You are on page 1of 5

The Use of Mini-Horizontal Directional Drilling

for Placement of HDPE Pipe in Water Applications


Lawrence M. Slavin

U
ser-friendly guidelines for the placement horizontal directional drilling (mini-HDD)
of high density polyethylene (HDPE) technology and typical project characteristics. Lawrence M. Slavin, Ph.D., is president of
pipe with mini-horizontal directional The document reflects the latest industry infor- Outside Plant Consulting Services, Inc., in
drilling equipment have recently been developed mation and also includes new information on Rockaway, N.J.
by the Plastics Pipe Institute (PPI). Technical Re- HDPE pipe selection methodology.
port TR-46, “Guidelines for Use of Mini-Hori- Figures 1 and 2 illustrate typical mini-hor-
zontal Directional Drilling for Placement of izontal directional drilling (mini-HDD) equip- length, and placing pipes of 48 inches or greater,
High Density Polyethylene Pipe,” represents a ment, and pilot boring and back reaming at depths up to 200 feet. Maxi-HDD machines
comprehensive set of information that can be operations, including placement (pullback) of may weigh as much as 30 tons, or greater, and are
used for water applications. The new document the product pipe for water applications. appropriate for placing pipes under large rivers
is intended to provide information analogous to Mini-HDD is typically employed for boring and other major obstacles.
that provided in ASTM F 1962,“Standard Guide segments less than 600 feet in length, at depths up The ASTM F 1962 provides recom-
for Use of Maxi-Horizontal Directional Drilling to 15 feet, and placing pipes up to 12 inches in di- mended procedures for the placement of HDPE
for Placement of Polyethylene Pipe or Conduit ameter. In contrast, maximum-horizontal direc- pipe using maxi-HDD. It provides overall guide-
Under Obstacles, Including River Crossings,”but tional drilling (maxi-HDD) technology is capable lines, addressing preliminary site investigation,
at a level appropriate for the less complex mini- of accurately boring holes thousands of feet in safety and environmental considerations, regu-
lations and damage prevention, bore path layout
and design, implementation, and inspection and
site cleanup. One of the significant contributions
of the document is the provision of a rational,
analytical method for selecting the polyethylene
pipe strength based on the estimated installation
and post-installation (operational) loads on the
polyethylene pipe. The ASTM F 1962 therefore
provides a means of determining project feasi-
bility, as well as initial design information.
While the ASTM F 1962 guidelines are con-
venient and practical to apply by experienced
engineers for a maxi-HDD operation, the cor-
responding equations and procedures represent
relatively complicated formulas, and an exten-
sive tedious methodology, when considering
Figure 1 Typical Mini-HDD Equipment and Pilot Boring Process smaller, lower-cost operations associated with
typical mini-HDD applications, including those
associated with placing a new water distribution
line. Nonetheless, some mini-HDD installations
may be considered to be relatively critical with
respect to the capability of the available drill rig
and/or the strength of the product pipe being
installed, and for which a relatively convenient,
although possibly less precise, design procedure
would be desirable. Furthermore, any construc-
tion procedure must address basic safety rules,
avoid damage to existing facilities, adhere to ap-
plicable government regulations, and consider
environmental issues. Report TR-46 was there-
fore developed to serve as an inclusive docu-
Figure 2 Typical Mini-HDD ment, providing practices for placement of
Back-Reaming and Pipe HDPE pipe for various applications, using mini-
Pullback Process HDD. The document is available via the PPI
website at http://plasticpipe.org/pdf/tr-46-hdd-
guidelines.pdf.
Report TR-46 reflects the latest industry in-

36 • OCTOBER 2011 • FLORIDA WATER RESOURCES JOURNAL


formation and also includes new information not applications, such pipe may be used for convey- equipment-related risks during mini-HDD op-
readily available elsewhere. For example, easy-to- ing various other fluids (natural gas, oil, etc.), as erations. Employees must be trained to prevent
understand guidelines are provided for proper well as conduits for containing utility cables. injury to themselves during the operation of the
drill rig positioning that are consistent with meet- equipment and be prepared to mitigate acci-
ing required placement depths and drill rod ca- P re l i m i n a r y S i t e I n v e s t i g a t i o n dents, so electric power and gas line strikes are
pabilities, as well as for estimating the relevant The general feasibility of utilizing mini- specifically addressed. Although not considered
forces and effects present during installation, al- HDD technology for placing the proposed to be hazardous materials, the proper handling
lowing proper selection of the pipe strength. pipeline(s) must be determined prior to any pro- and disposal of drilling fluid is also discussed to
posed construction activities. Such a preliminary avoid possible environmental issues.
Report Details investigation is required to gain an understanding
of the local characteristics in order to help ensure Regulations and Damage Prevention
Technical Report TR-46 contains several a cost-effective, efficient and, above all, safe oper- This section addresses the second category
main chapters or sections, briefly described ation. Of particular importance, and as addressed of potential safety issues, focusing on proce-
below. in other sections of the guidelines, is the aware- dures to eliminate or reduce hazards associated
ness of existing utilities in the vicinity of the pro- with damaging existing utilities, such as initial
S c o p e , R e l a te d In d u s t r y posed pipeline and the need to maintain boring or backreaming operations. Recom-
St a nd ards a n d Ter min o lo g y minimum specified clearances during the con- mended practices include: “call before you dig”
The TR-46 addresses planning, design, drill struction process. (811); properly locating and marking existing
rig setup, and installation practices for the place- utilities, as well as exposing such utilities at an-
ment of polyethylene pipe using mini-HDD S a f e t y a n d E nv i r o n m e n t a l C o n s i d e r a t i o n s ticipated crossings with the bore path; avoiding
equipment. The primary focus is on commonly Safety is a primary concern during any ac- mechanized digging within the required toler-
used high density polyethylene (HDPE) pipe tivity, including construction utilizing mini- ance zone; and the use of subsurface utility en-
with a material designation code of either HDD equipment and procedures. Potential gineering, as described in CI/ASCE 38,
PE3608 or PE4710. Information is also provided safety issues fall into two general categories: (1) “Standard Guidelines for the Collection and
for pipe of medium density polyethylene those directly related to the setup and operation Depiction of Existing Subsurface Utility Data.”
(MDPE) PE2406/2708 material. Depending on of the mini-HDD equipment, and (2) those as-
the diameter, polyethylene pipe may be supplied sociated with the proper location, identification, Pipe Design and Select ion Considerat ion s/
in continuous lengths on a reel, or by discrete and marking procedures intended to avoid con- Bore Path Planning and Drill Rig Setup
segments, which would typically be fused to- tact with, and damage to, existing utilities. This These two sections contain new informa-
gether in the field. In addition to water supply section provides practices to avoid or minimize Continued on page 38

FLORIDA WATER RESOURCES JOURNAL • OCTOBER 2011 • 37


Continued from page 37 tions. For water applications, any mud or de- ameter to wall thickness. The TR-46 guidelines
tion that is not readily available or in a con- bris that may have entered the pipe must be indicate that essentially all the commonly used
venient format elsewhere. This information is expelled, the pipeline flushed, and the system wall thicknesses for HDPE pipe (i.e., DR 7.3 to
discussed in greater detail below. pressurized and checked for leakage. DR 17) would be sufficiently strong for depths
to approximately 15 feet—the typical limit for
Im p l e m e n t a t i o n Pipe Design and mini-HDD installations. Thinner walled pipe,
It is beyond the scope of the TR-46 guide- Selection Considerations such as DR 21, are normally not used but may be
lines to provide detailed operational proce- adequate for very shallow depths, such as 7 feet
dures for the various mini-HDD and auxiliary Report TR-46 contains a convenient cal- or less, depending on the ability to withstand ex-
equipment, which are generally available from culation method for the selection of the HDPE pected surface loads. For depths greater than 15
the manufacturers or other sources. However, pipe strength. The procedure is presented in feet, very thin wall HDPE or MDPE pipe, or spe-
proper procedures are described for pilot bor- an easy-to-understand format and appropri- cial situations, the adequacy of the product for
ing, tracking, steering, reaming and pullback ate for users with various backgrounds. In par- the application should be verified using the sup-
operations, as well as pipe handling and con- ticular, the procedure provides a means of plementary information provided in the docu-
nection, and record keeping. selecting the pipe strength to avoid collapse ment. In some cases, such as very thin-walled
due to hydrostatic pressure at the desired pipe and/or relatively large depths, special prac-
C om p l e t i on placement depth and to withstand the re- tices or precautions not typically employed dur-
Following installation of the pipe, it is quired pulling loads during installation. ing mini-HDD installations may be required.
necessary to confirm the viability of the new For example, filling the pipe with water during
facility, provide a permanent record of the ac- Min imu m Wal l Thic k n ess pullback simultaneously reduces the net external
tual placement location, and ensure final site B a s e d up o n D e p t h hydrostatic pressure during (and following) in-
cleanup. In particular, the integrity of the pipes The HDPE pipe strength is directly related stallation and the buoyant weight of the pipe, re-
should be appropriately verified, depending to the wall thickness as specified by its dimen- sulting in reduced pull loads.
upon the application and the owner specifica- sion ratio (DR), defined as the ratio of pipe di-
Min imu m Wal l Thic k n ess Ba sed u po n
P ul l i n g L o a d
Table 1 Safe Pull Tension (lbs), HDPE (PE3608) Pipe, 1 Hour – IPS Sizes Table 1 provides the “safe pull tension” for
HDPE (PE3608) pipe as a function of pipe (nom-
inal) diameter and wall thickness (DR value).
These values are conservative, and are intended
to account for the cumulative load duration on
the pipe and avoid non-recoverable viscoelastic
deformation, as well as provide a degree of mar-
gin to account for inherent uncertainty in deter-
mining the pull load. This is difficult to predict,
regardless of the procedure used for such calcula-
tions (Slavin and Petroff, 2010). For MDPE pipe,
the tabulated values must be adjusted by a factor
of approximately 0.80 and, for PE4710 material
pipe, increased by a factor of approximately 1.05.
The following simplified equation has
been developed for the purpose of estimating
the pull load during mini-HDD installations
of polyethylene pipe:
Te ns ion (l bs) = [Bo re L e n g th (ft ) x Buoya nt
We ig ht (lbs/ ft) x (1 /3 )] x (1 .6)n
The buoyant weight may be conveniently de-
termined as:
Buoyan t We ig ht (l bs/ft ) = ½ [Pip e O ute r
Di ame t e r (in . )]2 – Pip e We ig h t (lbs /ft )
The term n is equal to the number (in-
cluding fractions) of effective 90° bends due to
cumulative route curvature, where n = n1 + n2.
The quantity n1 is the number of planned (de-
liberate) 90° route bends, and n2 is the number
of effective route bends resulting from typical
path corrections and route curvature during
the pilot boring operation, for which the fol-
lowing guideline is suggested:
n 2 = [ B o r e Le n g t h ( f t ) / 5 0 0 f t ] x [ 2 - i n / R o d
D i a me t e r ( i n . ) ]
The quantity n2 is shown in Figure 3 for
Figure 3: Unplanned Curvature, n2 various rod diameters.

38 • OCTOBER 2011 • FLORIDA WATER RESOURCES JOURNAL


are typically based on well-con-
trolled maxi-HDD installations and
not representative of actual mini-
HDD applications with respect to
anticipated pull loads.

Bore Path Planning


and Drill Rig Setup
In comparison to maxi-
HDD installations, for which the de-
sign of the bore path is typically
Figure 4: Drill Rig Setup and Re- performed by experienced engineers
lated Distances or organizations, the contractor
using mini-HDD is generally re-
sponsible for cost-effectively accom-
plishing this task. Thus, TR-46
provides user-friendly drill rig setup
and bore path planning information
For a specified pipe diameter, the procedure feet. Mini-HDD installations suffer relative to consistent with meeting the requirements of
for selecting an appropriate pipe strength (DR those performed using typical maxi-HDD tech- the project owner, including geographic con-
value) consists of comparing the estimated pull nology due to the lesser degree of control (e.g., straints and placement depth. The ability to
load to the strengths in Table 1. This procedure greater cumulative route curvature) and the de- satisfy the overall requirements depends on
is similar, but much less complicated, than that sire to forego the use of anti-buoyancy tech- the bending characteristics of the steel drill
incorporated in ASTM F 1962 for the more so- niques, such as inserting water into the pipe rods and the drill rig setup parameters.
phisticated maxi-HDD installations. The present during pullback to reduce buoyant weight and Figure 4 illustrates a typical mini-HDD
mini-HDD calculations will generally result in significantly reduce required pull loads. bore vertical profile trajectory, including occa-
considerably shorter placement distances than In general, the preceding formulas and sional pits along the route. These pits may be
those corresponding to the design methodology methodology are recommended for estimat- required for pipe splicing, completing lateral
provided in ASTM F 1962, which may result in ing pull loads for mini-HDD installations. connections, or exposing existing utilities. The
possible pullback distances of several thousand Other methods for determining pulling loads Continued on page 40

FLORIDA WATER RESOURCES JOURNAL • OCTOBER 2011 • 39


Continued from page 39 ing that there is sufficient space available to prop- necessary to become level at a shallower depth, a
pits may also be useful for collecting drilling erly perform the mini-HDD operation. For ex- lower entry angle and/or drill rod with a smaller
fluid from the boring or reaming operations. ample, point 1 (Figure 4) is located directly along allowable bend radius would be required.
The bending capability and length of the drill the entry path of the drill rod, where the resulting Information regarding other significant
rods, and their entry angle to ground surface, bore path is inclined at the entry angle, and the dimensions, including required horizontal dis-
will determine the minimum depth achievable setback distance corresponding to reaching the tance for surface rise, and for drill rods for dif-
at the beginning of the bore path. depth d1 is designated as S1. This represents the ferent characteristics, is also provided in a
In order to achieve a specified depth at a par- minimal setback distance for achieving a speci- similar format.
ticular point at the beginning of a pilot bore op- fied depth, independent of the orientation of the
eration, the front of the drill rig must be located bore path, which is not level at that point. Conclusions
an appropriate distance rearward from the point Beyond point 1, the drill rods are steered
of interest. Knowledge of such minimum setback such that the bore path trajectory becomes level at This new document is intended to provide
requirements is important with respect to verify- point 2, corresponding to a depth d2 and setback information analogous to that provided in
distance S2. For the same depth of interest, the ASTM F 1962 for maxi-HDD projects, but at
distance S2 is significantly greater than S1. The a level appropriate for the less complex mini-
greater distance is required to allow the drill rods HDD technology. Although the TR-46 guide-
to establish an upward curvature consistent with lines are primarily described with respect to
achieving a horizontal orientation. The S2 setback mini-HDD operations, guidelines for the use
distance depends on both the entry angle and rod of midi-HDD machines and associated prac-
characteristics. Due to the limited bending capa- tices may be obtained from the present TR-46
bility of the rods, as well as the recommendation document, and/or ASTM F 1962, depending
that the first drill rod be placed in the ground upon the particular application and the judg-
without any curvature or steering (see Figure 1), ment of the contractor or engineer.
there is a minimum depth, designated as (d2)min,
at which the trajectory is able to become level. References
The setback distances S1 and S2 are a func-
tion of the depth, d1 or d2, respectively, as shown • ASTM F 1962, “Standard Guide for Use of
in Figure 5, for a representative 10-foot-long drill Maxi-Horizontal Directional Drilling for Place-
rod, with a minimum bend radius or curvature ment of Polyethylene Pipe or Conduit Under
of 100 feet. The minimum depth (d2)min is iden- Obstacles, Including River Crossings,” Ameri-
tified by the minimum depth plotted for the S2 can Society for Testing and Materials.
curves. As an example, for an entry angle of 15°, • CI/ASCE 38, “Standard Guidelines for the Col-
a depth d1 of 72 inches will be achieved at a set- lection and Depiction of Existing Subsurface
back distance S1 of approximately 22 feet. In Utility Data,” American Society of Civil Engi-
comparison, a setback distance S2 of at least 35 neers.
feet is required to reach the same depth d2 at a • Slavin, L.M and Petroff, L., 2010. “Discussion of
level trajectory. Figure 5 also indicates that this ASTM F 1962 or ‘How are the Pulling Load
entry angle and drill rod combination is not con- Formulas Derived and How are they Used ?’,”
sistent with achieving a level trajectory at depths NO-DIG 2010, North American Society for
shallower than approximately 72 inches. If it is Trenchless Technology. 

Figure 5: Drill Rig Minimum Setback Distance Drill Rods:


10 Feet Long, 100 Feet Radius of Curvature

40 • OCTOBER 2011 • FLORIDA WATER RESOURCES JOURNAL

You might also like