Professional Documents
Culture Documents
Technical Guidelines on
Building Demolition Work
in Sri Lanka
National Building Research Organisation
OCTOBER 2019 //
Published by:
Funded by:
Government Research Grant - 2018
Copyright Reserved
No part of this Publication shall be reproduced or transmitted in any form or by any means without
permission of the National Building Research organisation (NBRO).
Disclaimer
With regard to the information available in this Document neither the National Building Research
Organisation nor any of its employees and/or agents make any warranty, express or implied or assumes
any legal liability or responsibility for accuracy or completeness of any information. The National
Building Research Oranisation shall not be liable to you or any third party for any, direct, incidental,
consequential or exemplary damages or loss of profit resulting from any use of such information.
i
FOREWORD
In the recent past, a series of tragic incidents with fatalities associated with building
demolition work have been reported specially in urban areas of Sri Lanka.
ii
Eng.(Ms.) Ishani Kulasekara - Assistant Director, Technology and
Research,
Construction Industry Development
Authority
My special thanks are due to Eng. (Mrs.) J.K. Jayawardena, Director Project
Management Division who first, conceptualized this initiative and also headed the
Steering Committee.
I greatly appreciate the valuable constructive suggestions & guidance offered by Archt.
G.A.P. Ganepola, Consultant Architect, NBRO and Dr. (Eng.) Sudhira De Silva, Senior
Lecturer, University of Ruhuna, Eng. Clarence Perera, Consultant, NBRO throughout the
planning, development and finalization of this Publication.
I wish to acknowledge with grateful thanks the support extended in numerous ways by
the NBRO staff towards successful completion of this Task.
I am also very grateful to the contractors in the field of building demolition who
supported the NBRO Research Team in numerous ways.
I hope that this Publication will be a useful guide at national level for relevant
professionals in the construction Industry in planning & direction, monitoring &
supervision in ensuring safety of life and property.
iii
PREFACE
Focus attention has been drawn to selected building demolition processes of different
scales recently carried out in Colombo while reviewing relevant on-going practices in
Sri Lanka as well as globally adopted codes and practices on building demolition.
These Technical Guidelines have been formulated mainly on the following in line with
the appropriate practices adopted globally:
iv
GLOSSARY
In this document, unless the context otherwise requires, the following interpretation of terms
and definitions holds good and correct solely for the purpose of this guideline
v
Catchfan is a temporary structure erected around and attached to or
abutting the exterior wall of the building being demolished
for the purpose of catching and retaining debris that fall
outside the building
Covered means a temporary structure with protective roof erected
Walkway along the site boundary and on or adjacent to the existing
footpath to protect pedestrians from the falling debris
during demolition
Hoarding means a temporary fence enclosure erected along the site
boundary to separate the demolition site from the adjacent
properties
Shoring System of auxiliary supports which provides a load path
to maintain stability during temporary states of the
structure
ABBRIVIATIONS
vi
CONTENTS
Page No.
Foreword ...........................................................................................................ii
Preface .............................................................................................................. iv
Glossary ............................................................................................................ v
Abbriviations ................................................................................................... vi
Table of Figures............................................................................................... ix
1. INTRODUCTION ..................................................................................... 1
2. Demolition Approaches............................................................................. 3
vii
6.1 Debris loading and unloading .............................................................. 32
References ....................................................................................................... 89
ANNEX 01 ........................................................................................................ 1
ANNEX 02 ........................................................................................................ 1
ANNEX 03 ........................................................................................................ 3
Sample Demolition Plan And Stability Report For Top Down mechanical
method ......................................................................................................... 4
ANNEX 04 ...................................................................................................... 11
viii
TABLE OF FIGURES
Page No.
ix
Figure 7.6 - Personal Protective Equipment ............................................................................ 52
Figure 7.7 - Site personal health governing factors ................................................................. 56
Figure 7.8 - Pressurized water spraying during demolition ..................................................... 58
Figure 8.1 - Flow chart for demolition sequence ..................................................................... 62
Figure 8.2 - Demolition of Cantilevered Reinforced Concrete Slab (Manual Method) .......... 63
Figure 8.3 - Demolition of Cantilevered Reinforced Concrete Slab and Beam (Manual Method)
.................................................................................................................................................. 64
Figure 8.4 - Demolition of external Beam (Manual Method) – dismantle the entire beam section
.................................................................................................................................................. 66
Figure 8.5 Adjustable steel jacket ............................................................................................ 67
Figure 8.6 - Details for Securing External Beams before Dismantling (Manual Method) ...... 67
Figure 8.7 – Pre-weakening of column – cut reinforcement in exterior side .......................... 68
Figure 8.8 - Pre-weakening and dismantling of column (Manual Method) ............................ 68
Figure 8.9 - Felling of a reinforced concrete wall with beam (Manual Method) .................... 70
Figure 8.10 - Felling of reinforced concrete wall separately from the cross beam (manual
method) .................................................................................................................................... 71
Figure 8.11 - Demolition of two way slab (Manual method) .................................................. 72
Figure 8.12 - Demolition of secondary beam (Manual Method) ............................................. 74
Figure 8.13 - Details for securing secondary beams before dismantling (Manual Method) ... 75
Figure 8.14 - Typical sequence of top down method with mechanical equipment ................. 80
Figure 8.15 - Demolition of cantilevered slab by mobile machine (conventional method) .... 81
Figure 8.16 - Demolition of reinforced concrete frame by excavator with breaker ................ 85
Figure 8.17 - Demolition of reinforced concrete wall by excavator ........................................ 87
x
LIST OF TABLES
Page No.
xi
Section 01
1. INTRODUCTION
This draft guideline was prepared to provide guidance on safe and good practices for
demolition works. Current practice of building demolition projects is mostly done using
the experience of the contractor. Introducing this guideline would make them aware of
the technical approach to the demolition activities.
1.1 Scope
Above mentioned scope had been established in the preparation of this guideline,
and this document covers only the subject matter falling within that scope. Any
other demolition method or activity may also be used subject to careful
consideration and recommendations made by a Registered Structural Engineer.
1
Section 01
The following documents were used in the preparation of preparing this document;
Given in Annex 04
2
Section 02
2. DEMOLITION APPROACHES
The following are some different options associated with building demolition
Complete
Demolition
Reuse
Partial Demolition
Rebuilding
Demolition Options
Whilst in Use
Structural
Refurbishment
Whilst not in Use
Following factors shall be taken into account when deciding the demolition process:
3
Section 02
In demolition activities the final anticipated outcome is the removal of the building
by executing a safe procedure to remove the building.
Three suitable methodologies for building demolition have been listed below.
a) Manual Method;
Manual Demolition
Remotely controlled machines and robotic devices
High-reach machines (Hydraulic crushers with long boom arm, Wrecking
ball)
Cutting by drilling and sawing
Use of chemical agents
Using explosives
High-pressure water jetting
There are number of demolition techniques available apart from the techniques
listed above. In this guidelines it is focused on Manual demolition methods and
mechanical demolition method only (Using excavator with breaker and excavator
with hydraulic crusher). Other methods of demolition can be used as per the
instructions and guidance by the Registered Structural Engineer.
4
Section 02
i. Client;
ii. Occupier of the building;
iii. Contractor;
iv. Any third parties.
5
Section 03
3.1.1. General
Following factors as described in Section 3.1.2 to 3.1.8 shall be addressed;
Before starting demolition work, the following factors should be studied and
these listed factors have been further described throughout the document.
Public
protection
Program and Structural
time stability of the
framework building
legal
Environmental
requirement
Management
and consents
6
Section 03
7
Section 03
Note 1: Project start and end dates shall be clearly mentioned in the
work program.
8
Section 03
a) Noise control;
b) Dust emission control;
c) Waste management;
d) Reuse and recycle methods of demolition waste;
e) Hazardous waste management;
9
Section 03
f) Air quality;
g) Ground vibration;
h) Conservation of environmental sensitive areas,
ecological, historical valuable areas.
a) Insurance cover;
b) Precautionary measures taken to protect the public and site
personnel;
c) Protection to adjacent properties;
d) Safety precautions taken for site personnel;
e) Health hazards;
f) Environmental Precautions.
10
Section 04
(a) Layout plan showing adjoining properties and their present uses
(provide in the reference - service station storing fuel,
warehouses, industries, public buildings such as schools,
hospitals and places of worship and buildings used as homes for
the disabled, children and the elderly);
(b) Neighboring building types (e.g. Schools, hospitals, residential,
commercial etc.) and dimensions and distance to the demolition
site;
(c) Neighborhood sensitivity to noise, vibration, dust and traffic
impact;
(d) Common staircases and party walls shared with adjoining
buildings;
(e) Pedestrian pavements, walk paths, hoarding and the requirement
for covered walkways;
(f) Roads, streets and railway lines;
(g) Record of existing traffic condition;
11
Section 04
12
Section 04
Note: If structural details are unavailable then cover meter tests, inspections
using BPR (Building Penetrating Radar) and bar sizes of the main elements
with approximate strength of the concrete shall be obtained by conducting
tests. Also examination of rebar condition by exposing some key structural
elements should be done as a part of condition assessment of the building.
13
Section 04
14
Section 04
15
Section 04
Format
This shall be prepared by the Registered Structural Engineer and shall include
the following:
16
Section 04
A check list for preparing a Demolition plan and stability report is depicted in
Annex 01
17
Section 05
18
Section 05
Yes
No
No this?
Yes
Figure 5.1 – Flowchart for ascertaining structural stability of the building for
demolition
(Source: BS 6187:2011 code of practice for full and partial demolition)
19
Section 05
Figure 5.2 - Space frame roof structure at Pallekele stadium, Sri Lanka
(https://www.inspirock.com/sri-lanka/kandy/pallekele-international-cricket-
stadium-a1139395553)
20
Section 05
http://www.nkb.nu/wp-content/uploads/2017/08/kia-led.jpg
21
Section 05
http://static.monolithic.com/gallery/nonprofit/solidhouse/pic13.html
https://pbs.twimg.com/media/DgOnFo2W4AE3ph2.jpg
22
Section 05
(a) (b)
https://skyrisecities.com/news/2017/04/tragedy-sparked-decline-lift-
slab-construction
v. Retained facades.
23
Section 05
https://www.google.com/maps/@6.9234131,79.8523035,3a,75y,357.68h,94.0
7t/data=!3m6!1e1!3m4!1s0kwmSNYOlRRuH9xdvSLthQ!2e0!7i13312!8i665
6
https://www.rmdkwikform.com/wp-content/uploads/2018/02/Refurbishment-
Portfolio-UK.pdf
24
Section 05
Source:https://www.som.com/FILE/16098/mccormickplacephase2_1
575x900_sadin_photo_group_ltd__1989_ben_altman_01jpg.jpg
25
Section 05
Demolition plan shall be prepared taking into consideration all structural aspects
before and during demolition and giving methods and sequences of work properly,
so that sudden and unintentional collapses can be prevented.
Approx. 9.14 m
(30’) height
walls
Without lateral
supports
(a) (b)
26
Section 05
Figure 5.11 - Collapsed building during demolition (a) 9.14 m height walls
without lateral supports (b) Collapsed building to the adjacent site causing
fatalities
CAUTION 2: Some floor slabs are strong in one direction but weak in
another direction. Therefore, this sensitivity to the orientation should be
carefully studied before imposing loadings such as machines or with
debris.
27
Section 05
28
Section 05
should be carried out carefully with in a contained area so that the surrounding
areas are safe. Debris removal should be done only when demolition or
modification work is not in progress.
Whenever there is sufficient buffer zone, sufficient working space and accurate
predicted debris area are all available then demolition of low-rise building can
be carried out at the ground level easily using machine mount on ground.
29
Section 05
1 – Exclusion zone
2 - Lift shaft
3 - Stairwell
Figure 5.14 - Typical structure demolition sequence working "top down"
outwards towards shear walls (strong points), i.e. lift shafts and stairwells
30
Section 05
shims1 shall be placed between the voids to control the premature collapse.
These demolition methods shall be approved only by Registered Structural
Engineer.
1 31
Shims - thin strip of material used to align parts, make them fit
Section 06
Debris generated in demolition sites are falling in the Construction and Demolition Waste
Category (C & D). In Sri Lanka generally around 40% of total waste generated are C &
D Waste (Central Environmental Authority, Guidelines on Sustainable Management of
Waster Matter Generated in the Construction and Demolition of Buildings, 2017).
In the Demolition sites, the demolition contractor is responsible to ensure that the
waste generated in the demolition site are handled and disposed properly complying with
the existing regulations. Following described are further details to refer and it is always
encouraged to reuse and recycle the debris generated to minimize the impact to
environment.
Demolition plan shall include waste management plan including method of debris
loading and unloading and precautionary measures taken to reduce risk involved in
those activities. A safe route and time plan shall be implemented with minimum
disturbance to the surrounding area.
When debris are allowed to fall freely to ground, exclusion zone or chute shall be
placed and appropriate measures to taken off the bouncing effect and dust created.
Effective communication should be established to ensure that the exclusion zones
are clear from personals. The safety officer shall be present at site to ensure the
safety.
6.1.1. Chute
Chutes are used to move debris from higher floor levels to down floor levels.
In demolition sites generally lift shafts are used as a chute. Debris shall be
removed periodically. If openings are created on floor following shall be
ensured;
i. Total openings shall not be greater than 25% of the total 1aggregate floor
area;
ii. Each opening shall not be larger than 900 × 900 mm unless it shall be
justified by engineering calculation remaining structure is safe to
withstand the impact force during demolition;
1
Aggregate floor area - the aggregate area of every floor in a building or extension, calculated by
reference to the finished internal faces of the walls enclosing the area, or if at any point there is no
such wall, by reference to the outermost edge of the floor 32
Section 06
iii. When forming openings, structural elements such as beams shall not
damage/cut any;
iv. Opening shall be protected by edge barriers.
https://www.hss.com/hire/p/rubbish-chute-section
33
Section 06
If chutes are created externally, adequate clear space and dust barrier shall be
present. Old metal barrels shall not be used to create refuse chutes. External refuse
chute shall be with adequate strength to withstand the impact when debris are
falling through the chute.
- Lowering the
Reduce amount of waste
produced
- Using Materials
Reuse repeatedly
34
Section 06
35
Section 06
36
Section 06
Firstly, ascertain the extent of hazardous risk which associate with the
chemicals and implement the preventative and protective measures required
for treatment and safe disposal.
For electronic waste, burning and disposal shall be avoided and storing
should have done carefully at all times. Specifically, before sent to the
recycling, compound/fluorescent electric bulbs should handle carefully.
Direct regulations for demolition waste management in Sri Lanka are not available.
But following regulations are relevant to management of demolition waste in Sri
Lanka.
Solid waste management rule of Western Province No.01 of 2008 were introduced
via extraordinary Gazatte No.1560/6 on 30th July 2008 status as any solid waste
generated from construction or any rubble or debris from demolition shall not be
37
Section 06
mixed with any other waste and shall be handed over to the respective Local
Authority or Authorized Body.
38
Section 07
Contractor shall obtain an insurance cover at least one from the following
categories. (This is a mandatory requirement for the contractor)
Demolition of a building is associated with risk based activities which can affect
the site personnel, general public, pedestrian, adjacent properties and traffic. Site
safety features shall be designed and prevent vulnerability of accidents, difficulties
attached in demolition activities and ensure the safety of the people. Proper safety
features shall be designed considering all possible loads and load combinations at
each stage of demolition and vibration impact by the Registered Structural
Engineer in order to make sure that the demolition can be carried out safely and the
site personnel is protected. The Contractor (Demolition) shall carry out the
demolition works including precautionary measures in accordance with the
approved plans and other related documents, and provide continuous supervision
to the works.
39
Section 07
Precautionary Prerequisite
measure
Hording a clear space between the building line and the lot
boundary equal to or more than the building
height (clear space)
Covered with clear space less than the building height
walkway
Covered With clear space less than half the building height.
walkway with No catch platform is required for building less
catch platform than 4 m high
hoarding and/or along the full length of the site boundary adjacent
covered to public access
walkway
40
Section 07
Building
Hoarding
H
Covered walkway
41
Section 07
Covered walkway
42
Section 07
b) Screen Covers
Over the scaffolds, two layers of protective screen shall be fixed to
completely enclose the building structure for retaining dust and small
debris.
c) Catch fan
Catch fans are installed to catch small pieces of building debris which
can pass through the protective screen and the net. A small piece could
be harmful when falling from heights with carried kinetic energy.
43
Section 07
ground), flying shores (horizontal props which transfer load to a stiff point
at same level in areas such as lift core or return wall).
(https://www.lakeside-hire.co.uk/towers-cantilever-scaffold-towers/ )
44
Section 07
(http://www.apexscaffolddesign.com/ind_portfolio.php?id=24#)
When the demolition affects adjacent properties such as buildings, utilities, slopes,
retaining walls or land precautionary measures shall be taken by means of above
Section 7.2 mentioned methods or any other. Shared party walls, stair cases,
maintaining access for adjacent properties need to pay special attention.
1.2.1. Vibration
Depending on the demolition method vibration will effect on neighboring
buildings in various extent. Also the traffic vibration caused by heavy duty
vehicles might effect in a significant level. Demolition contractors are
advised to carry out vibration monitoring and if needed pre-crack survey as
recommended by the Registered Structural Engineer.
45
Section 07
46
Section 07
Reduction measures: use equipment which are high tech with low vibration
mechanics, debris falling height reduce or use vibration absorbing materials
such as rubber at the point of falling, if possible temporary ground separation
between the source and receiver.
7.2.2 Shoring
Shoring shall be required in demolition work such as removing foundation,
demolition of buildings with basements etc.
47
Section 07
Contractor or his representative shall monitor the demolition work full time
throughout the day and ensure the safety of the partially demolished structure
at the end of the day before leaving the site.
48
Section 07
49
Section 07
50
Section 07
Site Safety
51
Section 07
Ear Plugs
Safety Boots High visibility cloths
a) Effective communication
b) Training on emergency procedures
c) Equipment for rescue and resuscitation
d) Measures for raising the alarm and rescue
e) Fire safety measures
f) First aid
52
Section 07
Following are some works which can damage the service lines:
53
Section 07
e) Temporary utility supply shall be given which will be needed for the
execution of the demolition work.
7.4.9. Maintenance of Certain Utilities
During demolition, the following shall be required to provide a safe and
healthy working environment:
a) Temporary water supply shall be required to provide water
spraying during demolition as dust pollution abatement
measures;
b) Temporary telecommunication link between the demolition site
and outside shall be maintained for both security and
communication reasons;
c) Temporary electricity supply for lighting and other construction
use;
d) Necessary approval shall be taken for temporary utility supplies;
e) In the case when temporary utilities are available, all such
temporary utilities, including electrical fittings shall be weather-
proofed;
f) Safety warning lights indicating connection lines and
“Emergency Stop” of connection lines;
7.4.11. Flooding
When demolition take place in areas like deep basements, underground
tunnels, cooling water culverts, plant rooms and excavations, the
contractor shall pay special attention to assess the risk of flooding.
When the work program is preparing adequate time allocation and
necessary precautions shall be given with predicted weather condition.
54
Section 07
Traffic controller outside the site shall be appointed and active alarms,
active warning alarms shall be installed. Sufficient illumination level
should be maintained outside the site, especially near walkways.
55
Section 07
Exposure to
dust
Occupational Exposure to
diseases chemicals
Fire damage
First aid
and
facilities
ventilation
Noise
Sanitation
exposure
Welfare facilities for the site personal shall be provided and maintained
sufficiently including sanitary facilities (including clean water and
washing facilities). Accommodation shall be provided in the immediate
vicinity to the site with convenient access for the work place.
b) First aid
A first aid box shall be present at site with enough equipment to cope
with the number of workers on site. A responsible person shall be
appointed at the beginning of the work to take charge of first aid
arrangements.
7.5.2. Lone-working
Lone workers are those who work by themselves without close or direct
supervision. The contactor has a duty to assess the risks to lone workers and
56
Section 07
57
Section 07
b) Noise
When the site personnel are exposed to noise at the construction sites
proper safety equipment should be made available. The employer
should provide safety gear to personnel if the noise exposures or exceed
an eight hour time weighted average sound level of 85 dBA.
For the increase of each 5dB the exposure period should decrease by
two fault. (Multiply by 0.5)
When the site personnel are exposed to sound levels exceeding those
levels administrative or engineering controls must be used. Concrete
cutting is a huge noise hazard on site and it is often around 110-
115dBA.
58
Section 07
7.6.3. Water
In demolition site main cause for water pollution is water contaminated with
demolished material which generally increase turbidity and dissolved matter.
Therefore use of simple filtering system or sedimentation tank will be
satisfied to treat waste water. However contamination with other chemical
materials may need satisfactory treatment.
The management of waste must fully comply with the Waste Disposal
Ordinance of CMC
59
Section 08
8. METHODS OF DEMOLITION
There are many techniques used in the world for demolition of buildings. Compact
machines, high-reach machines, tower and other high-reach cranes, remotely controlled
machines and robotic devices, demolition using chemical agents, by explosives, high
pressure water jetting and metal powder cutting etc.
This guideline describes only the demolition of common structural elements by manual
and mechanical (machine) methods. Other techniques mentioned above shall not be
discussed in this document.
8.1 General
The choice of the demolition method depends on the following factors as given in
clause 2.2
b) Structural Characteristics
c) Site Conditions/Locations
d) Demolition Cost
e) Time/Duration
This guideline describes only the demolition of common structural elements (slab,
beam and columns) by manual and mechanical (machine) methods. Other
techniques mentioned above shall not be discussed in this document. Each building
has its specific features to consider. Therefore, the demolition procedure for each
site has to be proposed by a competent engineer under guidance of Registered
Structural Engineer considering the factors given in Section 8.1.
For sites situated in busy urban areas, most applicable method is top down method.
If there is sufficient clear space, other mechanical methods which are applied from
the outside of the building may be used. Hand held tools or the cut and lift process
60
Section 08
may be used as a safe solution for structural projections such as balconies, canopies
and verandahs extending beyond the building lines.
Structural elements shall be broken down leaving the reinforcement, until the
concrete connecting to reinforcement is sufficiently broken away. In congested
areas cantilevered canopies, balconies and exterior walls are critical elements due
to the risks to the public.
If rope or tie wires are used to pull down the structural elements, the pulling wire
must be at least 4 times stronger than the anticipated pulling force. In addition,
workers shall be shielded from the rope or tie wires. The rope or tie wire shall be
checked at least twice per day.
a) Doors, windows and non- structural features shall be removed and re-
used as much as possible;
b) Prior to demolition of main structure, all cantilevered structures,
canopies, verandahs and features attached to the external walls shall
first be demolished;
c) All lift machine rooms and water tanks at the top shall be demolished
to the main roof level in “top down” sequence and roof structure shall
be dismantled or removed, and the material be re-used where
applicable;
d) Demolition of the floor slabs shall begin at mid span and work towards
the supporting beams;
e) Floor beams shall be demolished according to the order given below:
i. cantilevered beams;
ii. secondary beams;
iii. main beams.
61
Section 08
Roof structure
Floor beams
62
Section 08
63
Section 08
8.2.3. Arches
Arches can be fixed type or hinged type. Forces in the arches are carried to
ground as thrusts. In order to ensure the stability of the arches during
demolition, forces shall be balanced. Following can be applied where
applicable:
64
Section 08
Dismantling the entire beam section as shown in (b) Step 02: Lowering of
beam
65
Section 08
66
Section 08
Figure 8.6 - Details for Securing External Beams before Dismantling (Manual
Method)
c) Exterior Column
i. Using a wire and winch, top of the column shall be secured by
tying it to a nearby structural member;
ii. Bottom of the column shall be pre-weaken by breaking away the
concrete cover and cutting the reinforcement at the exterior side
of the column as shown in Figure 8.7;
67
Section 08
(iii) After pre-weakening, the column shall be pulled down by the wire and
winch towards the interior in a controlled manner (Figure 8.8).
68
Section 08
69
Section 08
Figure 8.9 - Felling of a reinforced concrete wall with beam (Manual Method)
70
Section 08
Figure 8.10 - Felling of reinforced concrete wall separately from the cross beam
(manual method)
71
Section 08
c) Flat Slab
A flat slab is a two-way reinforced concrete slab that usually does not
have beams or girders, and the loads are transferred directly to the
72
Section 08
73
Section 08
74
Section 08
When demolition is done using machines, first the mechanical plant is lifted and
placed on the slab using mobile crane or any other suitable method. Rest of the
sequence of top down by machine is similar to the top down manual method only
the demolition is done using mechanical plant. If rope or tie wires are used, wire
strength shall be at least 4 times the anticipated load and workers shall be protected
or stay away from the pulling area.
Structural Engineer shall assess the imposed load and the vibration induced
by the mechanical plant and adequate supports shall be provided. The
movement of the mechanical plant shall be prohibited in areas such as
building edges (minimum distance of 2m), floor openings (minimum
distance of 1m) and cantilever structures. Boundary of the mechanical plant
moving shall be marked by appropriate methods.
75
Section 08
b) Lifting of Machinery
Mechanical plant shall be moved down to the next floor by means of a ramp
made of steel or any other material which can be safely bear the load of the
mechanical plant and ramp shall be dismantled after moving the mechanical
plant.
76
Section 08
77
Section 08
78
Section 08
79
Section 08
Figure 8.14 - Typical sequence of top down method with mechanical equipment
80
Section 08
81
Section 08
82
Section 08
83
Section 08
84
Section 08
(a)
(b)
85
Section 08
(a)
(b)
86
Section 08
(c)
(d)
87
Section 08
Structure with basement or retaining wall shall be demolished under the guidance
and recommendation of a Registered Structural Engineer. Additional information
88
Section 08
REFERENCES
2. BSI. (2011). BS 6187 Code of Pracxtice for Full and Partial Demolition of Buildings.
British Standard Institute.
7. Sri Lanka Institute of Architects. (2016). Construction Site Safety Manual for
Consultants. Colombo 07: Professional Affairs Board, Sri Lanka Institute of Architects.
89
Annex 01
ANNEX 01
1
Annex 01
2
Annex 02
ANNEX 02
1
Annex 02
Industry Associations
Training Bodies Advance Construction Training Academy
2
Annex 03
ANNEX 03
3
Annex 03
1.2.1. The stability report of this project shall consist of the following:
a. A Stability report to justify the safety of the existing building
during all phases of demolition.
4
Annex 03
Stability Report
A Stability report to justify the safety of the existing
building during all phases of demolition.
A structural check with calculation on the support of
cantilevered slab and beams if available
A structural check with calculation on the support to typical
floors catering for the loading due to powered mechanical
plants
A structural check with calculation on the temporary ramp
design to allow the descending of the machines
A stability report with calculation to justify the safety of
lifting of the machine to the roof
A structural check with calculation on its hoarding,
covered walkway, and catch platform
5
Annex 03
- Address
- Contact details
2. Description of site area
- Address
6
Annex 03
3. Boundary Conditions
- North
- East
- South
- West
- Topography
4. Traffic Condition
5. Adjacent Utilities
- Above ground
- Under ground
- Structural conditions
Ex. No significant deterioration or damage to the structural element
or significant foundation settlement were observed. These adjacent
buildings appear to be properly maintained and would not be
adversely affected by the demolition of the building
7
Annex 03
- Details if available
Building Details
7. General information and dimensions
- Age :
- Use :
- Overall height
- Structure
Ex. The building is reinforced concrete construction with
conventional slab, beam, column and rigid frame design. It
is supported on pile foundation
- Present State
8
Annex 03
- Emergency exit
- Fire prevention
18. Training
19. Dust and noise
20. Maintenance and inspection
21. Emergency plan
9
Annex 03
10
Annex 04
ANNEX 04
11
Annex 04
12