Professional Documents
Culture Documents
monitoring
CM National Forum 2007
Ray Beebe
(Monash 16 years, following 28 years in power
generation)
www.monash.edu.au
1
Steam turbines: the major power producer
2
HP-IP opposed flow casing (Qld, Vic). 500MW Vic
has 1xLP, last stage blades 1060mm long
• Yallourn Vic
350MW+, 375MW+,
layout in line
3
500MW (UK) Parallel layout.
HP casing IP casing 3 x LP casings
4
500MW Vic HP, IP, 2xLP casings,
Crossover under centreline
10
5
Some parts: blading
11
12
6
Why use CM?
13
14
7
Some turbine problems and CM
• BLADING
Erosion by solid particles (also by water droplets
on latter LP blades)
Usually occurs gradually, worst at inlet blading.
Less usual on sets with drum boilers and/or sub-critical
inlet steam conditions, or with bypass systems.
Performance analysis detects.
15
16
8
Deposits
Likely to occur gradually.
More common with base loaded sets as cyclic loading
tends to have a blade washing effect).
Some on-load blade washing occurs with forced steam
cooling.
Performance analysis detects.
• MAIN STEAM STRAINERS
Deposits, damage
Likely to occur gradually or suddenly.
Performance analysis detects (but needs Diff Pressure).
17
18
9
Overall condition indicator:
Valves Wide Open test
19
20
10
Case study A: blade damage (200MW set)
21
22
11
Case study B: 200MW steam turbine generator
• Planned full Heat Rate test for more diagnostics, but piping
isolations delayed test for 3 months.
VWO was now 216MW
23
24
12
Test data TEST A Correctn TEST Correctn
factor B factor
Generator Output MW 355.8 349.7
Steam Pressure - Main kPa 12155 1.02285 12255 1.02053
Steam Temperature - Main °C 529.5 0.99832 526.7 0.99773
Steam Temperature - Reheat °C 525.8 1.0101 539.5 0.99873
Reheater Pressure Drop % 6.76 0.99814 6.03 0.99633
Condenser Pressure - kPa 9.34 1.01225 12.44 1.03615
Generator Power Factor 0.923 1.00012 0.945 1.00064
Steam Temp. Cont. Spray - Main kg/s 6.5 0.99889 24.6 0.99584
Steam Temp. Control Spray - Reheater 0 1 0 1
kg/s
Final Feedwater Temperature °C 234.9 1.0005 230.5 0.98957
Combined correction factor 1.04741 1.03521
Corrected VWO Output MW 372.7 362
25
Parameters:
Stage
pressures Corrected stage
pressures (to
…are closely standard inlet
linear with conditions)
flow/load (NOT Pressure ratios,
Last Stage). inlet/outlet
better – not
Can use ratios to dependent only
detect blockage in on turbine inlet
section pressure value.
26
13
Corrected stage
Effect of blade deposits, damage shows pressures (to
standard inlet
conditions)
Pressure ratios,
inlet/outlet
Pressure ratio,
inlet to outlet,
increases
27
28
14
P1
T1
Enthalpy Enthalpy
kJ/kg
Drop
Efficiency P2
Actual h
tests drop
T2
Entropy kJ/kg °K 29
Enthalpy Drop
Efficiency is a
Enthalpy Drop Efficiency is
key parameter: usually 85–90%.
but useful in
superheated Lowers with damage or
zone only blade deposits.
30
15
Steam
Forced
Cool run
here
Corrected
VWO
Output
31
IP Blading
32
16
Deposits on IP blading
33
34
17
Case study E: other uses of
Expansion line plot
Measured stage outlet
at A is higher than
expected. Steam is
bypassing blades to
mix with stage
extraction flow: joint
leak?
35
P1 T1
Enthalpy
kJ/kg
P2 Temperature usually
saturation - if above,
T2
then steam is
Expansion line superheated, has
bypassed blading.
Isentropic
•- A
enthalpy P3 T3
drop 255 °C temperature
noticed in LP2 feedwater
heater inlet piping. 95 °C
Saturated steam zone
is usual temperature (read
Entropy kJ/kg K in Control Room).
36
18
Inner
bellows
37
38
19
VWO results
39
40
20
• MSV strainer blockage
41
VWO up to now
530
520
510
500
490 DCS
480 data Turbine repairs
470 tests made here
460
31-Jan-93 28-Oct-95 24-Jul-98 19-Apr-01 14-Jan-04
Date of test
42
21
Enthalpy Drop Efficiency up to after repair (turbine inlet to
HP blading outlet)
DCS data
90
gave
89 inconsistent
point
HP enthalpy drop efficiency %
88
87
86
85
84
83
82
81
31-Jan-93 15-Jun-94 28-Oct-95 11-Mar-97 24-Jul-98 06-Dec-99 19-Apr-01 01-Sep-02
43
16500
16000
Corrected pressures kPa(abs)
15500
15000
13500
13000
12500
12000
11-Jan-93 8-Oct-95 4-Jul-98 30-Mar-01
Date
44
22
Enthalpy Drop Efficiency: up to date
91
90
Excessive
scatter in DCS
89
results for this
88 parameter
87
from DCS to
be useful for
86
CM
85
84
83
82
81
31-Jan-93 15-Jun-94 28-Oct-95 11-Mar- 24-Jul-98 6-Dec-99 19-Apr- 1-Sep-02 14-Jan-04
97 01
45
46
23
47
48
24
• New turbine, efficiency below guarantee
• High reheat temperature, hard to control
– Extra temperature control station added
– 20% of first stage boiler reheater tubing
removed
• N2 packing tests run later: leakage flow
estimated at 4 - 5 times design!
– Consistent with reheater overheating due to
flow of about 5 - 8% less than design
49
CONCLUSIONS
www.monash.edu.au
25
“The need is there, the time is now!”
(Dupont 2000)
Off campus postgrad programs in Maintenance
and reliability engineering
University of Tennessee
www.monash.edu.au
26