The document provides status updates for various road crossing projects, including which pipes have been completed, are ongoing, or have not yet started for different road crossings and carriers. It also notes the remaining distance to push pipes for some projects and reasons for holds on certain projects, such as permit issues.
The document provides status updates for various road crossing projects, including which pipes have been completed, are ongoing, or have not yet started for different road crossings and carriers. It also notes the remaining distance to push pipes for some projects and reasons for holds on certain projects, such as permit issues.
The document provides status updates for various road crossing projects, including which pipes have been completed, are ongoing, or have not yet started for different road crossings and carriers. It also notes the remaining distance to push pipes for some projects and reasons for holds on certain projects, such as permit issues.
RC-8 DONE carrier current status(12M PIPE) on going (12M PIPE)
ON GOING 5TH PIPE 6TH PIPE
N/A 2ND PIPE 3RD PIPE
ON GOING 1ST PIPE 2ND PIPE
N/A 8TH PIPE 9TH PIPE
N/A 7TH PIPE 8TH PIPE
not started yet 5TH PIPE 6TH PIPE (5m)
remaing pushing(mtr) since last week, not finshed pushing 6TH PIPE 24m out of 76m due to permit issue preperation on going for 3rd pipe, already 66M out of 90m lowered hold since last month due to some permit 153M out of 165 issue
62M out of 158 on going 9th PIPE already lowred
89M OUT OF 173M hold since 2 months
need to check this RC whether they pushed
need one more pipe for CP clearance 6th pipe for clearance or not