Professional Documents
Culture Documents
EARTHWORKS
EARTHWORKS
BASKETBALL COURT
Gravel bedding Cu. m 77.00 1,900 146,300
Concrete (0.15 Cu. m 72.00 4,920 354, 240
thick, w/ 2500 psi)
Forms (on sliding)) Sq. m 13.80 650 8,970
consider L=92m
Plain cement finish Sq. m 480 .00 497.25 238, 680
Reinforcing bars
10 mm kgs 1,856.28 60.11 111,571.71
16 mm kgs 60.11 1,709.39
SUBTOTAL 861,470.1
FINISHES
Exterior painting UNIT QUANTITY UNIT PRICE TOTAL AMOUNT
To basketball Sq. m 15.22 456.30 6,944.43
court lines
To basketball Sq. m 448.00 456.30 204, 422.40
court flooring
SUBTOTAL 211, 366.83
SPECIAL CONSTRUCTION
Basketball stand set 2.00 17,550 35,100
with ring
SUBTOTAL 35,100
GRAND TOTAL 1, 112,957.77