Professional Documents
Culture Documents
https://doi.org/10.1007/s40999-020-00504-9 (0123456789().,-volV)(0123456789().
,- volV)
RESEARCH PAPER
Abstract
Last planner system (LPS) has been recognized as one of the most formidable tools for implementing lean construction
(LC) and improving construction productivity. The past 25 years have witnessed the sequential development of LPS but
still, the construction industry is unable to utilize its full potentials. It was reported that users of LPS were only able to
achieve 70% of their weekly assignments with much potential to perform better. Considering it is a complete lean
construction tool, LPS is mostly implemented in isolation, thereby exposing many areas that are overlooked and poorly
managed. In this study, an effort has been made in developing strategies to overcome LPS implementation challenges by
integrating LPS with other available lean tools and techniques. A systematic literature review is carried out, followed by a
conceptual development of findings and theories into a robust integrated LPS implementation model. Thirteen (13) major
shortcomings in implementing LPS and sixteen (16) lean tools to overcome these shortcomings are identified. Presently,
LPS is managed as a single entity. However, due to its vast diversity, all of its stages should be managed independently. In
this study, lean tools are integrated within LPS stages to develop the innovative integrated last planner system (ILPS),
allowing the management of LPS stages independently. Additionally, a guideline for sequential amalgamation of LPS with
the lean tools at different stages is presented to smoothen the ILPS implementation process. The ILPS will facilitate the
construction industry in utilizing LPS to its fullest potential. This newly developed ILPS will help the lean practitioners in
increasing construction productivity and reducing cost and time.
Keywords Integrated last planner system (ILPS) Lean tools and techniques Shortcomings Look-ahead planning
Constraint analysis Visualization
1 Introduction
123
International Journal of Civil Engineering
inherent shortcomings [1, 3, 4, 6, 10–16]. Lack of visual- next team to subsequently integrate each component within
ization capabilities [17], incompatibility with project the final product. As an example, the architect hands over
delivery methods [18], underutilized look-ahead planning the drawing to the designer who, in turn, passes the design
[4, 6], nonperformance of constraint analysis [3] and lack to the construction team for its implementation. Hence, two
of considerations to continuous maintenance of flow [19] important aspects must be controlled within construction
are a few common shortcomings identified in the existing processes: (1) transforming conceptualized ideas into
LPS. Although LPS has resulted in improved percent plan reality and (2) maintaining continuous flow of products/
completion (PPC) of projects, lean practitioners are still information from one team to another in a reliable and
unable to complete more than 30% of weekly assignments sustainable manner. Diekmann et al. [27] have summarized
even after implementing LPS [20]. the five principles of LC as customer focus, culture/people,
Although state-of-the-art frameworks and implementing continuous improvement, workplace standardization, and
strategies are available to remove inefficiencies of the waste elimination. Ballard et al. [9] also used the same LC
existing LPS, these frameworks still lack the operational principles in their research for the Construction Industry
aspects of LPS. Most of the LPS implementation frame- Institute. The main foci of LC are to reduce waste within
works are broad-based and only target the macro-aspects of construction by maintaining constant flow, to provide
the project and organization [1, 11, 21, 22]. Concurrently, maximum value to the product in a sustainable way, and to
implementation strategies that specifically facilitate the continuously improve over time. All of its principles are set
implementation of various stages of the LPS are meagerly to achieve these goals for the overall benefit of the con-
explored [16, 23, 24]. Additionally, implementing strate- struction industry. The use of lean construction has ulti-
gies and shortcomings are explored in isolation to each mately resulted in cost and time reduction as well as
other and lack the necessary linkage between each other increased productivity of the construction process [28–30].
[3, 6, 23, 25]. This isolation in identifying shortcomings/ Over time, a number of tools and techniques have been
barriers and implementation strategies of LPS makes the identified which can simultaneously be used to achieve the
implementation process difficult and complicated. objective of LC. Ballard and Howell [31] have contributed
This paper outlines major shortcomings in the LPS a platform of LPS, on which many tools are grouped
through an extensive literature review with the purpose of together for efficiently addressing the objectives of LC.
developing implementation guidelines that can increase the LPS emphasizes the role and contribution of the last
efficiency of the existing LPS by incorporating new lean planner, a person who is responsible for the completion of
construction tools. The existing practices of LPS can be the production unit/individual task at the operational level
augmented by introducing tools and techniques that are [32]. The concept of LPS revolves around defining
compatible with LPS and have capabilities of reinforcing assignments based on what should be done, will be done,
the LPS implementation process. After integration with and can be done, through different stages such as master
other lean tools and techniques and targeting the required planning, reverse-phase planning, look-ahead planning and
shortcomings, an effort will be made to develop an inte- weekly planning. Master and reverse phase planning
grated last planner system (ILPS) model. This is a novel determines ‘‘what should be done’’ using the pull approach.
study in which the shortcomings in LPS are removed by As construction begins and recognition of resources and
utilizing the benefits of other tools in a sequenced and constraints becomes apparent, activities which ‘‘will be
phased manner, and implementation guidelines for imple- done’’ are identified using the look-ahead planning, nor-
menting each ILPS stage will be formulated. This research mally performed 5–6 weeks prior to the start of activities.
will benefit the contractors, owners, and clients in devel- Finally, during the weekly schedule, the construction crew
oping a more rational approach for implementing LPS will commit to perform the activities that ‘‘can be done’’
under the umbrella of LC philosophy. based on their capabilities and resource availability. During
execution of the assignments, the outcomes are measured
using the metric Percent Plan Complete (number of activ-
2 Lean Construction (LC) and Last Planner ities executed in a week/number of activities planned in a
System (LPS) week) to carry out depth analysis of all performed works.
The whole process revolves around achieving efficiency
Koskela introduced concepts of lean philosophy in con- through learning and collaboration by all the construction
struction by presenting construction as a production unit participants. The schematic explanation of the last planner
where production was conceptualized in three comple- is given in Fig. 1.
mentary ways: transformation, flow, and value [26]. Con-
struction relies on teams, each specializing in its own area
of expertise and capable of passing their product on to the
123
International Journal of Civil Engineering
Design to
Master Based on the Pull approach,
Work
Schedule what we should do
3 Impact of Last Planner System (LPS) sample of 50 projects to corroborate that projects with a
higher PPC also have higher performances. Since PPC is
Implementation of LPS has resulted in controlling cost and considered to be the most reliable method of measuring the
time overruns as well as enhancing construction produc- impact of LPS, researchers compared the LPS in terms of
tivity. Ballard et al. [33] assessed the performance of LPS change in PPC against existing management approaches.
in a number of projects and found a reduction of cost An increase in productivity along with average PPC
within the range of 10–50% as well as an increase in achieved after implementing LPS is shown in Table 1.
construction productivity by 30%. Similarly, other In comparison to traditional approaches, projects
researchers have also measured the performance of LPS in undertaken using LPS have clearly shown an increase in
terms of cost and schedule overruns and increased pro- PPC but at the same time, an average of 32% assignments
ductivity, and results concluded in favor of LPS is still not achieved. Howell and Macomber [41] further
[5, 32, 34, 35]. Thomassen et al. [36] and Mossman [37] concluded that companies should strive to achieve PPC
measured the safety-related benefits of LPS and concluded values over 80% and anything lower than 60% should be
a considerable decrease in safety incidents by the imple- considered as low performance. Similarly, Ballard and
mentation of LPS. Salem et al. [38] conducted a field study Zabelle [39] also recommended a PPC value of above 80%
to evaluate outcomes of the six lean construction tools as a benchmark for satisfactory performance. However,
(LPS, visualization, daily huddle meetings, first-run stud- based on the summary of results, the average PPC achieved
ies, 5S processes, and fail-safe for quality and safety) after implementing LPS is still around 68%, far below
through the lean implementation standards and perfor- expectations. Hence, there is a need for improving the LPS
mance criteria. Results implicated LPS as the only tool that by finding the main barriers hindering the construction
is complete in itself and can be applied to construction industry from using LPS to its fullest potential.
projects. In contrast, the author recommended modifica- The efficiency of LPS can never be underestimated but
tions for all the other tools prior to effective implementa- one should always remain in search of excellence to benefit
tion within construction in lean environments. the construction industry as a whole and lean practitioners
In most LC studies, the percent plan complete (PPC) is in particular. Lean construction philosophy advocates in
measured in terms of activities executed in a week divided attaining the best possible results through continuous
by activities planned in the same week [5, 39]. According improvement and learning from previous setbacks. Fol-
to Liu et al. [40], labor productivity was found to be pos- lowing the same path, LPS needs to be evaluated to remove
itively correlated with PPC and recommended to be used as drawbacks to achieve maximum efficiency.
a productivity measuring tool. Lagos et al. [21] used a
123
International Journal of Civil Engineering
4 Problem Statement and Current LPS the project level. Khanh and Kim [16] attempted to rank
Implementation Gaps the strategies for successful implementation of LPS but
were restricted to only look-ahead planning, team work-
Researchers have significantly contributed to developing shops and weekly work plans. In an attempt to develop a
LPS implementation frameworks and strategies. However, framework for successful implementation of LPS in Egypt,
there are still shortcomings in the developed frameworks Aboseif and Khallaf [23] proposed 9 strategies for 5
which need to be addressed for efficient application of LPS. identified challenges but fell short in providing the
Fernandez-Solis et al. [3] identified challenges for suc- methodologies for fitting the strategies into an overall LPS
cessful implementation of LPS at an organizational and model. Zaeri et al. [22] developed an automated excel
technical level but fell short in recommending the remedies spreadsheet to efficiently utilize project data in improving
for overcoming these challenges. Lagos et al. [21] sup- LPS implementation. The developed spreadsheet can be
ported the implementation of LPS using information used as an effective tool in the continuous improvement of
technology (IT); however, the use of IT in managing look- the applied LPS. Abusalem [24] identified critical success
ahead/weekly planning by removing the constraints along factors for implementing LPS at the project level; however,
with strategies to performing corrective actions was mea- detailed methodologies for incorporating critical success
gerly researched. Sabek and McCabe [1] developed a factors into the LPS model are not explained. Moreover,
framework for implementing LPS in mega projects by key barriers and success factors were also identified by
identifying 31 LPS implementation challenges and then other researchers to improve the efficiency of LPS [6, 10].
proposing a framework for successful implementation of Ebbs et al. [25] made an endeavor to provide the LPS path
the LPS. This framework discussed the holistic application clearing approach (PCA) by considering ‘‘shallow and
of the LPS at a macro-level but staged implementation of wide’’ organizational aspects rather than a more traditional
LPS at a micro-level (reverse phase planning, look-ahead/ ‘‘narrow and deep’’ project approach. According to the
weekly planning) is not elaborated upon. Micro-level authors, the 15-step action plan developed during the study
implementation strategies explaining each LPS stage will can effectively overcome LPS implementation barriers.
provide a way forward for new LPS users to implement at This implementation strategy is more focused on
123
International Journal of Civil Engineering
123
International Journal of Civil Engineering
Literature Review
Stage 1 Idenfying the shortcoming of LPS Case Studies
through systematically injecting the concepts of SS into planning and nonperformance of constraint analysis as key
LPS during all the stages of construction. A well-structured shortcomings in the LPS. According to the authors, two
framework was also presented by the author for inculcating main categories of LPS (planning and workforce) are too
SS in LPS [12]. Alarcon et al. [13] measured the impact of superficial to identify the causes of problems normally
LPS by studying more than hundreds of projects. Apart hampering construction performance. The major reason for
from the efficacy of LPS, few operational drawbacks in the the lack of effective implementation of look-ahead plan-
system were also identified. According to the authors, the ning as highlighted by Friblick et al. [44] is the non-in-
implementation of look-ahead planning remained a major volvement of employees and subcontractors.
problem due to the lack of understanding about look-ahead Implementation of LPS without the involvement of
planning. Moreover, corrective actions were also not taken downstream players can always be detrimental in achieving
anywhere during the implementation phase because com- true objectives of lean construction. According to Fuemana
panies found it difficult to accurately measure and analyze and Puolitaival [18], incompatibility of procurement
the performances. Another important shortcoming as methods with LPS is the key obstacle in implementing the
notified by the authors was the poor visualization capa- LPS. According to the authors, the traditional point-based
bilities of LPS in which information from one team could design method would not work in harmony with the LPS.
not be understood by the succeeding team. Use of infor- Lack of collaboration and employees/subcontractors
mation technology like building information modeling involvement during designing and planning processes are a
(BIM) to improve visualization has been recommended by few shortcomings of the traditional method that hampers
the author for further facilitating the implementation of the efficient implementation of LPS. To determine com-
LPS. Similarly, the major challenges identified by Dave patible methods of project delivery that work in harmony
et al. [15] in LPS are weak look-ahead planning, lack of with LPS, Matthew and Howell [45] suggested the use of
motivation for continuous improvement, and lack of root integrated project delivery (IPD) as a solution for the
cause analysis and collaborative aspects. Bortolazza and problems in which the whole team functions as a single
Formoso [20] performed quantitative analysis and reported unit with shared responsibilities.
the lack of effective implementation of look-ahead
123
International Journal of Civil Engineering
Ahiakwo et al. [17] highlighted the lack of material Table 3 List of major lean construction tools (unpublished)
availability as the topmost reason for incomplete assign- S/no. Lean construction tools Abbreviations
ments after the implementation of LPS along with diffi-
culties in managing the laborers, reworkings, incomplete 1. Last planner system LPS
design and poor weather. The authors concluded that the 2. Pull approach PULL
lack of material management, visualization of design into 3. Just In time JIT
construction, and risk assessment capabilities of LPS in the 4. Concurrent engineering CE
execution stage are some of the areas that need further 5. Poka Yoka PY
elaboration. 6. Daily huddle meeting DHM
Maintaining continuous flow is an essential component 7. Set-based design SBD
of Koskela’s three partite explanation of lean construction 8. Visual management VM
(transformation, flow, and value) [26]. Linghard and 9. First-run studies FRS
Wahdahl [19] analyzed the LPS in depth by taking into 10. Kanban KAN
account the mechanism of LPS in which the sequence of 11. Line of balance L of B
activities is determined based on duration and interrela- 12. Six sigma SS
tionships; whereas, the main themes of all types flow are 13. Prefabrication/modular PF/MOD
not taken into consideration. According to Linghard and 14. Fail safe for quality and safety FSQS
Wahdahl [19], in LPS, flow considerations are kept at look- 15. Integrated project delivery IPD
ahead level only in which different activities have to be 16. Building information modeling BIM
made ready for construction. Authors recommended 17. Value stream mapping VSM
incorporating the flow consideration during reverse phase, 18. 5S 5S
look-ahead and weekly scheduling also. The summary of 19. Theory of constraints TOC
the barriers is listed in Table 2 as well. 20. Target value design TVD
21. Standardized process SP
22. Kaizen KAIZ
7 Selection of the Lean Tools 23. Failure mode and effect analysis FMEA
123
International Journal of Civil Engineering
BR
Amalgamation of LPS with other lean tools and tech-
*
*
*
*
*
*
*
niques will help in removing shortcomings associated with
FMEA
LPS. It should be ensured that lean tools and techniques
have objectivities and application methodologies that are
*
*
*
*
fully compatible and aligned with the LPS processes. Lean
VSM
tools and techniques for this study are selected from the
*
*
*
unpublished work of authors, in which each lean tool is
TVD
characterized by its objectivity and application method-
*
ologies. It facilitated the selection of lean tools for target-
SBD
ing the specific shortcoming of LPS.
*
*
IPD
*
*
*
*
*
8 Integration of Lean Tools with LPS
BIM
to Overcome Its Shortcomings
*
*
*
*
*
SP
*
*
*
Based on the objectives and functionalities of lean tools, a
PY TOC
matrix as shown in Table 4 is developed in which targeted
*
*
*
*
*
shortcomings are cross-matched with the suitable tools to
overcome shortcomings within LPS. There are a number of
*
tools having the objectives and application methodologies
LOB
targeting the specific shortcomings in LPS. As an example,
*
tools like FRS, FSQS, SS, KAIZ, PY and TOC can facil- PF
*
itate LPS in finding the root causes of problems and sug-
CE
*
*
*
*
KAIZ, BIM and VSM can provide excellent visualization
KAIZ
*
*
*
Many tools actually target the same shortcomings,
JIT
*
*
tion industry in deciding the best tool, but can also increase
KAN
the opportunity window for selecting the best tool to fit into
*
*
the organizational and project environment. Organizations
SS
*
*
implementing LPS have to decide which tool best fits
FSQS
*
*
*
*
*
*
*
*
Constraint analysis
Visualization
123
International Journal of Civil Engineering
1 Root cause analysis SS and FRS 2 and 3 Conducting root cause analysis and suggesting corrective
actions
2 Visualization BIM and VSM 3 and 5 Schedule planning will become more reliable based on future
prediction of outcome in collaboration with
multidisciplinary teams
3 Supply chain management 5S, JIT, KAN 5, 8 and 10 Improves the supply chain of the project and reduce the
material waste
4 Lack of communication BIM and VM 4 and 14 Automatic generation and upkeep of all information with
access to all key stakeholders at any time
5 Constraint analysis SS, VSM, LOB 2, 6, 11 and 13 Pre-visualization of all upcoming constraints and eliminating
and TOC the constraints that are continually coming
Reduction of all non-value-adding activities thereby
improving the schedule and reducing waste related to
people
6 Contracting and legal issues IPD and CE 15 and 17 Improves relationship between all key stakeholders including
the subcontractors
7 Lack of collaboration IPD, BR and 15, BR and DHM Increased collaboration among all stakeholders, simultaneous
DHM not listed involvement of downstream players and subcontractors
8 Nonperformance of risk analysis BIM, TOC, 4, 13 and 22 Effect of external risks like climate change, site restriction,
FMEA material availability, etc. can be minimized
9 Issues related to flow BIM, SBD/ 4, 9, 2, 6 and 5 Improves and maintains continuous flow during construction
TOC, FRS, Minimize the conflicts that can occur due to wrong
VSM, 5S interpretation of design
Add value and reduce design changes
10 Involving IPD, DHM, 15, 6, BR and DHM Subcontractors will start owning the project and give their
people/subcontractors/suppliers BR, VSM not listed best because of the pain/gain concept
11 Lack of training FRS, BR 2 and BR not listed Provides firsthand knowledge about processes and
implementation strategies for any activity
12 Issues with Look-ahead planning BIM, BR, TOC 4, 13, BR and DHM Better visualization and collaboration, removal of constraints
not listed
performance. The recommended tools based on their planned work-ready for smooth execution. In the end,
ranked order along with perceived benefits after amalga- complete construction is monitored and continuously
mation are explained in Table 5. improved to achieve the desired efficiency. All these pha-
ses have distinct functions and outcomes which must be
managed separately. The diversity within LPS compels
9 Development of Integrated Last Planner users to manage each phase separately. The problem arises
System (ILPS) when LPS is treated and managed as one unit thereby
neglecting the diversity of each LPS stage. To remove
The biggest challenge for lean practitioners is to integrate shortcomings of existing LPS, the lean practitioners must
different lean tools and techniques into various phases of manage every LPS stage independently by taking measures
LPS. Each LPS phase has been developed to plan and which can increase the efficiency of each phase. Use of
execute assignments during various phases of construction. different lean tools and techniques during various LPS
The master and phase schedules have to be developed well stages can be an effective way to manage LPS.
before the start of construction to identify the key mile- As already explained, lean tools have exclusive objec-
stones that must be planned using reverse planning. Look- tives and functionalities that can only work in harmony
ahead plans are developed during the construction for with each LPS stage, if they are compatible and comple-
removing the likely constraints and making work-ready. mentary to each other. As an example, whereas Just in
Only activities that are constraint free are kept for con- Time (JIT) can be an effective tool in planning and
struction. Weekly schedules are developed to align the managing supply chain activities during the look-ahead
123
International Journal of Civil Engineering
BIM IPD
SBD/TVD
Design Procurement
TOC, BIM,
FRS, SS, JIT
FRS, KAN, VSM,
M FMEA
JIT, BIM, 5S Reverse Phase
Look Ahead L FRS
PULL,
Scheduling
Planning
C
Weekly
To ensure smooth
Planning
hand offs between
To ensure that all
trades and
resources, preceding
knowledge about
works, informaon
requirements of
and external
succeeding trades
condions are in full
by preceding trades
harmony and ready
for the workforce
On the Day
Measurements
PPC
Defects
stage, use of JIT during the master schedule can be less will decide the degree of implementation of LPS. More
effective. Similarly, the Theory of Constraint (TOC) can be collaboration among project participants will result in
used to remove constraints during look-ahead planning. better performance of LPS. Collaboration from the key
Based on the objectives and functionalities of lean tools stakeholders at the early stages and involvement of all team
that can effectively remove LPS shortcomings during dif- members including subcontractors in later planning will
ferent stages of LPS, a schematic model as presented in eradicate coordination problems among the project teams.
Fig. 3 is developed and explained below:
9.2 Improved Visualization During Design
9.1 Increased Collaboration and Construction
Collaboration through Big Room (BR) has to be ensured BIM being the most powerful tool should be utilized in
during all phases of LPS and the extent of collaboration visualizing the construction and should be incorporated in
123
International Journal of Civil Engineering
all the planning stages of LPS (master, reverse phase, look- subcontractors and suppliers. Their involvement will help
ahead and weekly). During the design stage, the integration in adjusting the tasks that have to be performed on-site. SS
of BIM and SBD/TVD will ensure the eradication of all is an excellent tool for analyzing the quality and perfor-
later on design and construction conflicts and also improve mance data and for identifying the likely causes of low
the workflow. Coupled with VSM, it will add value to the performance. JIT and KAN will effectively facilitate in
project in designing and master planning the project by planning the issues related to supply chain and material
incorporating all design/cost alternatives and removing/ management. Material management has to be deliberately
minimizing non-value-adding activities, respectively. planned and coordinated during look-ahead and weekly
During master planning, the use of BIM will be beneficial planning, respectively, using the JIT approach.
in identifying the milestones and planning the project in a
way it is best visualized. Efforts should be made that the 9.6 Improving Weekly Planning
design and master plan should be as realistic and con-
structive to reduce the later on changes in design and Weekly planning is carried out for all works that have to be
schedule to a minimum. performed. Last minute coordination and refinement within
the schedule is carried out. Downstream players and sub-
9.3 Improved Relationships contractors/suppliers are extensively involved in this stage
for identifying their state of readiness and for providing
The implementation process will be reinforced using the input. BIM can provide an excellent platform for coordi-
IPD method which works in harmony with the lean con- nation and final alignment of all teams for their respective
struction philosophy. IPD promotes collaboration, builds tasks. FRS can be utilized in refining the skills and getting
confidence and trust among stakeholders and ensures tak- acquainted with the new/uncommon activities. Tools like
ing measures that can be beneficial for all project JIT and KAN can be utilized for ensuring the timely
participants. delivery of materials from suppliers. Storage places, if
required, are further reconciled based on the site require-
9.4 Risk Analysis ments and adjustments are made. Worker’s tools can be
arranged using 5S so as to smoothen the issuing procedure
Reverse phase scheduling is based on the pull technique and ensuring safety at the site. The project will kick off
where the succeeding activity decides the delivery date of after weekly planning and will be measured for continuous
the preceding activity. Consideration of likely risks during improvement and assessed regularly during look-ahead and
this phase will remove uncertainties in planning. Moreover, weekly planning stages. DHM also provides a key platform
the use of FRS to streamline the implementation processes in which cross-functional teams work together to resolve
will enlighten the teams in performing tasks and will gear the issues in a coordinated manner. The whole cycle has to
them up for the coming assignments. To evaluate the be performed periodically, so that the implementation of
external risks, risk analysis should be performed after the LPS can result in enhanced benefits.
master planning or scheduling is complete and should be
given due diligence in the reverse phase scheduling by 9.7 Continuous Improvement
using tools like FMEA. VSM will further refine activities
based on their value-adding capabilities. After performing Organizations should develop performance measurement
the risk analysis and streamlining the implementation tools, so that they can analyze their performances and
process, the tasks that can be performed will be identified further improvements can be carried out. LPS uses weekly
and retained for look-ahead planning. PPC as an effective measurement tool for measuring con-
struction productivity. However, apart from PPC, the
9.5 Improving Lookahead Planning number of defects identified and rectified in weekly
assignments should be recorded and further analyzed to
Two important challenges for look-ahead planning are the ensure quality completion of construction assignments.
lack of constraint and root cause analysis. The reverse Analysis and results of both these measurements will be
phased schedule can further be scrutinized by performing used to ensure the refinement in the processes by correcting
constraint analysis to identify final tasks ready for work. the malfunctions and finally, a system should be evolved
Tools like TOC can be used in assessing the likely con- that looks to build itself through continuous learning.
straints and identifying the recommended strategies in
removing the constraints. Working procedures should be
redefined after removal of the constraints using BIM and
FRS and involve downstream players along with
123
International Journal of Civil Engineering
123
International Journal of Civil Engineering
No matter how efficient a model is, if it is not implemented The construction industry is in need of the efforts that can
properly, the results can be damaging. Unfortunately, the improve construction productivity and control time and
construction industry is struggling in utilizing LPS to its cost overruns. LC has been developed to overcome the
fullest potential due to the non-availability of any robust performance-based issues of the construction industry. LPS
implementation plan. Implementation of ILPS will always is a tool in practice for the last 24 years to achieve the
be a challenge for the construction industry due to its goals of LC. Although researchers have measured the
integration and amalgamation of many tools and tech- improved performances by implementing LPS, the full
niques. Realizing the implementation challenges, a com- benefits are still yet to be explored due to inherent issues
plete implementation guideline for ILPS is prepared based with the LPS. An effort has been made in this study to
on the model presented in Fig. 3. Each ILPS stage is fur- combat those areas of LPS that are hindering its efficient
ther explained in Table 6 to streamline the inputs, pro- implementation by integrating the existing LPS model with
cesses, and outputs required for its successful compatible LC tools and techniques. By identifying the
implementation. The organizations implementing ILPS can shortcomings of the LPS and attacking those shortcomings
follow the guidelines as shown in Table 6 to develop their with the best alternative tool, an efficient integrated last
own implementation techniques by duly incorporating lean planner system (ILPS) is modeled in this study. A toolbox
tools and techniques based on their capabilities, expertise, for implementing various stages of ILPS is also presented
resources, project environment and prevailing site to facilitate the construction industry for efficient imple-
conditions. mentation of ILPS. Theoretically, this study will increase
the body of knowledge by explaining the key functionali-
ties and methodologies involved during the efficient
10 Significance of ILPS implementation of LPS. It will increase the opportunity for
utilizing the LPS to its fullest potential by integrating it
Considering the tremendous benefits of lean construction, with other tools and techniques. Practically, this study will
organizations are always hunting for tools and techniques provide the contractors a way forward in implementing the
to better facilitate the adoption of lean practices. The LPS in a manner that will result in the best possible results
success of LPS clearly marked its ascendency over other with improved performances. Although the major aim of
lean tools. However, it was found that isolated application this study was to develop the conceptual efficient ILPS
of LPS exposed many areas in construction that were not model based on the literature and case studies, however,
managed by lean philosophies. Resultantly, the isolated the efficacy of this model should be tested in the field for
applications of LPS led to many shortcomings within the evaluating its practicability and validity. For the research-
system which prevented optimal performance. ILPS was ers, the ideas presented in this study can provide a foun-
developed to target the shortcomings of LPS by integrating dation for further exploring the integration of LPS with
them with other lean tools and techniques. Significance of other lean tools and refining the ILPS after its application
ILPS are: in construction projects.
1. Facilitate organizations in implementing LPS fully
2. Remove shortcomings of LPS
3. Capable of targeting all areas of construction as References
advocated by lean philosophy
4. Organizations can claim themselves as lean organiza- 1. El-Sabek LM, McCabe BY (2018) Framework for managing
tion as ILPS is developed to cover all principles of lean integration challenges of last planner system in IMPs. J Constr
construction Eng Manag 144(5):04018022. https://doi.org/10.1061/
(ASCE)CO.1943-7862.0001468
5. Implementation of ILPS will remove inefficiencies and 2. Brittle P, Gaedicke C, Akhavian R (2018) Perspective of the last
wastes prevalent in construction projects and will planner: effectiveness of the traditional critical path method in
improve productivity. comparison with the last planner system. J Supply Chain Oper
Manag 16(1):59
3. Fernandez-Solis JL et al (2013) Survey of motivations, benefits,
and implementation challenges of last planner system users.
J Constr Eng Manag 139(4):354–360. https://doi.org/10.1061/
(ASCE)CO.1943-7862.0000606
4. Priven V, Sacks R (2015) Effects of the last planner system on
social networks among construction trade crews. J Constr Eng
123
International Journal of Civil Engineering
Manag 141(6):04015006. https://doi.org/10.1061/(ASCE)CO. 20. Bortolazza RC, Formoso CT (2006) A Quantitative analysis of
1943-7862.0000975 data collected from the last planner system in Brazil. In: 14th
5. Ballard G (2008) The lean project delivery system: an update. annual conference of the international group for lean construc-
Lean Constr J:1–19. https://www.leanconstruction.org/media/ tion, Santiago, Chile, pp 625–635. https://iglc.net/Papers/Details/
docs/lcj/2008/LCJ_08_001.pdf 415
6. Vignesh CA (2017) Case study of implementing last planner 21. Lagos CI, Herrera RF, Alarcón LF (2019) Assessing the impacts
system in Tiruchirappalli district of Tamil Nadu-India. Int J Civ of an IT LPS support system on schedule accomplishment in
Eng Technol 8(4):1918–1927. https://www.iaeme.com/IJCIET/ construction projects. J Constr Eng Manag 145(10):04019055.
issues.asp?JType=IJCIET&VType=8&IType=4 https://doi.org/10.1061/(ASCE)CO.1943-7862.0001691
7. Gao S, Low SP (2014) The last planner system in China’s con- 22. Zaeri F, Rotimi JOB, Hosseini MR, Cox J (2017) Implementation
struction industry—a SWOT analysis on implementation. Int J of the LPS using an excel spreadsheet: a case study from the New
Project Manag 32(7):1260–1272. https://doi.org/10.1016/j.ijpro Zealand construction industry. Constr Innov 17(3):324–339.
man.2014.01.002 https://doi.org/10.1108/CI-01-2016-0002
8. Daniel EI, Pasquire C, Dickens G (2019) Development of 23. Aboseif E, Khallaf R (2020) A framework for last planner system
approach to support construction stakeholders in implementation implementation in Egypt. CIGOS, 2019 innovation for sustain-
of the last planner system. J Manag Eng 35(5):04019018. https:// able infrastructure. Springer, Singapore, pp 1019–1024
doi.org/10.1061/(ASCE)ME.1943-5479.0000699 24. Abusalem O (2018) Towards last planner system implementation
9. Ballard G, Kim YW, Jang JW, Liu M (2007) road map for lean in Gaza Strip, Palestine. Int J Constr Manag. https://doi.org/10.
implementation at the project level. The Construction Industry 1080/15623599.2018.1484861
Institute, Research Report 234-11, The University of Texas, 25. Ebbs P, Pasquire C, Daniel EI (2018) The Last Planner system
Austin. https://www.researchgate.net path clearing approach in action: a case study. In: 26th interna-
10. Tayeh BA, Al Hallaq K, Al Faqawi AH, Alaloul WS, Kim SY tional group for lean construction conference, Chennai, India.
(2018) success factors and barriers of last planner system https://doi.org/10.24928/2018/0433
implementation in the Gaza Strip construction industry. Open 26. Koskela L (1992) Application of the new production philosophy
Constr Build Technol J 12:1. https://doi.org/10.2174/ to construction, vol 72. Stanford University, Stanford. https://
1874836801812010389 www.leanconstruction.org/media/docs/Koskela-TR72.pdf
11. Perez AM, Ghosh S (2018) Barriers faced by new-adopter of last 27. Diekmann JE, Krewedl M, Balonick J, Stewart T, Won S (2004)
planner system: a case study. Eng Constr Archit Manag Application of lean manufacturing principles to construction.
25(9):1110–1126. https://doi.org/10.1108/ECAM-08-2017-0162 Boulder, CO, Construction Industry Institute, Project report by
12. Abdelhamid TS (2003) Six Sigma in lean construction systems: Project team 191. The University of Texas, Austin. https://doc
opportunities and challenges. In: Proceedings of the eleventh player.net/23504615-Application-of-lean-manufacturing-princi
annual conference of the international group for lean construc- ples-to-construction.html
tion, IGLC-11, Blacksburg, VA, USA, pp 22–24. https://iglc.net/ 28. Locatelli G, Mancini M, Gastaldo G, Mazza F (2013) Improving
Papers/Details/221 projects performance with lean construction: state of the art,
13. Alarcón LF, Diethelm S, Rojo O, Calderón R (2011) Assessing applicability and impacts. Organ Technol Manag Constr Int J
the impacts of implementing lean construction. Rev Ing Constr 5(Special):775–783. https://hrcak.srce.hr/111766
23(1):26–33. https://doi.org/10.4067/S0718-50732008000100003 29. More VD, Charhate DS, Sinha M (2016) Lean construction
14. Lindhard SM (2013) Exploring the last planner system in the techniques in Indian construction industry: some analysis. Int J
search for excellence. Doctoral dissertation. Aalborg University, Civ Eng Res 7(1):59–65. https://www.ripublication.com/ijcer16/
Department of Mechanical and Manufacturing Engineering. ijcerv7n1_08.pdf
https://vbn.aau.dk/ws/files/178075091/Thesis_S_ren_Munch_ 30. Agbulos A, Mohamed Y, Al-Hussein M, AbouRizk S, Roesch J
Lindhard.pdf (2006) Application of lean concepts and simulation analysis to
15. Dave B, Hämäläinen J-P, Koskela L (2015) Exploring the improve efficiency of drainage operations maintenance crews.
recurrent problems in the last planner implementation on con- J Constr Eng Manag 132:291–299. https://doi.org/10.1061/
struction projects. In: Proceedings of the Indian Lean Construc- (ASCE)0733-9364(2006)132:3(291)
tion Conference (ILCC 2015), p 9. https://urn.fi/URN:NBN:fi: 31. Ballard G, Howell G (1994) Implementing lean construction:
aalto-201503031948 stabilizing work flow. In: Alarcón L (ed) Lean construction in
16. Khanh HD, Kim SY (2016) A survey on production planning 1997. Balkema, Rotterdam, pp 101–110
system in construction projects based on last planner system. 32. Aziz RF, Hafez SM (2013) Applying lean thinking in construc-
KSCE J Civ Eng 20(1):1–11. https://doi.org/10.1007/s12205-015- tion and performance improvement. Alex Eng J 52(4):679–695.
1412-y https://doi.org/10.1016/j.aej.2013.04.008
17. Ahiakwo O, Oloke D, Suresh S, Khatib J (2013) A case study of 33. Ballard G, Tommelein I, Koskela L, Howell G (2007) Lean
last planner system implementation in Nigeria. In: Formoso CT, construction tools and techniques. In: Best R, de Valence G (eds)
Tzortzopoulos P (eds) 21th annual conference of the international Design and construction , vol 15. Routledge, pp 251–279. https://
group for lean construction, Fortaleza, Brazil, 31–2 Aug 2013, leanconstruction.org.uk/wp-content/uploads/2018/09/Ballard-et-
pp 699–707. https://iglc.net/Papers/Details/863 al.-Lean-Construction-tools-and-techniques.pdf
18. Fuemana J, Puolitaival T (2013) Last planner system—a step 34. Fiallo CM, Revelo PVH (2002) Applying the last planner control
towards improving the productivity of New Zealand Construc- system to a construction project—a case study in Quito, Ecuador.
tion. In: Formoso CT, Tzortzopoulos P (eds) 21th annual con- In: Formoso CT, Ballard G (eds) 10th annual conference of the
ference of the international group for lean construction, Fortaleza, international group for lean construction. Gramado, Brazil, 6–8
Brazil, 31–2 Aug 2013, pp 679–688. https://iglc.net/Papers/ Aug 2002. https://iglc.net/Papers/Details/183
Details/903 35. Babalola O, Ibem EO, Ezema IC (2018) Implementation of lean
19. Lindhard S, Wandahl S (2013) Looking for improvement in the practices in the construction industry: a systematic review. Build
last planner system: defining selection criteria. In: ICCREM Environ 148:34–43. https://doi.org/10.1016/j.buildenv.2018.10.
2013: construction and operation in the context of sustainability, 051
pp 27–35. https://doi.org/10.1061/9780784413135.003
123
International Journal of Civil Engineering
36. Thomassen MA, Sander D, Barnes KA, Nielsen A (2003) improvement. Doctoral Dissertation, Nottingham Trent Univer-
Experience and results from implementing lean construction in a sity. https://irep.ntu.ac.uk/id/eprint/31057/
large Danish Contracting Firm. In: 11th annual conference of the 43. Kim D (2002) Exploratory study of lean construction: assessment
international group for lean construction. Virginia, USA. https:// of lean implementation. Doctoral Dissertation. The University of
iglc.net/Papers/Details/270 Texas at Austin. https://hdl.handle.net/2152/11219
37. Mossman A (2015) Last Planner 5 ? 1 crucial & collaborative 44. Friblick F, Olsson V, Reslow J (2009) Prospects for imple-
conversations for predictable design & construction delivery, menting last planner in the construction industry. In: Cuperus Y,
December 2015. https://www.villego.com/wp-content/uploads/ Hirota EH (eds) 17th annual conference of the international group
2017/02/Mossman-2015-Last-Planner.pdf for lean construction, Taipei, Taiwan, 15–17 Jul 2009,
38. Salem O, Solomon J, Genaidy A, Luegring M (2005) Site pp 197–206. https://iglc.net/Papers/Details/635
implementation and assessment of lean construction techniques. 45. Matthews O, Howell GA (2005) Integrated project delivery an
Lean Constr J 2(2):1–21. https://www.leanconstruction.org/ example of relational contracting. Lean Constr J 2(1):46–61.
media/docs/lcj/V2_N2/LCJ_05_009.pdf https://www.leanconstruction.org/media/docs/lcj/V2_N1/LCJ_
39. Ballard G, Zabelle T (2000) Lean design: process tools and 05_003.pdf
techniques. White Paper# 10. Lean Construction Institute, USA. 46. Koskenvesa A, Koskela L (2012) Ten years of last planner in
https://www.p2sl.berkeley.edu. Finland—where are we? In: Tommelein ID, Pasquire CL (eds)
40. Liu M, Ballard G, Ibbs W (2010) Work flow variation and labor 20th annual conference of the international group for lean con-
productivity: case study. J Manag Eng 27(4):236–242. https://doi. struction, San Diego, USA, 18–20 Jul 2012. https://iglc.net/
org/10.1061/(ASCE)ME.1943-5479.0000056 Papers/Details/795
41. Howell G, Macomber H (2002) A guide for new users of the Last 47. Porwal V, Fernández-Solı́s J, Lavy S, Rybkowski ZK (2010) Last
PlannerTM System nine steps for success. Lean Projects Con- planner system implementation challenges. In: Walsh K, Alves T
sulting, Inc. https://www.academia.edu/28190875/A_guide_for_ (eds) 18th annual conference of the international group for lean
new_users_of_the_Last_Planner_System_nine_steps_for_ construction, Haifa, Israel, 14–16 Jul 2010. pp 548–556. https://
success iglc.net/Papers/Details/686
42. Daniel EI (2017) Exploratory study into the use of Last Planner
System and collaborative planning for construction process
123