You are on page 1of 8

1120 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 21, NO.

3, JULY 2006

Performance of Frequency Relays for


Distributed Generation Protection
Jose C. M. Vieira, Student Member, IEEE, Walmir Freitas, Member, IEEE, Wilsun Xu, Fellow, IEEE, and
Andre Morelato, Member, IEEE

Abstract—This paper investigates the efficiency of under/over As a standard practice, all distributed synchronous genera-
frequency relays for protection of distributed synchronous gener- tors are also equipped with under/over frequency relays, whose
ators considering islanding detection and frequency-tripping re- settings are established according to the generator manufacturer
quirements. Comparison between frequency and vector surge re-
lays, which are islanding detection-dedicated devices, shows that recommendations and to the utility frequency-tripping require-
the former can be as effective as the latter. This feature supports ments (or interconnection) guidelines [1]. Since both the vector
the idea that frequency relays can replace vector surge relays for is- surge and the frequency relays operate on the basis of system
landing detection purpose. In this case, frequency relays must also frequency deviation, one would wonder if the frequency relay
meet the generator manufacturer recommendations and the utility can replace the vector surge relay for anti-islanding detection
frequency-tripping requirements. In order to investigate the relay
capability to meet both necessities, it is proposed the concept of ap- application. If this is the case, installation of a dedicated is-
plication region, which defines a region in the detection time versus landing detection relay, such as the VSR, will become unnec-
active power imbalance space where frequency-based relays can be essary. The savings can be quite attractive for small-distributed
adjusted to satisfy the anti-islanding and frequency-tripping re- generators and the protection system would be much simpler.
quirements simultaneously. The paper also presents a set of for- Another significant issue raising from using frequency-based
mulas to determine directly the application region.
relays for anti-islanding protection is the conflicting require-
Index Terms—Distributed generation, dynamic simulation, ment on the relay performance. The IEEE distributed resources
frequency relay, islanding detection, synchronous generator. interconnection guide recommends that a DG must not be dis-
connected due to small frequency variations [1]. If the relay is
I. INTRODUCTION set to meet this requirement, it may not detect islanding condi-
tions within the required time. On the other hand, if the relay is

P ROTECTION systems of distributed synchronous genera-


tors must be able to detect islanding situations and meet the
utility frequency-tripping requirements. An islanding situation
set sensitive for anti-islanding protection, it may also trip the DG
due to small frequency variations. Thus, it is important to under-
stand if there is a region where the relay can satisfy both require-
occurs when part of a distribution system is disconnected from
ments and, if such a region exists, what are its characteristics.
the utility system, but it remains energized due to one or more
The main objective of this paper is to present our findings on
distributed generators connected to the isolated subsystem. This
the above two questions. Our results show that frequency relays
occurrence, also known as loss of mains, may lead to safety risks
have essentially the same performance of vector surge relays
to the utility personnel, deteriorate the quality of supply in the
for islanding detection. For the second question, we found that
island and cause damage to the distributed generator (DG) and
there is a region where the frequency relay can satisfy the both
loads. In an attempt to minimize such risks, the current prac-
requirements mentioned previously. A method to determine this
tice in the industry is to disconnect all distributed generators
region is proposed.
immediately after an islanding occurrence [1]–[3]. Typically,
This paper is organized as follows. Section II explains
the islanding situation should be detected within 200 to 400 ms,
the approach employed in this work to analyze the islanding
however, this requirement has been relaxed by some utilities and
detection capability of frequency-based relays. Section III
detection times up to 1 s are allowed. To achieve such a goal,
describes the network component models used in this work.
each distributed generator must be equipped with an islanding
Section IV presents a comparative study between the perfor-
detection device. Vector surge (or shift) relays (VSR) are devel-
mance of frequency relays (FR) and vector surge relays (VSRs)
oped for this purpose [4], [5]. These relays have gained wide-
for anti-islanding protection. Section V proposes the concept
spread acceptance of the industry.
of application region where the frequency relay can be used
for anti-islanding protection while maintaining immunity to
Manuscript received January 21, 2005; revised April 28, 2005. This work small frequency variation. The conclusions are presented in
was supported in part by FAPESP, in part by CNPq, and by PRPG/UNICAMP, Section VI. In Appendix, it is proposed a set of formulas to
Brazil. Paper no. TPWRD-00039-2005.
J. C. M Vieira, W. Freitas, and A. Morelato are with the Department of Elec- determine the application region without simulations.
trical Energy Systems, State University of Campinas, Campinas 13081-970,
Brazil (e-mail: jcarlos@dsee.fee.unicamp.br; walmir@ieee.org; morelato@ II. PERFORMANCE CURVES
dsee.fee.unicamp.br).
W. Xu is with the Department of Electrical and Computer Engineering, Uni- The usage of the performance curves, i.e. the detection time
versity of Alberta, Edmonton AB T6G 2V4, Canada (e-mail: wxu@ee.ualberta.
ca). versus active power imbalance curves, in order to characterize
Digital Object Identifier 10.1109/TPWRD.2005.858751 frequency-based relays was proposed in [6], where detailed
0885-8977/$20.00 © 2006 IEEE
VIEIRA et al.: PERFORMANCE OF FREQUENCY RELAYS 1121

Fig. 2. Single-line diagram of the system.

Fig. 1. Typical performance curve of frequency-based relays.

information can be found about this approach. However, to


facilitate the paper reading, the determination and analysis of
these curves are briefly explained in this section. The islanding Fig. 3. Frequency relay computational model.
detection capability of frequency-based anti-islanding relays
is strongly dependent on the active power imbalance existent III. NETWORK COMPONENT MODELS
in the islanded system, i.e. the mismatch between load and
Fig. 2 shows the single-line diagram of the network used
generation. When the mismatch of active power decreases, the
in this paper. It comprises a 132 kV, 60 Hz, subtransmission
capability to quickly detect islanding of these devices dimin-
system with short-circuit level of 1500 MVA, represented by
ishes accordingly [6]. In the extreme cases, where the load and
a Thévenin equivalent (Sub), which feeds a 33 kV distribution
generation in the islanded system are very close, the devices
system through a 132/33 kV, , transformer. In this system,
may fail to detect an islanding situation [6]. Thus, an approach
there is one 30 MW synchronous generator (SG) connected at
to evaluate the performance of frequency-based anti-islanding bus 5, which is connected to the network through one 33/0.69
relays is to understand the relationship between the detection kV, transformer. Such generator is equipped with an au-
time and active power imbalance. This relationship can be rep- tomatic voltage regulator (AVR).
resented through a detection time versus active power imbal- In this study, all network components were represented by
ance curve as shown in Fig. 1, which is obtained for a specific three-phase models. Distribution feeders were modeled as series
relay setting. impedances and transformers were modeled using the cir-
In Fig. 1, the -axis is the active power imbalance level of the cuit. Synchronous generators were represented by a sixth-order
islanded system referred to the rated MVA of the generator. The three-phase model in the rotor reference frame [7]. The gen-
y-axis is the time needed by the relay to operate. This curve can erator was considered equipped with an automatic voltage reg-
be obtained by repeated dynamic simulations of islanding oc- ulator represented by the IEEE—Type 1 model. The simulation
currences, in which the load-generation profile in the islanded duration is short (1 s), in addition, usually, distributed genera-
system is changed for each simulation. Thus, for each active tors do not participate in the frequency regulation of the system
power imbalance, the detection time is determined by dynamic and, therefore, they operate at constant active power mode [5].
simulation and then the performance curve is plotted. If it is re- Thus, the mechanical power was considered constant. The loads
quired to detect the islanding situation within 400 ms after its were modeled as constant impedance, because this type of load
occurrence, one can draw a 400-ms horizontal line. In this case, leads to the most conservative (pessimistic) islanding detection
the intersection of this line with the relay curve gives 21.7% of performance of frequency-based relays [6].
active power imbalance level. If the islanded system has an ac- Frequency relays measure the cycle duration of the terminal
tive power imbalance greater than 21.7%, it will take less than voltage by using some voltage zero crossing detection technique
400 ms to detect the islanding condition. Therefore, the relay and signal processing method. The frequency relay model im-
can be used with confidence. On the other hand, the relay will plemented in this work is presented in Fig. 3. The system fre-
take longer than 400 ms to operate if the active power imbal- quency is determined from the generator electrical speed .
ance level is less than 21.7%. Consequently, the relay or the set- If this signal is larger (or smaller) than the over frequency (under
ting employed is not suitable for this case. Such a threshold is frequency) setting of the relay and the magnitude of the ter-
called the critical active power imbalance level or simply crit- minal voltage is larger than the minimum voltage setting ,
ical power imbalance [6]. then the frequency relay sends a trip signal to the generator
1122 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 21, NO. 3, JULY 2006

circuit breaker. For simplicity, it was considered that the de- TABLE I
viations of the relay settings for under/over frequency are the CORRESPONDENCE BETWEEN FREQUENCY AND VECTOR SURGE
RELAYS SETTINGS IN A 60 HZ SYSTEM
same. Therefore, if a variation of frequency occurs, the
frequency relay becomes active. Frequency relays can be op-
erated with a time delay; in this case, the tripping conditions
(frequency variation) must persist during a pre-determined time
to trigger the relay. Typically, frequency relays can be adjusted
using multi-stages, therefore, instantaneous and time-delay set-
tings are employed simultaneously. Usually, frequency relays
can be blocked if the terminal voltage drops below an adjustable
level . This is to avoid, for example, the actuation of the
relay during generator start-up.
Vector surge relays measure the duration time of an elec-
trical cycle and start a new measurement at each zero rising
crossing of the terminal voltage and the current cycle duration
(measured waveform) is compared with the last one (reference
cycle). Variations of the cycle duration results in a proportional
variation of the terminal voltage angle, which is the input pa-
rameter of vector surge relays. If the variation of the terminal
voltage angle exceeds a pre-determined threshold, a trip signal
is immediately sent to the generator circuit breaker. Usually,
vector surge relays allow this angle threshold to be adjusted
in the range from 2 to 20 degrees. A detailed description of
vector surge relays is presented in [5]. VSRs were simulated as
follows. The generator terminal voltage angle is determined
in every integration step. A reference terminal voltage angle
is computed and updated at the beginning of each elec-
trical cycle. The absolute variation between these two angles, Fig. 4. Performance curves of VSR and frequency relays.
, is calculated in every integration step and com-
pared with the angle threshold . Additionally, the rms value TABLE II
CRITICAL POWER IMBALANCE: COMPARATIVE ANALYSIS BETWEEN FR
of the terminal voltage is also determined in every integration AND VSR ANTI-ISLANDING PERFORMANCES
step. If the angle variation is larger than the angle threshold
and the magnitude of the terminal voltage is larger than the
adjusted minimum voltage , the VSR immediately sends
a trip signal to the circuit breaker. More details about the VSR
computational model can be found in [6].
The main difference concerning the operating principles of
frequency and vector surge relays is the reference value used to
trigger the relay. While the frequency relay uses a fixed refer-
ence, the rated system frequency (60 Hz in this work), the ref-
erence value used by a vector surge relay is updated cycle by
cycle, indeed, the last cycle duration or some average value cal- generation-load profile. For each case of active power imbal-
culated using a few cycles [5], [6]. ance, dynamic simulation is conducted to determine the relay
detection time and then the curves are plotted [6].
In a 60 Hz system, 1 Hz corresponds to 6 electrical degrees.
IV. COMPARATIVE ANALYSIS BETWEEN FREQUENCY RELAYS
Therefore, the relationships presented in Table I are adopted for
AND VECTOR SURGE RELAYS FOR ISLANDING DETECTION
comparison purpose.
In this section, a comparison between the islanding detection The performance curves for three different vector surge and
capability of frequency and vector surge relays is carried out by frequency relays settings are presented in Fig. 4. Results show
using the performance curves. Such curves are obtained through that the performances of both relays are quite similar. The
repeated dynamic simulations. The islanding situation is sim- critical power imbalances for typical relays settings considering
ulated by opening the circuit breaker CB installed at bus 2 at that the required detection time is 300, 500 or 700 ms are
s (Fig. 2), which remains open until the end of the sim- presented in Table II. In this table, the values are in percentage
ulation at s. Then, if the relay installed at bus 5 does of the generator MVA rating; the frequency relay is referred
not become active within 1.0 s, it is considered that this device as FR and the vector surge relay as VSR. It can be noted that
fails to detect the islanding. The active power imbalance of the both relays lead to very similar critical power imbalances. The
islanded system is gradually varied from 0 to 1 pu, referred to significance of this finding is the following: the vector surge
the MVA rating of the generator, by changing the pre-islanding relay does not offer additional advantages than the frequency
VIEIRA et al.: PERFORMANCE OF FREQUENCY RELAYS 1123

TABLE III
INTERCONNECTION SYSTEM RESPONSE TO ABNORMAL FREQUENCIES

relay for anti-islanding protection. As a result, there is no


need to install a dedicated VSR for anti-islanding application
because a frequency relay can be as effective as the vector
surge relay.

V. CONSTRAINTS IMPOSED BY THE FREQUENCY-TRIPPING


REQUIREMENTS Fig. 5. Performance curves of frequency relays for delayed and instantaneous
operation.
Technical guides for DG interconnection recommend that the
generators should not be disconnected instantaneously due to TABLE IV
small frequency variations [1]. Table III shows the frequency- CRITICAL POWER IMBALANCES FOR FREQUENCY RELAYS
tripping requirements recommended in [1] for distributed gen-
erators during abnormal frequencies. As a result, one cannot set
a frequency relay very sensitive for anti-islanding protection.
A well-designed DG protection scheme must satisfy both the
anti-islanding and frequency-tripping requirements simultane-
ously. This section investigates if this objective can be met by
frequency relays.

A. Behavior of Frequency Relays


According to the recommendations stated in Table III, typical B. Application Region of Frequency Relays
time delays vary from 160 ms to 300 s. This delay includes the The results shown in Fig. 5 and Table IV indicate that there
circuit breaker opening time. Thus, time-delay settings as low is a region where the frequency relay can satisfy both anti-
as 100 ms can be used. In this section, a time delay equal to islanding and frequency-tripping requirements. Moreover, it is
300 ms was applied to the lower settings of the frequency relay also shown that a frequency relay can reach such objective if
(0.5 to 1.5 Hz). On the other hand, higher settings were oper- its instantaneous and time-delay settings are properly chosen.
ated instantaneously, as is usual. The required detection times This section proposes a graphical methodology that helps pro-
analyzed were 300, 500 and 700 ms. Dynamical simulations tection engineers to evaluate the frequency relay settings ac-
using the test system of Fig. 2 were carried out to determine the ceptable for both purposes. The methodology defines an accept-
performance curves of frequency relays considering time-delay able operating region for frequency relays in the detection time
and instantaneous settings. The results are summarized in Fig. 5 versus active power imbalance space. Such region is called ap-
and Table IV, where the values of the critical power imbalances plication region of frequency relays. Inside this region, both cri-
are in percentage of the distributed generator MVA rating. The teria are satisfied. Fig. 6 shows the application region for a fre-
second column of Table IV shows that time-delay settings are quency relay considering a required detection time of 500 ms
not able to detect an islanding condition if the detection time re- and the under frequency requirements of Table III. The applica-
quired is 300 ms. Frequency relays with instantaneous settings tion region was obtained by using the performance curves of the
can detect the islanding in all the cases, but the active power im- frequency relay. Such curves were obtained through dynamical
balance necessary to operate the relay can be higher than 50% simulation, using the test system of Fig. 2. It can be observed in
of the generator rated power. When the required detection time Fig. 6 that the application region is delimited by the following
is increased, the critical power imbalance necessary to a suc- curves.
cessful islanding detection decreases. In addition, the third and • Performance curve for the 0.2 Hz setting (59.8 Hz): this
fourth columns indicate that it is possible to coordinate the in- curve represents the lower limit of the region. Between
stantaneous and time-delay settings of frequency relays in such 59.8 Hz and 60 Hz the relay must not operate—this is the
a way that the frequency-tripping requirements are not violated frequency variation immunity requirement. Thus, curves
and the critical active power imbalance is minimized. An ap- below the 0.2 Hz curve refer to settings smaller than
proach to graphically determine these settings is proposed in the 0.2 Hz, which are not allowed. This curve is the frequency
next section. variation immunity curve.
1124 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 21, NO. 3, JULY 2006

Fig. 6. Application region of a frequency relay, considering underfrequency Fig. 8. Application region of a frequency relay: optimum setting.
settings (deficit of active power).

frequency-tripping requirements are satisfied but the islanding


detection capability of the frequency relay is limited by the
critical power imbalance of the 57 Hz-instantaneous curve. In
this case, this occurs if the time-delay is set equal to 500 ms.
On the other hand, if the time-delay stage is adjusted to operate
inside the application region, the frequency-tripping require-
ment is still satisfied and the islanding detection capability is
improved. For example, if the time-delay stage is set to 300
ms or 100 ms, the critical power imbalance is reduced from
38.15% to 33.82% and 21.76%, respectively.
Indeed, using the concept of application region, one can im-
prove even more the islanding detection capability of frequency
relays by choosing a more suitable time-delay setting. Fig. 8
shows the application region and the performance curve of the
frequency relay with a 59.7 Hz, 100 ms time-delay setting. In
this case, the critical power imbalance is reduced to 12.74% and
Fig. 7. Application region of a frequency relay: a practical application the frequency-tripping requirements are not violated. This is the
considering the underfrequency setting of 59 Hz and different time-delays. optimum setting if the relay must meet both requirements simul-
taneously.
• Performance curve for 3 Hz (57 Hz): it represents the In the cases above analyzed, the frequency relay is triggered
upper limit of the region. This curve is related to the instan- due to the under frequency settings because there is deficit of ac-
taneous requirements for the system frequency. Referring tive power in the islanded system. Similar analyzes and conclu-
to Table III, it refers to the 57 Hz setting. Curves above the sions can be obtained for the case with excess of active power,
upper limit curve indicate settings that are not allowed. where the relay is triggered due to the over frequency settings.
• Anti-islanding requirement: it is a horizontal line that rep- Although these cases have been simulated, they are not shown
resents the time required to detect the islanding condition. in this work due to space limitation.
Usually, frequency relays are equipped with two or more
groups of settings, which allow the relay to be configured VI. CONCLUSIONS
with time-delay and instantaneous settings simultaneously.
In the case analyzed in this work, it was assumed that the This paper presented an investigation of the performance of
instantaneous under frequency setting is adjusted to 3 Hz (57 standard under/over frequency relays for distributed generators
Hz), satisfying both the islanding and frequency requirements. protection. The analyzes of the results lead to important conclu-
Fig. 7 shows this situation and the usefulness of the application sions and contributions to protection engineers, which are sum-
region concept. For a 57 Hz setting the critical power imbalance marized as follows.
is 38.15%. The big issue is how to adjust the time-delay stage • Vector surge relays and frequency relays present very
of the relay under frequency setting. Assume that the value of similar performances for anti-islanding detection. Indeed,
59 Hz is chosen as the frequency setting for the time-delay vector surge relays can be considered a special case of
stage. The performance curve for such setting is presented in frequency relays. Thus, frequency relays can replace VSR
Fig. 7 considering different time-delays: 100, 300 and 500 ms. for islanding detection without adverse implications if
If the 59 Hz time-delay curve is above the application area, the proper settings are chosen.
VIEIRA et al.: PERFORMANCE OF FREQUENCY RELAYS 1125

• The frequency-tripping requirement will limit the is-


landing detection capability of frequency-based relays.
In order to determine the relay settings that meet both
requirements the application region of frequency relay can
be used. This graphical approach is the main contribution
of this paper. It can be used to determine the time-delay
settings of frequency relays.
It is worth pointing that the application region can be ex-
tended to any other frequency-based relays, such as vector surge
and rate of change of frequency relays. In the next step, we will
investigate this possibility.
In the Appendix a set of formulas is developed that permits
one to obtain the application region of frequency relays directly.
This procedure decreases considerably the time spent during the
design of frequency-based protection system of distributed gen- Fig. 9. Performance curves of frequency relays obtained by simulations and
erators. analytical formula (constant power loads).

APPENDIX The system angular speed in the time can be represented by


FORMULAS TO DETERMINE THE APPLICATION ; substituting it in (2), follows:
REGION OF FREQUENCY RELAYS
In this appendix, a set of formulas is introduced, which (3)
permits to build the application region of frequency relays
directly. With such formulas, a protection engineer can decide where . Therefore
if frequency relays are suitable for his/her system and adjust the
instantaneous and time-delay settings readily, decreasing the
(4)
amount of simulations considerably. The development of the
formula is based on the reasoning described in [6], however,
Equation (4) gives the relationship between frequency devia-
the final formulas are quite different because the principle of
tion (relay setting), detection time and active power imbalance.
the vector surge and frequency relays are distinct. Firstly, an
Solving (4) for , we have
analytical formula is developed considering constant power
loads. In the sequence, a correction factor is introduced to
extend the results to voltage-dependent loads. (5)

A. Analytical Formula where is the relay setting. Frequency relays can be adjusted
Considering the system presented in Fig. 2, at steady state with time-delay settings. In this case, frequency variation must
the mechanical power of the distributed generator is bal- persist during a pre-defined interval of time to activate the relay.
anced with the load electrical power and the electrical power Thus, the relay time-delay setting must be introduced in (5) as
provided (or consumed) by the power grid. Therefore, follows:
the distributed generator rotor speed and angle are constant.
If some disturbance occurs provoking an active power imbal- (6)
ance , the system frequency starts to change because the
power imbalance causes transients in the distributed gener- where is the time-delay applied. With (6), one can obtain
ator. The dynamic behavior of the synchronous generator can be the detection time versus power imbalance curves and, conse-
determined by using the machine swing equation. In the mathe- quently, the application region. The validity of the mathemat-
matical development below, the following assumptions are con- ical development is confirmed by simulation, considering con-
sidered: (a) the load is represented by a constant power model; stant power loads in the system of Fig. 2. The relay performance
(b) the generator is represented by the classical model. The curves obtained by simulation and the formula are presented in
swing equation of the synchronous generator is given by Fig. 9 for different instantaneous and time-delay settings. Very
good match can be observed between the two sets of the relay
performance curves.
(1)
B. Modified Empirical Formula
where is the generator inertia constant, is the synchronous
The analytical formula developed in the previous subsection
speed and the other variables have been defined previously. The
considers that the power imbalance after the opening of the cir-
rotor speed can be solved from (1) as
cuit breaker is constant. However, it occurs only if the loads have
characteristics of constant power. In addition, the islanding de-
(2) tection capability of frequency-based relay should be analyzed
1126 IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 21, NO. 3, JULY 2006

Fig. 10. Performance curves of frequency relays obtained by simulations


and by the modified empirical formula (constant impedance loads—the most
conservative case). Fig. 11. Application region of frequency relays obtained by simulations and
analytical formula (constant impedance loads).
taking into account the most conservative (pessimistic) situa-
tion, i.e. the situation where the critical active power imbalances
assumes the highest values. This occurs in the presence of con-
stant impedance loads [6]. In this case, the active power imbal-
ance may decrease after the islanding, becoming more difficult
to detect the islanding situation.
Based on extensive simulations carried out in different sys-
tems with different distributed generators, it has been observed
that the largest active power imbalance variation in the presence
of constant impedance loads is usually between 10% and 30%.
Such variation depends on the characteristic of the system and
generator as well as on the operating point. Thus, a 20% reduc-
tion factor can be roughly applied to active power imbalance in
(6). Furthermore, based on the results presented, it can be veri-
fied that the detection time increases almost exponentially when
the power imbalance decreases. Thus, the 20% reduction factor
should not be applied directly to different values of power im- Fig. 12. Application region of a frequency relay: optimum setting by using
balance. Adopting that the power imbalance correction factor formula (8).
affects the power imbalance in an exponential way, the final
power imbalance can be calculated as plication regions of the frequency relay obtained by simulation
and by formula (8) are compared in Fig. 11. Note that one region
(7) is over the other. It can be observed that reasonable accuracy is
obtained by using the modified empirical formula.
where is the initial power imbalance value at the instant
The possibility of obtaining the application region of fre-
of the opening of the circuit breaker. This power imbalance re-
quency relay and the performance curves using the formula
places in (6) to determine the frequency relay performance.
permits that protection engineers evaluate the efficiency of
Thus, the final modified empirical formula is given by
frequency-based protection systems of distributed generators
directly. This approach can also be used to determine the
(8)
best instantaneous and time-delay settings of frequency relays
regarding islanding detection and frequency-tripping require-
The accuracy of the modified empirical formula is shown in ments simultaneously. This procedure can save time during
Fig. 10, where the performance curves for instantaneous and project stage.
time-delay settings obtained by simulation and by the modified For example, the optimum time-delay setting can be esti-
empirical formula (8) are compared. Again very good match mated through formula (8) using the same procedure adopted
can be observed between the two sets of the relay performance in the previous section, where simulations were used. Fig. 12
curves. shows the application region and the performance curve for the
case in which the time-delay relay setting is adjusted equal to
C. Application Region 59.7 Hz, 100 ms. This figure was determined by using formula
The above mathematical development can be used to deter- (8). It can be verified that this setting does not violate the fre-
mine the application region of frequency relay directly. The ap- quency-tripping requirements and minimize the critical active
VIEIRA et al.: PERFORMANCE OF FREQUENCY RELAYS 1127

power imbalance. This result is similar to that obtained in Sec- Walmir Freitas (M’02) received the Ph.D. degree in electrical engineering from
tion V-B through simulation (Fig. 8). the State University of Campinas, Campinas, Brazil, in 2001.
From 2002 to 2003, he was a Post-Doctoral Fellow at the University of Al-
berta, Edmonton, AB, Canada. Currently, he is an Assistant Professor at the
ACKNOWLEDGMENT State University of Campinas. His research interests are power system stability
and control along with distributed generation.
The authors would like to thank Dr. Z. Huang of the Energy
Science and Technology Division, Pacific Northwest National
Laboratory, for his comments and help during the development
of this work.

REFERENCES
[1] IEEE Standard for Interconnecting Distributed Resources With Electric Wilsun Xu (M’90–SM’95–F’05) received the Ph.D. degree from the University
Power Systems, IEEE Std. 1547™, Jul. 21, 2003. of British Columbia, Vancouver, BC, Canada, in 1989.
[2] G59/1 Recommendations for the Connection of Embedded Generating From 1989 to 1996, he was an Electrical Engineer with BC Hydro, where he
Plant to the Regional Electricity Companies Distribution Systems, 1991. was responsible for power quality and voltage stability projects. He is currently
[3] “Impact of Increasing Contribution of Dispersed Generation on the an Adjunct Professor at Shandong University, Shandong, China, and a Professor
Power System,” CIGRÉ, Working Group 37.23, 1999. at the University of Alberta, Edmonton, AB, Canada. His main research interests
[4] “Dispersed Generation,” CIRED, CIRED Working Group 4, 1999. are power quality, voltage stability, and distributed generation.
[5] N. Jenkins, R. Allan, P. Crossley, D. Kirschen, and G. Strbac, Embedded
Generation, 1st ed. London, U.K.: Inst. Elect. Eng., 2000.
[6] W. Freitas, Z. Huang, and W. Xu, “A practical method for assessing the
effectiveness of vector surge relays for distributed generation applica-
tions,” IEEE Trans. Power Del., vol. 1, pp. 57–63, Jan. 2005.
[7] P. Kundur, Power System Stability and Control. New York: McGraw-
Hill, 1994.

Andre Morelato (M’89) received the Ph.D. degree in electrical engineering


Jose C. M. Vieira (S’97) received the M.Sc. degree in 1999 from the State from the State University of Campinas (UNICAMP), Campinas, Brazil, in 1982.
University of Campinas (UNICAMP), Campinas, Brazil, where he is currently Currently, he is a Full Professor of Electrical Engineering with the Depart-
pursuing the Ph.D. degree. ment of Electrical Energy Systems, UNICAMP. From 1991 to 1992, he was with
From 1999 to 2003, he was a Consulting Engineer with FIGENER, Sao Paulo, Hitachi Research Laboratory, Hitachi Ltd., Hitachi City, Japan. His research in-
Brazil. His research interests are distributed generation, power system control, terests are power system control and stability, distributed generation, and par-
as well as dynamic and optimal power flow and energy markets. allel processing applications.

You might also like