1.

When using activity-based costing all of the following are true EXCEPT that:
a. all cost drivers should be output unit-level cost drivers
b. there are a great number and variety of cost drivers and cost pools
c. industrial engineering, conference, and regression analysis can be used to
estimate slope coefficients
d. the more cost pools, the greater the chance of estimation error
Answer: a Difficulty: 2 Objective: 5
Terms to Learn: cost function, cost estimation

2. Over the short run, a nonlinear cost function would MOST likely result from all of
the following EXCEPT:
a. quantity discounts for each additional 10,000 parts purchased
b. purchasing another $250,000 printing machine to double production
c. hiring a third production supervisor
d. incurring greater total utility costs for each machine-hour of operation
Answer: d Difficulty: 3 Objective: 6
Terms to Learn: cost function, nonlinear cost function