1.

Wimmer’s Storage ran its freezer in February, a slow month, for 360 hours for a
total cost of $57,600. In July, a peak month, the freezer ran for 720 hours for a
total cost of $82,080.

Required:
a. What is the cost estimating equation for the department if hours of freezer
use are used as the cost driver?

b. What is the estimated total cost at an operating level of 500 hours?

Answer:
a. Slope (variable costs) = ($82,080 – $57,600) / (720 - 360) = $68

Constant (fixed cost) = $82,080 – (720 x $68) = $33,120

Estimating equation = $33,120 + $68DLH

b. Total costs of 500 hours = $33,120 + $68 x 500 = $67,120

Difficulty: 2 Objective: 4
Terms to Learn: cost estimation, cost function, cost predictions