Professional Documents
Culture Documents
Vineetha K1
Boominathan A2
Subhadeep Banerjee3
1
Researcher (Ph. D), 2 Professor, 3Associate Professor, Department of Civil Engineering, Indian Institute of Technology Madras, Chennai
– 600 036.
vineetha.kombiyil22@gmail.com, boomi@iitm.ac.in, subhadeep@iitm.ac.in
ABSTRACT: Mechanised tunnelling method using Tunnel Boring Machine (TBM) is widely used in urban settings due
to the lesser construction duration and minimal surface disruption. However, field monitoring studies report ground
movements and damages to the buildings under which the TBM ploughed through. Hence, it is important to attain a
detailed understanding of the TBM- ground interaction before the initiation of any new tunnel construction activity so as
to predict the variation in the in- situ ground conditions, avoid any damage to the structures adjacent to the tunnel
alignment and optimize the TBM performance. This paper comprises a brief review of various studies on the simulation of
tunnelling in soft soils followed by the numerical back- analysis of a typical field monitoring study involving underground
tunnelling in clay using the general purpose finite element suite, ABAQUS. A circular tunnel with 8.16 m diameter,
running straight and embedded in clay with 19.0 m overburden is considered. The deformation and pore pressure response
is monitored along the ground surface and near the tunnel crown, respectively, for each excavation stage of 1.5 m. The
numerical model clearly demonstrated the progressive changes in these parameters as the excavation advances.
Keywords: Mechanised Tunnelling, TBM, Finite Element, ABAQUS, Ground Movement
Standing and Selemetas (2013). The tunnels are of 8.16 element with trilinear displacement, pore pressure and
m diameter, running straight with 16.0 m centre- to reduced integration scheme) was used to discretise soil
centre distance and embedded in clay at a depth of 19.0 and grout sections, whereas, S4R (four- noded
m. Figure 1 shows the cross- section of the twin- tunnel conventional stress/ displacement shell element with
alignment and the site stratigraphy up to a depth of reduced integration scheme) was used for the TBM
35.0 m below the ground surface. shield and tunnel lining.
Translations in X and Y directions were constrained
along the vertical boundaries of the soil domain in YZ-
plane and XZ- plane, respectively. Translations in all
directions were constrained along the bottom boundary
of the model. All the three rotational degrees of
freedom were constrained for the TBM shield and
lining.
2.2 Materials and Constitutive Relations
Soil properties used in the analysis are shown in Table
1. Ground water table is assumed at the ground level.
TBM shield, grout and tunnel lining material
parameters used in the analysis are presented in Table
2.
Fig.1 Cross- section of the twin- tunnel alignment Table 1 Soil Parameters
2
Indian Geotechnical Conference IGC2016
15-17 December 2016, IIT Madras, Chennai, India
dilatancy when the material yields in shear. Drucker monitoring section. Both the field data and finite
Prager constitutive relation without a cap is used to element analysis results shows an initial heave (< 1
model the terrace gravel. The friction angle is 39 mm) as the TBM approaches the monitoring section
degrees for the Terrace gravel layer. Shield, lining and with the distance of face at about y= -20.0 m. This is
grout are modelled as simple linear elastic materials followed by a progressive settlement of about 3 mm in
with an assumption that elastic strains developed in the the field study and about 6 mm in the numerical study.
material are less than 5 %. 10
x= -12.5 m FE Study
125
shield- skin contact with the shield Monitoring Section Crown
100 Field Study
Tail grout 1.6 bar Excavated soil surface FE Study
75
pressure after shield removal
*Magnitudes are taken from Standing & Selemetas (2013) 50
25
4 RESULTS AND DISCUSSION
0
Ground response discussed in this section include Tunnelling Direction
-25
vertical displacement and pore pressure variation at -60 -40 -20 0 20 40 60
Distance from TBM face, y (m)
selected locations, monitored for each excavation stage
of 1.5 m during the excavation of the left- tunnel. Fig. 4 Pore water pressure variation near the tunnel crown
Results from the finite element study are compared during the tunnel advancement plotted against the
with the field monitoring data reported in Standing and distance of the TBM face from the monitoring
Selemetas (2013). Figure 3 shows the vertical section.
displacement profile on the ground surface along the
monitoring section against the distance of the TBM The finite element study overestimates the pore water
face from the monitoring section as the tunnel pressure variation beyond the monitoring section which
advances. The co- ordinates (x, y, z) = (0, 0, 0) might be due to the undrained analysis type. The
corresponds to the location on the ground surface adoption of tail grout pressure values gauged directly
above the centre- line of the left- tunnel lying in the from the pump would have also influenced the pore
pressure response. The values gauged from the pump
3
Numerical Modelling of Mechanised Tunnelling in Clay
will not be actually exerted in the field due to the International Journal for Numerical and Analytical
different losses which include the grouting pipe and Methods in Geomechanics, 28, pp1441- 1460.
outlet friction resistance. However, the dissipation Lambrughi, A., Rodriguez, L. M., Castellanza, R. (2012)
pattern of pore water pressure beyond the monitoring ‘Development and validation of a 3D numerical model
section in the finite element study is similar to the field for TBM– EPB mechanised excavations’, Computers
study. and Geotechnics, 40, pp97- 113.
5 CONCLUSION Mair, R. J., Taylor, R. N. and Bracegirdle, A. (1993)
‘Subsurface settlement profiles above tunnels in clays’,
A three dimensional finite element model is developed Geotechnique, 43(2), pp315- 320.
for simulating the mechanised shield tunnelling Marshall, A. M., Farrell, R., Klar, A. and Mair, R. (2012).
procedure in soft ground incorporating all the relevant ‘Tunnels in sands : The effect of size, depth and
components like torque, face pressure, shield- skin volume loss on greenfield displacements’,
friction, tail grout pressure, lining installation, back- up Geotechnique, 62(5), pp385- 399.
trailer weight, grout hardening and excavation. Profiles
Ng, C. W. W. and Lee, G. (2005) ‘Three-dimensional
were plotted demonstrating the ground responses in
ground settlements and stress- transfer mechanisms due
terms of deformation and pore pressure variation as the
to open-face tunnelling’, Canadian Geotechnical
tunnelling progresses. The results were found to be in Journal, 42, pp1015- 1029.
good agreement with the actual field data. The pore
pressure variation from the developed model highlights Pinto, F. and Whittle, A. J. (2014) ‘Ground movements
the significance of properly accounting for the relevant due to shallow tunnels in soft ground. I : Analytical
TBM components which are usually ignored in the solutions’, Journal of Geotechnical and
Geoenvironmental Engineering (ASCE), 140 (4),
numerical simulation of mechanised tunnel
pp04013040- 1- 17.
construction problems. Modelling methodology
proposed in this study is relevant in the estimation of Standing, J. R. and Selemetas, D. (2013) ‘Greenfield
ground behaviour for situations with similar ground ground response to EPBM tunnelling in London clay’,
conditions and excavation procedure. Geotechnique, 63(12), pp989- 1007.
Zheng, G., Lu, P. and Diao, Y. (2015) ‘Advance speed-
REFERENCES based parametric study of greenfield deformation
ABAQUS (2012), Inc. ABAQUS user’s manual, Version induced by EPBM tunnelling in soft ground’,
6.12. Pawtucket, R.I. Computers and Geotechnics, 65, pp220- 232.
Addenbrooke, T. I and Potts, D. M. (2001) ‘Twin tunnel
interaction: Surface and subsurface effects’, The
International Journal of Geomechanics, 1(2), pp249-
271.
Chen, R. P., Zhu, J., Liu, W. and Tang, X. W. (2011)
‘Ground movement induced by parallel EPB tunnels in
silty soils’, Tunnelling and Underground Space
Technology, 26(1), pp163- 171.
Comodromos, E. M., Papadopoulou, M. C. and
Konstantinidis, G. K. (2014) ‘Numerical assessment of
subsidence and adjacent building movements induced
by TBM-EPB tunneling’, Journal of Geotechnical and
Geoenvironmental Engineering (ASCE), 140 (11),
pp0401406- 1- 12.
Do, N., Dias, D., Oreste, P. and Djeran- Maigre, I. (2014)
‘Three-dimensional Numerical Simulation of a
Mechanized Twin Tunnels in Soft Ground’ Tunnelling
and Underground Space Technology, 42, pp40-51.
Houhou, M. N., Emeriault, F. and Vanoudheusden, E.
(2016) ‘Three- dimensional back- analysis of an
instrumented shallow tunnel excavated by a
conventional method’, Geotechnical and Geological
Engineering, 34, pp1101- 1117.
Kasper, T. and Meschke, G. (2004) ‘A 3D finite element
simulation model for TBM tunnelling in soft ground’,