Month Jan‐23 Feb‐23 Mar‐23 Apr‐23 May‐23 Jun‐23 Jul‐23 Aug‐23 Sep‐23 Oct‐23 Nov‐23 Dec‐23 Jan‐24 Feb‐24

23 Sep‐23 Oct‐23 Nov‐23 Dec‐23 Jan‐24 Feb‐24 Mar‐24


GRP Pipes
Plan Monthly % Progress 8.05% 14.49% 16.46% 24.60% 15.53% 13.62% 3.98% 2.08% 1.18%
DI Pipes
Plan Monthly % Progress 2.11% 5.46% 12.45% 28.72% 28.06% 18.63% 4.57%

Dismantling Joints , Stepped Coupling , Flange Adaptors For Infra Potable , Foul , Storm , TSE Water Applications
Plan Monthly % Progress 2.50% 7.32% 11.94% 17.28% 19.01% 15.79% 6.64% 4.74% 4.66% 4.79% 4.27% 1.05%

Polymer Concrete Manholes For Foul Sewer & Storm Water
Plan Monthly % Progress 1.08% 8.11% 12.53% 17.38% 16.15% 11.84% 10.06% 7.74% 6.76% 4.12% 4.24%
Power Cables
Plan Monthly % Progress 5.11% 6.68% 6.40% 8.60% 11.47% 14.96% 17.82% 17.63% 6.73% 3.83% 0.76%

Above Ground Fire Hydrant

Plan Monthly % Progress 23.96% 27.90% 25.82% 22.20%