You are on page 1of 25

TESTING AND COMMISSIONING PROCEDURE

FOR

CATERING EQUIPMENT INSTALLATION

IN

GOVERNMENT BUILDINGS

OF

THE HONG KONG SPECIAL ADMINISTRATIVE REGION

2022 EDITION

ARCHITECTURAL SERVICES DEPARTMENT


THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION
PREFACE

This Testing and Commissioning (T&C) Procedure aims to lay down the minimum testing and
commissioning requirements to be carried out on Catering Equipment Installation in Government
Buildings of the Hong Kong Special Administrative Region (HKSAR). Such requirements are applicable
to both new installations upon completion and existing ones after major alteration.

The present edition was developed from the General Specification for Building Services
Installation in Government Buildings of the Hong Kong Special Administrative Region 2022 Edition
that was established by the Architectural Services Department (ArchSD).

Electronic version of this T&C Procedure is to be viewed on and free for download from the
ArchSD Internet homepage. As part of the Government’s efforts to limit paper consumption, hard copies
will not be put up for sale.

The ArchSD welcomes comments on this T&C Procedure at any time since the updating of this
T&C Procedure is a continuous process to tie in with technological advances.
DISCLAIMER

This T&C Procedure is solely compiled for Catering Equipment Installation carried out for or on
behalf of the ArchSD in Government premises of the HKSAR.

There are no representations, either expressed or implied, as to the suitability of this T&C
Procedure for purposes other than that stated above. Users who choose to adopt this T&C Procedure for
their works are responsible for making their own assessments and judgement of all information contained
here. The ArchSD does not accept any liability and responsibility for any special, indirect or
consequential loss or damages whatsoever arising out of or in connection with the use of this T&C
Procedure or reliance placed on it.

The materials contained in this document may not be pertinent or fully cover the extent of the
installation in non-government buildings and there is no intimated or implied endorsement of the sales,
supply and installation of the materials and equipment specified in this T&C Procedure within the
territory of the HKSAR.
TABLE OF CONTENTS
Page

1. Introduction 1

2. Objectives of the Testing and Commissioning Works 1

3. Scope of the Testing and Commissioning Works 2

3.1 Tests and Inspections during Construction


3.2 Functional Performance Tests
3.3 Commissioning, Statutory Tests and Inspections
3.4 Documentation and Deliverables
3.5 Other Requirements

4. Testing and Commissioning Procedures 4

4.1 Water System Tests


4.2 Electrical Tests

Annex

Annex I Testing and Commissioning Progress Chart for Catering Equipment Installation

Annex II Testing and Commissioning Certificate for Catering Equipment Installation

Annex III List of Calibrated Equipment/Instruments Necessary for the Testing and
Commissioning Works

Table of Contents T&C Procedure for Catering Equipment Installation


Page 1 of 1 2022 Edition
(TCP-KE-2022)
Testing and Commissioning Procedure for
Catering Equipment Installation

1. Introduction

The procedures stated in this Testing and Commissioning (T&C) Procedure cover the activities
in preliminary tests and inspections, functional performance tests and the commissioning of
newly completed Installations and existing ones after major alteration. They are so compiled to
facilitate the work of Project Building Services Engineer (PBSE) and Project Building Services
Inspector (PBSI) / Project Electrical and Mechanical Inspector (PEMI), who are appointed as
the Supervising Officer’s Representatives, in the following aspects with respect to testing and
commissioning :

(a) to vet and approve the T&C procedures proposed and submitted by the contractor for
the Catering Equipment Installation (Contractor);

(b) to witness those T&C procedures as specified; and

(c) to accept the T&C certificates and other supporting data.

T&C works shall be carried out as detailed in this T&C Procedure. Supplementary T&C plans
may be proposed as appropriate and agreed by PBSE.

The administrative requirements for T&C works are in general as specified in the General
Specification for Building Services Installation 2022 Edition and all current
corrigenda/amendments thereto published before the date of first tender invitation for the Contract
issued by the ArchSD (the General Specification).

All words and expressions shall have the meaning as assigned to them under the General
Specification unless otherwise specified herein.

2. Objectives of the Testing and Commissioning Works

The objectives of the T&C works are:

(a) to verify proper functioning of the equipment/system after installation;

(b) to verify that the performance of the installed equipment/systems meet with the
specified design intent and statutory requirements, if any, through a series of tests and
adjustments; and

(c) to capture and record performance data of the whole Installation as the baseline for
future operation and maintenance.

For the avoidance of doubt, depending on the specific demands of individual installation, the
PBSE may require additional or substitute T&C works in regard to any elements in the
Installation other than those indicated in this T&C Procedure.

Page 1 of 4 T&C Procedure for Catering Equipment Installation


2022 Edition
(TCP-KE-2022)
3. Scope of the Testing and Commissioning Works

3.1 Tests and Inspections during Construction

The purpose of these tests is to ensure that all components and systems are in a satisfactory and
safe condition before start up. Preliminary adjustment and setting of equipment at this stage
shall also be carried out at the same time to pave way for the coming functional performance
tests.

Before carrying out any test, it shall ensure that the Installations comply with all relevant statutory
requirements and regulations. The T&C works shall also comply with all site safety regulatory
requirements currently in force. In particular, the Contractor shall note the statutory requirements
listed in the General Specification in carrying out the works.

3.2 Functional Performance Tests

The purpose of functional performance tests is to demonstrate that the Installations can meet the
functional and performance requirements as specified in the Contract. Functional performance
tests should proceed from the testing of individual components to the testing of different systems
in the Installations.

Temporary modifications may be made as the tests proceed. The specific tests required and the
order of tests will vary depending on the type and size of systems, number of systems, sequence of
construction, interface with other installations, relationship with the building elements and other
specific requirements as indicated in the Contract. The testing of systems may have to be carried
out in stages depending on the progress of work or as proposed.

Part of the tests may be required to be carried out in suppliers’ premises in accordance with the
provisions as specified in the Contract.

Any performance deficiencies revealed during the functional performance tests must be evaluated
to determine the cause. After completion of the necessary corrective measures, the tests shall be
repeated as appropriate.

If any test cannot be completed because of circumstances that are beyond the control, it shall be
properly documented and reported to the PBSE, who shall then liaise with the relevant parties to
resolve the situation. The testing shall be resumed immediately upon the attainment of a suitable
testing environment.

3.3 Commissioning, Statutory Tests and Inspections

Commissioning is the advancement of the Installations from the stage of static completion to full
working conditions and to meet the performance requirements as specified in the Contract. This
will include setting into operation and regulation of the Installations. Fine-tuning of the
commissioned system shall be carried out to match system performance to the actual needs of the
building occupier more closely.

Page 2 of 4 T&C Procedure for Catering Equipment Installation


2022 Edition
(TCP-KE-2022)
Tests to meet statutory requirements shall be carried out. After the proper testing and
commissioning of the Installations, the relevant authorities shall be notified through the PBSE on
the completion of the Installations and its readiness for statutory inspection and testing. Necessary
inspections and tests as required by the Authorities shall be arranged.

3.4 Documentation and Deliverables

Proposed T&C procedures together with the Testing and Commissioning Progress Chart shown in
Annex I shall be submitted to PBSE for approval.

All inspection and T&C results shall be recorded in the appropriate test record forms. A complete
set of these forms can be found in Annex II.

Data recorded in other formats may also be accepted subject to prior approval of the PBSE. Upon
completion of all the required T&C works, a testing and commissioning certificate shown in Annex
II shall be completed and signed to ensure that the agreed T&C works have been duly carried out.

A functional performance test report covering all measured data, data sheets, and a
comprehensive summary describing the operation of the system at the time of the functional
performance tests shall be prepared and submitted to the PBSE. Deviations in performance as
specified in the Contract or the design intent should be recorded, with a description and analysis
included.

A final performance evaluation of the Installations, where required in the Contract, shall be
included in the commissioning report.

3.5 Other Requirements

3.5.1 Testing Equipment Calibration

A list of calibrated equipment/instruments necessary for the T&C Works shall be


provided as specified in Annex III.

3.5.2 Certificates for Appliances

A certificate of test issued by a competent person shall be provided for each pressure
type boiler, steam generator and vessels incorporated in an appliance which operates
above atmospheric pressure, in accordance with the Boilers and Pressure Vessels
Ordinance, (Cap. 56), Laws of the Hong Kong Special Administrative Region.

When it is so required by the Gas Authority, the Contractor shall provide certificate
for gas appliances.

Page 3 of 4 T&C Procedure for Catering Equipment Installation


2022 Edition
(TCP-KE-2022)
4. Testing and Commissioning Procedures

4.1 Water System Tests

Water systems and circuits shall be tested hydraulically to 1.5 times the working pressure applied at the
highest point of the system and held for a period of not less than 1 hour without leaks appearing. (Allow
15 minutes to settle)

All pipework shall be thoroughly cleaned and flushed before test. The Contractor shall ascertain that
there is adequate drainage nearby to discharge by large hose in order to ensure flooding of low level
areas will not occur. Where necessary, the Contractor shall provide chemical cleaning to the pipes. After
flushing out the pipework, a flow test shall be performed on the water supply system in accordance to
the appropriate authorities’ requirements, e.g. Water Supplies Department.

The Contractor shall provide whatever hoses or drainage channels required to safely remove the test
water discharged while carrying out these tests in order to ensure that no damage to the building and
property caused by the test water.

The Contractor shall submit hydraulic test certificates/reports that shall be signed by the
Contractor’s authorised representative and by the Supervising Officer’s Representative who has
witnessed the test.

The test certificates/reports shall contain the following particulars:-

(a) Date of test


(b) Apparatus or section under test
(c) Make number (if any)
(d) Nature, duration and conditions of test
(e) Result of test
(f) Name of KE Contractor’s Representative in charge of test
(g) Name of Supervising Officer’s Representative at witness the test

4. Electrical Tests

Electrical wiring systems shall be tested generally as required by the General Specification. Low voltage
wiring shall be insulation tested to a DC voltage of twice the normal working voltage of the system. Any
tests that are liable to cause damage to the delicate components such as those incorporating electronic
circuits shall be carried out with the components disconnected.

Page 4 of 4 T&C Procedure for Catering Equipment Installation


2022 Edition
(TCP-KE-2022)
Annex I
Testing and Commissioning Progress Chart for
Catering Equipment Installation
Contract Number :
Contract Title :
Name of Sub-contractor :
Name of Main Contractor :
Contract Period: __/__/20__ to __/__/20__ *Revised /Actual Completion Date: __/__/20__
dd/mm/yyyy dd/mm/yyyy

Testing and Commissioning Progress Chart for Catering Equipment Installation (Rev. )
(Note 1)

Dates Remark
(Note 2)

Activities Reference to S A S A S A S A S A S A S A S A S A
Part 3 of T&C
Certificate
(Annex II)
1. Water Piping 3.1 / 3.2.2
System
Visual inspection
G/F
1/F
2/F
Submission test record

2. Gas Piping 3.1 / 3.2.2


System
Visual inspection
G/F
1/F
2/F
Submission test record

3. Electrical 3.2.1A & B /


Equipment 3.2.2
Visual inspection
G/F
1/F
2/F
Submission test record

Annex I T&C Procedure for Catering Equipment Installation


Page 1 of 3 2022 Edition
(TCP-KE-2022)
Testing and Commissioning Progress Chart for Catering Equipment Installation (Rev. )
(Note 1)

Dates Remark
(Note 2)

Activities Reference to S A S A S A S A S A S A S A S A S A
Part 3 of T&C
Certificate
(Annex II)
4. Gas Equipment 3.2.1 A, C
& F / 3.2.2
Visual inspection
G/F
1/F
2/F
Submission test record

5. Non-pressure / 3.2.1 A, D
Pressure Type & E / 3.2.2
Water Heater
Visual inspection
G/F
1/F
2/F
Submission test record

6. Steam 3.2.1 A & G


Equipment / 3.2.2
Visual inspection
G/F
1/F
2/F
Submission test record

7. Other Catering 3.2.1 A & H


Equipment / / 3.2.2
Appliances
Visual inspection
G/F
1/F
2/F
Submission test record

Annex I T&C Procedure for Catering Equipment Installation


Page 2 of 3 2022 Edition
(TCP-KE-2022)
Testing and Commissioning Progress Chart for Catering Equipment Installation (Rev. )
(Note 1)

Dates Remark
(Note 2)

Activities Reference to S A S A S A S A S A S A S A S A S A
Part 3 of T&C
Certificate
(Annex II)
8. Fixtures / 3.2.1 I /3.2.2
Furniture in
Kitchen
Visual inspection
G/F
1/F
2/F
Submission test record

9. Submission of
T&C Certificate

Notes
* Delete as appropriate
(1) Insert revision no.
(2) Insert additional columns as necessary
S - schedule % completion
A - actual % completion

Annex I T&C Procedure for Catering Equipment Installation


Page 3 of 3 2022 Edition
(TCP-KE-2022)
Annex II
Testing and Commissioning Certificate for
Catering Equipment Installation

Contract Number :
Contract Title :

Part 1 Details of Project

1.1 Project title :


1.2 P.W.P. No. :
1.3 Contract Number :
1.4 Sub-contractor :
1.5 Main Contractor :
1.6 Name of *PBSE :
1.7 Name of *PBSI :

Part 2 Declaration

2.1 I certify that the Catering Equipment Installation as specified in the Contract/Sub-
contract/Quotation at the above location has been inspected, tested and
commissioned in accordance with this Testing and Commissioning (T&C) Procedure
and/or any other procedures as agreed between the *PBSE and the Contractor. The
results are satisfactory in the aspects as mentioned in Part 3 and/or as recorded in
Part 4 of this Certificate, except that indicated in the COMMENTS items.

2.2 I also certify that site tests have been performed in accordance with the requirements
set in this T&C Procedure and that the results are satisfactory. A record of the tests
has been prepared and submitted to the *PBSE.

Name of Authorised Contractor’s Representative: Signature:

Designation /Post of Contractor’s Representative: Date Signed:

Name and Stamp of Contractor: Telephone Number:

* delete /amend if required

Annex II T&C Procedure for Catering Equipment Installation


Page 1 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
Part 3 : Items Inspected and Tested

3.1 Inspection, Testing and Commissioning of Piping System

3.1.1 Visual Inspection

(A) Steel and Copper Pipework

1. Are all pipelines of the correct types and approved by the *Yes/No *Yes/No
Supervising Officer?

2. Are all pipelines up to 13 mm bore of steel or copper *Yes/No *Yes/No


made?

3. Are all pipelines above 13 mm bore of steel made? *Yes/No *Yes/No

(B) Flexible Hoses and Tubing

1. Are all flexible hoses and tubing of correct types and *Yes/No *Yes/No
approved by the Supervising Officer?

2. Are corrosion resistant braiding for flexible hoses and *Yes/No/N.A. *Yes/No/N.A.
tubing used?

3. Are manual shut-off valves installed for vapour pipelines *Yes/No *Yes/No
at intermediate pressure or below to which the flexible
hoses are connected?

4. Is all flexible tubing within 2 m long? *Yes/No *Yes/No

5. Is any flexible tubing extended from one room to another *Yes/No *Yes/No
or passing through wall or ceiling?

6. Are all end fittings of the flexible hoses and tubing of *Yes/No *Yes/No
correct and approved type?

7. Are fittings for securing flexible hoses and tubing free *Yes/No *Yes/No
from burrs/sharp edges and not over-tightened?

(C) Pipe Joints and Fittings

1. Are all steel pipe joints over 50 mm bore welded or *Yes/No *Yes/No
welded flanged?

2. Is only electric arc welding used on steel pipes of 125 mm *Yes/No/N.A. *Yes/No/N.A.
bore and larger?

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 2 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor

3. Are copper pipe joints of compression type or sweated *Yes/No *Yes/No


type silver soldered or brazed using jointing material of
melting point exceeding 540°C?

4. Are soldering material free from lead with certificate and *Yes/No *Yes/No
approval from Supervising Officer?

5. Are pipe fittings of the correct and approved types? *Yes/No *Yes/No

6. Are gaskets used appropriate to the type of gas? *Yes/No *Yes/No

(D) Piping Installation

1. Are pipework installed in accordance with the approved *Yes/No *Yes/No


drawings?

2. Are all pipework buried in floor slabs protected against *Yes/No *Yes/No
corrosion and mechanical damage?

3. Are surface pipework adequately supported and are the *Yes/No/N.A. *Yes/No/N.A.
supports made of correct materials and correctly
constructed?

4. Are the pipe runs having adequate flexibility and facilities *Yes/No/N.A. *Yes/No/N.A.
to compensate for thermal expansion and contraction of
pipes, or mechanical stress at branch pipes?

5. Are all pipework protected against corrosion by wrapping, *Yes/No *Yes/No


galvanising or painting as appropriate?

6. Are pipework passing through walls or floor slabs *Yes/No *Yes/No


properly wrapped and enclosed in metal sleeves and
without joints?

7. Is a minimum clearance of 60 mm maintained between *Yes/No *Yes/No


gas pipes and electric conduits, trunking and cables?

8. Have identification labels been provided for all surface *Yes/No *Yes/No
distribution pipes?

(E) Valves and Accessories

1. Are all valves of correct and approved types? *Yes/No *Yes/No

2. Are all valves accessible and with clear indication of *Yes/No *Yes/No

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 3 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
direction of operation?

3.1.2 Testing and Commissioning

(A) Pipework

1. All pipework have been pressure and leak tested, by *Yes/No *Yes/No
means of *pressure drop hydraulic method/soap and water
pneumatic method, before and after applying corrosion
treatment, concealed or buried.

2. Before pressure testing, the units which are not capable of *Yes/No *Yes/No
accepting the test pressures have been isolated.

3. Pressures used for the testing were as follows: -

Working : *Yes/No *Yes/No

Testing : *Yes/No *Yes/No

4. Are all pipework and metal works properly painted in *Yes/No *Yes/No
accordance with the specification?

5. Are proper identifications provided for water /steam *Yes/No *Yes/No


/refrigeration /fuel oil /fuel gas pipework, wirings and
equipment?

6. Are results of pressure test on water / steam / refrigeration *Yes/No *Yes/No


/ fuel oil / fuel gas pipework satisfactory?

7. Are lead-free test for soldering material and joints *Yes/No *Yes/No
satisfactory?

(B) Valves and Accessories

1. During the pressure testing, have all isolating valves and *Yes/No *Yes/No
quick-acting shut-off valves been checked and no leakage
at fully closed positions?

2. Are all pressure gauges working properly and reading *Yes/No *Yes/No
correct figures?

(C) Cables, Wiring and Other Interconnections

1. Are insulation test of all cables and wiring tested with all *Yes/No *Yes/No

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 4 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
insulation resistance ≧ 1.0 MΩ?

2. Is the completed circuit tested as recommended by the *Yes/No *Yes/No


equipment manufacturer?

3. Is earth continuity and earth-loop impedance tested with *Yes/No *Yes/No


results in compliance with the Code?

3.1.3 Miscellaneous and Document

(A) Miscellaneous

1. Are water tanks clear of debris? *Yes/No *Yes/No

2. Is permanent electricity supply connected? *Yes/No *Yes/No

3. Is permanent electricity supply connected? *Yes/No *Yes/No

4. Is emergency electricity supply available? *Yes/No/N.A. *Yes/No/N.A.

(B) As-fitted Catering Equipment installation drawings


including the followings are provided: -

1. Schematic control diagrams showing the types, size and *Yes/No *Yes/No
connection of all cables and wiring for safety / protection
devices.

2. Floor layout plans showing the location of quick isolating *Yes/No *Yes/No
valves / switches for emergency operation.

(C) Approval/Acceptance letters from various Authorities for


the following equipment are provided: -

1. WSD Ref. : *Yes/No *Yes/No

2. FSD Ref. : *Yes/No *Yes/No

3. GasSO Ref : *Yes/No *Yes/No

3.1 Inspection, Testing and Commissioning of Catering Equipment

3.2.1 Visual Inspection

(A) General

1. Are all equipment/appliances of correct and approved *Yes/No *Yes/No

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 5 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
models and with Grade 1 energy label when these
appliances (e.g. water heater, cooker, electrical appliances
and domestic gas appliances) are covered under the EEO
MEEL or VEEL schemes?

2. Are all equipment / appliances installed properly in *Yes/No *Yes/No


accordance with manufacturer’s instructions?

3. Are adequate access panels provided for equipment *Yes/No *Yes/No


operation/maintenance?

4. Are adequate spaces adjoining the equipment allowed to *Yes/No *Yes/No


facilitate cleansing?

5. Is manual isolating valve, switch or control provided for *Yes/No *Yes/No


each equipment / appliances for the steam, gas, water or
electricity supply?

6. Is the manual isolating valve located at a readily *Yes/No *Yes/No


accessible position?

7. Are the materials for the equipment / appliances were *Yes/No *Yes/No
constructed in accordance with the Contract?

8. Are the thickness of the stainless steel sheet in accordance *Yes/No/N.A. *Yes/No/N.A.
with the Contract?

9. Is welding of stainless steel carried out in accordance with *Yes/No/N.A. *Yes/No/N.A.


the Contract and completed with a high quality finish?

10. Is the welding material free of lead? *Yes/No/N.A. *Yes/No/N.A

11. Is the surface of the appliance/equipment in touch of *Yes/No/N.A. *Yes/No/N.A.


drinking water or food free from lead?

12. Are all metal casings of the equipment / appliances *Yes/No *Yes/No
provided with continuous equipotential bonding and
connected to the main isolating switch?

13. Are all floor mounting equipment provided with *Yes/No/N.A. *Yes/No/N.A.
adjustable legs?

14. Is drain of equipment properly connected to drain water *Yes/No/N.A *Yes/No/N.A


channel or drain point?

15. All mechanical moving parts and cutting surfaces shall be *Yes/No/N.A *Yes/No/N.A

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 6 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
adequately protected with guards.

(B) Electrical Equipment / Appliances

1. Are the electrical equipment / appliances suitable for 380 *Yes/No/N.A. *Yes/No/N.A.
V 3 phase 50 Hz or 220 V 1 phase 50 Hz?

2. Are the electrical equipment / appliances provided with *Yes/No/N.A. *Yes/No/N.A.


isolating switch?

3. Are the electrical equipment / appliances provided with *Yes/No/N.A. *Yes/No/N.A.


sufficient length of flexible cable with plug as specified?

4. Are the rating of the equipment / appliances matched that *Yes/No/N.A. *Yes/No/N.A.
of the power supply switch or socket?

5. Are all exposed conductive parts of the equipment / *Yes/No/N.A. *Yes/No/N.A.


appliances (other than live parts) effectively connected to
the consumer’s earth terminal via the circuit protective
conductors of the final circuits, or taken effective
precautions such as the use of double insulated equipment
or the use of isolating transformer to prevent danger?

6. Is the electric motors protected by the appropriate motor *Yes/No/N.A. *Yes/No/N.A.


protection?

7. Snap-on type connectors should not be used to connect *Yes/No/N.A. *Yes/No/N.A.


conductor that are associated with bonding and earthing of
an appliance?

8. Is all wiring properly protected in enclosures? *Yes/No/N.A. *Yes/No/N.A.

9. Is overheat safety cutout provided? *Yes/No/N.A. *Yes/No/N.A.

(C) Gas Equipment/Appliances

1. Are flues readily accessible for inspection and suitable for *Yes/No/N.A. *Yes/No/N.A.
future maintenance?

2. Are flues properly installed where they pass through roof, *Yes/No/N.A. *Yes/No/N.A.
ceiling and seal with non-combustible materials?

3. For flues incorporating forced draught devices and *Yes/No/N.A. *Yes/No/N.A.


automatically operated damper devices: Are these devices
interlocked with the gas supply to burners?

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 7 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
4. Are manual operated dampers incorporated in flue *Yes/No/N.A. *Yes/No/N.A.
systems and maintained in fixed open position?

5. Is flue discharge to exhaust hood provided with fume *Yes/No/N.A. *Yes/No/N.A.


diverter?

6. Are flame failure devices of approved type provided for *Yes/No/N.A. *Yes/No/N.A.
totally enclosed and semi-enclosed burner?

7. Are the flame failure devices protected against draught *Yes/No/N.A. *Yes/No/N.A.
and sheltered from over-spilling and over-heating?

8. Is the manual on/off switch and automatic safety cut-out *Yes/No/N.A. *Yes/No/N.A.
device (if fitted) of a main burner also controlling its
associate pilot burner?

(D) Non-pressure Type Water Heating Appliances

1. Is vent to atmosphere provided? *Yes/No/N.A. *Yes/No/N.A.

2. Are low level water protective and safety devices tested to *Yes/No/N.A. *Yes/No/N.A.
the manufacturer’s recommendation?

3. Are the accuracies of all meters and gauges tested to its *Yes/No/N.A. *Yes/No/N.A.
proper operating ranges?

(E) Pressure Type Water Heating Appliances

1. Is pressure safety valve provided? *Yes/No/N.A. *Yes/No/N.A.

2. uum (pressure/vacuum) release valve provided? *Yes/No/N.A. *Yes/No/N.A.

3. Is pressure gauge provided and tested to its accuracies / *Yes/No/N.A. *Yes/No/N.A.


proper operating ranges?

4. Is low water level cut out provided? *Yes/No/N.A. *Yes/No/N.A.

5. Is water level gauge(s) provided (except boiling pan)? *Yes/No/N.A. *Yes/No/N.A.

(F) Fryer

1. Is high temperature cut-out provided? *Yes/No/N.A. *Yes/No/N.A.

2. Is cut-out device provided when tilting pan displaced? *Yes/No/N.A. *Yes/No/N.A.

3. Is permanent maximum oil level marker provided? *Yes/No/N.A *Yes/No/N.A

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 8 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor

(G) Steam Equipment

1. Is working pressure of the equipment suitable for the *Yes/No/N.A. *Yes/No/N.A.


supply pressure?

2. Are the pressure reducing valves provided for lower *Yes/No/N.A. *Yes/No/N.A.
pressure equipment and accessories?

3. Are steam trap facilities provided for collecting *Yes/No/N.A. *Yes/No/N.A.


condensate?

4. Is adjustable thermostatic control provided for the *Yes/No/N.A. *Yes/No/N.A.


equipment with accuracies tested?

(H) Refrigeration Equipment/Appliances

1. Is internal light provided as specified in the Particular *Yes/No/N.A. *Yes/No/N.A.


Contract?

2. Is low voltage strip heater provided for doors? *Yes/No/N.A. *Yes/No/N.A.

3. Is dial gauge or other type of thermometer provided as *Yes/No/N.A. *Yes/No/N.A.


specified in the Particular Specification with accuracies
tested?

4. Is all hand wheels, knobs and handle for refrigerated *Yes/No/N.A. *Yes/No/N.A.
appliances effectively insulated?

(I) Sink and Fixture

1. Is the sink provided with chromium plated brass/bronze *Yes/No/N.A. *Yes/No/N.A.


faucet?

2. Is the exposed surface free of bolt, screw and rivet head? *Yes/No/N.A. *Yes/No/N.A.

3. Are the legs rigid enough and not more than 1800 mm *Yes/No/N.A. *Yes/No/N.A.
centre?

4. Are bracing provided under stainless steel counter table, *Yes/No/N.A. *Yes/No/N.A.
drain board, dish tabletop, etc.?

5. Is sink provided with connected overflow? *Yes/No/N.A. *Yes/No/N.A.

6. Is anti-syphon provided for hand basin? *Yes/No/N.A. *Yes/No/N.A.

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 9 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor
7. Is splash back provided for sink, and table counter against *Yes/No/N.A. *Yes/No/N.A.
wall?

8. Are the surfaces/welding material of the sink or fixture in *Yes/No/N.A. *Yes/No/N.A.


touch of drinking water or food free from lead?

3.2.2 Testing and Commissioning

1. Are gas supply pressure, water supply pressure and *Yes/No/N.A. *Yes/No/N.A.
electricity supply voltage within the operating range of the
equipment / appliances?

2. Are all safety controls tested and ensured in proper *Yes/No/N.A. *Yes/No/N.A.
working order?

3. Are indicating lamp(s) and light(s) in proper function? *Yes/No/N.A. *Yes/No/N.A.

4. Do the meter, gauge and other indication devices function *Yes/No/N.A. *Yes/No/N.A.
accurately?

5. Is the manual control switch working properly? *Yes/No/N.A. *Yes/No/N.A.

6. Is the automatic on / off or modulating thermostatic *Yes/No/N.A. *Yes/No/N.A.


control working properly?

7. Is the timer switch and sequencing control switch working *Yes/No/N.A. *Yes/No/N.A.
properly?

8. Are the ignition, combustion and air supply properly *Yes/No/N.A. *Yes/No/N.A.
sequenced for automatic combustion system?

9. Are the gas / air ratio of burners adjusted correctly for *Yes/No/N.A. *Yes/No/N.A.
proper combustion?

10. Is the interlock between gas supply and forced draught *Yes/No/N.A. *Yes/No/N.A.
dampers working properly?

11. Are the ignition devices working properly? *Yes/No/N.A. *Yes/No/N.A.

12. Are the flame failure devices working properly? *Yes/No/N.A. *Yes/No/N.A.

13. Is the compressor for refrigeration equipment/ appliances *Yes/No/N.A. *Yes/No/N.A.


working properly without excessive noise?

14. Is the condenser of the refrigeration equipment / *Yes/No/N.A. *Yes/No/N.A.


appliances ventilated effectively and not over heated?

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 10 of 13 2022 Edition
(TCP-KE-2022)
Items tested/ Items witnessed
checked by by PBSE/PBSI
Contractor

15. Does the door strip heater for refrigeration *Yes/No/N.A. *Yes/No/N.A.
equipment/appliances function properly?

16. Is the refrigeration equipment/appliances able to maintain *Yes/No/N.A. *Yes/No/N.A.


the specified temperature?

17. Is the refrigeration equipment/appliances able to achieve *Yes/No/N.A. *Yes/No/N.A.


the required temperature within the specified period from
the loading temperature?

18. Is the insulation and earth continuity of the electrical *Yes/No/N.A. *Yes/No/N.A.
circuit of the equipment/appliances within the standards?

19. For exhaust hood equipped with UV-C grease


decomposition features: -

Ozone sensor installed at kitchen discharge outlet for *Yes/No/N.A. *Yes/No/N.A.


monitoring of ozone level

inter-locking provided to turn off the UV-C light tube *Yes/No/N.A. *Yes/No/N.A.
while the exhaust hood is not in operation or when ozone
level at kitchen or discharge outlet is higher than the
threshold value specified under the contract

3.3 Comments (if any) :

3.4 Testing and Commissioning for Other Equipment

1. *Yes/No/N.A. *Yes/No/N.A.

2. *Yes/No/N.A. *Yes/No/N.A.

3. *Yes/No/N.A. *Yes/No/N.A.

4. *Yes/No/N.A. *Yes/No/N.A.

5. *Yes/No/N.A. *Yes/No/N.A.

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 11 of 13 2022 Edition
(TCP-KE-2022)
Part 4 : Test Records attached to the Test Certificate

4.1 Test Record

Date of Test Type of Test Test Result

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 12 of 13 2022 Edition
(TCP-KE-2022)
4.2 Test Certificates

Location and address of installation:

This is to certify that the following Catering Equipment Installation *has/have been tested with the following
test certificates: -

Date of Test Type of Test Test Result

Tested / Checked by : Signature - Post :


(Name of Authorised Contractor’s Representative) Tel. No. :
( ) Date :
Witnessed by : Signature - Post :
(Name(s) of *PBSE/PBSI) Tel. No. :
( ) Date :

Annex II T&C Procedure for Catering Equipment Installation


Page 13 of 13 2022 Edition
(TCP-KE-2022)
Annex III

List of Calibrated Equipment/ Instruments Necessary for the


Testing & Commissioning Works

Serial No. of Date of


Type Model Instrument Calibration

*Delete if not applicable

Annex III T&C Procedure for Catering Equipment Installation


Page 1 of 1 2022 Edition
(TCP-KE-2022)

You might also like