You are on page 1of 1

Preparatory 

Exam Solutions  
Question 1 

Chainage at CT = 1269.66 + 151.51 = 1421.17 m 1 mark


Final Subarc = 1421.17 - 1420 = 1.17 m 1 mark
Tangential (deflection) angle for initial subarc= 00 29' 37" 1 mark
Tangential (deflection) angle for generall subarc= 00 57' 18'' 1 mark
Tangential (deflection) angle for initial subarc= 00 03' 21" 1 mark

Tabulated Data

Length - Cummulative
Rsin(defle deflection
Point Chainage ction) angles
TC 1269.66 0 00 00 00
1 1280 10.34 00 29' 37" 1 mark
2 1300 30.337 01 26' 55" 1 mark
3 1320 50 02 24' 13" 1 mark
4 1340 70.3 03 21' 31" 1 mark
5 1360 90.255 04 18' 49" 1 mark
6 1380 110.185 05 16' 07" 1 mark
7 1400 130.084 06 13' 25" 1 mark
8 1420 149.947 07 10' 43" 1 mark
CT 1421.17 151.109 07 14' 04" 1 mark

Question 2 

CH Chainage x RL delta 1 delta 2


Beginning VC PC 4370 0 0.00 844.480
Crest 4400 30 0.30 845.331 0.851
Crest 4500 130 1.30 847.467 2.136 1.285
Crest 4600 230 2.30 848.523 1.056 -1.080
Crest 4700 330 3.30 848.499 -0.024 -1.080
Crest 4800 430 4.30 847.395 -1.104 -1.080
End VC PT 4870 500 5.00 845.980 -1.415 -0.311
 General formula RL = ½rx2 + G1x + RLBVC 