Professional Documents
Culture Documents
ABSTRACT: In this paper, design and construction of cross passage of urban metro are discussed using a case history
from Contract BC- 16 of Delhi metro. In order to start to build permanent structural works in TBM shafts as soon as
possible, construction activities of cross passage should be isolated from TBM shafts. Vertical shafts for cross passage
were thus installed between the two main running tunnels from ground surface level to increase workable areas as well
as to transport excavated spoil. Details of design and construction of the cross passage will be reported in this paper.
Analyses using 3- dimensional FEM program MIDAS GTS will be undertaken in order to evaluate ground deformations
induced by the construction of the cross passage. It is concluded that the ground deformation induced is very small (up
to 5mm) and this might be connected with high soil stiffness as well as arch influence generated by a circular excavation.
At last, engineering properties of soils at BC- 16 are explored and it was found that the silt and silty clay on site are
overconsolidated so parameters used for design might not fit the reality.
4850 mm
3850 mm Surface level
6350 mm 6350 mm
5800 mm 5800 mm
Table 1 Soil parameters used for design (b) Construction of cross passage
Soil Thickness t Su E Fig. 3 Construction of shaft and cross passage
type (m) (kN/m3) (kPa) (kPa)
ML 6.4 17.7 0 23800 0.3 DEFORMATION ANALYSES
CL 8.6 18.9 155 54250 0.35 In order to indicate possible ground deformation induced
ML 8.5 18.0 0 44800 0.3 by construction of CP1, analyses using 3- dimensional
CL 6.5 18.8 185 99750 0.35 FEM program MIDAS GTS are undertaken in order to
evaluate ground deformations. As shown in Figure 4,
Figure 3 presents construction of CP1, the 16.4m deep similar analyses were delivered using the other software
3.85m of diameter of vertical shaft was constructed from LUSAS for excavation of cross passage and ventilation
surface level first. The shaft was retained by wire mesh shaft in Heathrow Terminal 5 project in London
and shot concrete. During the excavation of the vertical (FaberaMaunsell Ltd., 2003) but soil parameters are
shaft, a steel rib ring was installed and attached along the hardly given since LUSAS doesn’t have such function. In
shaft in the shape of 20 boundaries in one meter interval addition, only stresses on structural elements are
vertically in order to strengthen the stiffness of the concerned but not for evaluation of deformations.
retaining structure. Construction sequences of CP1 In this paper, as shown in Figure 5, a 30m × 30m × 35m
include: (i) install dewatering system and keep the water 3- dimensional mesh was used for analyses. The elastic -
level 1m below dredge level; (ii) install temporary support
perfect plastic modified Mohr- Coulomb model was Lateral movement (mm)
applied and the same soil parameters with initial design 6 5 4 3 2 1 0
were used for analyses in this paper. Groundwater level 0
was set at 14m below surface level. Construction
sequence stated above was used in the simulation. Excavate to 7m bgl
2
Figure 6 presents the horizontal displacements of retaining Completion of shafe
structure at various stages. It was found that the Completion of cross passage
4
horizontal displacement gradually increased from 2mm
(excavate to 7m below surface level) to 5mm. The
6
maximum lateral displacement occurred at the place
Depth (m,bgl )
slightly higher than level of excavation depth.
8
10
12
14
16
18
2
Fig. 5 Analytical mesh
3
connected to soil stiffness so higher stiffness of clay here Fig. 7 Surface settlement outside the shaft
is thought to be one of reasons leading to small
displacement. Further, through observations and a RETHINK OF SOIL PARAMETERS
simulation of a large- scale cofferdam excavation, Hsiung Unfortunately, no reliable field observation data is
and Chuay (2006) recommended that the arch effect available to be compared with prediction. Figure 8 shows
generated by a circular excavation could successfully effective stress failure envelope for highly
reduce ground deformations and this should be connected overconsolidated clay (Das, 1992). Shear strength of soil
to small displacement induced also. at failure (f) is determined by
For overconsolidated clay
f C ' ' tan 1 (1)
For normally consolidated clay
f ' tan (2)
in which C’ is cohesion intercept; ’ is normal stress and
35m
’1 and ’ is effective friction angle of overconsolidated
clay and normal consolidated clay, respectively.
It is seen that cohesion interception of shear stress does
exist for overconsolidated material and which is not
consistent with parameters given in Table 1. Therefore,
soil parameters are thus re-examined. Table 2 indicates TBM shafts. Therefore, a circular vertical shaft was
the results of laboratory tests and they show cohesion thus installed between the two main running tunnels
intercept is in the range of 20 to 26 kPa and effective from ground surface level and then horizontal cross
friction angle varies from 32° to 34.6°. Figure 9 illustrates passages were built at bottom of the shaft to connect
the result of one of 3 oedometer tests and the test results two running tunnels in order to increase workable
have given compression index Cc of about 0.12 as well as areas as well as to transport excavated spoil.
overconsolidation ratios (OCR) in the range of 1.38 to
2. A 3- dimensional analysis using the program of
2.05. These evidences approve the materials on site are
MIDAS- GTS was undertaken to simulate ground
over- consolidated and the assumption of no cohesion
deformation induced by the construction of shaft and
intercept with 30° of effective friction angle is under-
cross passages. The predicted maximum lateral and
estimated shear strength of soil and may not fit the reality.
vertical deformation is very small, up to 5mm in both
directions. High stiffness of soil and arch influence
Overconsolidated Normally consolidated
provided by circular excavation should be the reasons
led to such small displacement.
Shear Stress
C
REFERENCES
1’ = 1 Normal stress Das, B. M. (2002). Principle of Geotechical Engineering,
3’ = 3 c’ = c 2nd edition, PWS Publishing Company
Fig. 8 Effective stress failure envelope
FaberMaunsell Ltd. (2003). Independent Check Report of
Heathrow Terminal 5 Rail Tunnels- Storm Water
Table 2 C’ and 1’ of soils obtained from labotary tests
Outfall Tunnel, Spray Concrete Lining Works Project
Borehole Depth (m) C’ (kPa) Effective
Number: 722049
Number friction
angle (°) Hsiung, B. C. B. (2009). A Case Study on the Behaviour
SMB-04 14.7- 15.0 20.0 34.6 of a Deep Excavation in Sand, Computer and
SMB-05 10.0- 10.3 33.0 32.0 Geotechnics, Volume 36, Issue 4, 665- 675
SMB-11 15.0- 15.3 26.0 33.0
Hsiung, B. C. B. and Hwang, R. N. (2009). Evaluating
performance of diaphragm walls by wall deflection
paths, Journal of Geotechnical Engineering, Southeast
Asia Geotechnical Society, Volume 40, No. 2, 81- 90
Hsiung, B. C. B. and Chuay, H. Y. (2006). Geotechnical
Risk Assessment and Performance-Based Evaluation of
a Deep Excavation in the Kaohsiung MRT System
Project, TAIPEI2006 International Symposium on New
Generation Design Codes for Geotechnical
Engineering Practice, Taipei, Taiwan
Izumi, C. Lovelock, C., Tyagi, J. and Gupta, S. K. (2007),
A review of Delhi metro tunnel constrution with 14
EPB shield TBMs, World Tunnel Cogress, Parague,
Czeck Republic
ACKNOWLEDGMENTS
Fig. 9 The result of oedometer test The authors would like to thank for permission of use of
data from Continental Engineering Corporation and
CONCLUSIONS assistance Mr. Chang, Chin- Hau and Mr. Hsieh, Fong-
The following conclusions can be made based on this Chen, postgraduate students in KUAS, Taiwan provided
study. for preparation of this paper is also appreciated.
1. In order to start to build permanent structural works
in TBM shafts as soon as possible, construction
activities of cross passage should be isolated from