You are on page 1of 63

INPUT THE DATA ON THE YELLOW CELL (THIS IS NOT A LOCKED SPREADSHEET, HENCE YOU

PROJECT TITLE: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
PROJECT LOCATION: ZAMBOANGA CITY

Item Manpower / DIRECT COST


Equipment/
Item of Works Qty Units Remarks
Number Labor Tools
CIVIL WORKS
800(1) CLEARING
INDIVIDUALAND GRUBBING
REMOVAL OF TREES (UPTO 200.00 SQ.M. Area
Numberof the project
of trees to for clearing from
be removed 600.00 21,555.20
800(3)a 300MM DIAMETER) 5.00 EACH project site 1,375.00 9,772.35
803(1)a STRUCTURE EXCAVATION (COMMON SOIL 23.00 CU.M. Volume to be excavated by Backhoe 287.50 #N/A
803(1)a STRUCTURE EXCAVATION (SOFT ROCK) - CU.M. Volume to be excavated by Backhoe - #REF!
804(4) GRAVEL BEDDING
CONCRETE STRUCTURES FOR ONE- 3.00 CU.M. Putting
by directgravel as bedding
counting on plan,inget
foundation
its total 625.00 #N/A
902(1) STOREY, GRADE 40/60 1,500.00 KGS. weight in kgs. 9,673.17 #REF!
This is for two to 5 storey only. After
REINFORCING STEEL OF REINFORCED estimating the number of steel bars by
CONCRETE STRUCTURES FOR TWO direct counting on plan, get its total
902(1) UPTO FIVE STOREY - KGS. weight in kgs. - #REF!

STRUCTURAL CONCRETE FOR FOOTING Total concrete volume of Footing & Slab
900(1)c2 AND SLAB ON
TIE BEAM, FILL (CLASS
COLUMN, A, 28 DAYS)
SUSPENDED SLAB, 12.40 CU.M. on grade
Total volume of concrete for beam, 13,025.21 #N/A
900(1) GIRDER/BEAM (CLASS A, 28 DAYS)
FORMWORKS AND FALSEWORKS (FOR 23.60 CU.M. column
and othertiestructural
beam, suspended
membersslab
that&need
girder 32,777.78 #N/A
903(2) ONE-STOREY BUILDING) 49.00 SQ.M. form for concreting 9,285.80 928.58
100MM CHB NON LOAD
BEARING/LOAD BEARING (INCLUDING
1046 REINFORCING
150mm. CHB NONSTEEL)
LOAD BEARING 189.00 SQ.M. Total area of wall using 4" CHB 19,764.71 #N/A
1046 (including Reinforcing
CEMENT PLASTER FINISH Steel)
WITH 19MM 36.00 SQ.M. Total
Total area
area of
of wall usingsurface
concrete 6" CHBto be 4,528.30 #N/A
Determine the steel materials by direct
1027(1) THICK & 1:3 MORTAR MIXTURE 420.00 SQ.M. plastered
counting on plan, then convert it to by 26,526.32 2,652.63
Determine the number of C-Purlins
1047(2)b STRUCTURAL STEEL ROOF TRUSS - KGS. weight in kilograms
direct counting on plan, then convert it to - -
1047(2)c STRUCTURAL STEEL PURLINS 200.00 KGS. weight in kilograms 995.02 895.52
FABRICATED METAL ROOFING
ACCESSORY (RIDGE/HIP Determine the roof area to be covered
1013(1) CORRUGATED METAL ROOFING
ROLLS/FLASHING/COUNTER FLASHING/ - SQ.M. by corrugated
Determine theroof
totalsheet
length of Flashing, - -
1013(2) VALLEY ROLL)
FABRICATED METAL ROOFING 38.00 M. Ridge Roll and Valley Roll 855.00 85.50
1013(2) ACCESSORY
PREPAINTED(GUTTER)
METAL SHEETS 13.00 M. Determine
Determine the
the total length
roof area to of
beGutter
covered 247.88 24.79
1014 (CORRUGATE, SHORTSHEETS
PREPAINTED METAL SPAN/LONG SPAN)
(RIB TYPE - SQ.M. by prepainted corrugated roof sheet
Determine the roof area to be covered - -
1014 0.4-0.5MM THICK) 140.00 SQ.M. by prepainted rib-type roof sheet 13,903.94 1,390.39
1016(1)a WATERPROOFING
UNGLAZED TILES/ CEMENT TILES/
GRANITE BASE 66.00 SQ.M. Determine the area for waterproofing 7,920.00 792.00
FIBER CEMENT BOARD/MARINE
1018 SYNTHETIC GRANITE TILES
PLYWOOD/ORDINARY PLYWOOD ON 80.00 SQ.M. Determine the area for tiles 29,743.59 2,974.36
1003(1) METAL FRAME CEILING 130.00 SQ.M. Determine
Determine the
and area
inputfor
theCeiling
total area of 28,761.06 2,876.11
1010(2)a HOLLOW
WOODENCORE
PANELFLUSH
DOORDOOR
WITH HEAVY 5.04 SQ.M. flush type door
Determine the total area of Wooden 3,543.75 354.38
1010(2) DUTY DOOR KNOB
PVC DOORS AND FRAMES W/ HEAVY 2.10 SQ.M. Panel Door 1,604.17 160.42
1043(1) DUTY DOOR KNOB 1.26 SQ.M. Determine
Determine the
the total
area ofarea of PVC surface
concrete Door 900.00 90.00
1032(1)a PAINTING WORKS (MASONRY PAINTING) 540.00 SQ.M. for painting the area of metal surface for
Determine 77,142.86 -
1032(1)c PAINTING WORKS
SUPPLY AND (METAL PAINTING)
INSTALLATION OF ANALOK 45.00 SQ.M. painting
Determine the total area of sliding 6,750.00 -
SPL - ? TYPE SLIDING WINDOW 11.34 SQ.M. window - -
If you need additional item that is not
found in this spreadsheet, you may use
this and go to "Other Item" Tab to create
SPL - ? (INPUT ITEM DESCRIPTION) 1.00 L.S. item of work - -
ItDetermine
is suggested thethat
number andfor
the unit length
this ofPLUMBING
item WORKS
50MM DIA - 100MM DIA SANITARY PVC Sanitary
is alwaysPipes by Sizes
1.00 Lump and The
Sum. indicate in in
estimator
1001(1)a PIPE, SERIES 600/1000 12.00 M. the
shall estimate DUPA tab 1,100.00 110.00
Inputgotheto total
its DUPA tab and
quantity indicate
of the waterthe
1002(6) WATERLINE
WATER CLOSET/PIPESURINAL
& FITTINGS
W/ COMPLETE 1.00 L.S. necessary
closet materials,
plustotal
urinal. tools
Also, go and
to manpower
the DUPA 2,200.00 220.00
Input
Input the
the in
total quantity of the Sinks. Also,
1002(5) ACCESSORIES
KITCHEN SINK/ SCRUB/ SLOPUNDER
SINK W/ 1.00 SET and
go toinput
the DUPA thequantity
necessary
and input
of materials.
the
in the 450.00 45.00
WALL HANG/COUNTERTOP/ Countertops/Lavatory. Also, go to the
1002(5) COMPLETE ACCESSORIES
COUNTER LAVATORY W/ COMPLETE 1.00 SET necessary
DUPA materials. 450.00 45.00
Input and inputnumber
the total in the necessary
of floor drain. Go
1002(5) ACCESSORIES 1.00 SET materials.
to DUPA 450.00 45.00
Input theand
totalupdate
number or input the& Soap
of Toilet
1002(5) FLOOR DRAIN PLATES
SOAP HOLDER /TOILET(ANY SIZE)
SOAP/LIQUID 2.00 SET necessary
Holder. materials
Goarea
to DUPA 180.00 18.00
Input the of theand update
mirrior. or input
Update the
1002(5) SOAP/TISSUE HOLDER 1.00 SET the
DUPA necessary materials 168.75 16.88
(INPUT OTHER PLUMBING WORK ITEM Go to by inputting
DUPA theinput
Tab and necessary
the necessary
1002(5)p FACIAL
THAT IS MIRROR
NOT FOUND IN THIS 0.50 SQ.M. materials
materials, manpower and equipment 281.25 28.13
SPL- ? SPREADSHEET) 1.00 L.S. requirements. - -
Input the total length of the conduit and
update
Inpu the the materials
total number requirement inELECTRICAL
of utility box, the WORKS
1002(5) 15MM-25MM DIA. FLEXIBLE CONDUIT 200.00 M. DUPA
junction Tab Go to DUPA Tab and update 12,733.45 1,273.35
Input thebox.total length of Electrical Wire.
1100 JUNCTION UTILITY/PULL
1.6MM2 - 5.5MM2 / SQUARE
ELECTRIC WIRE BOX 33.00 PC. the
Go to necessary
DUPA Tab materials
and breakdown the 2,970.00 297.00
1101(2) (TW/THHN/TWHN2) 600.00 M. materials accroding to wire size 5,400.00 540.00
SINGLE CONVINENCE OUTLET/
RECEPTACLE, GROUNDING
DUPLEX CONVINENCE TYPE/HEAVY
OUTLET/ Input the total number of Single
1101 DUTY CONVENIENCE
RECEPTACLE, OUTLET 13.00 SET Convenience Outlet 731.25 -
PANEL BOARDGROUNDING
WITH MAINTYPE/HEAVY Input
Input the
the total
numbernumber
of set.ofGo
Double
to DUPA tab
1101 DUTY CONVENIENCE
BREAKER/BRANCHES, OUTLET
3 WIRES, 1 WITH 10.00 SET Convenience
and Outlet 675.00 -
FLOURESCENT LIGHTING FIXTURE Count and input the number of Bulbs.and
update the materials component Go
1102 NEUTRAL,
BALLAST/ 50AMP-200AMP
LIGHTELECTRICAL
EMITTING DIODE 1.00 SET indicate the needed Circuit Breakers. 1,512.50 -
(INPUT OTHER WORK(LED)
ITEM to DUPA tab to update the materials
Go to DUPA Tab and input the necessary
1103(2) BULB, 1 BULB
THAT IS NOT FOUND IN THIS 40.00 SET requirements
materials, manpower and equipment 9,000.00 900.00
SPL- ? SPREADSHEET) 1.00 L.S. requirements. - -
329,138.26 #N/A
Manpower / Equipment/
MARK-UPS Labor Tools
OCM 5%
PROFIT 10%
VALUE ADDED TAX (VAT) 0%
EET, HENCE YOU CAN CUSTOMIZE BASE ON YOUR NEEDS)

TIAL BUILDING

RECT COST INDIRECT COST


Materials OCM Profit VAT Total Cost Unit Cost

- 1,107.76 2,215.52 - 25,478.48 127.39


- 557.37 1,114.74 - 12,819.45 2,563.89
- #N/A #N/A #N/A #N/A #N/A
- #REF! #REF! #REF! #REF! #REF!
4,200.00 #N/A #N/A #N/A #N/A #N/A
120,251.25 #REF! #REF! #REF! #REF! #REF!

- #REF! #REF! #REF! #REF! #REF!

55,942.60 #N/A #N/A #N/A #N/A #N/A


99,391.40 #N/A #N/A #N/A #N/A #N/A
29,647.03 1,993.07 3,986.14 - 45,840.62 935.52

120,511.13 #N/A #N/A #N/A #N/A #N/A


33,660.00 #N/A #N/A #N/A #N/A #N/A
57,141.00 4,316.00 8,632.00 - 99,267.94 236.35
- - - - - #DIV/0!
16,107.00 899.88 1,799.75 - 20,697.17 103.49
- - - - - #DIV/0!
8,167.21 455.39 910.77 - 10,473.87 275.63
2,941.34 160.70 321.40 - 3,696.11 284.32
- - - - - #DIV/0!
53,354.00 3,432.42 6,864.83 - 78,945.58 563.90
3,499.47 610.57 1,221.15 - 14,043.19 212.78
70,502.00 5,161.00 10,321.99 - 118,702.94 1,483.79
125,787.57 7,871.24 15,742.47 - 181,038.45 1,392.60
11,550.00 772.41 1,544.81 - 17,765.35 3,524.87
6,600.00 418.23 836.46 - 9,619.28 4,580.61
2,625.00 180.75 361.50 - 4,157.25 3,299.40
78,160.10 7,765.15 15,530.30 - 178,598.40 330.74
22,411.13 1,458.06 2,916.11 - 33,535.30 745.23
45,360.00 2,268.00 4,536.00 - 52,164.00 4,600.00

- - - - - -

1,980.00 159.50 319.00 - 3,668.50 305.71


2,780.00 260.00 520.00 - 5,980.00 5,980.00
6,600.00 354.75 709.50 - 8,159.25 8,159.25
4,950.00 272.25 544.50 - 6,261.75 6,261.75
3,850.00 217.25 434.50 - 4,996.75 4,996.75
770.00 48.40 96.80 - 1,113.20 556.60
385.00 28.53 57.06 - 656.22 656.22
495.00 40.22 80.44 - 925.03 1,850.06
- - - - - -

3,300.00 865.34 1,730.68 - 19,902.81 99.51


1,633.50 245.03 490.05 - 5,635.58 170.78
19,140.00 1,254.00 2,508.00 - 28,842.00 48.07
2,574.00 165.26 330.53 - 3,801.04 292.39
2,530.00 160.25 320.50 - 3,685.75 368.58
6,656.00 408.43 816.85 - 9,393.78 9,393.78
7,920.00 891.00 1,782.00 - 20,493.00 512.33
- - - - -
1,033,372.73 #N/A #N/A #N/A #N/A

Materials OCM Profit VAT Total Cost


(PUT YOUR HEADER/LOGO)

PROJECT TITLE: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Project Location: ZAMBOANGA CITY

BREAKDOWN OF EXPENDITURES % OF TOTAL AMOUNT PERCENTAGE


DIRECT COST:
Materials #N/A 1,033,372.73 #N/A MATERIALS
Labor/Manpower #N/A 329,138.26 #N/A LABOR
Equipment/Tools Expenses #N/A #N/A #N/A EQUIPMENT
SUB-TOTAL (DIRECT COST) #N/A #N/A 34,376,992.18 xxx p-1 34,376,992.18
INDIRECT COST:
Overhead, Contingency & Misc. #N/A #N/A
Contractor's Profit #N/A #N/A
Value Added Tax #N/A #N/A
SUB-TOTAL (INDIRECT COST)
TOTAL PROJECT COST #N/A #N/A 27,089,626.00

Prepared by:

Licensed Engineer/Registered Master Plumber/Master Electrician

NOTE:
1. FOR QUERIES REGARDING THIS, YOU MAY COMMUNICATE WITH THE AUTHOR AT em.bautistajr@yahoo.com OR ON HIS YOUTUBE CHANNEL
2. THIS ESTIMATE FORMAT IN DETAILED UNIT PRICE ANALYSIS IS A PERSONAL PROPERTY OF ENGR. EDITO M. BAUTISTA, JR. CE, EnP, RMP, RME
3. IF YOU USE THIS IN A STUDY OR RESEARCH, PLEASE ACKNOWLEDGE THE AUTHOR.
4. DISCLAIMER: THE AUTHOR OF THIS SPREADSHEET IS DENYING ANY AND ALL LIABILITY FOR ANY DAMAGES ARISING OUT FROM USING THIS SPREADSHEET.
5. THE BASIS FOR THE DERIVATION OF THIS SPREADSHEET IS THE DPWH DEPARTMENT ORDER NO. 137 SERIES OF 2017, COST ESTIMATION MANUAL FOR LOW RISE BUILDING (UPTO 5 STOREY BUILDING)
6. THE USER MAY CHANGE THE MANPOWER RATES, EQUIPMENT RATES, MATERIALS PRICES AND THE MARK-UPS (OCM, PROFIT & TAX)
(PUT YOUR HEADER/LOGO)

PROJECT TITLE: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
Project Location: ZAMBOANGA CITY

MARK-UPS
TOTAL MARK-UP
ITEM ESTIMATED IN PERCENT
DESCRIPTION QUANTITY UNIT VAT
NO. DIRECT COST
OCM PROFIT % VALUE
(9) (10)
-1 (2) (3) (4) (5) (6) (7) (8)
(5)X(8) (5)+(9))
CIVIL WORKS
800(1) CLEARING AND GRUBBING 200.00 SQ.M. 22,155.20 5% 10% 15% 3,323.28 0.00
800(3)a INDIVIDUAL REMOVAL OF TREES (UPTO 5.00 EACH 11,147.35 5% 10% 15% 1,672.10 0.00
803(1)a 300MM DIAMETER)
STRUCTURE EXCAVATION (COMMON SOIL) 23.00 CU.M. #N/A 5% 10% 15% #N/A #N/A
803(1)a STRUCTURE EXCAVATION (SOFT ROCK) 0.00 CU.M. #REF! 5% 10% 15% #REF! #REF!
804(4) GRAVEL BEDDING 3.00 CU.M. #N/A 5% 10% 15% #N/A #N/A

902(1) REINFORCING STEEL OF REINFORCED 1,500.00 KGS. #REF! 5% 10% 15% #REF! #REF!
CONCRETE STRUCTURES FOR ONE-
STOREY, GRADE 40/60

902(1) REINFORCING STEEL OF REINFORCED 0.00 KGS. #REF! 5% 10% 15% #REF! #REF!
CONCRETE STRUCTURES FOR TWO UPTO
FIVE STOREY
900(1)c2 STRUCTURAL CONCRETE FOR FOOTING 12.40 CU.M. #N/A 5% 10% 15% #N/A #N/A
AND SLAB ON FILL (CLASS A, 28 DAYS)
900(1) STRUCTURAL CONCRETE FOR FOOTING 23.60 CU.M. #N/A 5% 10% 15% #N/A #N/A
903(2) TIE BEAM, COLUMN,
FORMWORKS SUSPENDED SLAB,
AND FALSEWORKS (FOR 49.00 SQ.M. 39,861.41 5% 10% 15% 5,979.21 0.00
1046 GIRDER/BEAM
ONE-STOREY (CLASS
LOADA,BEARING/LOAD
BUILDING)
100MM CHB NON 28 DAYS) 189.00 SQ.M. #N/A 5% 10% 15% #N/A #N/A
BEARING (INCLUDING REINFORCING STEEL)

1046 150mm. CHB NON LOAD BEARING (including 36.00 SQ.M. #N/A 5% 10% 15% #N/A #N/A
Reinforcing Steel)
1027(1) CEMENT PLASTER FINISH WITH 19MM 420.00 SQ.M. 86,319.95 5% 10% 15% 12,947.99 0.00
THICK & 1:3 MORTAR MIXTURE
1047(2)b STRUCTURAL STEEL ROOF TRUSS 0.00 KGS. 0.00 5% 10% 15% 0.00 0.00
1047(2)c STRUCTURAL STEEL PURLINS 200.00 KGS. 17,997.54 5% 10% 15% 2,699.63 0.00
1013(1) CORRUGATED METAL ROOFING 0.00 SQ.M. 0.00 5% 10% 15% 0.00 0.00
1013(2) FABRICATED METAL ROOFING ACCESSORY 38.00 M. 9,107.71 5% 10% 15% 1,366.16 0.00
(RIDGE/HIP ROLLS/FLASHING/COUNTER
FLASHING/ VALLEY ROLL)

1013(2) FABRICATED METAL ROOFING ACCESSORY 13.00 M. 3,214.01 5% 10% 15% 482.10 0.00
(GUTTER)
1014 PREPAINTED METAL SHEETS 0.00 SQ.M. 0.00 5% 10% 15% 0.00 0.00
(CORRUGATE, SHORT SPAN/LONG SPAN)
1014 PREPAINTED METAL SHEETS (RIB TYPE 0.4- 140.00 SQ.M. 68,648.33 5% 10% 15% 10,297.25 0.00
0.5MM THICK)
1016(1)a WATERPROOFING CEMENT BASE 66.00 SQ.M. 12,211.47 5% 10% 15% 1,831.72 0.00

1018 UNGLAZED TILES/ GRANITE TILES/ 80.00 SQ.M. 103,219.95 5% 10% 15% 15,482.99 0.00
SYNTHETIC GRANITE TILES
1003(1) FIBER CEMENT BOARD/MARINE 130.00 SQ.M. 157,424.74 5% 10% 15% 23,613.71 0.00
PLYWOOD/ORDINARY PLYWOOD ON METAL
FRAME CEILING
1010(2)a HOLLOW CORE FLUSH DOOR 5.04 SQ.M. 15,448.13 5% 10% 15% 2,317.22 0.00

1010(2) WOODEN PANEL DOOR WITH HEAVY DUTY 2.10 SQ.M. 8,364.59 5% 10% 15% 1,254.69 0.00
DOOR KNOB
1043(1) PVC DOORS AND FRAMES W/ HEAVY DUTY 1.26 SQ.M. 3,615.00 5% 10% 15% 542.25 0.00
DOOR KNOB
1032(1)a PAINTING WORKS (MASONRY PAINTING) 540.00 SQ.M. 155,302.96 5% 10% 15% 23,295.44 0.00

1032(1)c PAINTING WORKS (METAL PAINTING) 45.00 SQ.M. 29,161.13 5% 10% 15% 4,374.17 0.00

SPL - ? SUPPLY AND INSTALLATION OF ANALOK 11.34 SQ.M. 45,360.00 5% 10% 15% 6,804.00 0.00
TYPE SLIDING WINDOW
SPL - ? (INPUT ITEM DESCRIPTION) 1.00 L.S. 0.00 5% 10% 15% 0.00 0.00
PLUMBING WORKS
1001(1)a 50MM DIA - 100MM DIA SANITARY PVC PIPE, 12.00 M. 3,190.00 5% 10% 15% 478.50 0.00
SERIES 600/1000

1002(6) WATERLINE PIPES & FITTINGS 1.00 L.S. 5,200.00 5% 10% 15% 780.00 0.00
1002(5) WATER CLOSET/ URINAL W/ COMPLETE 1.00 SET 7,095.00 5% 10% 15% 1,064.25 0.00
1002(5) ACCESSORIES
KITCHEN SINK/ SCRUB/ SLOP SINK W/ 1.00 SET 5,445.00 5% 10% 15% 816.75 0.00
COMPLETE ACCESSORIES

1002(5) WALL HANG/COUNTERTOP/ UNDER 1.00 SET 4,345.00 5% 10% 15% 651.75 0.00
COUNTER LAVATORY W/ COMPLETE
ACCESSORIES
1002(5) FLOOR DRAIN PLATES (ANY SIZE) 2.00 SET 968.00 5% 10% 15% 145.20 0.00

1002(5) SOAP HOLDER /TOILET SOAP/LIQUID 1.00 SET 570.63 5% 10% 15% 85.59 0.00
SOAP/TISSUE HOLDER
1002(5)p FACIAL MIRROR 0.50 SQ.M. 804.38 5% 10% 15% 120.66 0.00

SPL- ? (INPUT OTHER PLUMBING WORK ITEM 1.00 L.S. 0.00 5% 10% 15% 0.00 0.00
THAT IS NOT FOUND IN THIS
SPREADSHEET)
ELECTRICAL WORKS
1002(5) 15MM-25MM DIA. FLEXIBLE CONDUIT 200.00 M. 17,306.80 5% 10% 15% 2,596.02 0.00
1100 JUNCTION UTILITY/PULL / SQUARE BOX 33.00 PC. 4,900.50 5% 10% 15% 735.08 0.00
1101(2) 1.6MM2 - 5.5MM2 ELECTRIC WIRE 600.00 M. 25,080.00 5% 10% 15% 3,762.00 0.00
(TW/THHN/TWHN2)
1101 SINGLE CONVINENCE OUTLET/ 13.00 SET 3,305.25 5% 10% 15% 495.79 0.00
RECEPTACLE, GROUNDING TYPE/HEAVY
DUTY CONVENIENCE OUTLET

1101 DUPLEX CONVINENCE OUTLET/ 10.00 SET 3,205.00 5% 10% 15% 480.75 0.00
RECEPTACLE, GROUNDING TYPE/HEAVY
DUTY CONVENIENCE OUTLET

1102 PANEL BOARD WITH MAIN 1.00 SET 8,168.50 5% 10% 15% 1,225.28 0.00
BREAKER/BRANCHES, 3 WIRES, 1 NEUTRAL,
1103(2) 50AMP-200AMP
FLOURESCENT LIGHTING FIXTURE WITH 40.00 SET 17,820.00 5% 10% 15% 2,673.00 0.00
BALLAST/ LIGHT EMITTING DIODE (LED)
BULB, 1 BULB

SPL- ? (INPUT OTHER ELECTRICAL WORK ITEM 1.00 L.S. 0.00 5% 10% 15% 0.00 0.00
THAT IS NOT FOUND IN THIS
SPREADSHEET)

Prepared by:

Licensed Engineer/Registered Master Plumber/Master Electrician


G

TOTAL UNIT
TOTAL COST
INDIRECT COST COST

(11) (12) (13)


(9)+(10) (5)+(11) (12)/(3)

3,323.28 25,478.48 127.39 Php -


1,672.10 12,819.45 2,563.89 Php -
#N/A #N/A #N/A #N/A
#REF! #REF! #REF! #REF!
#N/A #N/A #N/A
#N/A
#REF! #REF! #REF!

#REF!
#REF! #REF! #REF!

#REF!
#N/A #N/A #N/A
#N/A
#N/A #N/A #N/A #N/A
5,979.21 45,840.62 935.52 Php -
#N/A #N/A #N/A

#N/A
#N/A #N/A #N/A
#N/A
12,947.99 99,267.94 236.35
Php -
0.00 0.00 #DIV/0! Php -
2,699.63 20,697.17 103.49 Php -
0.00 0.00 #DIV/0!
Php -
1,366.16 10,473.87 275.63

Php -
482.10 3,696.11 284.32
Php -
0.00 0.00 #DIV/0!
Php -
10,297.25 78,945.58 563.90
Php -
1,831.72 14,043.19 212.78
Php -
15,482.99 118,702.94 1,483.79
Php -
23,613.71 181,038.45 1,392.60

Php -
2,317.22 17,765.35 3,524.87
Php -
1,254.69 9,619.28 4,580.61
Php -
542.25 4,157.25 3,299.40
Php -
23,295.44 178,598.40 330.74
Php -
4,374.17 33,535.30 745.23
Php -
6,804.00 52,164.00 4,600.00
Php -
0.00 0.00 0.00 Php -
Php -
478.50 3,668.50 305.71
Php -
780.00 5,980.00 5,980.00 Php -
1,064.25 8,159.25 8,159.25 Php -
816.75 6,261.75 6,261.75
Php -
651.75 4,996.75 4,996.75

Php -
145.20 1,113.20 556.60
Php -
85.59 656.22 656.22 Php -
120.66 925.03 1,850.06
Php -
0.00 0.00 0.00
Php -
Php -
2,596.02 19,902.81 99.51
Php -
735.08 5,635.58 170.78
Php -
3,762.00 28,842.00 48.07
Php -
495.79 3,801.04 292.39

Php -
480.75 3,685.75 368.58

Php -
1,225.28 9,393.78 9,393.78
Php -
2,673.00 20,493.00 512.33

Php -
0.00 0.00 0.00
Php -
#N/A
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 800(1) CLEARING AND GRUBBING


UNIT Unit of Measurement: SQ.M.
Output per day: 500.00 SQ.M./DAY
QTY Quantity: 200.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.40 700.00 280.00
b. Laborer 2 0.40 400.00 320.00

Number of Teams:
LABOR Sub-Total for A P 600.00 1.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck 2 0.40 10,816.00 8,652.80
b. Payloader 1 0.40 13,864.00 5,545.60
c. Bulldozer 1 0.40 18,392.00 7,356.80

EQUIPMENT Sub-Total for B P 21,555.20


C. Total (A+B) 22,155.20
D. Output per day = 500.00 SQ.M./DAY 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
N/A 4.00

0.00 2.00 4.00

MATERIAL Sub-Total for E P


F. Direct Cost (C+E) 22,155.20
G. Overhead, Contingencies & Miscellaneous 5% 1,107.76
H. Contractor's Profit (CP) 10% 2,215.52
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 25,478.48
ADJUSTED CHECKING k. Total Unit Cost 127.39
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 800(3)a INDIVIDUAL REMOVAL OF TREES (UPTO 300MM DIAMETER)
UNIT Unit of Measurement: EACH
Output per day: 8.00 EACH/DAY
QTY Quantity: 5.00 EACH

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.63 800.00 500.00
b. Skilled Laborer 1 0.63 600.00 375.00
c. Laborer 2 0.63 400.00 500.00

Number of Teams:
LABOR Sub-Total for A P 1,375.00 1.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Backhoe 1 1.25 16,599.00 20,748.75
b. Dump Truck 1 0.85 10,816.00 9,193.60
c. Chainsaw 1 0.85 600.00 510.00
Minor Tools (5% of Labor Cost) 1 68.75

EQUIPMENT Sub-Total for B P 9,772.35


C. Total (A+B) 11,147.35
D. Output per day = 8.00 EACH/DAY 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
N/A 4.00

0.00 2.00 4.00

MATERIAL Sub-Total for E P


F. Direct Cost (C+E) 11,147.35
G. Overhead, Contingencies & Miscellaneous 5% 557.37
H. Contractor's Profit (CP) 10% 1,114.74
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 12,819.45
ADJUSTED CHECKING k. Total Unit Cost 2,563.89
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 803(1)a STRUCTURE EXCAVATION (COMMON SOIL) NO. OF TEAM: 1
UNIT Unit of Measurement: CU.M.
Output per day: 160.00 CU.M./DAY
QTY Quantity: 23.00 CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.14 800.00 115.00
b. Laborer 3 0.14 400.00 172.50

LABOR Sub-Total for A P 287.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck 2 0.14 #N/A #N/A
b. Backhoe 1 0.14 #N/A #N/A
Minor Tools (10%) 28.75

EQUIPMENT Sub-Total for B P #N/A


C. Total (A+B) #N/A
D. Output per day = 160.00 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N.A.

MATERIAL Sub-Total for E P


F. Direct Cost (C+E) #N/A
G. Overhead, Contingencies & Miscellaneous 5% #N/A
H. Contractor's Profit (CP) 10% #N/A
I. Value Added Tax (VAT) 0% #N/A
CHECKING J. Total Cost #N/A
ADJUSTED CHECKING k. Total Unit Cost #N/A
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 803(1)a STRUCTURE EXCAVATION (SOFT ROCK) NO. OF TEAM: 1
UNIT Unit of Measurement: CU.M.
Output per day: 112.00 CU.M./DAY
QTY Quantity: 0.00 CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.00 800.00 0.00
b. Laborer 3 0.00 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Dump Truck 2 0.00 #REF! #REF!
b. Backhoe 1 0.00 #REF! #REF!
c. Backhoe with Breaker 1 0.00 #REF! #REF!
Minor Tools (10%) 0.00

EQUIPMENT Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 112.00 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
N.A.

MATERIAL Sub-Total for E P


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 5% #REF!
H. Contractor's Profit (CP) 10% #REF!
I. Value Added Tax (VAT) 0% #REF!
CHECKING J. Total Cost #REF!
ADJUSTED CHECKING k. Total Unit Cost #REF!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 804(4) GRAVEL BEDDING NO. OF TEAM: 1


UNIT Unit of Measurement: CU.M.
Output per day: 9.60 CU.M./DAY
QTY Quantity: 3.00 CU.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.31 800.00 250.00
b. Laborer 3 0.31 400.00 375.00

LABOR Sub-Total for A P 625.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Plate Compactor 2 0.31 #N/A #N/A
Minor Tools (10%) 62.50

EQUIPMENT Sub-Total for B P #N/A


C. Total (A+B) #N/A
D. Output per day = 9.60 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Gravel Bedding 3.00 cu.m. 1400.00 4,200.00

MATERIAL Sub-Total for E P 4,200.00


F. Direct Cost (C+E) #N/A
G. Overhead, Contingencies & Miscellaneous 5% #N/A
H. Contractor's Profit (CP) 10% #N/A
I. Value Added Tax (VAT) 0% #N/A
CHECKING J. Total Cost #N/A
ADJUSTED CHECKING k. Total Unit Cost #N/A
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 902(1) REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES FOR ONE-STOREY, GRADE
UNIT Unit of Measurement: KGS. 40/60
Output per day: 1,147.50 KGS./DAY
QTY Quantity: 1,500.00 KGS.

NO. OF TEAM
Designation No. Person No. of Days Daily Rate Amount
1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 1.307 800.00 1,045.75
b. Skilled Laborer 3 1.307 600.00 2,352.93
b. Laborer 12 1.307 400.00 6,274.49

LABOR Sub-Total for A P 9,673.17

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Bar Cutter 1 0.65 #REF! #REF!
b. Bar Bender 1 0.65 #REF! #REF!
c. Cargo Truck/Hauling Truck 1 0.20 #REF! #REF!

EQUIPMENT Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 1,147.50 KGS./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Deformed Reinforcing Steel Bar (Grade 40) 1500.00 kgs. 75.00 112,500.00
b. #16 G.I. Tie-wire 22.50 kgs. 90.00 2,025.00
Consumables (5% of Materials Cost) 5,726.25

MATERIAL Sub-Total for E P 120,251.25


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 5% #REF!
H. Contractor's Profit (CP) 10% #REF!
I. Value Added Tax (VAT) 0% #REF!
CHECKING J. Total Cost #REF!
ADJUSTED CHECKING k. Total Unit Cost #REF!

Input here the quantity of Steel Bars:


Unit Wt. Total kgs
*25mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 3.86 23.13
*20mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 2.47 14.80
*16mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 1.58 9.47
*12mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 0.89 5.33
*10mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 0.62 3.70

56.43
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 902(1) REINFORCING STEEL OF REINFORCED CONCRETE STRUCTURES FOR TWO UPTO FIVE STOREY
UNIT Unit of Measurement: KGS.
Output per day: 1,032.75 KGS./DAY
QTY Quantity: 0.00 KGS.

NO. OF TEAM
Designation No. Person No. of Days Daily Rate Amount
1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.000 800.00 0.00
b. Skilled Laborer 3 0.000 600.00 0.00
b. Laborer 12 0.000 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Bar Cutter 1 0.00 #REF! #REF!
b. Bar Bender 1 0.00 #REF! #REF!
Minor Tools (10% of Labor Cost) 0.00

EQUIPMENT Sub-Total for B P #REF!


C. Total (A+B) #REF!
D. Output per day = 1,032.75 KGS./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Deformed Reinforcing Steel Bar (Grade 40) 0.00 kg. 75.00 0.00
b. #16 G.I. Tie-wire 0.00 kg. 90.00 0.00
Consumables (5% of Materials Cost) 0.00

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) #REF!
G. Overhead, Contingencies & Miscellaneous 5% #REF!
H. Contractor's Profit (CP) 10% #REF!
I. Value Added Tax (VAT) 0% #REF!
CHECKING J. Total Cost #REF!
ADJUSTED CHECKING k. Total Unit Cost #REF!

Input here the quantity of Steel Bars:


Unit Wt. Total kgs
*25mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 3.86 23.13
*20mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 2.47 14.80
*16mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 1.58 9.47
*12mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 0.89 5.33
*10mmØ x 6.00m Deformed Reinforcing Steel Bar 1.00 0.62 3.70

56.43
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 900(1)c2 STRUCTURAL CONCRETE FOR FOOTING AND SLAB ON FILL (CLASS A, 28 DAYS)
UNIT Unit of Measurement: CU.M.
Output per day: 2.86 CU.M./DAY
QTY Quantity: 12.40 CU.M.

NO. OF TEAM
Designation No. Person No. of Days Daily Rate Amount
1
A. Labor
Concrete Pouring Works
DURATION a. Construction Foreman/Engineering Assistant 1 4.342 800.00 3,473.39
b. Skilled Laborer 1 4.342 600.00 2,605.04
c. Laborer 4 4.342 400.00 6,946.78

LABOR Sub-Total for A P 13,025.21

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 4.342 #N/A #N/A
Minor Tools (10% of Labor Cost) 1,302.52

EQUIPMENT Sub-Total for B P #N/A


C. Total (A+B) #N/A
D. Output per day = 2.86 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Portland Cement 112.84 bags 265.00 29,902.60
b. Sand 6.20 cu.m. 1,400.00 8,680.00
c. Gravel 12.40 cu.m. 1,400.00 17,360.00

MATERIAL Sub-Total for E P 55,942.60


F. Direct Cost (C+E) #N/A
G. Overhead, Contingencies & Miscellaneous 5% #N/A
H. Contractor's Profit (CP) 10% #N/A
I. Value Added Tax (VAT) 0% #N/A
CHECKING J. Total Cost #N/A
ADJUSTED CHECKING k. Total Unit Cost #N/A

3500
170
14.70588235
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: STRUCTURAL CONCRETE FOR FOOTING TIE BEAM, COLUMN, SUSPENDED SLAB,
GIRDER/BEAM (CLASS A, 28 DAYS)
900(1)
UNIT Unit of Measurement: CU.M.
Output per day: 2.16 CU.M./DAY
QTY Quantity: 23.60 CU.M.

NO. OF TEAM
Designation No. Person No. of Days Daily Rate Amount
1
A. Labor
Concrete Pouring Works
DURATION a. Construction Foreman/Engineering Assistant 1 10.926 800.00 8,740.74
b. Skilled Laborer 1 10.926 600.00 6,555.56
c. Laborer 4 10.926 400.00 17,481.48

LABOR Sub-Total for A P 32,777.78

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 10.926 #N/A #N/A
Minor Tools (10% of Labor Cost) 3,277.78

EQUIPMENT Sub-Total for B P #N/A


C. Total (A+B) #N/A
D. Output per day = 2.16 CU.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Portland Cement 214.76 bags 265.00 56,911.40
b. Sand 11.80 cu.m. 1,200.00 14,160.00
c. Gravel 23.60 cu.m. 1,200.00 28,320.00

MATERIAL Sub-Total for E P 99,391.40


F. Direct Cost (C+E) #N/A
G. Overhead, Contingencies & Miscellaneous 5% #N/A
H. Contractor's Profit (CP) 10% #N/A
I. Value Added Tax (VAT) 0% #N/A
CHECKING J. Total Cost #N/A
ADJUSTED CHECKING k. Total Unit Cost #N/A

3500
170
14.70588235
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 903(2) FORMWORKS AND FALSEWORKS (FOR ONE-STOREY BUILDING)

UNIT Unit of Measurement: SQ.M.


Output per day: 25.92 SQ.M.DAY
QTY Quantity: 49.00 SQ.M.

NO. OF TEAM
Designation No. Person No. of Days Daily Rate Amount
1
A. Labor
Installation:
DURATION a. Construction Foreman/Engineering Assistant 1 1.890 800.00 1,512.35
b. Skilled Laborer 2 1.890 600.00 2,268.52
c. Laborer 4 1.890 400.00 3,024.69

Stripping:
a. Construction Foreman/Engineering Assistant 1 0.775 800.00 620.06
b. Laborer 6 0.775 400.00 1,860.19

LABOR Sub-Total for A P 9,285.80

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

Minor Tools (10% of Labor Cost) 928.58

EQUIPMENT Sub-Total for B P 928.58


C. Total (A+B) 10,214.38
D. Output per day = 25.92 SQ.M.DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Ordinary Plywood - 3 uses 17.00 pcs. 890.00 15,132.67
b. Good Lumber - 3 uses 352.31 bd. Ft. 35.00 12,330.85
c. Assorted Common Wire Nails 10.29 kgs. 75.00 771.75
d. Consumables (5% of Materials Cost) 1,411.76

MATERIAL Sub-Total for E P 29,647.03


F. Direct Cost (C+E) 39,861.41
G. Overhead, Contingencies & Miscellaneous 5% 1,993.07
H. Contractor's Profit (CP) 10% 3,986.14
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 45,840.62
ADJUSTED CHECKING k. Total Unit Cost 935.52

3500
170
14.70588235
DETAILED UNIT PRICE ANALYSIS
NO. OF TEAMS 1.00
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING
0.00
ITEM NO. Item No./Description: 1046 100MM CHB NON LOAD BEARING/LOAD BEARING (INCLUDING REINFORCING STEEL)
UNIT Unit of Measurement: SQ.M.
Output per day: 30.60 SQ.M./DAY
QTY Quantity: 189.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
Concrete Pouring Works
DURATION a. Construction Foreman/Engineering Assistant 1 6.176 800.00 4,941.18
b. Mason 2 6.176 600.00 7,411.76
c. Laborer 3 6.176 400.00 7,411.76

LABOR Sub-Total for A P 19,764.71

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 6.176 #N/A #N/A
Minor Tools (10% of Labor Cost) 1,976.47

EQUIPMENT Sub-Total for B P #N/A


C. Total (A+B) #N/A
D. Output per day = 30.60 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. 100mm x 200mm x 400mm Concrete Hollow Blocks 2,457.00 pcs. 15.00 36,855.00
b. Portland Cement 99.23 bags 265.00 26,294.63
c. Washed Sand 7.56 cu.m. 1,400.00 10,584.00
Deformed Reinforcing Steel Bar (Sizes to be determined by 75.00 45,927.00
d. 612.36 kgs.
Estimator)
e. #16 G.I. Tie-wire 9.45 kgs. 90.00 850.50

MATERIAL Sub-Total for E P 120,511.13


F. Direct Cost (C+E) #N/A
G. Overhead, Contingencies & Miscellaneous 5% #N/A
H. Contractor's Profit (CP) 10% #N/A
I. Value Added Tax (VAT) 0% #N/A
CHECKING J. Total Cost #N/A
ADJUSTED CHECKING k. Total Unit Cost #N/A
DETAILED UNIT PRICE ANALYSIS
NO. OF TEAMS 1.00
PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1046 150mm. CHB NON LOAD BEARING (including Reinforcing Steel)
UNIT Unit of Measurement: SQ.M.
Output per day: 25.44 SQ.M./DAY
QTY Quantity: 36.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
Concrete Pouring Works
DURATION a. Construction Foreman/Engineering Assistant 1 1.415 800.00 1,132.08
b. Mason 2 1.415 600.00 1,698.11
c. Laborer 3 1.415 400.00 1,698.11

LABOR Sub-Total for A P 4,528.30

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. One Bagger Mixer 1 1.415 #N/A #N/A
Minor Tools (10% of Labor Cost) 452.83

EQUIPMENT Sub-Total for B P #N/A


C. Total (A+B) #N/A
D. Output per day = 25.44 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. 150mm x 200mm x 400mm Concrete Hollow Blocks 468.00 pcs. 18.00 8,424.00
b. Portland Cement 54.00 bags 265.00 14,310.00
c. Washed Sand 1.44 cu.m. 1,400.00 2,016.00
Deformed Reinforcing Steel Bar (Sizes to be determined by 75.00 8,748.00
d. 116.64 kgs.
Estimator)
e. #16 G.I. Tie-wire 1.80 kgs. 90.00 162.00

MATERIAL Sub-Total for E P 33,660.00


F. Direct Cost (C+E) #N/A
G. Overhead, Contingencies & Miscellaneous 5% #N/A
H. Contractor's Profit (CP) 10% #N/A
I. Value Added Tax (VAT) 0% #N/A
CHECKING J. Total Cost #N/A
ADJUSTED CHECKING k. Total Unit Cost #N/A
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1027(1) CEMENT PLASTER FINISH WITH 19MM THICK & 1:3 MORTAR MIXTURE
UNIT Unit of Measurement: SQ.M.
Output per day: 57.000 SQ.M./DAY
QTY Quantity: 420.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 7.37 800.00 5,894.74
b. Mason 2 7.37 600.00 8,842.11
c. Laborer 4 7.37 400.00 11,789.47

LABOR Sub-Total for A P 26,526.32

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 2,652.63

EQUIPMENT Sub-Total for B P 2,652.63


C. Total (A+B) 29,178.95
D. Output per day = 57.00 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Portland Cement 138.60 bags 265.00 36,729.00
b. Fine Sand 11.34 cu.m. 1,800.00 20,412.00

MATERIAL Sub-Total for E P 57,141.00


F. Direct Cost (C+E) 86,319.95
G. Overhead, Contingencies & Miscellaneous 5% 4,316.00
H. Contractor's Profit (CP) 10% 8,632.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 99,267.94
ADJUSTED CHECKING k. Total Unit Cost 236.35
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1047(2)b STRUCTURAL STEEL ROOF TRUSS


UNIT Unit of Measurement: KGS.
Output per day: 680.000 KGS./DAY
QTY Quantity: 0.00 KGS.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 0.00 800.00 0.00
b. Skilled Laborer 2 0.00 600.00 0.00
c. Laborer 2 0.00 400.00 0.00

Erection:
a. Skilled Laborer 3 0.00 600.00 0.00
b. Laborer 3 0.00 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Welding Machine 1 0.000 2,160.00 0.00
b. Cutting Outfit 1 0.000 364.00 0.00
c. Truck Mounted Crane (20-25 mt) 1 0.00 14,176.00 0.00
Minor Tools (10% of Labor Cost) 0.00

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 680.00 KGS./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Structural Steel 0.00 kgs. 70.00 0.00
b. Acetylene 0.00 cyl 3,500.00 0.00
c. Oxygene 0.00 cyl 1,800.00 0.00
d. Welding Rod 0.00 kgs. 160.00 0.00
Consumable (5% of Materials Cost) 0.00

The estimate need to count and specify the stee materials and
compute for its weight in kilograms

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 0.00
ADJUSTED CHECKING k. Total Unit Cost #DIV/0!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1047(2)c STRUCTURAL STEEL PURLINS


UNIT Unit of Measurement: KGS.
Output per day: 723.600 KGS./DAY
QTY Quantity: 200.00 KGS.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 0.28 800.00 221.12
b. Skilled Laborer 2 0.28 600.00 331.67
c. Laborer 4 0.28 400.00 442.23

LABOR Sub-Total for A P 995.02

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Welding Machine 2 0.207 2,160.00 895.52

EQUIPMENT Sub-Total for B P 895.52


C. Total (A+B) 1,890.54
D. Output per day = 723.60 KGS./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Structural Steel Purlins 210.00 kgs. 70.00 14,700.00
b. Welding Rod 4.00 kgs. 160.00 640.00
c. Consumable (5% of Materials Cost) 767.00

The estimate need to count and specify the stee materials and
compute for its weight in kilograms

MATERIAL Sub-Total for E P 16,107.00


F. Direct Cost (C+E) 17,997.54
G. Overhead, Contingencies & Miscellaneous 5% 899.88
H. Contractor's Profit (CP) 10% 1,799.75
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 20,697.17
ADJUSTED CHECKING k. Total Unit Cost 103.49
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1013(1) CORRUGATED METAL ROOFING


UNIT Unit of Measurement: SQ.M.
Output per day: 16.608 SQ.M./DAY
QTY Quantity: 0.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 0.00 800.00 0.00
b. Skilled Laborer 1 0.00 600.00 0.00
c. Laborer 2 0.00 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 0.00

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 16.61 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Corrugated Roofing Sheet 0.00 sq.m. 400.00 0.00
b. Tekscrew/ J-bolt with Washers 0.00 pc. 1.50 0.00
c. Consumables (3% of Materials Costs) 0.00

The estimator may include additional materials such as insualtor


foam to meet the detailed engineering plan.

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 0.00
ADJUSTED CHECKING k. Total Unit Cost #DIV/0!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: FABRICATED METAL ROOFING ACCESSORY (RIDGE/HIP ROLLS/FLASHING/COUNTER
1013(2) FLASHING/ VALLEY ROLL)
UNIT Unit of Measurement: M.
Output per day: 80.000 M./DAY
QTY Quantity: 38.00 M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 0.48 800.00 380.00
b. Skilled Laborer 1 0.48 600.00 285.00
c. Laborer 1 0.48 400.00 190.00

LABOR Sub-Total for A P 855.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 85.50

EQUIPMENT Sub-Total for B P 85.50


C. Total (A+B) 940.50
D. Output per day = 80.00 M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Ridge/Hip Rolls/Flashing/Valley Roll/ Counter Flashing (0.4- 183.33 6,966.67
a. 38.00 m
0.6mm Thk
b. Blind Rivets 722.00 pc. 1.33 962.67
c. Consumables (3% of Materials Costs) 237.88

MATERIAL Sub-Total for E P 8,167.21


F. Direct Cost (C+E) 9,107.71
G. Overhead, Contingencies & Miscellaneous 5% 455.39
H. Contractor's Profit (CP) 10% 910.77
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 10,473.87
ADJUSTED CHECKING k. Total Unit Cost 275.63
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: FABRICATED METAL ROOFING ACCESSORY (GUTTER)


1013(2)
UNIT Unit of Measurement: M.
Output per day: 94.400 M./DAY
QTY Quantity: 13.00 M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 0.14 800.00 110.17
b. Skilled Laborer 1 0.14 600.00 82.63
c. Laborer 1 0.14 400.00 55.08

LABOR Sub-Total for A P 247.88

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost) 24.79

EQUIPMENT Sub-Total for B P 24.79


C. Total (A+B) 272.67
D. Output per day = 94.40 M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
Ridge/Hip Rolls/Flashing/Valley Roll/ Counter Flashing (0.4- 183.33 2,383.33
a. 13.00 m
0.6mm Thk
b. 12" x 1" Plain GI Strap 39.00 pc. 5.00 195.00
c. Blind Rivets 208.00 pc. 1.33 277.33
d. Consumables (3% of Materials Costs) 85.67

MATERIAL Sub-Total for E P 2,941.34


F. Direct Cost (C+E) 3,214.01
G. Overhead, Contingencies & Miscellaneous 5% 160.70
H. Contractor's Profit (CP) 10% 321.40
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 3,696.11
ADJUSTED CHECKING k. Total Unit Cost 284.32
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1014 PREPAINTED METAL SHEETS (CORRUGATE, SHORT SPAN/LONG SPAN)
UNIT Unit of Measurement: SQ.M.
Output per day: 16.608 SQ.M./DAY
QTY Quantity: 0.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 0.00 800.00 0.00
b. Skilled Laborer 1 0.00 600.00 0.00
c. Laborer 2 0.00 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost. 0.00

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 16.61 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Prepainted Metal Roof Sheets (0.4-0.6mm Thick) 0.00 sq.m. 320.00 0.00
b. Teks Screw/ J-Bolt With Washers 0.00 pc. 5.00 0.00
c. Consumables (3% of Materials Costs) 0.00

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 0.00
ADJUSTED CHECKING k. Total Unit Cost #DIV/0!
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1014 PREPAINTED METAL SHEETS (RIB TYPE 0.4-0.5MM THICK)
UNIT Unit of Measurement: SQ.M.
Output per day: 22.152 SQ.M./DAY
QTY Quantity: 140.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
Fabrication:
DURATION a. Construction Foreman/Engineering Assistant 1 6.32 800.00 5,055.98
b. Skilled Laborer 1 6.32 600.00 3,791.98
c. Laborer 2 6.32 400.00 5,055.98

LABOR Sub-Total for A P 13,903.94

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of Labor Cost. 1,390.39

EQUIPMENT Sub-Total for B P 1,390.39


C. Total (A+B) 15,294.33
D. Output per day = 22.15 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Prepainted Metal Roof Sheets (Rib Type) 140.00 m 320.00 44,800.00
b. Teks Screw/ J-Bolt With Washers 1,400.00 pc. 5.00 7,000.00
c. Consumables (3% of Materials Costs) 1,554.00

MATERIAL Sub-Total for E P 53,354.00


F. Direct Cost (C+E) 68,648.33
G. Overhead, Contingencies & Miscellaneous 5% 3,432.42
H. Contractor's Profit (CP) 10% 6,864.83
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 78,945.58
ADJUSTED CHECKING k. Total Unit Cost 563.90
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1016(1)a WATERPROOFING CEMENT BASE


UNIT Unit of Measurement: SQ.M. 0
Output per day: 15.00 SQ.M./DAY 0
QTY Quantity: 66.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 4.40 800.00 3,520.00
b. Skilled Worker 1 4.40 600.00 2,640.00
c. Laborer 1 4.40 400.00 1,760.00

LABOR Sub-Total for A P 7,920.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 792.00

EQUIPMENT Sub-Total for B P 792.00


C. Total (A+B) 8,712.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Cementitious Type Waterproofing Membrane 3.54 gals. 950.00 3,358.93 4.00
b. Portland Cement 0.53 bag 265.00 140.54
0.00 2.00 4.00

MATERIAL Sub-Total for E P 3,499.47


F. Direct Cost (C+E) 12,211.47
G. Overhead, Contingencies & Miscellaneous 5% 610.57
H. Contractor's Profit (CP) 10% 1,221.15
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 14,043.19
ADJUSTED CHECKING k. Total Unit Cost 212.78
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1018 UNGLAZED TILES/ GRANITE TILES/ SYNTHETIC GRANITE TILES
UNIT Unit of Measurement: SQ.M. 0
Output per day: 15.60 SQ.M./DAY 0
QTY Quantity: 80.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 5.13 800.00 4,102.56
b. Skilled Worker 5 5.13 600.00 15,384.62
c. Laborer 5 5.13 400.00 10,256.41

LABOR Sub-Total for A P 29,743.59

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 2,974.36

EQUIPMENT Sub-Total for B P 2,974.36


C. Total (A+B) 32,717.95
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Unglazed Tiles/Granite Tiles 80.00 sq.m. 750.00 60,000.00 4.00
b. Portland Cement 26.00 bags 265.00 6,890.00
c. Sand 2.08 cu.m. 1,400.00 2,912.00 0.00 2.00 4.00
d. Tile Grout 10.00 bag 70.00 700.00

MATERIAL Sub-Total for E P 70,502.00


F. Direct Cost (C+E) 103,219.95
G. Overhead, Contingencies & Miscellaneous 5% 5,161.00
H. Contractor's Profit (CP) 10% 10,321.99
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 118,702.94
ADJUSTED CHECKING k. Total Unit Cost 1,483.79
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1003(1) FIBER CEMENT BOARD/MARINE PLYWOOD/ORDINARY PLYWOOD ON METAL FRAME CEILING
UNIT Unit of Measurement: SQ.M. 0
Output per day: 9.94 SQ.M./DAY 0
QTY Quantity: 130.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 13.07 800.00 10,458.57
b. Skilled Worker 1 13.07 600.00 7,843.93
c. Laborer 2 13.07 400.00 10,458.57

LABOR Sub-Total for A P 28,761.06

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 2,876.11

EQUIPMENT Sub-Total for B P 2,876.11


C. Total (A+B) 31,637.17
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. 4.5mm Fiber Cement Board 47.45 pc. 420.00 19,929.00 4.00
b. 2" Metal Furring x 3 meter length 147.03 bags 150.00 22,054.50
c. Carrying Channels 2" 46.41 cu.m. 80.00 3,712.80 0.00 2.00 4.00
d. Hanger Bars/Rod - 12mm 130.00 pc. 46.67 6,066.67
e. Channel Clip 780.00 pc. 90.00 70,200.00
f. Wall Angle 30.94 pc. 90.00 2,784.60
g. 1/8" Blind Rivet 2.17 boxes 480.00 1,040.00

MATERIAL Sub-Total for E P 125,787.57


F. Direct Cost (C+E) 157,424.74
G. Overhead, Contingencies & Miscellaneous 5% 7,871.24
H. Contractor's Profit (CP) 10% 15,742.47
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 181,038.45
ADJUSTED CHECKING k. Total Unit Cost 1,392.60
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1010(2)a HOLLOW CORE FLUSH DOOR


UNIT Unit of Measurement: SQ.M.
Output per day: 2.56 SQ.M./DAY
QTY Quantity: 5.04 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 1.97 800.00 1,575.00
b. Carpenter 1 1.97 600.00 1,181.25 3.047851265
c. Laborer 1 1.97 400.00 787.50

LABOR Sub-Total for A P 3,543.75

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 354.38

EQUIPMENT Sub-Total for B P 354.38


C. Total (A+B) 3,898.13
D. Output per day = 2.56 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Hollow Core Flush Door 5.04 sq.m. 2,083.33 10,500.00
b. Consumables (5% of Material Cost) 1,050.00

MATERIAL Sub-Total for E P 11,550.00


F. Direct Cost (C+E) 15,448.13
G. Overhead, Contingencies & Miscellaneous 5% 772.41
H. Contractor's Profit (CP) 10% 1,544.81
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 17,765.35
ADJUSTED CHECKING k. Total Unit Cost 3,524.87
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1010(2) WOODEN PANEL DOOR WITH HEAVY DUTY DOOR KNOB
UNIT Unit of Measurement: SQ.M.
Output per day: 2.88 SQ.M./DAY
QTY Quantity: 2.10 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.73 800.00 583.33
b. Skilled Laborer 1 0.73 600.00 437.50 3.047851265
c. Laborer 2 0.73 400.00 583.33

LABOR Sub-Total for A P 1,604.17

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 160.42

EQUIPMENT Sub-Total for B P 160.42


C. Total (A+B) 1,764.59
D. Output per day = 2.88 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Wooden PANEL Type Door with Jambs and Header 2.10 SQ.M. 2,857.14 6,000.00
b. Consumables (5% of Material Cost) 600.00

MATERIAL Sub-Total for E P 6,600.00


F. Direct Cost (C+E) 8,364.59
G. Overhead, Contingencies & Miscellaneous 5% 418.23
H. Contractor's Profit (CP) 10% 836.46
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 9,619.28
ADJUSTED CHECKING k. Total Unit Cost 4,580.61
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1043(1) PVC DOORS AND FRAMES W/ HEAVY DUTY DOOR KNOB
UNIT Unit of Measurement: SQ.M.
Output per day: 2.52 SQ.M./DAY
QTY Quantity: 1.26 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.50 800.00 400.00
b. Carpenter 1 0.50 600.00 300.00 3.047851265
c. Laborer 1 0.50 400.00 200.00

LABOR Sub-Total for A P 900.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a. Minor Tools (10% of labor Cost) 90.00

EQUIPMENT Sub-Total for B P 90.00


C. Total (A+B) 990.00
D. Output per day = 2.52 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a. Wooden PANEL Type Door with Jambs and Header 1.26 SQ.M. 1,984.13 2,500.00

b. Consumables (5% of Materials Cost) 125.00

MATERIAL Sub-Total for E P 2,625.00


F. Direct Cost (C+E) 3,615.00
G. Overhead, Contingencies & Miscellaneous 5% 180.75
H. Contractor's Profit (CP) 10% 361.50
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 4,157.25
ADJUSTED CHECKING k. Total Unit Cost 3,299.40
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1032(1)a PAINTING WORKS (MASONRY PAINTING)


UNIT Unit of Measurement: SQ.M.
Output per day: 16.80 SQ.M./DAY
QTY Quantity: 540.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 32.14 800.00 25,714.29
b. Painter 2 32.14 600.00 38,571.43
c. Laborer 1 32.14 400.00 12,857.14

LABOR Sub-Total for A P 77,142.86

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N/A

EQUIPMENT Sub-Total for B P


C. Total (A+B) 77,142.86
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Concrete Penetrating Sealer 16.88 gals. 590.00 9,956.25 4.00
b. Solvent Base Acrylic Primer 24.55 gals. 950.00 23,318.18
c. Patching Compound 54.00 kgs. 70.00 3,780.00 0.00 2.00 4.00
d. Semi Gloss Solvent Base Paint (Top Coat) 27.00 gals. 910.00 24,570.00
e. Baby Roller 16.20 pcs. 76.00 1,231.20
f. 2" Paint Brush 16.20 pcs. 65.00 1,053.00
g. 4" Paint Brush 16.20 pcs. 80.00 1,296.00
h. Body Filler 9.00 gal. 650.00 5,850.00
i Other Consumables 7,105.46

MATERIAL Sub-Total for E P 78,160.10


F. Direct Cost (C+E) 155,302.96
G. Overhead, Contingencies & Miscellaneous 5% 7,765.15
H. Contractor's Profit (CP) 10% 15,530.30
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 178,598.40
ADJUSTED CHECKING k. Total Unit Cost 330.74
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

Item No./Description: 1032(1)c PAINTING WORKS (METAL PAINTING)


Unit of Measurement: SQ.M.
Output per day: 16.00 SQ.M./DAY
Quantity: 45.00 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
a. Construction Foreman/Engineering Assistant 1 2.81 800.00 2,250.00
b. Painter 2 2.81 600.00 3,375.00
c. Laborer 1 2.81 400.00 1,125.00

Sub-Total for A P 6,750.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
N/A

Sub-Total for B P
C. Total (A+B) 6,750.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Red Oxide Metal Primer 1.80 gals. 550.00 990.00 4.00
b. Quick Dry Enamel Paint 4.50 gals. 670.00 3,015.00
c. Paint Thinner 33.75 gal. 469.00 15,828.75 0.00 2.00 4.00
d. Tinting Color 4.50 pints. 120.00 540.00
e. Consumables (5% of Material Cost) 2,037.38

Sub-Total for E P 22,411.13


F. Direct Cost (C+E) 29,161.13
G. Overhead, Contingencies & Miscellaneous 5% 1,458.06
H. Contractor's Profit (CP) 10% 2,916.11
I. Value Added Tax (VAT) 0% 0.00
J. Total Cost 33,535.30
k. Total Unit Cost 745.23
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: SPL - ? SUPPLY AND INSTALLATION OF ANALOK TYPE SLIDING WINDOW
UNIT Unit of Measurement: SQ.M.
Output per day: 12.00 SQ.M./DAY
QTY Quantity: 11.34 SQ.M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION Included in the Package

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Included in the Package

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 12.00 SQ.M./DAY

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
11.34 sq.m. 4,000.00 45,360.00
a. Aluminum Framing Analok Type -6mm. Thk. Glass

Note: With installation

MATERIAL Sub-Total for E P 45,360.00


F. Direct Cost (C+E) 45,360.00
G. Overhead, Contingencies & Miscellaneous 5% 2,268.00
H. Contractor's Profit (CP) 10% 4,536.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 52,164.00
ADJUSTED CHECKING k. Total Unit Cost 4,600.00
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: SPL - ? (INPUT ITEM DESCRIPTION)


UNIT Unit of Measurement: L.S.
Output per day:
QTY Quantity: 1.00 L.S.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a.
b.
c.

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
a.
b.
c.

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 0.00 0

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials
a.
b.
c.

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 0.00
ADJUSTED CHECKING k. Total Unit Cost 0.00
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1001(1)a 50MM DIA - 100MM DIA SANITARY PVC PIPE, SERIES 600/1000
UNIT Unit of Measurement: M.
Output per day: 24.00 M./DAY
QTY Quantity: 12.00 M.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.50 800.00 400.00
b. Skilled Laborer 1 0.50 600.00 300.00
c. Laborer 2 0.50 400.00 400.00
ABC

LABOR Sub-Total for A P 1,100.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 110.00

DESCRIPTION AREA
EXIST. EXTERIOR CONCRETE SURFACE 1st
EXIST. INTERIOR CONCRETE SURFACE 1st
EQUIPMENT Sub-Total for B P 110.00 EXIST. EXTERIOR CONCRETE SURFACE 2nd
C. Total (A+B) 1,210.00 EXIST. INTERIOR CONCRETE SURFACE 2nd
D. Output per day = EXIST. EXTERIOR CONCRETE SURFACE 3rd 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling
EXIST. INTERIOR CONCRETE SURFACE 3rd
Name and Specifications Quantity Unit Unit Cost Amount
PROP. CONCRETE SURFACE
E. Materials CEILING & INT. DRY WALL SURFACE 2.00
a. 100mm Sanitary PVC Pipe Series 600/1999 12.00 m. 150.00 1,800.00 METAL SURFACE #REF! 4.00
b. Consumables (5% of Material Cost) 180.00

Estimator shall include the bends/elbow in the material take-off

MATERIAL Sub-Total for E P 1,980.00


F. Direct Cost (C+E) 3,190.00
G. Overhead, Contingencies & Miscellaneous 5% 159.50
H. Contractor's Profit (CP) 10% 319.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 3,668.50
ADJUSTED CHECKING k. Total Unit Cost 305.71
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(6) WATERLINE PIPES & FITTINGS


UNIT Unit of Measurement: L.S.
Output per day:
QTY Quantity: 1.00 L.S.

Designation No. Person No. of Days Daily Rate Amount


NO .OF TEAM 1
A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 1.00 800.00 800.00
b. Skilled Laborer 1 1.00 600.00 600.00
c. Laborer 2 1.00 400.00 800.00
ABC

LABOR Sub-Total for A P 2,200.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 220.00

DESCRIPTION AREA
EXIST. EXTERIOR CONCRETE SURFACE 1st
EXIST. INTERIOR CONCRETE SURFACE 1st
EQUIPMENT Sub-Total for B P 220.00 EXIST. EXTERIOR CONCRETE SURFACE 2nd
C. Total (A+B) 2,420.00 EXIST. INTERIOR CONCRETE SURFACE 2nd
D. Output per day = EXIST. EXTERIOR CONCRETE SURFACE 3rd 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling
EXIST. INTERIOR CONCRETE SURFACE 3rd
Name and Specifications Quantity Unit Unit Cost Amount
PROP. CONCRETE SURFACE
E. Materials CEILING & INT. DRY WALL SURFACE 2.00
a. 12mm PPR Pipe 6 pc. 380.00 2,280.00 METAL SURFACE #REF! 4.00
b. 12mm PPR Fittins 1 lot 500.00 500.00

NOTE:

The estimator shall determine the needed materials and determine


the duration to complete this item.

MATERIAL Sub-Total for E P 2,780.00


F. Direct Cost (C+E) 5,200.00
G. Overhead, Contingencies & Miscellaneous 5% 260.00
H. Contractor's Profit (CP) 10% 520.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 5,980.00
ADJUSTED CHECKING k. Total Unit Cost 5,980.00
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) WATER CLOSET/ URINAL W/ COMPLETE ACCESSORIES
UNIT Unit of Measurement: SET
Output per day: 4.00 SET/DAY
QTY Quantity: 1.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.25 800.00 200.00
b. Skilled Laborer 1 0.25 600.00 150.00
c. Laborer 1 0.25 400.00 100.00

LABOR Sub-Total for A P 450.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 45.00

EQUIPMENT Sub-Total for B P 45.00


C. Total (A+B) 495.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Water Closet / Urinal w/ Complete Accessories 1.00 set 6,000.00 6,000.00 4.00
b. Consumables (5% of Material Cost) 600.00

MATERIAL Sub-Total for E P 6,600.00


F. Direct Cost (C+E) 7,095.00
G. Overhead, Contingencies & Miscellaneous 5% 354.75
H. Contractor's Profit (CP) 10% 709.50
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 8,159.25
ADJUSTED CHECKING k. Total Unit Cost 8,159.25
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) KITCHEN SINK/ SCRUB/ SLOP SINK W/ COMPLETE ACCESSORIES
UNIT Unit of Measurement: SET
Output per day: 4.00 SET/DAY
QTY Quantity: 1.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.25 800.00 200.00
b. Skilled Laborer 1 0.25 600.00 150.00
c. Laborer 1 0.25 400.00 100.00

LABOR Sub-Total for A P 450.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 45.00

EQUIPMENT Sub-Total for B P 45.00


C. Total (A+B) 495.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Kitchen Sink w/ Complete Accessories 1.00 set 4,500.00 4,500.00 4.00
b. Consumables (5% of Material Cost) 450.00

MATERIAL Sub-Total for E P 4,950.00


F. Direct Cost (C+E) 5,445.00
G. Overhead, Contingencies & Miscellaneous 5% 272.25
H. Contractor's Profit (CP) 10% 544.50
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 6,261.75
ADJUSTED CHECKING k. Total Unit Cost 6,261.75
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) WALL HANG/COUNTERTOP/ UNDER COUNTER LAVATORY W/ COMPLETE ACCESSORIES
UNIT Unit of Measurement: SET
Output per day: 4.00 SET/DAY
QTY Quantity: 1.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.25 800.00 200.00
b. Skilled Laborer 1 0.25 600.00 150.00
c. Laborer 1 0.25 400.00 100.00

LABOR Sub-Total for A P 450.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 45.00

EQUIPMENT Sub-Total for B P 45.00


C. Total (A+B) 495.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Lavatory/Sinks 1.00 set 3,500.00 3,500.00 4.00
b. Consumables (5% of Material Cost) 350.00

MATERIAL Sub-Total for E P 3,850.00


F. Direct Cost (C+E) 4,345.00
G. Overhead, Contingencies & Miscellaneous 5% 217.25
H. Contractor's Profit (CP) 10% 434.50
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 4,996.75
ADJUSTED CHECKING k. Total Unit Cost 4,996.75
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) FLOOR DRAIN PLATES (ANY SIZE)
UNIT Unit of Measurement: SET
Output per day: 20.00 SET/DAY
QTY Quantity: 2.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.10 800.00 80.00
b. Skilled Laborer 1 0.10 600.00 60.00
c. Laborer 1 0.10 400.00 40.00

LABOR Sub-Total for A P 180.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 18.00

EQUIPMENT Sub-Total for B P 18.00


C. Total (A+B) 198.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Floor Drain Plate 2.00 set 350.00 700.00 4.00
b. Consumables (5% of Material Cost) 70.00

MATERIAL Sub-Total for E P 770.00


F. Direct Cost (C+E) 968.00
G. Overhead, Contingencies & Miscellaneous 5% 48.40
H. Contractor's Profit (CP) 10% 96.80
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 1,113.20
ADJUSTED CHECKING k. Total Unit Cost 556.60
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) SOAP HOLDER /TOILET SOAP/LIQUID SOAP/TISSUE HOLDER
UNIT Unit of Measurement: SET
Output per day: 10.67 SET/DAY
QTY Quantity: 1.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.09 800.00 75.00
b. Skilled Laborer 1 0.09 600.00 56.25
c. Laborer 1 0.09 400.00 37.50

LABOR Sub-Total for A P 168.75

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 16.88

EQUIPMENT Sub-Total for B P 16.88


C. Total (A+B) 185.63
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Soap Holder & Tissue Holder 1.00 set 350.00 350.00 4.00
b. Consumables (5% of Material Cost) 35.00

MATERIAL Sub-Total for E P 385.00


F. Direct Cost (C+E) 570.63
G. Overhead, Contingencies & Miscellaneous 5% 28.53
H. Contractor's Profit (CP) 10% 57.06
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 656.22
ADJUSTED CHECKING k. Total Unit Cost 656.22
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) SHOWER HEAD /SHOWER VALVE


UNIT Unit of Measurement: SET
Output per day: 8.00 SET/DAY
QTY Quantity: 1.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.13 800.00 100.00
b. Skilled Laborer 1 0.13 600.00 75.00
c. Laborer 1 0.13 400.00 50.00

LABOR Sub-Total for A P 225.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 22.50

EQUIPMENT Sub-Total for B P


C. Total (A+B) 225.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Shower Head & Valve 1.00 set 2,600.00 2,600.00 4.00
b. Consumables (5% of Material Cost) 260.00

MATERIAL Sub-Total for E P 2,860.00


F. Direct Cost (C+E) 3,085.00
G. Overhead, Contingencies & Miscellaneous 5% 154.25
H. Contractor's Profit (CP) 10% 308.50
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 3,547.75
ADJUSTED CHECKING k. Total Unit Cost 3,547.75
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5)p FACIAL MIRROR


UNIT Unit of Measurement: SQ.M.
Output per day: 3.20 SQ.M./DAY
QTY Quantity: 0.50 SQ.M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.16 800.00 125.00
b. Skilled Laborer 1 0.16 600.00 93.75
c. Laborer 1 0.16 400.00 62.50

LABOR Sub-Total for A P 281.25

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 28.13

EQUIPMENT Sub-Total for B P 28.13


C. Total (A+B) 309.38
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Facial Mirror 0.50 sq.m. 900.00 450.00 4.00
b. Consumables (5% of Material Cost) 45.00

MATERIAL Sub-Total for E P 495.00


F. Direct Cost (C+E) 804.38
G. Overhead, Contingencies & Miscellaneous 5% 40.22
H. Contractor's Profit (CP) 10% 80.44
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 925.03
ADJUSTED CHECKING k. Total Unit Cost 1,850.06
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: SPL- ? (INPUT OTHER PLUMBING WORK ITEM THAT IS NOT FOUND IN THIS SPREADSHEET)
UNIT Unit of Measurement: L.S.
Output per day:
QTY Quantity: 1.00 L.S.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 800.00 0.00
b. Skilled Laborer 600.00 0.00
c. Laborer 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 0.00

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. 4.00
b.

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 0.00
ADJUSTED CHECKING k. Total Unit Cost 0.00
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1002(5) 15MM-25MM DIA. FLEXIBLE CONDUIT


UNIT Unit of Measurement: M.
Output per day: 28.27 M./DAY
QTY Quantity: 200.00 M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 7.07 800.00 5,659.31
b. Skilled Laborer 1 7.07 600.00 4,244.48
c. Laborer 1 7.07 400.00 2,829.65

LABOR Sub-Total for A P 12,733.45

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 1,273.35

EQUIPMENT Sub-Total for B P 1,273.35


C. Total (A+B) 14,006.80
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Flexible/ Rigid Conduit 200.00 m. 15.00 3,000.00 4.00
b. Consumables (5% of Material Cost) 300.00

Estimator shall Include fittings in the material take-off.

MATERIAL Sub-Total for E P 3,300.00


F. Direct Cost (C+E) 17,306.80
G. Overhead, Contingencies & Miscellaneous 5% 865.34
H. Contractor's Profit (CP) 10% 1,730.68
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 19,902.81
ADJUSTED CHECKING k. Total Unit Cost 99.51
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1100 JUNCTION UTILITY/PULL / SQUARE BOX


UNIT Unit of Measurement: PC.
Output per day: 20.00 PC./DAY
QTY Quantity: 33.00 PC.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 1.65 800.00 1,320.00
b. Skilled Laborer 1 1.65 600.00 990.00
c. Laborer 1 1.65 400.00 660.00

LABOR Sub-Total for A P 2,970.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 297.00

EQUIPMENT Sub-Total for B P 297.00


C. Total (A+B) 3,267.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Junction/ Utility/ Pull/ Square Box 33.00 pc. 45.00 1,485.00 4.00
b. Consumables (5% of Material Cost) 148.50

MATERIAL Sub-Total for E P 1,633.50


F. Direct Cost (C+E) 4,900.50
G. Overhead, Contingencies & Miscellaneous 5% 245.03
H. Contractor's Profit (CP) 10% 490.05
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 5,635.58
ADJUSTED CHECKING k. Total Unit Cost 170.78
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1101(2) 1.6MM 2 - 5.5MM 2 ELECTRIC WIRE (TW/THHN/TWHN 2)
UNIT Unit of Measurement: M.
Output per day: 200.00 M./DAY
QTY Quantity: 600.00 M.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 3.00 800.00 2,400.00
b. Skilled Laborer 1 3.00 600.00 1,800.00
c. Laborer 1 3.00 400.00 1,200.00

LABOR Sub-Total for A P 5,400.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 540.00

EQUIPMENT Sub-Total for B P 540.00


C. Total (A+B) 5,940.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. 1.6mm2 - 5.5mm2 Electric Wire (TW/THHN/TWHN2) 600.00 m. 29.00 17,400.00 4.00
b. Consumables (5% of Material Cost) 1,740.00

The estimator shall breakdown the electrical wire requirements

MATERIAL Sub-Total for E P 19,140.00


F. Direct Cost (C+E) 25,080.00
G. Overhead, Contingencies & Miscellaneous 5% 1,254.00
H. Contractor's Profit (CP) 10% 2,508.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 28,842.00
ADJUSTED CHECKING k. Total Unit Cost 48.07
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1101 SINGLE CONVINENCE OUTLET/ RECEPTACLE, GROUNDING TYPE/HEAVY DUTY
UNIT Unit of Measurement: SET CONVENIENCE OUTLET
Output per day: 32.00 SET/DAY
QTY Quantity: 13.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.41 800.00 325.00
b. Skilled Laborer 1 0.41 600.00 243.75
c. Laborer 1 0.41 400.00 162.50

LABOR Sub-Total for A P 731.25

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 731.25
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Single Convenience Outlet/ or Equivalent 13.00 set 180.00 2,340.00 4.00
234.00

MATERIAL Sub-Total for E P 2,574.00


F. Direct Cost (C+E) 3,305.25
G. Overhead, Contingencies & Miscellaneous 5% 165.26
H. Contractor's Profit (CP) 10% 330.53
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 3,801.04
ADJUSTED CHECKING k. Total Unit Cost 292.39
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1101 DUPLEX CONVINENCE OUTLET/ RECEPTACLE, GROUNDING TYPE/HEAVY DUTY
UNIT Unit of Measurement: SET CONVENIENCE OUTLET
Output per day: 26.67 SET/DAY
QTY Quantity: 10.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.38 800.00 300.00
b. Skilled Laborer 1 0.38 600.00 225.00
c. Laborer 1 0.38 400.00 150.00

LABOR Sub-Total for A P 675.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 675.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Duplex Convenience Outlet/ or Equivalent 10.00 set 230.00 2,300.00 4.00
230.00

MATERIAL Sub-Total for E P 2,530.00


F. Direct Cost (C+E) 3,205.00
G. Overhead, Contingencies & Miscellaneous 5% 160.25
H. Contractor's Profit (CP) 10% 320.50
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 3,685.75
ADJUSTED CHECKING k. Total Unit Cost 368.58
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1102 PANEL BOARD WITH MAIN BREAKER/BRANCHES, 3 WIRES, 1 NEUTRAL, 50AMP-200AMP
UNIT Unit of Measurement: SET
Output per day: 1.45 SET/DAY
QTY Quantity: 1.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 0.69 800.00 550.00
b. Skilled Laborer 1 0.69 600.00 412.50
c. Laborer 2 0.69 400.00 550.00

LABOR Sub-Total for A P 1,512.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 1,512.50
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Panel Board with Main Breaker and 8-Branches 1.00 set 4,000.00 4,000.00 4.00
b. Consumables (5% of Material Cost) 400.00
Include the Circuits Breaker needed:
c. ?? Amp Circuit Breaker 1.00 set 450.00 450.00
d. ?? Amp Circuit Breaker 2.00 set 451.00 902.00
e. ?? Amp Circuit Breaker 2.00 set 452.00 904.00

MATERIAL Sub-Total for E P 6,656.00


F. Direct Cost (C+E) 8,168.50
G. Overhead, Contingencies & Miscellaneous 5% 408.43
H. Contractor's Profit (CP) 10% 816.85
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 9,393.78
ADJUSTED CHECKING k. Total Unit Cost 9,393.78
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: 1103(2) FLOURESCENT LIGHTING FIXTURE WITH BALLAST/ LIGHT EMITTING DIODE (LED) BULB, 1
UNIT Unit of Measurement: SET BULB
Output per day: 8.00 SET/DAY
QTY Quantity: 40.00 SET

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 5.00 800.00 4,000.00
b. Skilled Laborer 1 5.00 600.00 3,000.00
c. Laborer 1 5.00 400.00 2,000.00

LABOR Sub-Total for A P 9,000.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 900.00

EQUIPMENT Sub-Total for B P 900.00


C. Total (A+B) 9,900.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. Lighting Fixture e.i. 20watts LED Surface Mounted 40.00 set 180.00 7,200.00 4.00
720.00

MATERIAL Sub-Total for E P 7,920.00


F. Direct Cost (C+E) 17,820.00
G. Overhead, Contingencies & Miscellaneous 5% 891.00
H. Contractor's Profit (CP) 10% 1,782.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 20,493.00
ADJUSTED CHECKING k. Total Unit Cost 512.33
DETAILED UNIT PRICE ANALYSIS

PROJECT NAME: PROPOSED ONE STOREY TWO BED ROOM RESIDENTIAL BUILDING

ITEM NO. Item No./Description: SPL- ? (INPUT OTHER ELECTRICAL WORK ITEM THAT IS NOT FOUND IN THIS SPREADSHEET)
UNIT Unit of Measurement: L.S.
Output per day:
QTY Quantity: 1.00 L.S.

Designation No. Person No. of Days Daily Rate Amount

A. Labor
DURATION a. Construction Foreman/Engineering Assistant 1 800.00 0.00
b. Skilled Laborer 1 600.00 0.00
c. Laborer 1 400.00 0.00

LABOR Sub-Total for A P 0.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment
Minor Tools (10% of labor Cost) 0.00

EQUIPMENT Sub-Total for B P 0.00


C. Total (A+B) 0.00
D. Output per day = 2Ø 45° bend 2Øx2Ø tee 4Øx4Ø coupling

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials 2.00
a. 4.00

MATERIAL Sub-Total for E P 0.00


F. Direct Cost (C+E) 0.00
G. Overhead, Contingencies & Miscellaneous 5% 0.00
H. Contractor's Profit (CP) 10% 0.00
I. Value Added Tax (VAT) 0% 0.00
CHECKING J. Total Cost 0.00
ADJUSTED CHECKING k. Total Unit Cost 0.00

You might also like