You are on page 1of 4

Feature

Cover Story
Report

Implementing a Corrosion-
Under-Insulation Program
CPI facilities need to put Phase 1
Initiate CUI
CUI Initial Descision Tree
evaluation, identify
in place a systematic suspect equipment Pre-inspection

program for preventing


and mitigating corrosion Is
construction NO
Is it
austenitic NO
Consult
with materials
material carbon stainless engineer for CUI
under insulation steel? steel? susceptibility
YES
YES
Russ Davis
The Mistras Group, Inc. Is
Operates Cycling Cycling operating
NO in and out of in and out NO temperature
between 10

C
orrosion to the external sur- and 400°F? 10 and 400°F of 120 and between 120 and
range? 400°F? 400°F?
face of process piping and ves- NO
sels that is hidden under the
insulation is referred to as No CUI expected
YES YES YES YES
corrosion under insulation (CUI).
Aging piping and equipment in
chemical plants and petroleum re- Implement
Potential for
Potential for risk-based
fineries have made CUI detection CUI exists inspection stress-corrosion
cracking exists
and assessment requirements in- program
creasingly important. Because the
need to detect and assess CUI is
critical in chemical process indus- IDMS download Perform risk
of identified assessment
tries (CPI) facilities, inspection and equipment to prioritize
testing methodologies have been susceptible to CUI inspection plan
pushed to improve. However, many
CPI facilities lack an insulation- FIGURE 1. The initial phase
Perform field of a comprehensive CUI pro-
repair program. The best approach walkdown, review gram involves a team assess-
to address the problem of CUI is to asset history,
cyclic service, ment of process vessels and
develop and adopt a comprehensive plant turnaround piping to determine which
schedule pieces of equipment may be
and facility-wide CUI program. This
susceptible to CUI
article describes the components of
such a program and is designed to
help facility managers and engi- the risk posed by CUI for potential steels are also susceptible to CUI,
neers identify strategies to imple- exposure to hazardous chemicals, as especially in coastal geographic re-
ment it. well as the potential fire and explo- gions where the normal atmosphere
Industry estimates indicate that sion hazards, resulting from the loss contains chlorides and where the
CUI costs the chemical and oil-and- of containment of highly hazardous equipment operates between 140°F
gas industries in excess of $100 mil- chemicals. Sometimes, corrosion- (60°C) and 400°F (205°C). Chloride-
lion annually. This cost represents preventive painting programs are induced stress corrosion cracking
only the estimated damage to the cut when budgets are tight. (SCC) has been found in austenitic
equipment, and does not include CUI primarily affects carbon- stainless steels due to the chloride
the losses that may be associated steel and low-alloy steel vessels and content of the normal environment.
with process downtime. Taking piping. Operating conditions noted
equipment and piping out of ser- for making equipment susceptible Program components
vice when they are needed to make to CUI range from 10°F (–12°C) It is essential that a programmatic
product will raise the level of losses. to 400°F (205°C). Austenitic stain- approach to reducing the risk of
This estimate also does not include less steels and duplex stainless operations includes a focus on CUI
40 CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2014
TABLE 1. NON-DESTRUCTIVE EXAMINATION (NDE) METHODS FOR DETERMINING
THE PRESENCE OF CUI: ADVANTAGES AND DISADVANTAGES
Method Advantages Disadvantages
Visual inspection of pipes t2VBMJUBUJWFJOTQFDUJPO t3FRVJSFTTUSJQQJOHPGBMMJOTVMBUJPO
and equipment t*NNFEJBUFWBMJEBUJPOPGSFTVMUT t&YUFOTJWFTUBHJOHPSTDBGGPMEJOHNBZCF
SFRVJSFE
t4MPX
t&YQFOTJWFXIFSFIB[BSEPVTNBUFSJBMT
BSFQSFTFOU
t1PUFOUJBMUPNJTTDSJUJDBMMPDBUJPOT
Radiography film t2VBMJUBUJWFBOERVBOUJUBUJWFSFTVMUT t-POHFSFYQPTVSFUJNFT
$POWFOUJPOBM9SBZUFDIOPM QPTTJCMF t"DDVSBDJFTBSFœ
PHZXIFSFSBEJBUJPOQBTTFT t5IJDLOFTTNFBTVSFNFOUTBSFQPTTJCMF t'JMNQSPDFTTJOHJTSFRVJSFE TPSFTVMUTBSF
UISPVHINBUFSJBMBOE t$BOJEFOUJGZDPOEJUJPOTPGCPUIPVUFS EFMBZFE
DSFBUFTJNBHFPOGJMN EJBNFUFSBOEJOOFSEJBNFUFS t&OWJSPONFOUBMJTTVFTXJUIDIFNJDBMT
t*NBHFBEKVTUNFOUJTOPUQPTTJCMF
t"SDIJWBMSFTUSJDUJPOT
Radiography CR (com- t2VBMJUBUJWFBOERVBOUJUBUJWFSFTVMUT t$PWFSTMJNJUFEBSFB
puted radiography) QPTTJCMF t3FRVJSFTEJSFDUBDDFTTUPJOTQFDUJPO
9SBZJNBHFTBSFEJHJUJ[FE t"DDVSBUFNFBTVSFNFOUTQPTTJCMF BSFB
BOEEJTQMBZFEPODPNQVUFS t$BOJEFOUJGZDPOEJUJPOTPGCPUIPVUFS t$PTUDPOUSPMJTCBTFEPOBDDFTTBOE
EJBNFUFSBOEJOOFSEJBNFUFS QSPEVDUJPOSBUF
t/PJOTVMBUJPOSFNPWBMSFRVJSFE t3BEJBUJPOIB[BSET
t4PGUXBSFJNBHFFOIBODFNFOUQPTTJCMF t*NBHJOHQMBUFDBSFSFRVJSFE
t&MFDUSPOJDNFEJBGPSFBTZBSDIJWJOH
Realtime (RT) radiography t*EFOUJGJFTPVUFSTVSGBDFDPOEJUJPOT t$MPTFQSPYJNJUZQJQJOHSVOTBOEQJQFHF
-PXQPXFS9SBZPSJTPUPQF t"MMPXTGBTU JNNFEJBUF
SFTVMUT PNFUSZDBOSFTUSJDUJOTQFDUJPO
CBTFEEJHJUBMGMVPSPTDPQZ t/PJOTVMBUJPOSFNPWBMSFRVJSFE t1SPEVDUJPOTMPXFSJODMPTFTQBDFE
FRVJQNFOUUIBUQSPWJEFT t/PSBEJBUJPOIB[BSET QJQJOH
WJFXPGPVUFSEJBNFUFSPG t*OTQFDUJPOVOJUJTDVNCFSTPNFJOUJHIU
pipe TQBDFT
Guided wave inspection t3BQJEJOTQFDUJPOPGMPOHMFOHUITPGQJQF t2VBMJUBUJWFTDSFFOJOH
6TFTMPXGSFRVFODZVMUSB BSFQPTTJCMF  UP GUE
t3FRVJSFTTFDPOEBSZNFUIPEGPSWFSJGJDB
TPOJDXBWFTUPEFUFDUHFO tWPMVNFUSJDDPWFSBHF UJPOPGBOPNBMJFT
FSBMDPSSPTJPOBOEXBMMMPTT t-JNJUFEJOTVMBUJPOSFNPWBMGPSJOTQFDUJPO t(FPNFUSZDBOSFTUSJDUJOTQFDUJPO
t"DDVSBUFMPDBUJPOPGQJQFGFBUVSFTBOE
DPSSPTJPO
t4FNJRVBMJUBUJWFBOBMZTJTPGXBMMMPTT
t5FNQFSBUVSFSBOHFUP¡'
t.PTUDPTUFGGFDUJWFNFUIPEGPSWFSZMPOH
MFOHUITPGQJQF
Pulsed eddy current (PEC) t'BTU t$MPTFQSPYJNJUZQJQJOHDBOMJNJUBDDFTT
&MFDUSJDDVSSFOUJTJOUSP t/PJOTVMBUJPOSFNPWBMSFRVJSFE t*OTQFDUJPOPGQJQJOHMFTTUIBOJOJOEJ
EVDFE UIFOTXJUDIFEPGG t&BTJMZEFQMPZFE BNFUFSJTOPUQPTTJCMF
UPHFOFSBUFFEEZDVSSFOUT  t)JHIUFNQFSBUVSFDBQBCJMJUZ
XIJDIBSFEFUFDUFECZSF t/PODPOUBDUNFUIPE
DFJWFSDPJMT t2VBMJUBUJWFEBUB
Hydrotector t*OJUJBMTDSFFOJOHGPSXFUJOTVMBUJPOCFGPSF t0OMZVTFGVMGPSXFUJOTVMBUJPOEPFTOPU
%FUFSNJOFTNPJTUVSFDPO FNQMPZJOHPUIFS$6*NFUIPET EFUFDUESZJOTVMBUJPOUIBUIBTCFFOXFU
UFOUJOJOTVMBUJPOCZNFBTVS t'BTU t4DSFFOJOHUPPMPOMZ
JOHOFVUSPOTDBUUFSCZIZ t/PJOTVMBUJPOSFNPWBMSFRVJSFE t/PEBUBPOBDUVBMQJQFDPOEJUJPO
ESPHFOBUPNTJOUIFXBUFS

detection and mitigation. In gen- the vessels and piping identified process vessels and piping to de-
eral, a comprehensive CUI program in the first phase termine what is susceptible to CUI.
should consist of at least the follow- t1FSGPSNJOH FGGFDUJWF BOE FGGJ- The team should evaluate and con-
ing aspects: cient inspection and testing of the sider the operating temperatures
t1SFWFOUJPOPG$6* FRVJQNFOUBOEQJQJOH and material of construction of
t&BSMZEFUFDUJPO For each phase of the CUI program, FBDI PG UIF QJFDFT PG FRVJQNFOU UP
t.JUJHBUJPO this article includes a decision tree NBLF UIF EFUFSNJOBUJPO 5IJT JO-
t.FDIBOJDBMJOUFHSJUZ QSFWFOUB- that is designed to assist engineers GPSNBUJPONBZDPNFGSPNQMBOUFO-
tive maintenance programs de- BOENBOBHFSTUPTZTUFNBUJDBMMZBQ- gineering files and operational his-
TJHOFEUPDPOUJOVBMMZBEESFTTUIF proach CUI assessments, repairs UPSZ  PS JU DBO CF EPXOMPBEFE GSPN
hazards of CUI and documentation. The decision the inspection data management
The process for addressing CUI trees can be found in Figures 1–4. TZTUFN *%.4

XJUIJO UIF DPNQSFIFOTJWF GBDJMJUZ After the team has determined
specific program should consist of Phase I XIBU FRVJQNFOU XJMM CF JODMVEFE
at least these three phases: 5IF JOJUJBM 1IBTF  EFUFSNJOBUJPO in the program, it is good practice
t%FUFSNJOJOH XIBU FRVJQNFOU JT PGXIBUFRVJQNFOUJTUPCFJODMVEFE UPQSJPSJUJ[FUIPTFFRVJQNFOUJUFNT
in the program JOUIF$6*QSPHSBNHFOFSBMMZDPO- CZQFSGPSNJOHBSJTLBTTFTTNFOUUP
t1FSGPSNJOH B GJFME XBMLEPXO PG sists of a team assessment of the determine where the higher-conse-
CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2014 41
Phase 2 Initial Field Visit

Cover Story
Initiate visual
inspection of Perform
applicable assets – NO engineering
quence events would occur if there Field walkdown assessment
to defer
was a loss of containment. The team inspection
must always fully understand the
Inspection
operating process and include those methodology
Are
vessels that are frequently idle, there any areas selection
even if they operate in a tempera- with damaged
insulation
ture range not usually noted for
Implement
susceptibility to CUI. YES inspection plan
The team should be composed YES
of at least one member who is fa- Document areas
miliar with the materials of con- on asset ISO
drawing.
struction of the vessels and piping Perform moisture
NO
being evaluated, as well as at least detection to isolate
suspect areas
one member knowledgeable in the FIGURE 2. In the field-walkdown
process temperatures at which the Document areas on
stage of the CUI program, subject-
equipment operates, and a mem- asset ISO drawing matter experts inspect equipment
Determine
that are suspect recommended to determine which method(s) will
ber knowledgeable about the CUI for CUI. inspection plan be most effective to evaluating
damage mechanism. In addition Establish methodology whether and how CUI is affecting
the team should include a member inspection each equipment item
methodology
who is familiar with the inspection to be utilized
history of the vessels and piping
within the program.
The analysis team should use a
formalized approach to the deter- Phase 3 Field Inspection
mination. A logic decision tree can
be very helpful (Figure 1).
The team’s initial assessment
Recommend Inspection Excecute
should pay particular attention to Field work and paint and complete. inspection
follow up
the following equipment and piping inspection
re-insulate asset Document finding plan
susceptible to CUI: Document Mark ISO drawing Follow up on
t"SFBTFYQPTFEUPNJTUPWFSTQSBZ recommendation with location NDE findings and
inspected, update make necessary
from cooling water towers Remove Follow-up asset files repairs
t"SFBT TVCKFDUFE UP QSPDFTT TQJMMT  insulation re-insulation
at suspect of asset and Follow up Perform
ingress of moisture or acid vapors locations close work re-insulation engineering
order and close fitness for service
t%FBEMFHT BOE BUUBDINFOUT UIBU work order when required
is, drains, vents and so on
Inspector Document
t1JQFIBOHFSTBOEPUIFSTVQQPSUT performs corrective action
t7JCSBUJOHQJQJOHTZTUFNT visual asset
Update ISO and
inspection NO YES
t4UFBNUSBDFEQJQJOHTZTUFNTUIBU at exposed follow closure of
NBZFYQFSJFODFUSBDJOHMFBLT locations work order
and document

Phase 2 YES
1IBTFDPOTJTUTPGBGJFMEXBMLEPXO Is
NO Does
evidence of
CZRVBMJGJFETVCKFDUNBUUFSFYQFSUT corrosion present?
paint meet
plant
4.&T
 5IFTF FYQFSUT EFUFSNJOF (cracks or criteria? Inspection
thinning) decision
XIBU OPOEFTUSVDUJWF FYBNJOBUJPO
/%&
 NFUIPEPMPHZ JT CFTU TVJUFE YES
for discovering whether and how
FIGURE 3. When the field inspection
CUI may be affecting each vessel Inspector to decide between:
plan is carried out, the need for more
a. advanced NDE;
BOE QJQJOH TZTUFN 5IF 4.&T DBO b. additional insulation removal; extensive testing can be determined
also determine the most efficient c. engineering assessment; and possible recommendations for
d. combination of a, b, c options repair can be developed
and effective method for perform-
ing the inspection and tests. Table
 TIPXT B CSJFG BOBMZTJT PG /%& QJQJOHDBOBMTPCFBOBMZ[FE%FUFS- inspection and testing field. Inspec-
methods that can be used to deter- NJOJOH GPSFYBNQMF XIFSFTDBGGPME- UPST BSF BCMF UP QFSGPSN BOZ /%&
mine the presence of CUI. ing must be utilized or where rope method from ropes, thus reducing
%VSJOH UIF 1IBTF  GJFME BTTFTT- access is needed can be of signifi- the need for scaffolding and greatly
ment, accessibility issues associated cant value. Rope access has made reducing the cost of inspections.
with each piece of equipment and a tremendous contribution to the There must be anchor points avail-
42 CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2014
Inspector to determine:
Inspection a. advanced NDE
decision b. insulation removal
c. engineering analysis
d. combination of a, b, c options

the most effective and economical


method for follow-up inspections.
Figure 4 is a logic flow for determin-
If stainless-steel ing whether or not follow-up inspec-
asset, perform YES YES Perform
localized SCC crack additional tions should be performed, as well
penetrant-test present inspections
exam as if advanced non-destructive eval-
VBUJPO "/%&
 NFUIPET TIPVME CF
NO used in lieu of insulation stripping.
Strip the larger of:
a. all suspect
It is costly to remove and replace in-
Carbon steel Document and damaged sulation, especially if it is not fully
asset with and close insulation
corrosion scale locations; necessary. In many cases, the most
or pits
b. 20% of asset economical method could be an
area/length "/%&NFUIPE5IFBEWBOUBHFTBOE
NO
EJTBEWBOUBHFT PG "/%& NFUIPET
Does are also discussed in Table 1.
the piping NO
Is cross waterway? Is
wall loss
greater than NO Is the piping a class 1 YES asset
suitable for
Summary remarks
or class 2 circuit?
corrosion
Is the calculated risk-
advanced $6* JT B TFSJPVT IB[BSE BGGFDUJOH
allowance? ANDE?
based inspection the safety and reliability of chemi-
consequence
A or B? cal plants, petroleum refineries,
YES YES midstream terminals and just about
all oil-and-gas operating facilities.
Inspect 100% To best address the problem, CUI
of carbon steel Perform ANDE must be addressed in a systematic
asset with ANDE
or programmatic approach. The
program must be fully defined and
Note 1: staffed with qualified personnel. Ef-
1. If there are additional findings, then follow-up inspection will be required in accordance fective and economical inspection
with this process. If there are no additional findings, then spot repairs will be completed
and inspection results documented in the asset inspection files. and testing methodologies should
CFVUJMJ[FEBTQBSUPGUIF$6*EFUFD-
FIGURE 4. If corrosion is observed at suspect CUI locations, more in-depth assess- tion program. By addressing CUI
ments, probably involving advanced non-destructive testing methods, are undertaken effectively, the risk of operations
is reduced significantly and the
able for the rope access team to use Phase 3 equipment and plant reliability is
for anchoring their ropes. The field 1IBTFPGUIFQSPHSBNTIPVMEDPO- JODSFBTFE"TBGFMZBOESFMJBCMZPQ-
assessment can determine where sist of the most effective and efficient erating facility is the product of a
rope access would be effective and methods of testing and inspection proactive CUI program. ■
which NDE method will yield the for the detection of CUI. Inspection Edited by Scott Jenkins
most significant data at the right and testing findings can be evalu-
cost level. Figure 2 is an example of ated, and additional inspection and Author
Russ Davis is the National
the logic flow the field team can fol- testing needs can be quickly deter- "TTFU*OUFHSJUZ.BOBHFNFOU
low to determine the most effective mined. Recommendations can then 4FSWJDFT "*.4
 NBOBHFS JO
the services division of the
inspection and test methodology. be developed to address those issues .JTUSBT (SPVQ *OD 
The field walkdown team should that were identified in the previ- 6OEFSXPPE 3PBE  -B1PSUF 
59  1IPOF 
pay particular attention to: ous phase. Vessel and piping repair  &NBJM 3VTT%BWJT!
NJTUSBTHSPVQDPN
 %BWJT
t5IF CPUUPN PG IPSJ[POUBM MJOFT plans can be developed and next has spent over 26 years in
in piping systems susceptible to JOTQFDUJPOEBUFTTFU'JHVSFJTBO mechanical-integrity pro-
gram development and
CUI FYBNQMFPGBMPHJDGMPXGPS1IBTF implementation. His experience includes pres-
t"OZ CSFBL JO UIF WBQPS SFUBSEFS that the testing and inspection team sure vessels, aboveground storage tanks, and
piping inspection, testing and evaluation. Davis
on cold lines can use during the screening part of has an extensive background in process safety
t%BNBHFE PS NJTTJOH JOTVMBUJPO the implementation phase. NBOBHFNFOU JODMVEJOHIB[BSEBTTFTTNFOUBOE
consequence evaluation. He has developed and
jacketing It is not economical or feasible to EJSFDUFENFDIBOJDBMJOUFHSJUZ .*
QSPHSBNTGPS
t-PDBUJPO XIFSF JOTQFDUJPO QMVHT expect that the inspection and test- aBOglobal chemical company. Davis has served as
.* DPOTVMUBOU  BT XFMM BT FYUFSOBM DPOTVM-
have been removed ing will cover 100% of the equip- UBOUGPSUIFJNQMFNFOUBUJPOPG.*QSPHSBNT)F
t1JQJOHTZTUFNTXJUIEFUFSJPSBUFE ment and piping susceptible to CUI. has a solid working knowledge of NDE, damage
mechanisms, and materials of construction for
coatings or wrappings Screening inspections and testing equipment in the petroleum refining, chemical
and energy industries. He is also experienced
t5FSNJOBUJPO PG JOTVMBUJPO will be conducted to identify suspect in equipment failure analysis, lifecycle analysis
at flanges and other piping areas. Once these areas are identi- BOE GBJMVSF GSFRVFODJFT %BWJT JT BO"1*DFSUJ-
GJFE JOTQFDUPS  BO *4"  'VOEBNFOUBMT 4QF-
components fied, the decision will be made on cialist and a certified safety professional.
CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2014 43

You might also like