You are on page 1of 8

From To On Route Distance Nodes

O A 1 2 O
O B 0 5 A
O C 0 4 B
A B 1 2 C
A D 0 7 D
B C 0 1 E
B D 1 4 T
B E 0 3
C B 0 1
C E 0 4
D E 0 1
D T 1 5
E D 0 1
E T 0 7

Total 13
Net Flow Supply/Demand
1 is equal to 1
0 is equal to 0
0 is equal to 0
0 is equal to 0
0 is equal to 0
0 is equal to 0
-1 is equal to -1
From To Ship Capacity Unit cost Nodes
F1 W1 30 700 F1
F1 DC 50 <= 50 300 F2
F2 W2 40 1000 DC
F2 DC 30 <= 50 500 W1
DC W1 30 <= 50 200 W2
DC W2 50 <= 50 400

Total Cost 117000


Net Flow Supply/Demand
80 is equal to 80
70 is equal to 70
0 is equal to 0
-60 is equal to -60
-90 is equal to -90
From To Flow Capacity Node
O A 3 <= 5 O
O B 7 <= 7 A
O C 4 <= 4 B
A B 0 <= 1 C
A D 3 <= 3 D
B C 0 <= 2 E
B D 4 <= 4 T
B E 3 <= 5
C E 4 <= 4
D T 8 <= 9
E D 1 <= 1
E T 6 <= 6

Total Flow 14
Netflow Supply/Demand
14
0 is equal to 0
0 is equal to 0
0 is equal to 0
0 is equal to 0
0 is equal to 0
-14

You might also like