Filling and compaction shall be done fairly in level, undesired elevations and undulations shall

not be accepted.

Phase1 Earthworks compaction

Verifications No. of controls Rejection criteria

1.1 Dimensions
in plan 1 by 20
m. Errors exceeding Filling and compaction shall be Elevations and undulations
1 per unit
2.5 done fairly in level
Camada shall not be accepted.
‰.

Tolerancia

1.2 Water shall be mixed as 1 per unit the moisture content of the
necessary Volume entire layer cannot be
greater than +/- 3% of the
moisture content
Pendant network for baths
1.3 1 per unit Greater than 10%
and showers

Less than 1%
1.4 Pendants 1 per unit
Above 4%