Power Energy Bridge

SPECIFICATION OF THE BATTERY BRIDGE.

AC OUTPUT SPECIFICATIONS
3 PHASE
Nominal voltage (AC) 220 V (LINE)
127 V (PHASE)
Voltage accuracy 2%

Frequency 60 Hz

Frequency accuracy 0.03 %

Nominal current 78 A
AC OUTPUT POWER
Output power (resistive load) 10,000 W
Short time overload capacity 150% 15 second

Permanent overload capacity 110%

DC INPUT SPECIFICATIONS

Number of inputs 2
Voltage range (DC) 30 - 42 V

Nominal current (at 32Vdc) 156 A

Maximum input current (at 30Vdc) 200 A

AC INPUT SPECIFICATIONS
3 PHASE
Nominal voltage (AC) 220 V (LINE)
127 V (PHASE)
Power Factor >99%
Frequency 60 Hz
ENVIRONMENT
Ambient temperature -20 to 50 °C
Storage temperature -20 to 70 °C
Relative humidity 95% , non condensing
PHU
Number of units 2
Nominal input voltage (AC) 127 V (PHASE)
Nominal current 3A
WEIGHT & DIMENSIONS
Width 700 mm
Depth 800 mm
Height 48 U
Weight 200 Kg

Material (casing) Coated steel


DESCRIPTION OF THE 10 KW EMERGENCY POWER SUPPLY SYSTEM
The 10 kW emergency power supply system electrical diagram is presented in Figure 1, 2.The
system consists of:
(1) Two Electrochemical Generators (ECG) G5, 5 kW rated power;
(2) Heat Utilization Units (HUU);
(3) Preheating Unit (PHU);
(4) DC/DC Converters FLATPACK2 (18-75V/48V);
(5) AC/DC Charger (2kW);
(6) Two phase monitoring relays;
(7) Battery bank 8x92Ah;
(8) LVBD;
(9) Manual SBS (bypass);
(10) DC/AC Inverters TSI BRAVO 48/120;
(11) 4x48 FANS with Temperature Switch.

Components (3)-(11) are located in electrical cabinet (Figure 1, 2).

10

7
2 3
HUU PHU

4
1

4
1 8

HUU PHU
2 3

44U CABINET

11

Figure 1. EMERGENCY POWER SUPPLY SYSTEM FOR STC METRO


11
3

10
9
6

Figure 2. ENERGY BRIDGE FOR STC METRO


Figure 3. ENERGY BRIDGE CONNECTION PANEL

During normal mode of operation, power to the load is supplied from the grid by DC/AC inverter BRAVO (10). At the
same time, a battery bank (7) is charged by a charger (5).

In case of main grid disappearance, the load receives necessary back up power from the battery bank (7), initially. At
the same time phase monitoring relays (6), send start up signal to the ECGs (1). Within several minutes, the ECGs
become fully operational and start providing necessary AC power to the load via DC/DC converters (4) and DC/AC
inverters (10).

When the grid resumes, phase monitoring relays (6) open dry contacts and ECGs (1) enter in standby mode. The ECGs
(1) remain in standby mode until the charger (5) recharges the batteries. Consequently, the ECGs execute shut down
procedure when the battery bank is fully charged.

Preheating Unit (PHU) (3) is used to keep batteries inside electrical box of the generator G5 always charged, when the
generator is in stand-by mode. And also, if needed to keep electrolyte inside generator under certain temperature in
stand-by mode.
LIST OF MAIN COMPONENTS
Item Q-TY Descreption Part No: Vendor

1 8 ELTEK DC/DC In 18-75V Out 48/1350W 241115.602 ELTEC


2 2 Shelf DC/DC 4 Pos 273820 ELTEC
3 1 Smartpack 2 Basic 242100.501 MICR SP2 ELTEC
4 1 Smartpack2 Master/Display G2 242100.500 FP2 SP2 ELTEC
5 3 1U 19Inch Bracket Set 106991 ELTEC
6 3 DB Cable - System connection cable 200781 ELTEC
7 2 RJ45 terminator 105681 ELTEC
8 10 2M canbus cable 30400.014 ELTEC
9 1 DC-AC 12KW 3FAZE bravo inverter S32A53E0612 ELTEC
10 1 Eltek Shunt 300A 201333 ELTEC
11 1 Eltek LVD 300A 266014 ELTEC
12 1 CABINET 44U ZBOX1890
13 1 Battery 92Ah 12V BT1292-SBS
14 1 BOX 3U_19"_380mm FRONT PANEL BLANK ZBOX2824
15 1 FRONT PANEL 2U ZBOX4020
16 1 Miniature Circuit Breaker S201M SC6 ABB ZCB1406 ABB
17 1 Miniature Circuit Breaker S201M SC16 ABB ZCB1404 ABB
18 1 Miniature Circuit Breaker S203M C50 (3X50A) ABB ZCB1512 ABB
19 1 Miniature Circuit Breaker S203M C63 (3X63A) ABB ZCB1513 ABB
20 13 W-Compact 70 mm² WDU 70N/35 9512190000
21 1 C.BREAKER TMAX XT1C 160 FIXED THREE-POLE XT1C 160 TMD 160-1600 3p F F ABB
Three-phase Voltage and Phase-sequence Phase-loss
22 2 K8AK-PM OMRON
Relay
23 4 Electrical socket DIN rail assembly
24 2 Cable Phase-loss Relay
25 1 Cable Electrical socket
26 1 Cable Charger