You are on page 1of 26

Steam Turbines: case studies in condition

monitoring
CM National Forum 2007

Ray Beebe
(Monash 16 years, following 28 years in power
generation)

www.monash.edu.au

• Steam turbines not your scene? Some


of the concepts could be applied to other
plant
• Today: several case studies of general
engineering interest
• Paper with more detail is on CD, and
others available: just ask
ray.beebe@eng.monash.edu

1
Steam turbines: the major power producer

• Australia has machines up to 660MW in


service (NSW)
• Larger unit coming on 720MW (Qld)
• Most are sub-critical pressure, some
new in Qld are super-critical
• Many makes: sourced Europe, Japan

Steam turbines: the major power producer

• Design layouts differ, but all have:


• Large steel casings
• Blading, moving and stationary
• Shaft seals/glands/packing to keep steam in!
• Bearings
• Control valves, hydraulic systems
• Lots of piping
– Selection of pictures follow

2
HP-IP opposed flow casing (Qld, Vic). 500MW Vic
has 1xLP, last stage blades 1060mm long

• Yallourn Vic
350MW+, 375MW+,
layout in line

3
500MW (UK) Parallel layout.
HP casing IP casing 3 x LP casings

500MW Vic HP, IP, 2 x LP casings.


Crossover on top (as 660 MW NSW)

4
500MW Vic HP, IP, 2xLP casings,
Crossover under centreline

Many smaller machines

10

5
Some parts: blading

11

Some parts: casings, shaft glands, rotors

12

6
Why use CM?

• Decision makers have to start


somewhere
• Open if compelling technical and
economic reasons. (High temperature
parts get heat affected, may be difficult
to dissemble).
• OEM advice: consider

13

• Turbines are critical plant, well justify


application of CM.
• Several CM techniques can be used.
• Vibration analysis and performance
analysis are the most usual for owners.
• Here: use of performance analysis
methods.

14

7
Some turbine problems and CM

• BLADING
Erosion by solid particles (also by water droplets
on latter LP blades)
Usually occurs gradually, worst at inlet blading.
Less usual on sets with drum boilers and/or sub-critical
inlet steam conditions, or with bypass systems.
Performance analysis detects.

Parts breaking off


Usually sudden. Vibration monitoring/analysis and
Performance analysis detects.

15

16

8
Deposits
Likely to occur gradually.
More common with base loaded sets as cyclic loading
tends to have a blade washing effect).
Some on-load blade washing occurs with forced steam
cooling.
Performance analysis detects.
• MAIN STEAM STRAINERS
Deposits, damage
Likely to occur gradually or suddenly.
Performance analysis detects (but needs Diff Pressure).

17

Inlet strainer and


blading blockage –
turbine troubles
detectable
by performance
analysis

18

9
Overall condition indicator:
Valves Wide Open test

– Control valves WIDE open, checked


– Steady conditions for hour
– May need to run at reduced inlet pressure
– Test readings of key temperatures,
pressures, MW (or panel instruments/DCS
if proven)
– No special test flow measurements
– MW are corrected for any variations from
rated values.

19

Typical OEM correction


curves for VWOutput

20

10
Case study A: blade damage (200MW set)

21

Metal piece bent stationary blades

22

11
Case study B: 200MW steam turbine generator

• Usual loading: 210MW. Steam control valves about


90% open. VWO when new: 216MW

• One day, operator noticed steam control valves


100% open. So, VWO test run: 210MW (-6MW )

• Planned full Heat Rate test for more diagnostics, but piping
isolations delayed test for 3 months.
VWO was now 216MW

[Unit had 11 shutdowns in this time ! Likely problem: deposits


on blading, removed by startup/shutdown blade washing
effect]

23

Case study C: 350MW set

24

12
Test data TEST A Correctn TEST Correctn
factor B factor
Generator Output MW 355.8 349.7
Steam Pressure - Main kPa 12155 1.02285 12255 1.02053
Steam Temperature - Main °C 529.5 0.99832 526.7 0.99773
Steam Temperature - Reheat °C 525.8 1.0101 539.5 0.99873
Reheater Pressure Drop % 6.76 0.99814 6.03 0.99633
Condenser Pressure - kPa 9.34 1.01225 12.44 1.03615
Generator Power Factor 0.923 1.00012 0.945 1.00064
Steam Temp. Cont. Spray - Main kg/s 6.5 0.99889 24.6 0.99584
Steam Temp. Control Spray - Reheater 0 1 0 1
kg/s
Final Feedwater Temperature °C 234.9 1.0005 230.5 0.98957
Combined correction factor 1.04741 1.03521
Corrected VWO Output MW 372.7 362

Some years apart. Now, to investigate why a10MW drop!

25

Parameters:
Stage
pressures Corrected stage
pressures (to
…are closely standard inlet
linear with conditions)
flow/load (NOT Pressure ratios,
Last Stage). inlet/outlet
better – not
Can use ratios to dependent only
detect blockage in on turbine inlet
section pressure value.

26

13
Corrected stage
Effect of blade deposits, damage shows pressures (to
standard inlet
conditions)
Pressure ratios,
inlet/outlet

Pressure ratio,
inlet to outlet,
increases

27

Revisit Case study A: blade damage (200MW set)

28

14
P1
T1
Enthalpy Enthalpy
kJ/kg
Drop
Efficiency P2
Actual h
tests drop
T2

Ideal h Expansion line


drop
Isentropic
enthalpy P3 T3
drop
Efficiency =
Actual h drop
Ideal h Drop

Entropy kJ/kg °K 29

Enthalpy, entropy found


from temperature and
pressure.

Free steam tables:


www.pepse.com

Enthalpy Drop
Efficiency is a
Enthalpy Drop Efficiency is
key parameter: usually 85–90%.
but useful in
superheated Lowers with damage or
zone only blade deposits.

30

15
Steam
Forced
Cool run
here

Corrected
VWO
Output

31

IP Blading

32

16
Deposits on IP blading

33

Case study D: other uses of


Stage pressures vs
Flow/output Pressure at Stage
4 becomes positive
Air leakage into at that load.
turbine was very
high – all air pumps Leaking flange
had to run to start found in piping
machine up. from gland to
feedheater line.
At 45% load, air
leakage problem
ceased.

34

17
Case study E: other uses of
Expansion line plot
Measured stage outlet
at A is higher than
expected. Steam is
bypassing blades to
mix with stage
extraction flow: joint
leak?

35

P1 T1
Enthalpy
kJ/kg

P2 Temperature usually
saturation - if above,
T2
then steam is
Expansion line superheated, has
bypassed blading.

Isentropic
•- A
enthalpy P3 T3
drop 255 °C temperature
noticed in LP2 feedwater
heater inlet piping. 95 °C
Saturated steam zone
is usual temperature (read
Entropy kJ/kg K in Control Room).

36

18
Inner
bellows

Expansion bellows had failed.


914mm diameter,
two sets in each of 4 pipes.

37

Case study F: 500MW

• Initial test was for Acceptance


• High accuracy tests run 2 yearly, to also get
before/after steam path inspections
• Slight decline in performance from new evident,
but not unusual
• After Test 4, operators noticed greater control
valves opening needed, so DCS tests run
weekly
• Clear degradation somewhere.

38

19
VWO results

• Plant has DCS


• Calibration of key instruments has
revealed little drift
• Array of screen-based displays
• VWO accurate tests set up, data taken
into historian system (Uniformance PHD)
can be accessed in office
• VWO found both ways:

39

VWO Output from


DCS trend close to special tests
VWO using special
test instruments

VWO from plant


instruments

40

20
• MSV strainer blockage

41

VWO up to now

High accuracy tests


Corrected VWO Output MW

530
520
510
500
490 DCS
480 data Turbine repairs
470 tests made here
460
31-Jan-93 28-Oct-95 24-Jul-98 19-Apr-01 14-Jan-04

Date of test

42

21
Enthalpy Drop Efficiency up to after repair (turbine inlet to
HP blading outlet)

DCS data
90
gave
89 inconsistent
point
HP enthalpy drop efficiency %

88

87

86

85

84

83

82

81
31-Jan-93 15-Jun-94 28-Oct-95 11-Mar-97 24-Jul-98 06-Dec-99 19-Apr-01 01-Sep-02

43

Corrected pressures up to after repair: After control valves


and First Stage

16500

16000
Corrected pressures kPa(abs)

15500

15000

14500 Corr FSP


Corr PAGVs
14000

13500

13000

12500

12000
11-Jan-93 8-Oct-95 4-Jul-98 30-Mar-01
Date
44

22
Enthalpy Drop Efficiency: up to date

91

90
Excessive
scatter in DCS
89
results for this
88 parameter
87
from DCS to
be useful for
86
CM
85

84

83

82

81
31-Jan-93 15-Jun-94 28-Oct-95 11-Mar- 24-Jul-98 6-Dec-99 19-Apr- 1-Sep-02 14-Jan-04
97 01

45

Case study G: N2 leakage

• Peculiar to HP-IP combined casing


design

46

23
47

48

24
• New turbine, efficiency below guarantee
• High reheat temperature, hard to control
– Extra temperature control station added
– 20% of first stage boiler reheater tubing
removed
• N2 packing tests run later: leakage flow
estimated at 4 - 5 times design!
– Consistent with reheater overheating due to
flow of about 5 - 8% less than design
49

CONCLUSIONS

Information from condition monitoring can help the maintenance


decision – to open a turbine only when there is a technically and
economically compelling reason.

Same methods can be used to investigate observed


performance shortfalls.

Special test instrumentation needed, but worth trying use of


DCS.

Other CM methods needed: vibration analysis, NDT inspection,


maybe oil checks.

www.monash.edu.au

25
“The need is there, the time is now!”
(Dupont 2000)
Off campus postgrad programs in Maintenance
and reliability engineering

in collaboration for North America with

University of Tennessee

www.monash.edu.au

26

You might also like