Flood escape network V • --
Dual channel
Sub-area boundaries
< "jrr
Q sc= (TA.
i' 50 (L/S) (3.1 )
0.36
Where:
Q = storage-corrected capacity
so
flow in flood escape path
(Table 9.1B of handbook)
^50 = average rainfall intensity
(mm/h)
TA^ = tributary (impervious)
area (ha)
rearranged,
TA. = 0.36Q
1 sc
1 50
= Q.sc (ha) (3.2)
416.7
ADDI1DNAL NOTES
, Catchment location :
Maroubra Junction
Contour plan of catchmt. :
see Figure 3.2
Roads :
16 m & 20 m roadway resrves
10 m & 7.5 m carriageways,
kerb & gutter, concrete;
width = 375 m ; Za = 8
pavement, hotmix; cross-
slopes Zg = 30 & 40
7.5 m dual-channel Stormwater d i s p o s a l p t .
carriageway in 10 m c o i n c i d e s with B.
road reserve , pavemen|t Residential land use areas :
cross-slope ZB=40 design r/d , 15 res./ha
stonnwater passes to fron-
ting gutters.
Adopted design ARI= 5 yrs.
Road. 0.2P
S=0.603
B.I (node point)
F i g u r e 3 . 3 Sub-catchment B details
of d i v i s i o n s .
61
B
.2N1R B
.2E1
R
"v \ \
^
J
B.2E2
^ ^B.2E1
B.2
4 Inspectio
n pit
( see Guidlin
e 3
, Tabl
e 2
.4 )
B
.1N1R jI
i
j nspectionpit
B
.1W1R
B
.1W1 .1E1
.
1
NOTE :
Pipe location fixe
d by Guidelin
e 1
,
Table 2
.4 - ma
jor and m
ino
r roads
DRAINAGE LIN
E CONVEYING
W FLOW TO REM L INLET
INA
>
H w
a^ PQ• '
s
o >
• Hpc; £ H
EH
w
p E
H
« S
^ H H EH W FF
I P
tiKl
^ O W
w 0 EH W D 2 H EH K < S >H W •-Q \
s > 2 C H
E
OP O fa REMARKS
i s S a EH < cu
TH
ff H
O
EH H
U
H
<
U w ^ U S O W H I So
S 0 c O H S W( J > H V
-
w TH w
P^
Z E
H
H O
O W
^ U H o—
H F
Ö "
faO
O
H £ HiJ
w < o w EH
< 1 H H
s <
S H
< W H H W U S
u c >H H - O « O C W
u 1 1 EH 04 U CCI F
I
4 W <c < H U I
-Q pe
í ui
EH PQ C Q E-I EH 5 W Q PC ; c H H E
H < fa' o « o 1< TJH
C D s Di
J O W >H D( J >HO O fa wq H < tó C
U W W W U Q ff i CO U <•< EH U EH fa H W E H u u U Ü
1 2 3 4 5 6 7 8 9 10 1 1 12 13 14 15 16
B .
2 NODE 101
.30 - -
N1R 101
.33 1
0m rd
.paved 0
.31 D 255 20 225 0
.05 ZB=40 60
N1 101
.33 1
0m rd
.paved 0
.31 D 255 20 0
.05 ZB=40
255 60
/ha0
residí.15res .82 D 255 20
E1R 101
.50 1
0m rd
.paved 0
.06 D 65 1 0
.02 ZB=40
32 70
/ha 0
residí.15res .64 C 32 1
E1 101
.30 1
0m rd
.paved 0
.06 D 65 1 .002ZB=40 100
65 0
B 1 NODE 98
. .4 - - - - - - - - - -
N1 98
.81 1
0 .paved
m rd 0
.24 D 220 2
.5 0
.006ZB=40
220 80
/ha 1
residí.15res .23 D 220 2
.5
El 98
.8 1
0 .paved
m rd 0
.13 D 65 0
.4 .003ZB=40
0
65 90
/ha0
residí.15res .5 D 65 0
.4 -
N1R 1 98
.711
0 .paved
m rd 0
.24 D 220 2
.5 0
.006ZB=40
220 80
residí.15res
/ha 1
.73 D 220 2
.5
W1R 98
.61 1
0 .paved
m rd 0
.13 D .5 280 0
280 2 .003ZB=40 90
W1 98
.61 1
0 .paved
m rd 0
.13 D 280 3 .003 ZB=40 90
.7 280 0
Notes :
Road surfac
e - pave
d firs
t grad
e
15 - Approac
h flo
w fo
r 95
% captur
e i
s obtaine
d
from desig
n curv
e fo
r a combine
d inle
t o
f
2 m sid
e entr
y an
d 1 m gratin
g ( D
.P.w
.
report No
. 207
,197
7 )
.
63
LEGEMD :
C = concentrated contribution
D = distributed distribution
• = gutter i n l e t
—o- = inspection p i t
= main drainage pipeline
Ta
ble3 .4 F l owE st
im a
tio
ni nP r
im ar
yD rai nageL i
nes:N =5y rs
.
p r
im arydarai- TIM EC F EW I
R
Y aj
ii
p.rainfa
lli n
t. cai
ip
o t p
n rimar
yo o
nt -
n agec o n
ttr i
-c xmp
one
ntt ra v
eltimec h.o ru /gp ipet uD
tali nm
/
h for are a ( E
IA
)^O to
t a
l f
lew
a rea toch.oru /gp ip
e trav e
l to en
t. pte c
avistor
md ur.= o r g •
H
i
a
t.( 20
)o
r(21) e quiv •
H r
H
E
H •co
H ve
rlan dallotmntgut
t er u/g pipe Pt
.
' So • • S• ^4 J
H 1 f
lo
w d
rain n a
t uralt r
avel an
]a
l.fu l
l-part- fH rH H full
-part-• B
EMi
mS
area area 1
1
H U channel •
H an a
l.anal. a
re aarea r H
§^ 4J N N 1 f orf o
r
1 c
u
i i|
rH 5 (T
J
1t
(
i
0 are a
§ r
H
S
1
MH
s 0U5
N
y
=
rs
.
N=
5y
rs.
0
M)0
)
If M
- 0 1 1r
l( H
i
H iH .
H H H
P
i 5y r
s5y r
s r
H
R L.S^11
"
iii £^b (
0- p• HIMI p i w r HH -l'J a
m
inm n irmmi i
i
nmmn inm mm inmJ i hah a L
.S~
1 234 5 6 7 891 01 11 213141 5161 71 81 9202 1r 2n
2n
/hmn
t
2i
/3h 2 4 2 5 2 62 72 82 9 3 0 3 1 3 2
I / O /
X
V
•2R floo^
N fo^cc
t
- - -.SS2
2 02
— é6 / 7r ns • 34 'è
f • 3
/ /S
I iS
i /
A
/^
J-
eT
iE
y
e/
V)
/A/
A
ÉNt to^ f^y^a-dL
- - - —
AoìkU S
r. - - 3 - —- zo 2
- . 6 - ¿
-h
4a — •3/• 3
/ ù>
^odU / S
" .S - IS- - 2,0 2
- . — — /
- 77 - •4
/Z i
cu m .sTOAI
f^ AA. O
I>J '77 114 iGh To
rta
i, 33^> / A
/
o£
-/ V,
/A/
Ar
e
.o r
Bi fOm
f
i. / - 3 - — - / - — ^ ns- — n
s- •oé> ¿> <7oO-EA l/A
/
ATS
/S
-
- f^
— a - - n- 7 114
- - - C 101
/ O
/v» /2 -
E!
f^'OCul - - z -
- - - é n
s - ns
-- ^o (>
— •o
r ¿> </O
D
B> N
to
I /I
ccu
t B
r-• - - - - - - zxo 3 - - '
2
.7 '
24
. ¿>
/
vA
«
a
T»
'. - - - — - a - - - n 7 '62 0
CA t
ri S
7 eA
7fO
r^1 7 114 TOT
/KL >&
) 7
e
<«
/V
7INATS
E
f tonn
AOAU fS
i- — - - 3 — - - / - - é •14
- •f3 o
5 - - /
S
" - - - i
rS-d
. - — 07
IT
I >
S
7OA^ 2A
r 7 114 yoT
fi
su /
7S > 9o i
/^oeTe
fZr^ /
/V
AT
S
N
I /O
r^
Afi^Xeut - - - - - aio 3 - - - 6
- »^7 '9
^
fi
it
'ct
t
s-
s
-— - /
s
-— — — — — 7 '
•3 •
7 r•8
?
CA iT
tC S7OA
/ 2A
7F n 7 /
/4L f
ia
i. TO
TAL I
'
ll 3
rj. >
¿0 IF^OERSA
/yy /
/VA
r
e
W/fO n
A^octo po^nd
d /S tBn 3_ 23C d 2
.— — - é> n
s OS '
/r 3•
•
/ /
3 tS
! /S
I' >90
W/fi^oe^d Aft^iC
to /V
I P^
— - - 3 - _ — i
ic - - n
s n
s .IS •
/
3Ò fS
/ '£1 > tNùE
r&i
/^t
i^A T
c
i
i
65
V,
63
63
63
V.
63
63
r
63
V
25 17
24 148
S.
24
B.I
120
99
30
1 20 99
|30 |ii
I
120
> 99
11
60
99
•l30 11
LJ
108 43 66
s».
43
108 43 12
A
B.2'
43 NOTES:
120>^» = captured flow L.S - 1
8
£ £ w
I
\1
IQ
1 H ü -P•
H U-P-
H 5 5 5
^
H BH
2 P M ^ -P S
< h
cn S w 5< hCO 2^ t/)U
Z H Q r< Ö ^i-i
1 26 g | g tt-91 ^ >1h in^ H 11-9 >1^% IT^)
sw cn S W PM i p II < II icu M 6P ISI ^ II
C \
1 2 3 4 5 6 t-73 8 9 1 0 1 1 1 2 1 31 41 51 6 17 18 19
B •2 ^OiK^cLpCü^tcL
V
Ä// *
E/p. pco^d 6 (p h
fy
Ä
•2 iE/ lÄÄAi ü G .¿»iT • CT• ! •)
S.z
£2
17 r l-fi Iii S'u/
i'/lJ) JCoo Ö-2
& • / Fk. ^
S i/ß i.
Nt Roo^ct P>CKA/<A
1/ ^ •H
Ei
n 7 •JS" '¿r ¿6
r iCi
• U^pu.j' i
Rtfa,f<~
NIH ly •i? •rr ¿.¡S
W/2 f^ti^cl u
.'IL.
W/ n »1 y u 73 •
^63
63 '
63 •
[126
63 1
N
63 ' 189
•
,63
63
63 252
,126
25 ' 19 f315
24 148
1 475
M72
24
1
1
194
' 521
120
108
108
108
1102
Figure 3.6 Design flows in all pipe
components
( not to scale )
69
Table 3.6 Pit Water Levels, Pipe Diameters and H.G.L. Analysis
PIT WATERLEVEL
£ 10
9
» Q) 5 RiMARKS
gline glineassndtrial vel. f
H
^
V^/2g
^ £
4 5 water pipe V K fN a
4
J
r
sj £ BWL &
pipe & pit in.
levels fixed
0 w r^O i
level dia. 5 n m adop hydrau
i by Guidlines
r^O g
s
-ted -lie 11 & 12 tables
S §
^
T
B C
O
• £ H
table table (AWL)
D°
dia. grade (^-f)
8ii
g s fi line except where
1 B t— r
g S^ +
i M
-
S
l<
a S H (m) (m) (m/s) (m) 0 J
G
r
— (
N indicated
r^O 5-i (m) (m)
1 H p
i i e (m) (m)
11
'
^^ > J
Jo i -
U
(0 4
J
U1
B •
H
D I
jA/
)
-
W § i J i
i s
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
&WL.= AWi.- ,-A
/.
'S
:
f>ipo
6 •
2U I-4.Z ¿3 bO .
cjr / /
/-i
-g '
'dCC
- V04i •/
79 Z-/ • gy -
5-9
:1 '3oc
N5 fOi-g^no^e s•iis
ro r-dd c /
iS 07-g9
/O^.OOr /S'^Pi fSfOgg .
7pi Pi^ iOg- j
-i/
q
/ og
- S
TJPi- /
N/^ to^.
ifS
•- o
-i:
A/4 0 • o^ 10%.^i; O
-iT •^SG ^
io-
) /
•£>
5:4
•a'
O/ V4- iSxs - loy^
ls
N
i So pg i-97 •976 /OS
,. po^
ff^n
O -/o
iS ' OS i
'^S fQb-
lXS' •vro •/60 •
10^
.(aS /o^. • Ta
iT o
-c •
lit 'c
?7SJ
'X/
\ lS to
t- C
MJ^
-^/
Vvo
.
/oa»g 3«J
7 L
a '
•73 • •S
'
AJX S' •C
f JL.
OO 100•
toh io ys
/>-Ay/ K
JhSS OS f
cpa
N! P
'P-t O oi^
lOf
.f
i eg /
•gr zoo
- 6a
fof-3S A
//- 6J •
/B" Z-3A
S
NodU lOhog /^P
ilNP
'P^L
-l AMC^H O
) fVC
yP
l^TA
/OO
./o p it
EiRi P 'P^
/O .tre
f iRi-e
iR. /Of
.go— /O t
-S-Q ^
•OjL a0 • q '4
-lh /^Sx (
S00 fo
• r^i»x^
thio^
c
/fi
. /
o •c
oat
.c/
.fs/
o/. /<
?h/
i:•
¿/S
o OQ IOC
-
30 •
£/
•ox /o
i 3;
-/ o
/.0
5"/
OA0
5 '
/A. OS •0¿
i-•
¿5/
0 •
033 1- •o
<i3 •
4S0 lOO
- -4.
2f^
-f-
ip^U
NoeU,S.: -40
(no Q
VUL
. /
TOA
/AJP
ipeu v
/e
^ T
/o/
v^
100-
/0
P
iPeiiA
- -'
e /
\NC,H > 8-2 -
No <Lt.
6.:
i
-k'To
'f>;b
B> /oo-/oU i
tK ' Af
P'h- 5-i
/iS .oo6 - - l
-^o 0 • •643 • ^ ^ '
¿00 O
Vvf
^/o
—J
B /NtO)r
f Art
j' f>
p
ipe. • /69 •/
ot T- 1 •/40 /
•/o I
/ -
A/S-
A/76 3
/a- •oo6
s o
-x •
A
/7 /
>./
)«(Jp
.
)
¿
fi
A
/
p
'7
p^- 7 S-
/5 A
. OS" lOA • Oi ' /8
i
7
Nh pi
'pe. U)P. 4/
u
ji'
riy g.-h
p/
fA ^<
10 0s
: •J
-00 l
-jv
fi
T yy .ot
/• //
N
/>~ A/
j
70
Table 3.6A Pit Water Levels, Pipe Diameters & H.G.L. Analysis
P
IT WATER LEVEL
£
J REMARKS
C
M SB
gline g
line assnd trial vel. ? ^S
v^/2g i pipe & pitin .
ON 5
4 5 water p
ipe V K 4J BWL & levels f
ixe d
0 w r^O 0^0 1
ina adop hydrau by Guidlines
table table level d
ia. J
E
Hi < -ted -lie 11 & 12 tables
T Q° s
g CO i
) 2 4) (AWL
( ) ?1 dia. grade )
• J § m <
E
H J"5 x:- - line except where
H f
N
H« (m
) (m
) (m
) (m
) (m/s
) (m
) 0• CNJ indicate d
8 C
U H 0^0 (m) (m)
i e I
I 4J 4J
i
w > 10
^ •
H^ w
8 É Si 1§ Da • ii
il
i
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A
/5- J-
AiO/V
AX5 99-/o 99 OS
o •ooé.
/ A.i o-s: ,//i J-
J.A - /• vL
f. iiib •
75-
0
N5~N4-
A/4 J-
.P.to/
fi
t
l^r^
'pipa
pè
fyt
•75X
? 2
,! ¿>
0 •
Jo-s J-/ /
•03 •750
/V4
-/V
3
Nh
03 9-
f-
P
'PC
. /I .00
6 •v
ro 0
.3- •3/f .0^
7 !'064- 1 ./So ! i2 /•
iyx •750
J
.f
ì.ùoi
tU
ouo si.
/
/?/ •006 •750 0
-5- •Ih
i J
NO
.' r^
i
X.0
0 •oq-x •/O
:L •
'94 l-s
, f-
iòa
N
i .U
J^P i
.f^
9-f i>g
P
tpe
. a
-
N
i- £»
/ io 'OoG 97- 6
7
•9
cX5 • 07
0 I
'^XO
E
t p
i>^
/rA
8 -
P
'p^ io
ji •
003 «0
7 •/
s-/ •509 / 0-
li 0.40/
/ •
iCT
O /•
rg
E
! JF oo
ifk
.
9P-47
fO
.•003 /• 0-r I-X6
•U
S-o /•
J
Jo og 97-69
/
€fPi'
i
6 7 o
f. -
p/p^ /
o I- /
102 /
•0 • •O
l^ •
\
rJ1 J-p
.UJ
i'
tt,
9.
/
.0 •r •C
SV • 02
-6 • •XS
'é 97-93
W»-P
,/ Ho
71
LIST Or SURrACr:; \V!iH ROUGilN' Si, U:-0:wr.
r.iii
K) Jf! '.->01 ;,;•.>
fxtco:.!. or v.;'.;, or cOuUu-}.
bfViuotn ll J r,
CIRCULAR. PIPES
ROUGHNESS FACTOR k = 0,3 rnrr»
72
B
.2N5
126
JP1
63
i219
B
.2N4
252
<3
.2N3
Figure 3.8 Desig
n flow
s in
V315 all pipe
s L
.S-
I
JP2
378
B
.2N2
441
B
.2N1
25
V475 B
.2E1
R B
.2E1
R
148^
172
B
.2
197
521
.B
.1N
8
631
g B
.1N
7 (IP
)
120
751
B
.1N5
981
90
37
B
.1W1R
'
'l0
8
B
.1W1
110
74
50 m
300 mm
15 m
10 m 300 mm
3 7 5 riTTi
32 m
3 7 5 mm
50 m
375 im
10 m 8 m
, 300 mm 450 mm
22 m 34 m
4 5 0 mm ? n n nrm^
34 m
3 0 0 mm
88 m 4 m
525 mi li 4 5 0 nm
25 m
10 m 6 0 0 mm
5 2 5 mm
O
37 m
6 7 5 mm
'20 m
6 0 0 mm
10 m
525mm
10 m
6 7 5 mm
24 m
6 7 5 mm
12 m
675 mn
10 m
•—450 mm
22 m
10 m 21 m
750 urn
300 nin 3 7 5 iTiTi
10 m
375 rmi
12 m
3 7 5 mm
106.68 m
75
108.25 m
105.60 m
103.20 m
102.62
101.90 m
100.65 m
101.13 m
100.23 m
100.25 m 100.90 m
98.90 5 100.15 m
<98.38 m
99.06 m, ¿98.08 m
97.85 m
98.53 m 97.70 m
¿97.50 m
97.50 m
97.25 m
98.22 m
97.61 m
76
N
•7
\\
\
\
ts-
9 , —
12 11
13
Duration (Minutes)
6 7. 5 10 15 20 25 30 40 50 60
2 YR ARI (mm.h ^) 1 48.0 137. 6 123. 5 103.1 89. 2 79.1 71.4 60. 5 53. 1 47. 7
t.i-o-'' 44. 3 53. 8 68. 7 95.8 120. 6 143.6 165.4 206. 4 244. 9 281 .6
100 yr ARI (mm.h"^) 258. 9 240. 7 21 6.0 180.5 156. 2 138.4 124.9 105. 8 92. 8 84. 4
Ratio 2:100 • 57 • 57 •
57 .57 57 .57 57 • 57 • 57 • 57
Fraction Impervious 00
from tables:
F = 1.41x1.75
= 2.47
Inspection of the Intensity-Duration-Frequehcy table
indicatés that a decrease in duration will increase
intensity by a factor of 1.1. Thus overall factor used
was 2.47x1.1 = 2.72.
The computation of design flow rates for major and
minor systems is presented in Table 3.9. The design flow
rates for individual pipes are presented in Table 3.10.
Table 3.11 shows the hydraulic design computation of thé
underground pipes. Figure 3.^12 shows the imformation.
extracted from Table 3.11 .
80
Table 3
.9 Desig
n Flo
w Rate
s fo
r Major
/Mino
r System
s PIT INLE
T MAJOR SYSTE
M
EOCV.
FLCW T
IME
S I
IMP.AR. CO
I I CO
w w w w
"
e
•
S V
D
B C
O•
H E
h
c
rv o O
h
CO CO
RHMAE^
i
? I
s S
a 6
00
a
s
C
O
gI
CO
< <
u
11 •
i g
ai H
e
u H u u a •
CQ
N
8 1 011 12 13 1 4 15 16 17 1
8 19 21 22 23 24 25 26 27
P
/r/ /
sg '
/So 23 •9
/5
C
t^i
i
' o
s^o 72 >0
o
j
-c^
a.)
Cp
aHi
'c
,!
Z
/S-
X
11 '3x
o 0
S2) 2 ^ /a
- ¿»
eg o
.u
<
?D
X> q
r-i
Uf
ir
Jj
z
:2-
j
•
11
f
i^O
CUi To •
/gr a
t
/
^/
f- J
L .
/ro i
C
* 756 O
./C
L i
^l
'cJ
r c
^itU
.Q /
^o O
C r-r(
'
(T
O o
lo 6y •
LCfO 9/ 60 /
•a
- ZT
iJ
f
^Si
ad. /
s
CM- 60 •
C7
S-
0 Xo lo O
^Lf 0
3t ib
S 4
.) 4/ 2 4
i /
•a
- 6
.0 O
.
/t,
p
/t M
l oU
fh
f
i^a
JL 0
^0 IQ
, •?
o Xo
if>
109 2^ /i
/ 60 cii
z wi-
f
'U £ fU
^icd 4
$ o
/b /7
7
CH- , /
^oa
^ 0
2 76 07a O
JTo fS
-4 3? - o
¿)¿2
-2 is fo ¿
».A
:.
=
c
/dl ¿-
J«
CM- 006 6a ar 9/
C o
- (>
oY H
a
81
Table 3.9A Design Flow Rates for Major/Minor Systems PITINLET MAJOR S
YST
EJy
i
BQIV.
FLOW TIMES
IMP.AR. CO CO 1 I
I CO CO
CO w W W h
i
¿ 5 d
C g
•H V
D
E o
^ r
o f I I
Eh
U E
h 5 o H
CO CO
REMARKS
5 C
l^
I§ H CO
O
a
a 6
C
Q
g I < u ^
E
h 0
H
CM
Q
H U U
u I
I
<
y
^
§
P
Q È
»
8 10 11 12 13 14 15 16 17 18 19 20 2
1 2
2 23 24 25 26 27
r
iè'
f
locxT
cL oo
t. ù>
i •
i p
c^- ¿KK
f ecL
,
2J2 "mr
i
P
it0 • oo^ in •^
is
i 9o 0
-u,
.
li/^f-
i
t! /
ay 177
^
/•¿
ci:
, o
/x
f
ioc
ini c
ch i
r? >o
Pa r f^
'sd
l inn io 7
io \7
C;
91
y
y ion
Lpo^
t- 8r
/
f
loCLo
t r ro
P
ii Q i
lo r/
( ^h f^CKO
i so yo 094 r
y IS
^cX
oo6 S/ 2 lè
sr go /
¿i.
7
=/c
;a;
fi»r8
f^
ici
l no ÒO
(, .
59 r
^/
(Hi- 0 <
tG • /ÌO
7< 7
/
/
ay - ioo 77/1
-
yi f^
r I /a ^o /Oéc
17 /
67 /
//6
7 % 7
c /
J.O /If
82
Table 3.9b Design Flow Rates for Major/Minor Systems PIT INLET , MAJOR SYSTEM
EQIV.
FLOW TIMES IMP.AR, I
CO CO
I I
¿
CO CO CO CO
•
H S KD
E C
O• I
H B C
O
EH CO CO
REMARKS
S
"I? •
g S 9
H a I
5 •'
a 6 a
E
h H C
O H• ^
• C
6
C
O O
g 1 < <
u
II^ I
^ i
0
4 H U U a •PQ
O
Q
8 10 11 12 13 1 4 15 16 17 18 19 20 21 22 23 24 25 26 27
•
Oj
sr
/
A X f
/ l^ 7o 1^ 9
c?
7
/x/
.;
9o C < i
t ^ to
¡ft
'G
2^
/
¿O /
¿o ^f/o
n oa^ op ODS go
Cha
-
Oo^ K^X OS 2
.t^ fo
i^to ^
P /cCI Ho ooi>
EL
C ^
It- ^^o
ckJL8o OPS Ub •
"To •oo^
7
83
Table 3.10 Design Flow Rates for Individual Pipe {Partial-Area) PIT INLET MAJOR SYSTEM
BQIV.
FLOW TIMES
IMP.AR. CO CO I I
CO CO
CO in w CO
.5 VD
I
H ro Qh
CO CO
REMARKS
5 04
& 6 o a
5
i
H
H • r"
Eh H CO H n
• • Ui X
g I < < pc:
u II I p
s i
PU H U U w a PQ
m
8 jT 12 h3 14 15 16 17 18 T9 20 21 22 23 24 25 26 27
A/xe 9 /¿2
l^o
V-3
if (Xo A /-i«/i^o
g99
-i-L
(Oh C>rx
TJaT ¿,00
9-g
io-n fy^ rt
/ra
Pi'f^
fH cs-^
/a -/3>
/4 io^
84
Table 3.1 OA Design Flow Rates for Individual Pipe (Full-Area) PIT INLCT MAJOR SYSTEM
EQIV.
FLOW TIMES I
IMP.AR, CO CO I
I CO CO
CO CO CO CO T
¿
•SB 5 VD
H m Eh 1 I
o
CO CO
s
cy\
W a RHyiARKS
CI*
& 6
5
g%
o H
W E-i H CO H• ^• Pn
W CO g
g I
w
< < U ^ CO
Eh
H
S
Q
u II ^
CU H u u IAJ a CP
PQ
8 10 11 12 13 14 15 16 17 18 19 ZO 21 22 23 24 25 26 27
PiflSl
/- i y^r
XLfO
P'f^ '9fo
A - 3,
P/fie. ^ f6o
P/p.
7C> ¿3
/i^e-
3 ' G UZc^
6/ 1!
9 - i
Pipe.
fO-l\ 3/
-OS,
H h /3
P.'fx^
Tx-tb
n-fi^
85
Table 3
.11 Hydrauli
c Desig
n o
f Undergroun
d Pipe
s
U
/S INVER
T LEVEL
S D
/S INVER
T LEVEL
S
r
o (m) (m
)
I w
i
REMARKS
I
w
J
§
00
H Q
Z;^ 5
5 T C
N CO
§
a
f
vj
c
r> vo CM
I
a
c'i
I
H u u ^ 00 S
i —
H H ^ r
o
0 H (
N KD C
N Qro
W 0
4 C
U M <
N
C
N W
pjh
i• C
O
< I CÑ
w
T
a w w C
O g C
O
H •»
w H »W C
OS >i
n S o
c
u D D B ffiC
O C
O Q H(N
fe 0
4 -
8 1
0 11 1
2 13 14 1
5- 17 1? 19 2
.P 21 23 2^ 2S:
(
z-n /O
^- 7
5
'
•97 tob
.ys to6
.é>o 4-
'o /-
or 0/03 •36X tog- /
o - - 7
3^ 033
S
"/ ^
7
:1- /
OS"
-/o /rs
" too
.- <
7/6 /o
i.S
V --
Oá /o
/,¿
¿i
" oro
/o
í^.
ii
r
i
j^o
/
o /02
. c^S-y fo
:L. (% /OX
.5ó fox
. io
o/o/
•77
7 lofni^ 0
/0
39 •
iOc fO
i.60 .Oéo CO/ .oo^ /oxS^ /
COL
.eo/o
r /.
£=3
2
.61 •i6¿ /o o/
a-T oa
.
,ao /
OX
- O
/;
; iS"- •0
- S 3 fo
f- S
^J.
3-6 -
to
f. 6í>r
TTT
7-
6 C
7é 04
.4. n av^ 67a - %
9g
.
•¿
>3 2
/^
é-S
,
'OC
f. ¿
ra. es fb
l 0
({ h H
i, 9B Q< ib
i - • - c
-0/0
/
o 9? éé
i fS
.lcC
f -
- O-CO
')
9x.9
/0
•éo
o O
ÍT 0
/4 •C
f.0
/ 92 O
IX J
iSC ?
f3 - '9
'iS
,
97
-^í
a o. ooé
9
7-9
7^ 9?.r
ían
'WTT
-
' 9
2-X»
lo -K 1\ ¿
fo o
.Olí ¿
s'. 'Sé
., D 0^2
.
9
7- 9
7-¿
o
- •Oi 9q.
09,9á.>C /
•s
- co4 03 /
Se 9í-2SO ¿
3.C
/2
7
7 "7-
.faM9 r
?.-
» '
/^
•¿rr
f
rrTT
<4a
M e
j
ls: •
3SV ¿í
.o Olt e
ro g
92 97. 7a7 •S is
' oco-¿
9?. 97.ró^
86
105
.43 m
35 m
375 m
m
104
.24 m
51 m
375 m
m
5 m
101
.77^m
10 m ^^01.76 m
300 m
105 m
425 m
m
11 m
98
.67 j
p 300 m
m
98
.60 m
LEGEND
105
.43m= pit inver
t
104 m level
575 m
n
10 m
97
.98 nk—
325L
_n
25 m 97.92 m
600 Tok
'1
0 m
19 m 300 m
m
97
.60 i
f
l 300 m
m
97
.57 m
97
.42 m
4.4 Conclusions
The final results of the two methods (Figures 3.10-3.12)
are different because:
* different ARIs were used.
* in the ARRB method, it was assumed that the minor
system did not exist and therefore the design procedure
could be basically followed step-by-step whereas for
the AR&R method, design was based on the existing
location of the inlets and pipe layout.
Had one value of the design ARI for the minor drainage
system been used for both methods, the end results would
invariably be expected to be very similar since
both methods employ the same theoretical concepts. However,
the AR&R method presents an alternative design tool using
the enhenced ILLUDAS model called ILLSAX. Finally it can
be concluded that the AR&R method is more flexible than
the ARRB method.
REFERENCES
R. 1
FRENCH,R.,PILGRIM,D.H.,and LAURENSON.E.M.-Experimental
examination of the rational method for small rural
catchments.Civil Eng. Trans. I.E.Aust.,vol.CEl 6,1 974,
pp95-102.
KUICHLING,E.-The relationship between rainfall and the
discharge of sewers in populous areas.Trans. ASCE,vol.20
,1889,No.1,pp 60.
0 50 65
Drainage length from terminal i n l e t (m)
A.3
B.1N1R
Flow a c c u m u l a t i o n and c a p t u r e g r a p h s f o r d r a i n a g e
l i n e s t e r m i n a t i n g a t B.1N1 and B.1E1 - 90% c a p t u r e d
flow.
400
300
m
'¡J
200
Cn
100
-I !•
50 65
Drainage length from terminal i n l e t (m)
A. 5
B.1N1R
400
B.1N1
y f ,
t .'i
tWßM
•y
.. A
' '"Im
' S . • . r
t <' " ir
w
-f m
- ' „ - • -
-, -f
m
• vx - rJ
I v ' i ,
lfm
, i , • ^
'tis? , )
ß
j - V
t S M
: ^
4 ' ' i
• ; ij
l . t