You are on page 1of 179

1 of 179

-n=;=_ -n=;=_

ABSTRACT OF COST
F/Y : 077/78
Project:
S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks
1 Construction Cost 199,210,858.26
Insurance of works, equipment, Contractor's workmen and employees and Third party
2 PS 1.00 660,040.90
Insurance against damage to other persons and property.
Total (1,2,3)=(A) 199,870,899.16
Contingencies @5% of (A)=(B) 9,993,544.96
Total with Contingencies @5% (C) 209,864,444.12
VAT @13% of -
Total including VAT & Contingency(F+G)=(H) -
Grand Total -
Insurance Premium
1 Insurance premium for the work, plant and materials damage for contract work for all risk including Riot,Strike,
Damage,Malicious damage and Terrorism for contract
Insurance with value workperfor
Rs. 3.03 project period 24 months
thousand Rs + 1 year Maintenance period.
603,608.90
Premium Rs 603,608.90
for stamp duty Rs 10.00
Premium with stamp duty Rs 603,618.90
Total Amount without VAT Rs 603,618.90

2 Insurance premium for the insurance of owner and consultant staff (named) Rs. 10,00,000.00 per person for 7 persons with
unlimited
Personnel number
accidentofofoccurances perfor
10,00,000.00 annum
7 Rs.2.00 per thousand Rs 14,000.00
Premium Rs 14,000.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 14,010.00
Total Amount without VAT Rs 14,010.00 Per Annum
Total Amount without VAT Rs 42,030.00 Per period

3 Insurance Premium for construction equipments and machines with value of Rs.20,00,000.00 for 24 months
Insurance premium of Rs. 20,00,000.00 Rs.2.03 per thousand Rs 4060.00
Premium Rs 4060.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 4070.00
Total Amount without VAT Rs 4070.00

4 Insurance Premium for third party liability personal only per person Rs.2,00,000.00 for 7 persons for 24months
P.A. of third party 7 person=14,00,000.00 Rs. 3.03 per thousand Rs 4242.00
Premium Rs 4242.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 4252.00
Total Amount without VAT Rs 4252.00

5 Insurance Premium for Contractor's Workers(Un named) per person only Rs.2,00,000.00 for 10 persons for 24months
P.A. of third party 10 person=2,00,000.00 Rs. 3.03 per thousand Rs 6060.00
Premium Rs 6060.00
For stamp duty Rs 10.00
Premium with stamp duty Rs 6070.00
Total Amount without VAT Rs 6,070.00

Grand Total 660,040.90


Project:
S.N. Description Amount (NRs.)
1 Building 199,210,858.26
Total 199,210,858.26
Contingencies @10% 19,921,085.83
Total with Contingencies 219,131,944.08
VAT @13% of Total 25,897,411.57
Total with VAT 245,029,355.66
Item: Abstract of Cost of Debate Chamber Block
S.N. Description Unit Quantity Rate NRs. Amount NRs.
Clearing of grass, removing roots, breaking sods
1 levelling the surface and disposal as per m2 2400.00 19.44 46,656.00
specification

2 Earth work excavation in foundation in clay & m3 3256.09 497.49 1,619,872.84


silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with
3 watering & lead upto 1o.00 mtr. & proper m3 5250.44 603.75 3,169,951.04
manual compaction.
4 Dry flat Brick paving work m2 4358.50 892.34 3,889,265.76

5 P.C.C. (1:3:6) work in foundation, wall (crushed m3 322.46 13,584.52 4,380,486.16


or stone ballast)
P.C.C. (1:1:2) for R.C.C. work(USED
6 MACHINE) in slab, beam etc (crushed or stone m3 1117.30 19,866.26 22,196,670.64
ballast)
P.C.C. (1:1½:3) for R.C.C. work(USED
7 MACHINE) in slab, beam etc (crushed or stone m3 1900.88 16,105.86 30,615,230.93
ballast)
Torsteel reinforcement bar for R.C.C. work with
8 cutting, bending, binding & laying with all Mt 473.85 115,020.00 54,502,720.90
complete.

9 Trench work open type form work ( 1.50 to m2 512.75 815.48 418,133.29
3.00 Mtr.)
Form work shuttering & centering (BEAM-0.30-
10 0.80 Mtr) with (USED LOCAL WOOD) all m2 4572.50 1,014.60 4,639,259.51
complete.
Form work shuttering & centering (COLUMN)
11 with (USED LOCAL WOOD) all complete. m2 1995.20 1,864.41 3,719,870.83

Form work shuttering & centering with MS pipe


12 (prop), plyboard for slab etc m2 7237.90 1,241.52 8,986,003.57

13 First class chimney brick masonry work in (1:4) m3 463.63 13,589.09 6,300,275.28
cement sand mortar in G. F.

14 First class chimney brick masonry work in (1:4) m3 113.24 14,210.95 1,609,178.34
cement sand mortar in F. F.

15 First class chimney brick masonry work in (1:4) m3 73.08 15,081.56 1,102,121.19
cement sand mortar in S. F.

16 25 mm or 1" thick P.C.C. (1:2:4) work in floor m2 3604.17 551.82 1,988,853.09


with all complete.

17 12.5 mm. thick cement sand plaster work 1:4 on m2 7756.32 417.17 3,235,704.01
wall.
12.5 mm. thick cement sand plaster work 1:4 on
18 ceilling m2 11729.72 487.20 5,714,721.14
Item: Abstract of Cost of Debate Chamber Block
S.N. Description Unit Quantity Rate NRs. Amount NRs.

Supplying and fixing of aluminium sliding


19 window without ventilator section m2 487.76 8,166.84 3,983,449.71
101x45x1.80mm including 4mm glass and
gasket all complete
22 Two coat white washing work on ceilling. m2 11729.72 44.88 526,429.98
Two coat distemper painting work without
23 primer coat. m2 12004.26 113.71 1,365,004.40

Two coat weather proof painting work over


24 primer coat. m2 4990.56 246.66 1,230,970.54

15 mm thick marble tile 600x600 mm paving


25 with 20 mm thick cement sand mortar 1:2 m2 150.00 3,921.07 588,160.50
rubbing & polishing work with all complete.
Fabrication of steel railing with 3 row of 1"
26 horizontal pipe and vertical post and hand rail of Rm 47.00 3,831.04 180,058.88
2"
Total Civil works 166,009,048.55
Sanitary Works (10%) 16,600,904.85
Electrical Work (10%) 16,600,904.85
Total = 199,210,858.26
Item: Abstract of Cost of Landscape
S.N. Description Unit Quantity Rate NRs. Amount NRs.
Clearing of grass, removing roots, breaking sods
1 levelling the surface and disposal as per m2 1010.00 19.44 19,634.40
specification

2 Surface dressing work with cutting of raised soil m3 27.20 8.45 229.80
& filling the ditches.

3 P.C.C. (1:3:6) work in foundation, wall (crushed m3 9.07 13,584.52 123,245.56


or stone ballast)

4 First class chimney brick masonry work in (1:4) m3 0.63 13,589.09 8,583.14
cement sand mortar in G. F.

5 12.5 mm. thick cement sand plaster work 1:4 on m2 5.74 417.17 2,395.39
wall.
Grass turfing including cutting grass block,
6 spraying of water and fertilizer including m2 58.95 654.92 38,607.53
transportation also.
Cement tile(Machine Made) paving work in
7 cement sand (1:4) mortar m2 18.00 2,927.66 52,697.84

80mm Heavy Duty Concrete Interlocking Tiles


8 on 50 mm thick crush stone dust m2 247.30 1,250.94 309,356.23

Total Civil works 554,749.89


Total = 554,749.89
Item: Abstract of Cost of Boundary wall
S.N. Description Unit Quantity Rate NRs. Amount NRs.

1 Earth work excavation in foundation in clay & m3 40.25 497.49 20,023.97


silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with
2 watering & lead upto 1o.00 mtr. & proper m3 16.10 603.75 9,720.38
manual compaction.

P.C.C. (1:1:2) for R.C.C. work(USED


3 MACHINE) in slab, beam etc (crushed or stone m3 39.19 19,866.26 778,509.06
ballast)
Torsteel reinforcement bar for R.C.C. work with
4 cutting, bending, binding & laying with all Mt 3.08 115,020.00 353,826.68
complete.

5 First class chimney brick masonry work in (1:4) m3 52.70 13,589.09 716,145.04
cement sand mortar in G. F.

6 12.5 mm. thick cement sand plaster work 1:4 on m2 577.44 417.17 240,890.64
wall.
7 Two coat white washing work on wall. m2 577.44 38.03 21,960.04
Two coat distemper painting work without
8 primer coat. m2 577.44 113.71 65,660.70

9 Metal Fence m2 75.00 1,900.00 142,500.00


Total Civil works 2,349,236.53
Total = 2,349,236.53
Item: Abstract of Cost of Gate
S.N. Description Unit Quantity Rate NRs. Amount NRs.

1 Earth work excavation in foundation in clay & m3 9.75 497.49 4,852.02


silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with
2 watering & lead upto 1o.00 mtr. & proper m3 3.90 603.75 2,355.35
manual compaction.
3 Dry flat Brick paving work m2 6.81 892.34 6,076.84

4 P.C.C. (1:3:6) work in foundation, wall (crushed m3 0.51 13,584.52 6,938.29


or stone ballast)
P.C.C. (1:1:2) for R.C.C. work(USED
5 MACHINE) in slab, beam etc (crushed or stone m3 4.53 19,866.26 90,040.84
ballast)
Torsteel reinforcement bar for R.C.C. work with
6 cutting, bending, binding & laying with all Mt 0.71 115,020.00 81,845.81
complete.

7 Trench work open type form work ( 1.50 to m2 2.44 815.48 1,989.77
3.00 Mtr.)
Form work shuttering & centering (BEAM-0.30-
8 0.80 Mtr) with (USED LOCAL WOOD) all m2 15.39 1,014.60 15,614.69
complete.
Form work shuttering & centering (COLUMN)
9 with (USED LOCAL WOOD) all complete. m2 12.40 1,864.41 23,126.14

10 First class chimney brick masonry work in (1:4) m3 6.25 13,589.09 84,897.84
cement sand mortar in G. F.

11 12.5 mm. thick cement sand plaster work 1:4 on m2 5.84 417.17 2,435.44
wall.
12 Two coat white washing work on wall. m2 5.84 38.03 222.02
Two coat weather proof painting work over
13 primer coat. m2 5.84 246.66 1,440.00

Providing and fixing Iron gate 16 guage (with


frame 50 mm X 50 mm X 5 mm) ready made
and applying red oxide paint with labour cost
14 Sqm 9.30 5,246.87 48,795.89
and all neccesary fittings as per specification
and as per instructed.

Total Civil works 370,630.95


Total = 370,630.95
Item: Abstract of Cost of Water tank
S.N. Description Unit Quantity Rate NRs. Amount NRs.

1 Earth work excavation in foundation in clay & m3 16.02 497.49 7,969.06


silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with
2 watering & lead upto 1o.00 mtr. & proper m3 4.81 603.75 2,901.36
manual compaction.
3 Dry flat Brick paving work m2 10.97 892.34 9,790.40

4 R.R. stone masonry work in cement sand (1:6) m3 4.16 11,742.88 48,853.20
mortar
P.C.C. (1:1:2) for R.C.C. work(USED
5 MACHINE) in slab, beam etc (crushed or stone m3 2.41 19,866.26 47,837.95
ballast)
Torsteel reinforcement bar for R.C.C. work with
6 cutting, bending, binding & laying with all Mt 0.27 115,020.00 30,923.77
complete.
Form work shuttering & centering (BEAM-0.30-
7 0.80 Mtr) with (USED LOCAL WOOD) all m2 27.92 4,572.50 127,664.23
complete.

8 12.5 mm. thick cement sand plaster work 1:4 on m2 25.76 417.17 10,746.30
wall.
9 3 mm thick neat cement punning work. m2 25.76 1,153.56 29,715.71
Total Civil works 316,401.97
Total = 316,401.97
Item: Abstract of Cost of Soakpit
S.N. Description Unit Quantity Rate NRs. Amount NRs.
Earth work excavation in foundation in clay &
1 m3 16.33 497.49 8,126.14
silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
2 Dry flat Brick paving work m2 9.07 892.34 8,093.52
P.C.C. (1:1½:3) for R.C.C. work(USED
3 MACHINE) in slab, beam etc (crushed or stone m3 0.39 16,105.86 6,321.55
ballast)
Torsteel reinforcement bar for R.C.C. work with
4 cutting, bending, binding & laying with all Mt 0.02 115,020.00 1,925.30
complete.
Form work shuttering & centering with MS pipe
5 (prop), plyboard for slab etc m2 8.72 1,241.52 10,824.28

6 R.R. stone masonry work in cement sand (1:6) m3 0.79 11,742.88 9,300.36
mortar

7 Sand filling work with watering & proper m3 1.76 3,692.70 6,513.92
manual compaction.
Total Civil works 51,105.08
Total = 51,105.08
Item: Abstract of Cost of Manhole
S.N. Description Unit Quantity Rate NRs. Amount NRs.

1 Earth work excavation in foundation in clay & m3 53.91 497.49 26,818.18


silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
2 Dry flat Brick paving work m2 7.30 892.34 6,514.80

3 P.C.C. (1:3:6) work in foundation, wall (crushed m3 0.73 13,584.52 9,917.79


or stone ballast)
P.C.C. (1:1½:3) for R.C.C. work(USED
4 MACHINE) in slab, beam etc (crushed or stone m3 0.77 16,105.86 12,369.30
ballast)
Torsteel reinforcement bar for R.C.C. work with
5 cutting, bending, binding & laying with all Mt 0.06 115,020.00 6,890.16
complete.
Form work shuttering & centering with MS pipe
6 (prop), plyboard for slab etc m2 3.62 1,241.52 4,499.27

7 R.R. stone masonry work in cement sand (1:6) m3 2.41 11,742.88 28,245.62
mortar

8 12.5 mm. thick cement sand plaster work 1:4 on m2 10.93 417.17 4,560.00
wall.
9 3 mm thick neat cement punning work. m2 10.93 1,153.56 12,609.33
Total Civil works 112,424.45
Total = 112,424.45
Item: Abstract of Cost of Septic Tank
S.N. Description Unit Quantity Rate NRs. Amount NRs.

1 Earth work excavation in foundation in clay & m3 19.79 497.49 9,846.57


silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
2 Dry flat Brick paving work m2 11.31 892.34 10,092.37

3 P.C.C. (1:3:6) work in foundation, wall (crushed m3 0.85 13,584.52 11,523.07


or stone ballast)
P.C.C. (1:1½:3) for R.C.C. work(USED
4 MACHINE) in slab, beam etc (crushed or stone m3 2.54 16,105.86 40,985.39
ballast)
Torsteel reinforcement bar for R.C.C. work with
5 cutting, bending, binding & laying with all Mt 0.07 115,020.00 7,950.60
complete.
Form work shuttering & centering with MS pipe
6 (prop), plyboard for slab etc m2 12.67 1,241.52 15,730.06

7 R.R. stone masonry work in cement sand (1:6) m3 6.37 11,742.88 74,808.02
mortar

8 12.5 mm. thick cement sand plaster work 1:4 on m2 26.55 417.17 11,074.82
wall.
9 3 mm thick neat cement punning work. m2 26.55 1,153.56 30,624.13
Total Civil works 212,635.02
Total = 212,635.02
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

1 Clearing of grass, removing roots, breaking sods levelling the surface and disposal as per specification
Site area 1 2400 2400.00 m2

2 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Footing
F1 15 3.25 3.25 2.50 396.09
F2 6 4.45 4.45 2.50 297.04
F3 6 3.85 3.85 2.50 222.34
F4 4 4.45 4.45 2.50 198.03
F5 1 5.10 5.10 2.50 65.03
F6 10 5.70 5.70 2.50 812.25
CF1 1 7.50 3.15 2.50 59.06
CF2 2 17.76 4.28 2.50 380.06
Tie Beam
Grid A-A 1 13.79 0.70 2.00 19.31
Grid B-B 1 7.89 0.70 2.00 11.05
Grid C-C 1 7.89 0.70 2.00 11.05
Grid D-D 1 7.92 0.70 2.00 11.09
Grid E-E 1 7.92 0.70 2.00 11.09
Grid F-F 1 7.89 0.70 2.00 11.05
Grid G-G 1 13.66 0.70 2.00 19.12
Grid H-H 1 12.97 0.70 2.00 18.16
Grid I-I 1 7.92 0.70 2.00 11.09
Grid J-J 1 7.89 0.70 2.00 11.05
Grid K-K 1 13.01 0.70 2.00 18.21
Grid L-L 1 12.16 0.70 2.00 17.02
Grid M-M 1 7.92 0.70 2.00 11.09
Grid N-N 1 7.89 0.70 2.00 11.05
Grid O-O 1 12.75 0.70 2.00 17.85
Grid P-P 1 13.79 0.70 2.00 19.31
Beam around th dome
Inner 1 92.20 0.70 2.00 129.08
Middle 1 150.32 0.70 2.00 210.45
Outer 1 184.36 0.70 2.00 258.10

Total Excavation = 3256.09 m3

Earth filling work in every 15-15 cm. layer with watering & lead upto 1o.00 mtr. & proper manual
3 compaction.
Total excavation 3256.09
Total filling 40% of excavation 1302.44
Filling upto plinth 1 2272.00 1.5 3408.00
1 900.00 0.6 540.00

Total 5250.44 m3
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

4 Dry flat Brick paving work


Footing
F1 15 3.05 3.05 139.54
F2 6 4.25 4.25 108.38
F3 6 3.65 3.65 79.94
F4 4 4.25 4.25 72.25
F5 1 4.90 4.90 24.01
F6 10 5.50 5.50 302.50
CF1 1 7.30 2.95 21.54
CF2 2 17.56 4.08 143.29

Tie Beam
Grid A-A 1 13.79 0.5 6.90
Grid B-B 1 7.89 0.5 3.95
Grid C-C 1 7.89 0.5 3.95
Grid D-D 1 7.92 0.5 3.96
Grid E-E 1 7.92 0.5 3.96
Grid F-F 1 7.89 0.5 3.95
Grid G-G 1 13.66 0.5 6.83
Grid H-H 1 12.97 0.5 6.49
Grid I-I 1 7.92 0.5 3.96
Grid J-J 1 7.89 0.5 3.95
Grid K-K 1 13.01 0.5 6.51
Grid L-L 1 12.16 0.5 6.08
Grid M-M 1 7.92 0.5 3.96
Grid N-N 1 7.89 0.5 3.95
Grid O-O 1 12.75 0.5 6.38
Grid P-P 1 13.79 0.5 6.90
Beam around th dome 0.5 0.00
Inner 1 92.20 0.5 46.10
Middle 1 150.32 0.5 75.16
Outer 1 184.36 0.5 92.18

Floor 1 2272.00 2272.00


1 900.00 900.00

Total= 4358.50 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
5 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)
Footing
F1 15 3.05 3.05 0.075 10.47
F2 6 4.25 4.25 0.075 8.13
F3 6 3.65 3.65 0.075 6.00
F4 4 4.25 4.25 0.075 5.42
F5 1 4.90 4.90 0.075 1.80
F6 10 5.50 5.50 0.075 22.69
CF1 1 7.30 2.95 0.075 1.62
CF2 2 17.56 4.08 0.075 10.75

Tie Beam
Grid A-A 1 13.79 0.4 0.075 0.41
Grid B-B 1 7.89 0.4 0.075 0.24
Grid C-C 1 7.89 0.4 0.075 0.24
Grid D-D 1 7.92 0.4 0.075 0.24
Grid E-E 1 7.92 0.4 0.075 0.24
Grid F-F 1 7.89 0.4 0.075 0.24
Grid G-G 1 13.66 0.4 0.075 0.41
Grid H-H 1 12.97 0.4 0.075 0.39
Grid I-I 1 7.92 0.4 0.075 0.24
Grid J-J 1 7.89 0.4 0.075 0.24
Grid K-K 1 13.01 0.4 0.075 0.39
Grid L-L 1 12.16 0.4 0.075 0.36
Grid M-M 1 7.92 0.4 0.075 0.24
Grid N-N 1 7.89 0.4 0.075 0.24
Grid O-O 1 12.75 0.4 0.075 0.38
Grid P-P 1 13.79 0.4 0.075 0.41
Beam around th dome
Inner 1 92.20 0.4 0.075 2.77
Middle 1 150.32 0.4 0.075 4.51
Outer 1 184.36 0.4 0.075 5.53

Floor 1 2272.00 0.075 170.40


1 900.00 0.075 67.50

Total= 322.46 m3
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

6 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Up to plinth
Footing
F1 15 3.05 3.05 0.6 83.72
F2 6 4.25 4.25 0.6 65.03
F3 6 3.65 3.65 0.6 47.96
F4 4 4.25 4.25 0.65 46.96
F5 1 4.90 4.90 0.65 15.61
F6 10 5.50 5.50 0.7 211.75
CF1 1 7.30 2.95 0.65 14.00
CF2 2 17.56 4.08 0.75 107.47
Column
C 11 0.75 0.75 2 12.38
C1 7 0.75 0.75 2 7.88
C2 16 0.75 0.75 2 18.00
C3 16 1.25 0.90 2 36.00
Ground Floor
Column
C 11 0.75 0.75 4.45 27.53
C1 7 0.75 0.75 4.45 17.52
C2 16 0.75 0.75 4.45 40.05
C3 16 1.25 0.90 4.45 80.10
1st Floors
Column
C 11 0.75 0.75 4.45 27.53
C1 7 0.75 0.75 4.45 17.52
C2 16 0.75 0.75 4.45 40.05
C3 16 1.25 0.90 4.45 80.10
2nd Floor
Column
C2 16 0.75 0.75 4.45 40.05
C3 16 1.25 0.90 4.45 80.10

Total = 1117.30 m3
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
7 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Up to plinth
Tie Beam
Grid A-A 1 13.79 0.40 0.70 3.86
Grid B-B 1 7.89 0.40 0.70 2.21
Grid C-C 1 7.89 0.40 0.70 2.21
Grid D-D 1 7.92 0.40 0.70 2.22
Grid E-E 1 7.92 0.40 0.70 2.22
Grid F-F 1 7.89 0.40 0.70 2.21
Grid G-G 1 13.66 0.40 0.70 3.82
Grid H-H 1 12.97 0.40 0.70 3.63
Grid I-I 1 7.92 0.40 0.70 2.22
Grid J-J 1 7.89 0.40 0.70 2.21
Grid K-K 1 13.01 0.40 0.70 3.64
Grid L-L 1 12.16 0.40 0.70 3.40
Grid M-M 1 7.92 0.40 0.70 2.22
Grid N-N 1 7.89 0.40 0.70 2.21
Grid O-O 1 12.75 0.40 0.70 3.57
Grid P-P 1 13.79 0.40 0.70 3.86
Beam around th dome
Inner 1 92.20 0.40 0.70 25.82
Middle 1 150.32 0.40 0.70 42.09
Outer 1 184.36 0.40 0.70 51.62

Beam at 0m level
Main Beam
Grid A-A 1 14.39 0.40 0.70 4.03
Grid B-B 1 8.49 0.40 0.70 2.38
Grid C-C 1 8.49 0.40 0.70 2.38
Grid D-D 1 8.52 0.40 0.70 2.39
Grid E-E 1 8.52 0.40 0.70 2.39
Grid F-F 1 7.89 0.40 0.70 2.21
Grid G-G 1 13.66 0.40 0.70 3.82
Grid H-H 1 12.97 0.40 0.70 3.63
Grid I-I 1 7.92 0.40 0.70 2.22
Grid J-J 1 7.89 0.40 0.70 2.21
Grid K-K 1 13.01 0.40 0.70 3.64
Grid L-L 1 12.76 0.40 0.70 3.57
Grid M-M 1 8.52 0.40 0.70 2.39
Grid N-N 1 8.49 0.40 0.70 2.38
Grid O-O 1 13.35 0.40 0.70 3.74
Grid P-P 1 14.39 0.40 0.70 4.03
Beam around th dome
Inner 1 92.20 0.40 0.70 25.82
Middle 1 150.32 0.40 0.70 42.09
Outer 1 30.12 0.40 0.70 8.43
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Ground Floor 4.5 m level
Main Beam
Grid A-A 1 14.39 0.40 0.70 4.03
Grid B-B 1 8.49 0.40 0.70 2.38
Grid C-C 1 8.49 0.40 0.70 2.38
Grid D-D 1 8.52 0.40 0.70 2.39
Grid E-E 1 8.52 0.40 0.70 2.39
Grid F-F 1 7.89 0.40 0.70 2.21
Grid G-G 1 13.66 0.40 0.70 3.82
Grid H-H 1 12.97 0.40 0.70 3.63
Grid I-I 1 7.92 0.40 0.70 2.22
Grid J-J 1 7.89 0.40 0.70 2.21
Grid K-K 1 13.01 0.40 0.70 3.64
Grid L-L 1 12.76 0.40 0.70 3.57
Grid M-M 1 8.52 0.40 0.70 2.39
Grid N-N 1 8.49 0.40 0.70 2.38
Grid O-O 1 13.35 0.40 0.70 3.74
Grid P-P 1 14.39 0.40 0.70 4.03
Beam around th dome
Inner 1 92.20 0.40 0.65 23.97
Middle 1 150.32 0.40 0.70 42.09
Outer 1 30.12 0.40 0.70 8.43
Secondary beam
Beam between inner & middle 1 61.21 0.40 0.70 17.14
Between Grid A & B 1 8.08 0.30 0.40 0.97
Between Grid B & C 1 8.08 0.30 0.40 0.97
Between Grid D & E 1 8.10 0.30 0.40 0.97
Between Grid E & F 1 8.10 0.30 0.40 0.97
Between Grid G & H 1 8.10 0.30 0.40 0.97
Between Grid H & I 1 3.16 0.30 0.40 0.38
Between Grid I & J 1 8.10 0.30 0.40 0.97
Between Grid J & K 1 8.08 0.30 0.40 0.97
Between Grid K & L 1 8.08 0.30 0.40 0.97
Between Grid L & M 1 8.08 0.30 0.40 0.97
Between Grid M & N 1 8.08 0.30 0.40 0.97
Between Grid N & O 1 8.08 0.30 0.40 0.97
Between Grid P & A 1 4.50 0.30 0.40 0.54

Beam between inner & middle 1 48.19 0.30 0.40 5.78


Beam inside inner beam 1 56.20 0.30 0.40 6.74
1 13.79 0.30 0.40 1.65
Stair beam 1 8.46 0.40 0.65 2.20
1 4.55 0.40 0.65 1.18
1 8.50 0.40 0.65 2.21
1 2.87 0.40 0.65 0.75
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

Slab 1 1237.49 0.125 154.69

Stair SC1
landing 1 7.78 0.150 1.17
1st and 2nd flight 2 1.60 3.20

Stair S1
landing 1 2.93 0.150 0.44
1 2.51 0.150 0.38
1st flight 1 1.60 1.60
3rd flight 1 1.38 1.38
2nd flight 1 0.39 0.39

Stair S2
landing 1 7.78 0.150 1.17
1st and 2nd flight 2 1.77 3.53

1st Floors
Main Beam
Grid A-A 1 14.65 0.40 0.70 4.10
Grid B-B 1 5.43 0.40 0.70 1.52
Grid C-C 1 5.43 0.40 0.70 1.52
Grid D-D 1 5.46 0.40 0.70 1.53
Grid E-E 1 5.44 0.40 0.70 1.52
Grid F-F 1 5.44 0.40 0.70 1.52
Grid G-G 1 14.54 0.40 0.70 4.07
Grid H-H 1 13.86 0.40 0.70 3.88
Grid I-I 1 5.44 0.40 0.70 1.52
Grid J-J 1 5.92 0.40 0.70 1.66
Grid K-K 1 13.86 0.40 0.70 3.88
Grid L-L 1 13.06 0.40 0.70 3.66
Grid M-M 1 5.43 0.40 0.70 1.52
Grid N-N 1 5.43 0.40 0.70 1.52
Grid O-O 1 13.62 0.40 0.70 3.81
Grid P-P 1 0.89 0.40 0.70 0.25
Beam around th dome
Inner 1 92.20 0.40 0.65 23.97
Middle 1 129.20 0.40 0.70 36.18
Outer 1 30.75 0.40 0.70 8.61
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Secondary beam
Beam between inner & middle 1 113.39 0.40 0.70 31.75
Between Grid A & B 1 4.82 0.30 0.40 0.58
Between Grid B & C 1 4.82 0.30 0.40 0.58
Between Grid D & E 1 4.82 0.30 0.40 0.58
Between Grid E & F 1 4.82 0.30 0.40 0.58
Between Grid G & H 1 21.26 0.30 0.40 2.55
Between Grid H & I 1 4.82 0.30 0.40 0.58
Between Grid I & J 1 4.82 0.30 0.40 0.58
Between Grid J & K 1 4.82 0.30 0.40 0.58
Between Grid K & L 1 22.21 0.30 0.40 2.67
Between Grid L & M 1 4.82 0.30 0.40 0.58
Between Grid M & N 1 4.82 0.30 0.40 0.58
Between Grid N & O 1 4.82 0.30 0.40 0.58
Between Grid O & P 1 7.34 0.30 0.40 0.88
Between Grid P & A 1 23.09 0.30 0.40 2.77

Beam inside inner beam 1 95.28 0.30 0.40 11.43


Stair beam 1 5.12 0.40 0.65 1.33
1 5.33 0.40 0.65 1.39

Slab 1 1129.19 0.125 141.15

Stair
landing 2 5.10 0.125 1.28
1st and 3rd flight 2 0.51 1.03
2nd flight 1 0.53 0.53

Stair SC1
landing 1 7.78 0.150 1.17
1st and 2nd flight 2 1.60 3.20

Stair S1
landing 1 2.93 0.150 0.44
1 2.51 0.150 0.38
1st flight 1 1.60 1.60
3rd flight 1 1.38 1.38
2nd flight 1 0.39 0.39
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
2nd Floor
Main Beam
Inner 1 92.20 1.225 1.225 138.36
Around centre 1 22.30 0.55 0.55 6.75

Dome slab 1 4619.25 0.175 808.37

Total = 1900.88 m3

Torsteel reinforcement bar for R.C.C.


8 work with cutting, bending, binding &
laying with all complete.
2% of RCC work 473.85
Total= 473.85 Mt

9 Trench work open type form work ( 1.50 to 3.00 Mtr.)


Up to plinth
Footing
F1 60 3.05 0.6 109.80
F2 24 4.25 0.6 61.20
F3 24 3.65 0.6 52.56
F4 16 4.25 0.65 44.20
F5 4 4.90 0.65 12.74
F6 40 5.50 0.7 154.00
CF1 2 7.30 0.65 9.49
2 2.95 0.65 3.84
CF2 4 17.56 0.75 52.68
4 4.08 0.75 12.24

Total = 512.75

Form work shuttering & centering


(BEAM-0.30-0.80 Mtr) with (USED
10 LOCAL WOOD) all complete.
Up to plinth
Tie Beam
Grid A-A 1 13.79 0.4 5.52
2 13.79 0.7 19.31
Grid B-B 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid C-C 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid D-D 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid E-E 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid F-F 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid G-G 1 13.66 0.4 5.46
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
2 13.66 0.7 19.12
Grid H-H 1 12.97 0.4 5.19
2 12.97 0.7 18.16
Grid I-I 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid J-J 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid K-K 1 13.01 0.4 5.20
2 13.01 0.7 18.21
Grid L-L 1 12.16 0.4 4.86
2 12.16 0.7 17.02
Grid M-M 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid N-N 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid O-O 1 12.75 0.4 5.10
2 12.75 0.7 17.85
Grid P-P 1 13.79 0.4 5.52
2 13.79 0.7 19.31
Beam around th dome
Inner 1 92.20 0.4 36.88
2 92.20 0.7 129.08
Middle 1 150.32 0.4 60.13
2 150.32 0.7 210.45
Outer 1 184.36 0.4 73.74
2 184.36 0.7 258.10
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Beam at 0m level
Main Beam
Grid A-A 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Grid B-B 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid C-C 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid D-D 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid E-E 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid F-F 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid G-G 1 13.66 0.4 5.46
2 13.66 0.7 19.12
Grid H-H 1 12.97 0.4 5.19
2 12.97 0.7 18.16
Grid I-I 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid J-J 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid K-K 1 13.01 0.4 5.20
2 13.01 0.7 18.21
Grid L-L 1 12.76 0.4 5.10
2 12.76 0.7 17.86
Grid M-M 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid N-N 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid O-O 1 13.35 0.4 5.34
2 13.35 0.7 18.69
Grid P-P 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Beam around th dome
Inner 1 92.20 0.4 36.88
2 92.20 0.7 129.08
Middle 1 150.32 0.4 60.13
2 150.32 0.7 210.45
Outer 1 30.12 0.4 12.05
2 30.12 0.7 42.17
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Ground Floor
Main Beam
Grid A-A 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Grid B-B 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid C-C 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid D-D 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid E-E 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid F-F 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid G-G 1 13.66 0.4 5.46
2 13.66 0.7 19.12
Grid H-H 1 12.97 0.4 5.19
2 12.97 0.7 18.16
Grid I-I 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid J-J 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid K-K 1 13.01 0.4 5.20
2 13.01 0.7 18.21
Grid L-L 1 12.76 0.4 5.10
2 12.76 0.7 17.86
Grid M-M 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid N-N 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid O-O 1 13.35 0.4 5.34
2 13.35 0.7 18.69
Grid P-P 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Beam around th dome
Inner 1 92.20 0.4 36.88
2 92.20 0.7 129.08
Middle 1 150.32 0.4 60.13
2 150.32 0.7 210.45
Outer 1 30.12 0.4 12.05
2 30.12 0.7 42.17
Secondary beam
Beam between inner & middle 1 61.21 0.4 24.48
2 61.21 0.7 85.69
Between Grid A & B 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid B & C 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid D & E 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Between Grid E & F 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid G & H 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid H & I 1 3.16 0.3 0.95
2 3.16 0.4 2.53
Between Grid I & J 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid J & K 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid K & L 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid L & M 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid M & N 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid N & O 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid P & A 1 4.50 0.3 1.35
2 4.50 0.4 3.60
Beam between inner & middle 1 48.19 0.3 14.46
2 48.19 0.4 38.55
Beam inside inner beam 1 56.20 0.3 16.86
2 56.20 0.4 44.96
1 13.79 0.3 4.14
2 13.79 0.4 11.03
Stair beam 1 8.46 0.4 3.38
2 8.46 0.65 11.00
1 4.55 0.4 1.82
2 4.55 0.65 5.92
1 8.50 0.4 3.40
2 8.50 0.65 11.05
1 2.87 0.4 1.15
2 2.87 0.65 3.73

1st Floors
Main Beam
Grid A-A 1 14.65 0.4 5.86
2 14.65 0.7 20.51
Grid B-B 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid C-C 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid D-D 1 5.46 0.4 2.18
2 5.46 0.7 7.64
Grid E-E 1 5.44 0.4 2.18
2 5.44 0.7 7.62
Grid F-F 1 5.44 0.4 2.18
2 5.44 0.7 7.62
Grid G-G 1 14.54 0.4 5.82
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
2 14.54 0.7 20.36
Grid H-H 1 13.86 0.4 5.54
2 13.86 0.7 19.40
Grid I-I 1 5.44 0.4 2.18
2 5.44 0.7 7.62
Grid J-J 1 5.92 0.4 2.37
2 5.92 0.7 8.29
Grid K-K 1 13.86 0.4 5.54
2 13.86 0.7 19.40
Grid L-L 1 13.06 0.4 5.22
2 13.06 0.7 18.28
Grid M-M 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid N-N 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid O-O 1 13.62 0.4 5.45
2 13.62 0.7 19.07
Grid P-P 1 0.89 0.4 0.36
2 0.89 0.7 1.25
Beam around th dome
Inner 1 92.20 0.4 36.88
2 92.20 0.7 129.08
Middle 1 129.20 0.4 51.68
2 129.20 0.7 180.88
Outer 1 30.75 0.4 12.30
2 30.75 0.7 43.05

Secondary beam
Beam between inner & middle 1 113.39 0.4 45.36
2 113.39 0.7 158.75
Between Grid A & B 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid B & C 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid D & E 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid E & F 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid G & H 1 21.26 0.3 6.38
2 21.26 0.4 17.01
Between Grid H & I 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid I & J 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid J & K 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid K & L 1 22.21 0.3 6.66
2 22.21 0.4 17.77
Between Grid L & M 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Between Grid M & N 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid N & O 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid O & P 1 7.34 0.3 2.20
2 7.34 0.4 5.87
Between Grid P & A 1 23.09 0.3 6.93
2 23.09 0.4 18.47
Beam inside inner beam 1 95.28 0.3 28.58
2 95.28 0.4 76.22
Stair beam 1 5.12 0.4 2.05
2 5.12 0.65 6.66
1 5.33 0.4 2.13
2 5.33 0.65 6.93
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

2nd Floor
Main Beam
Inner 1 92.20 1.225 112.95
2 92.20 1.225 225.89
Around centre 1 22.30 0.55 12.27
2 22.30 0.55 24.53

Total = 4572.50 m2

11 Form work shuttering & centering (COLUMN) with (USED LOCAL WOOD) all complete.
Up to plinth
C 44 0.75 2 66.00
C1 4 0.75 2 6.00
C2 64 0.75 2 96.00
C3 32 1.25 2 80.00
32 0.90 2 57.60
Ground Floor
C 44 0.75 4 132.00
C1 4 0.75 4 12.00
C2 64 0.75 4 192.00
C3 32 1.25 4 160.00
32 0.90 4 115.20
1st Floors
C 44 0.75 4 132.00
C1 4 0.75 4 12.00
C2 64 0.75 4 192.00
C3 32 1.25 4 160.00
32 0.90 4 115.20
2nd Floor
C2 64 0.75 4 192.00
C3 32 1.25 4 160.00
32 0.90 4 115.20

Total = 1995.20 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

12 Form work shuttering & centering with MS pipe (prop), plyboard for slab etc
Ground Floor
Slab 1 1237.49 0.125 1237.49
1 302.89 0.125 37.86

Stair SC1
landing 1 7.78 7.78
Riser 26 1.50 0.15 5.85
1st and 2nd flight 2 6.54 13.08
4 1.50 0.245 1.47
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Riser 26 1.50 0.15 5.85
1st flight 1 6.54 6.54
2 1.50 0.245 0.74
2nd flight 1 1.60 1.60
2 1.60 0.245 0.78
3rd flight 1 5.63 5.63
2 1.40 0.245 0.69
Stair S2
landing 1 7.78 7.78
Riser 26 1.96 0.15 7.64
1st and 2nd flight 2 7.21 14.43
4 1.96 0.245 1.92

1st Floors
Slab 1 1129.19 1129.19
1 317.51 0.125 39.69

Stair SC1
landing 1 7.78 7.78
Riser 26 1.50 0.15 5.85
1st and 2nd flight 2 6.54 13.08
4 1.50 0.245 1.47
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
Riser 26 1.50 0.15 5.85
1st flight 1 6.54 6.54
2 1.50 0.245 0.74
2nd flight 1 1.60 1.60
2 1.60 0.245 0.78
3rd flight 1 5.63 5.63
2 1.40 0.245 0.69
Stair S2
landing 1 7.78 7.78
Riser 26 1.96 0.15 7.64
1st and 2nd flight 2 7.21 14.43
4 1.96 0.245 1.92

Dome slab 1 4619.25 4619.25

Total = 7237.90 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

13 First class chimney brick masonry work in (1:4) cement sand mortar in G. F.
Below Ground level
Tie Beam
Grid A-A 1 13.79 0.23 0.8 2.54
Grid B-B 1 7.89 0.23 0.8 1.45
Grid C-C 1 7.89 0.23 0.8 1.45
Grid D-D 1 7.92 0.23 0.8 1.46
Grid E-E 1 7.92 0.23 0.8 1.46
Grid F-F 1 7.89 0.23 0.8 1.45
Grid G-G 1 13.66 0.23 0.8 2.51
Grid H-H 1 12.97 0.23 0.8 2.39
Grid I-I 1 7.92 0.23 0.8 1.46
Grid J-J 1 7.89 0.23 0.8 1.45
Grid K-K 1 13.01 0.23 0.8 2.39
Grid L-L 1 12.16 0.23 0.8 2.24
Grid M-M 1 7.92 0.23 0.8 1.46
Grid N-N 1 7.89 0.23 0.8 1.45
Grid O-O 1 12.75 0.23 0.8 2.35
Grid P-P 1 13.79 0.23 0.8 2.54
Beam around th dome
Inner 1 92.20 0.23 0.8 16.96
Middle 1 150.32 0.23 0.8 27.66
Outer 1 184.36 0.23 0.8 33.92

Ground Floor
Outer wall
Grid P-P 1 17.33 0.23 4.45 17.74
Grid O-O 1 13.62 0.23 4.45 13.94
Grid G-G 1 14.06 0.23 4.45 14.39
Grid H-H 1 12.64 0.23 4.45 12.94
Grid K-K 1 13.55 0.23 4.45 13.87
Grid L-L 1 12.24 0.23 4.45 12.53

Inner wall
1 85.26 0.23 4.45 87.26
1 129.20 0.11 4.45 63.24
1 46.20 0.23 4.45 47.29
Inner wall 1 91.50 0.11 4.45 44.79
Toilet partation 1 31.70 0.11 4.45 15.52
Toilet partation 1 46.80 0.11 4.45 22.91
Deduction
inner wall opening
D1 -8 1.2 0.11 2.1 -2.218
D2 -17 1 0.11 2.1 -3.927
D3 -21 0.75 0.11 2.1 -3.638
w -4 1.5 0.11 2.4 -1.584

Total = 463.63 m3
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

14 First class chimney brick masonry work in (1:4) cement sand mortar in F. F.
First floor
Inner wall
1 135.20 0.11 4.45 66.18
Inner wall 1 54.70 0.11 4.45 26.78
Toilet partation 1 26.90 0.11 4.45 13.17
1 27.60 0.11 4.45 13.51
inner wall opening
D1 -6 1.2 0.11 2.1 -1.663
D2 -7 1 0.11 2.1 -1.617
D3 -18 0.75 0.11 2.1 -3.119

Total = 113.24 m3

15 First class chimney brick masonry work in (1:4) cement sand mortar in S. F.
Second floor
Inner wall
Inner 1 97.70 0.11 5.9 63.41
Between Grid 3 & 4 1 14.90 0.11 5.9 9.67

Total = 73.08 m3

16 25 mm or 1" thick P.C.C. (1:2:4) work in floor with all complete.


Ground Floor 1 1237.49 1237.49
1st Floors 1 1237.49 1237.49
2nd Floor 1 1129.19 1129.19

Total = 3604.17 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
17 12.5 mm. thick cement sand plaster work 1:4 on wall.
Ground Floor
Outer wall
Grid P-P 2 17.33 4.45 154.24
Grid O-O 2 13.62 4.45 121.22
Grid G-G 2 14.06 4.45 125.13
Grid H-H 2 12.64 4.45 112.50
Grid K-K 2 13.55 4.45 120.60
Grid L-L 2 12.24 4.45 108.94

Inner wall 0.00


2 85.26 4.45 758.81
2 129.20 4.45 1149.88
2 46.20 4.45 411.18
Inner wall 2 91.50 4.45 814.35
Toilet partation 2 31.70 4.45 282.13
Toilet partation 2 46.80 4.45 416.52
Deduction
inner wall opening
D1 -16 1.2 2.1 -40.32
D2 -34 1 2.1 -71.40
D3 -42 0.75 2.1 -66.15
w -8 1.5 2.4 -28.80

First floor
Inner wall
2 135.20 4.45 1203.28
Inner wall 2 54.70 4.45 486.83
Toilet partation 2 26.90 4.45 239.41
2 27.60 4.45 245.64
Deduction
inner wall opening
D1 -12 1.2 2.1 -30.24
D2 -14 1 2.1 -29.40
D3 -36 0.75 2.1 -56.70

Second floor
Inner wall
Inner 2 97.70 5.9 1152.86
Between Grid 3 & 4 2 14.90 5.9 175.82

Total plaster = 7756.32 m2

18 12.5 mm. thick cement sand plaster work 1:4 on ceilling


Ground Floor
Slab 1 1237.49 0.125 1237.49

Stair SC1
landing 1 7.78 7.78
1st and 2nd flight 2 6.54 13.08
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
1st flight 1 6.54 6.54
2nd flight 1 1.60 1.60
3rd flight 1 5.63 5.63
Stair S2
landing 1 7.78 7.78
1st and 2nd flight 2 7.21 14.43

1st Floors
Slab 1 1129.19 1129.19

Stair SC1
landing 1 7.78 7.78
1st and 2nd flight 2 6.54 13.08
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
1st flight 1 6.54 6.54
2nd flight 1 1.60 1.60
3rd flight 1 5.63 5.63
Stair S2
landing 1 7.78 7.78
1st and 2nd flight 2 7.21 14.43

Dome slab 2 4619.25 9238.50

Total= 11729.72 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
Supplying and fixing of aluminium
sliding window without ventilator section
19
101x45x1.80mm including 4mm glass
and gasket all complete
Ground Floor
outer window 1 65.17 4.45 290.01
1 28.86 1.5 43.29
1 32.76 2.25 73.71
D1 4 1.2 2.1 10.08
D2 8.5 1 2.1 17.85
D3 10.5 0.75 2.1 16.54
w 2 1.5 2.4 7.20

First floor
inner wall opening 0.00
D1 3 1.2 2.1 7.56
D2 3.5 1 2.1 7.35
D3 9 0.75 2.1 14.18

Total = 487.76 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

20 Two coat white washing work on ceilling.


Same as ceiling plaster 1 11729.72 11729.72
Total = 11729.72 m2

21 Two coat distemper painting work without primer coat.


Ground Floor
Outer wall
Grid P-P 1 17.33 4.45 77.12
Grid O-O 1 13.62 4.45 60.61
Grid G-G 1 14.06 4.45 62.57
Grid H-H 1 12.64 4.45 56.25
Grid K-K 1 13.55 4.45 60.30
Grid L-L 1 12.24 4.45 54.47

Inner wall 0.00


2 85.26 4.45 758.81
2 129.20 4.45 1149.88
2 46.20 4.45 411.18
Inner wall 2 91.50 4.45 814.35
Toilet partation 2 31.70 4.45 282.13
Toilet partation 2 46.80 4.45 416.52
Deduction
inner wall opening
D1 -16 1.2 2.1 -40.32
D2 -34 1 2.1 -71.40
D3 -42 0.75 2.1 -66.15
w -8 1.5 2.4 -28.80

First floor
Inner wall
2 135.20 4.45 1203.28
Inner wall 2 54.70 4.45 486.83
Toilet partation 2 26.90 4.45 239.41
2 27.60 4.45 245.64
Deduction
inner wall opening
D1 -12 1.2 2.1 -30.24
D2 -14 1 2.1 -29.40
D3 -36 0.75 2.1 -56.70

Second floor
Inner wall
Inner 2 97.70 5.9 1152.86
Between Grid 3 & 4 2 14.90 5.9 175.82

Dome slab 1 4619.25 4619.25

Total = 12004.26 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit
22 Two coat weather proof painting work over primer coat.
Ground Floor
Outer wall
Grid P-P 1 17.33 4.45 77.12
Grid O-O 1 13.62 4.45 60.61
Grid G-G 1 14.06 4.45 62.57
Grid H-H 1 12.64 4.45 56.25
Grid K-K 1 13.55 4.45 60.30
Grid L-L 1 12.24 4.45 54.47

Dome slab 1 4619.25 4619.25

Total = 4990.56 m2

15 mm thick marble tile 600x600 mm


26 paving with 20 mm thick cement sand
mortar 1:2 rubbing & polishing work
with all complete.
Ground Floor
Stair SC1
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S2
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
First floor
Stair SC1
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S2
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85

Total = 150.00 m2
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity Unit

26 Fabrication of steel railing with 3 row of 1" horizontal pipe and vertical post and hand rail of 2"
Ground Floor
Stair SC1 1 7.5 7.50
Stair S1 1 8.5 8.50
Stair S2 1 7.5 7.50
First floor
Stair SC1 1 7.5 7.50
Stair S1 1 8.5 8.50
Stair S2 1 7.5 7.50

Total= 47.00 Rm
Item: Quantity Estimate of Landscape
S.N. Description No. Length Breadth Height Quantity Unit

1 Clearing of grass, removing roots, breaking sods levelling the surface and disposal as per specification
1 1010 1010.00 m2

2 Surface dressing work with cutting of raised soil & filling the ditches.
At entrance 1 23.25 0.5 11.63
Raised Sitting Space 1 34.6 0.45 15.57

Total Excavation = 27.20 m3

3 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)


Parking 1 72.58 0.125 9.07

Total= 9.07 m3

4 First class chimney brick masonry work in (1:4) cement sand mortar in G. F.
Wall surrounding Flower plantation 3 6.38 0.11 0.3 0.63

Total = 0.63 m3

5 12.5 mm. thick cement sand plaster work 1:4 on wall.


Wall surrounding Flower plantation 3 6.38 0.3 5.74

Total plaster = 5.74 m2


Item: Quantity Estimate of Landscape
S.N. Description No. Length Breadth Height Quantity Unit

6 Grass turfing including cutting grass block, spraying of water and fertilizer including transportation also.
1 58.95 58.95

Total= 58.95 m2

Cement tile(Machine Made) paving work


7 in cement sand (1:4) mortar
Raised Sitting Space 1 18 18.00

Total= 18.00 m2

80mm Heavy Duty Concrete Interlocking


8 Tiles on 50 mm thick crush stone dust

Path way 1 247.30 247.30

Total= 247.30 m2
Item: Quantity Estimate of Boundary wall
S.N. Description No. Length Breadth Height Quantity Unit

1 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Bounday wall footing 1 125 0.46 0.7 40.25

Total Excavation = 40.25 m3

Earth filling work in every 15-15 cm. layer with watering & lead upto 1o.00 mtr. & proper manual
2 compaction.
Total excavation 40.25
Total filling 40% of excavation 16.10
Total 16.10 m3

3 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Boundary wall
Brick Post(300*300mm) 83 0.36 1.20 36.00
Top band 1 125 0.11 0.075 1.03
Footing band 1 125 0.23 0.075 2.16

Total = 39.19 m3

Torsteel reinforcement bar for R.C.C.


4 work with cutting, bending, binding &
laying with all complete.
1% of RCC work 3.08
Total= 3.08 Mt

5 First class chimney brick masonry work in (1:4) cement sand mortar in G. F.
Boundary wall 1 125 0.11 1.2 16.50
Brick Post(300*300mm) 83 1.2 0.11 1.2 13.20
Bounday wall footing
230 wall 1 125 0.23 0.4 11.50
Base 1 125 0.46 0.2 11.50
Total = 52.70 m3

6 12.5 mm. thick cement sand plaster work 1:4 on wall.


Boundary wall 2 125 1.2 300
Brick Post(300*300mm) 193 1.2 1.2 277.44

Total plaster = 577.44 m2


Item: Quantity Estimate of Boundary wall
S.N. Description No. Length Breadth Height Quantity Unit
7 Two coat white washing work on wall.
1 577.44 577.44
Total = 577.44 m2

8 Two coat distemper painting work without primer coat.


1 577.44 577.44
Total = 577.44 m2

9 Metal Fence
Boundary wall 1 125.00 0.60 75.00
Total = 75.00 m2
Item: Quantity Estimate of Gate
S.N. Description No. Length Breadth Height Quantity Unit

1 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
F1 2.00 1.500 1.500 1.500 6.750
Trench Wall 1.00 3.850 0.600 1.300 3.003

Total Excavation = 9.75 m3

Earth filling work in every 15-15 cm. layer with watering & lead upto 1o.00 mtr. & proper manual
2 compaction.
Total excavation 9.75
Total filling 40% of excavation 3.90
Total 3.90 m3

3 Dry flat Brick paving work


F1 2.00 1.500 1.500 4.500
Trench Wall 1.00 3.850 0.600 2.310
Total= 6.81 m2

4 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)


F1 2.00 1.500 1.500 0.075 0.338
Trench Wall 1.00 3.850 0.600 0.075 0.173

Total= 0.51 m3

5 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
For Foundation(Base) 2.00 1.500 1.500 0.200 0.900
For Foundation(Pyramid) 2.00 1.200 1.200 0.350 1.008
For Column upto plinth level 2.00 0.350 0.350 1.370 0.336
For Column above plinth level 2.00 0.350 0.350 3.060 0.750
Foundation Tie Beam 1.00 5.700 0.300 0.300 0.513
Plinth Tie Beam 1.00 5.700 0.300 0.300 0.513
Top Beam 1.00 5.700 0.300 0.300 0.513

Total = 4.53 m3
Item: Quantity Estimate of Gate
S.N. Description No. Length Breadth Height Quantity Unit
Torsteel reinforcement bar for R.C.C.
6 work with cutting, bending, binding &
laying with all complete.
2% of RCC work 0.71
Total= 0.71 Mt

7 Trench work open type form work ( 1.50 to 3.00 Mtr.)


Foundation 2.00 6.100 0.200 2.440
Total = 2.44

Form work shuttering & centering


(BEAM-0.30-0.80 Mtr) with (USED
8 LOCAL WOOD) all complete.
Foundation Tie Beam 1 5.700 0.3 1.71
2 5.700 0.3 3.42
Plinth Tie Beam 1 5.700 0.3 1.71
2 5.700 0.3 3.42
Top Beam 1 5.700 0.3 1.71
2 5.700 0.3 3.42

Total = 15.39 m2

9 Form work shuttering & centering (COLUMN) with (USED LOCAL WOOD) all complete.
For Column upto plinth level 2.00 1.400 1.370 3.836
For Column above plinth level 2.00 1.400 3.060 8.568

Total = 12.40 m2

10 First class chimney brick masonry work in (1:4) cement sand mortar in G. F.
Plinth Wall 1.00 5.700 0.250 3.100 4.418
Wall on top 1.00 6.100 0.300 1.000 1.830
Total = 6.25 m3
Item: Quantity Estimate of Gate
S.N. Description No. Length Breadth Height Quantity Unit
11 12.5 mm. thick cement sand plaster work 1:4 on wall.
2.00 1.200 1.370 3.288
On Top of Column 2.00 0.600 0.600 0.720
On Top wall 1.00 6.100 0.300 1.830

Total plaster = 5.84 m2

12 Two coat white washing work on wall.


In wall (Outer+ Inner wall)
Same as plaster 1 5.84 5.84
Total = 5.84 m2

13 Two coat weather proof painting work over primer coat.


(Outer wall) 1 5.84 5.84
Total = 5.84 m2

Providing and fixing Iron gate 16 guage


(with frame 50 mm X 50 mm X 5 mm)
ready made and applying red oxide paint
14 with labour cost and all neccesary
fittings as per specification and as per
instructed.

1.00 5.000 1.860 9.300


Total = 9.30 Sqm
Item: Quantity Estimate of Water tank
S.N. Description No. Length Breadth Height Quantity Unit

1 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Water Tank 1 4.46 2.46 1.46 16.02

Total Excavation = 16.02 m3

Earth filling work in every 15-15 cm. layer with watering & lead upto 1o.00 mtr. & proper manual
2 compaction.
Total excavation 16.02
Total filling 30% of excavation 4.81
Total 4.81 m3

3 Dry flat Brick paving work


1 4.46 2.46 10.97

Total= 10.97 m2
Item: Quantity Estimate of Water tank
S.N. Description No. Length Breadth Height Quantity Unit

4 R.R. stone masonry work in cement sand (1:6) mortar


Long wall 2 4.46 0.23 1.4 2.87
Short wall 2 2.00 0.23 1.4 1.29

Total= 4.16 m3

5 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Water Tank
On Floor 1 4.00 2.00 0.1 0.80
On wall
Long wall 2 4.00 0.10 1.2 0.96
Short wall 3 1.80 0.10 1.20 0.65

Total = 2.41 m3
Item: Quantity Estimate of Water tank
S.N. Description No. Length Breadth Height Quantity Unit
Torsteel reinforcement bar for R.C.C.
6 work with cutting, bending, binding &
laying with all complete.
10 mm dia 100 mm C/C
Long side 38 4.4 167.20
Short side 19 6.4 121.60
Partition portion 19 1.5 28.50
Overlap 60 dia 28 0.6 16.80
334.10 m
Unit weight 0.62 kg/m 207.14 Kg
8 mm dia 100 mm C/C
Cover of tank
Long side 38 2 76.00
Short side 19 4 76.00
Overlap 60 dia 13 0.48 6.24
158.24 m
Unit weight 0.39 kg/m 61.71 Kg

Total= 0.27 Mt

Form work shuttering & centering


7 (BEAM-0.30-0.80 Mtr) with (USED
LOCAL WOOD) all complete.
Water Tank
On wall
Long wall 2 3.80 1.2 9.12
Short wall 4 1.80 1.5 10.80
For Cover 1 4.00 2 8.00

Total = 27.92 m2
Item: Quantity Estimate of Water tank
S.N. Description No. Length Breadth Height Quantity Unit
8 12.5 mm. thick cement sand plaster work 1:4 on wall.
Water Tank
On floor 1 4.00 2 8.00
On wall
Long wall 2 3.80 1.2 9.12
Short wall 4 1.80 1.2 8.64

Total plaster = 25.76 m2


Item: Quantity Estimate of Water tank
S.N. Description No. Length Breadth Height Quantity Unit

9 3 mm thick neat cement punning work.


Water Tank
On floor 1 4.00 2.00 8.00
On wall
Long wall 2 3.80 1.2 9.12
Short wall 4 1.80 1.2 8.64

Total= 25.76 m2
Item: Quantity Estimate of Soakpit
S.N. Description No. Length Breadth Height Quantity Unit

1 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
1 9.07 1.8 16.33

Total Excavation = 16.33 m3

2 Dry flat Brick paving work


Floor 1 9.07 9.07
Total= 9.07 m2
Item: Quantity Estimate of Soakpit
S.N. Description No. Length Breadth Height Quantity Unit
3 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
slab 1 3.14 0.125 0.39

Total = 0.39 m3
Item: Quantity Estimate of Soakpit
S.N. Description No. Length Breadth Height Quantity Unit
Torsteel reinforcement bar for R.C.C.
4 work with cutting, bending, binding &
laying with all complete.
8 mm dia 100 mm C/C
On cover both side 2 21.46 42.92 m
Unit weight 0.39 kg/m 16.74
Total= 0.02 Mt
Item: Quantity Estimate of Soakpit
S.N. Description No. Length Breadth Height Quantity Unit
5 Form work shuttering & centering with MS pipe (prop), plyboard for slab etc
Slab 1 3.14 3.14
1 7.10 0.125 5.58

Total = 8.72 m2

6 R.R. stone masonry work in cement sand (1:6) mortar


1 3.14 1.32 4.14
-1 2.54 1.32 -3.35

Total = 0.79 m3

7 Sand filling work with watering & proper manual compaction.


1 2.63 1.8 4.73
-1 1.65 1.8 -2.97

Total = 1.76 m3
Item: Quantity Estimate of Manhole
S.N. Description No. Length Breadth Height Quantity Unit

1 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
3 1.56 1.56 1.22 8.91
For pipe laying 1 50.00 0.90 1 45.00

Total Excavation = 53.91 m3

2 Dry flat Brick paving work

3 1.56 1.56 7.30

Total= 7.30 m2
Item: Quantity Estimate of Manhole
S.N. Description No. Length Breadth Height Quantity Unit

3 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)


3 1.56 1.56 0.1 0.73

Total= 0.73 m3
Item: Quantity Estimate of Manhole
S.N. Description No. Length Breadth Height Quantity Unit
4 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
3 1.60 1.6 0.1 0.77

Total = 0.77 m3
Item: Quantity Estimate of Manhole
S.N. Description No. Length Breadth Height Quantity Unit
Torsteel reinforcement bar for R.C.C.
5 work with cutting, bending, binding &
laying with all complete.
8 mm dia 100 mm C/C (Both Side) 32 1.6 51.20
Unit weight 0.39 kg/m 19.97
3 nos manhole 59.90

Total= 0.06 Mt
Item: Quantity Estimate of Manhole
S.N. Description No. Length Breadth Height Quantity Unit
6 Form work shuttering & centering with MS pipe (prop), plyboard for slab etc
base and cover side 6 4.24 0.1 2.54
cover 3 0.60 0.6 1.08

Total = 3.62 m2

7 R.R. stone masonry work in cement sand (1:6) mortar


3 3.32 0.23 1.05 2.41

Total = 2.41 m3
Item: Quantity Estimate of Manhole
S.N. Description No. Length Breadth Height Quantity Unit
8 12.5 mm. thick cement sand plaster work 1:4 on wall.
base 3 1.06 1.06 3.37
Side 12 0.60 1.05 7.56

Total plaster = 10.93 m2

9 3 mm thick neat cement punning work.


1 10.93 10.93

Total = 10.93 m2
Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit

1 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
1 3.90 2.90 1.75 19.79

Total Excavation = 19.79 m3

2 Dry flat Brick paving work


1 3.90 2.90 11.31
Total= 11.31 m2
Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit

3 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)


1 3.90 2.90 0.075 0.85

Total= 0.85 m3
Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit
4 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Base 1 3.90 2.9 0.15 1.70
Cover 1 3.90 2.9 0.075 0.85

Total = 2.54 m3
Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit
Torsteel reinforcement bar for R.C.C.
5 work with cutting, bending, binding &
laying with all complete.
8 mm dia 100 mm C/C
In cover
Long Side 29 3 87.00
Short Side 21 4 84.00
Overlap 60 dia 13 0.48 6.24
177.24 m
Unit weight 0.39 kg/m 69.12
Total= 0.07 Mt
Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit
6 Form work shuttering & centering with MS pipe (prop), plyboard for slab etc
Cover 1 3.9 2.9 11.31
Cover side 1 13.60 0.1 1.36

Total = 12.67 m2

7 R.R. stone masonry work in cement sand (1:6) mortar


Side Wall
First step
Long wall 2 3.75 0.6 0.3 1.35
Short wall 2 1.55 0.6 0.3 0.56
Second step
Long wall 2 3.45 0.45 0.3 0.93
Short wall 2 1.55 0.45 0.3 0.42
Third step
Long wall 2 3.25 0.35 0.3 0.68
Short wall 2 1.55 0.35 0.3 0.33
Fourth Step
Long wall 2 3.00 0.23 0.75 1.04
Short wall 2 1.55 0.23 0.75 0.53
Baffle wall 1 1.55 0.2300 1.5 0.53

Total = 6.37 m3
Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit
8 12.5 mm. thick cement sand plaster work 1:4 on wall.
Base 1 2.55 1.55 3.95
Wall 1 11.00 1.6 17.60
Baffle wall 2 1.55 1.5 4.65
Top of baffle wall 1 1.50 0.23 0.35

Total plaster = 26.55 m2


Item: Quantity Estimate of Septic Tank
S.N. Description No. Length Breadth Height Quantity Unit

9 3 mm thick neat cement punning work.


1 26.55 26.55

Total= 26.55 m2
Item:Unit Rate
Civil Works
S.N. Description Unit Rate (NRs.)
SITE PREPARATION WORK
Cutting of tree, branch & log etc. (12-30 cm. girth above 1.00 mtr. From
1 Nos. 109.88
G.L.) with lead upto 15 mtr.
Cutting of tree, branch & log etc. (31-60 cm. girth above 1.00 mtr. From
2 Nos. 329.64
G.L.) with lead upto 15 mtr.
Cutting of tree, branch & log etc. (61-120 cm. girth above 1.00 mtr. From
3 Nos. 828.34
G.L.) with lead upto 15 mtr.
Removing of tree root (12-30 cm. girth above 1.00 mtr. From G.L.) with
4 Nos. 338.10
lead upto 15 mtr.
Removing of tree root (31-60 cm. girth above 1.00 mtr. From G.L.) with
5 Nos. 447.98
lead upto 15 mtr.
Removing of tree root (61-120 cm. girth above 1.00 mtr. From G.L.) with
6 Nos. 2,130.03
lead upto 15 mtr.
Cutting of grass, taking of root & brocken of uplecutting of raised soil &
7 Sqm. 19.44
site leveling with all complete
8 Surface dressing work with cutting of raised soil & filling the ditches. sqm. 8.45
9 Soil test, digging bor hole,sample collection & testing all complete. Nos. 56,072.85
EARTH & SAND WORK
Earth work excavation in foundation in clay & silty soft soil lead upto 10
10 Cum. 497.49
mtr. & lift 1.5 mtr.
Earth work excavation in foundation in clay & soft murram stone (30 cm.)
11 Cum. 696.48
hard soil lead upto 10 mtr. & lift 1.5 mtr.
Earth filling work in every 15-15 cm. layer with watering & lead upto
12 Cum. 603.75
1o.00 mtr. & proper manual compaction.
Earth filling (Earth transported from 5 Km. surronding) work in every 15-
13 Cum. 1,399.03
15 cm. layer with watering & proper manual compaction.
Earth filling work in every 15-15 cm. layer without watering & proper
14 Cum. 211.31
manual compaction.
Earth filling (Earth transported from 5 Km. surronding) work in every 15-
15 Cum. 1,055.98
15 cm. layer without watering & proper manual compaction.
16 Sand filling work with watering & proper manual compaction. Cum. 3,692.70
Gravel Sand mixed (agg-50% + sand 50%) filling work with proper
17 Cum. 3,733.18
manual compaction.
18 Pumping of water from foundation or trench 1000 ltr 34.50
19 Compaction of filled earth by 8-10 M.T. roller in 20/20 cm layer Cum. 21.12
Earth work excavation in foundation in SOFT SOIL(USED 0.80 CUM.
20 Cum. 79.93
CAPACITY Hydraulic EXCAVATOR)
Earth work excavation in foundation in HARD SOIL USED 0.80 CUM.
21 Cum. 99.19
CAPACITY Hydraulic EXCAVATOR)

22 Earth work excavation in foundation in HARD SOIL Used 0.80 Cum 99.19
capecity Hydraulic excavator Cum.
Item:Unit Rate
Civil Works
S.N. Description Unit Rate (NRs.)
MASONRY WORK
First class chimney brick masonry work in (1:3) cement sand mortar in G.
23 Cum. 14,102.79
F.
First class chimney brick masonry work in (1:3) cement sand mortar in F.
24 Cum. 14,724.65
F.
First class chimney brick masonry work in (1:3) cement sand mortar in S.
25 Cum. 15,595.26
F.

26 First class chimney brick masonry work in (1:4) cement sand mortar in 13,589.09
G. F. Cum.
First class chimney brick masonry work in (1:4) cement sand mortar in F.
27 Cum. 14,210.95
F.
First class chimney brick masonry work in (1:4) cement sand mortar in S.
28 Cum. 15,081.56
F.

29 First class chimney brick masonry work in (1:6) cement sand mortar in 13,099.99
G. F. Cum.
30 First class chimney brick masonry work in (1:6) cement sand mortar in F. 13,721.85
F. Cum.
31 First class chimney brick masonry work in (1:6) cement sand mortar in S 14,592.46
F. Cum.
32 First class chimney brick masonry work in mud mortar in G. F. Cum. 10,253.51
33 First class chimney brick masonry work in mud mortar in F. F. Cum. 10,875.37
34 First class chimney brick masonry work in mud mortar in S. F. Cum. 11,745.98
35 R.R. stone masonry work in cement sand (1:3) mortar Cum. 13,188.43
36 R.R. stone masonry work in cement sand (1:4) mortar Cum. 12,641.95
37 R.R. stone masonry work in cement sand (1:6) mortar Cum. 11,742.88
38 Stone filling in trench with proper leveling Cum. 3,958.87
CEMENT CONCRETE WORK
39 P.C.C. (1:4:8) work in foundation, wall (River bed) Cum. 12,686.14
40 P.C.C. (1:3:6) work in foundation, wall (River bed) Cum. 13,584.52
41 P.C.C. (1:2:4) work in foundation, wall (River bed) Cum. 15,120.52
42 P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (River bed) Cum. 17,414.77
43 P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (River bed) Cum. 18,857.75
44 P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (River bed) Cum. 22,618.15
45 P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall (River bed) Cum. 12,992.96
46 P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall (River bed) Cum. 14,688.88

47 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc 16,105.86
(River bed) Cum.
48 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc 19,866.26
(River bed) Cum.
49 P.C.C. (1:1:2) for R.C.C. work in slab (River bed) with micro silica & 41,266.89
super plasticiser Cum.
Item:Unit Rate
Civil Works
S.N. Description Unit Rate (NRs.)
50 P.C.C. (1:4:8) work in foundation, wall (crushed or stone ballast) Cum. 12,686.14
51 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast) Cum. 13,584.52
52 P.C.C. (1:2:4) work in foundation, wall (crushed or stone ballast) Cum. 15,120.52

53 17,414.77
P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (crushed or stone ballast) Cum.
54 P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (crushed or stone 18,857.75
ballast) Cum.
55 22,618.15
P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (crushed or stone ballast) Cum.
56 P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall (crushed or 12,992.96
stone ballast) Cum.
57 P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall (crushed or 14,688.88
stone ballast) Cum.
58 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc 16,105.86
(crushed or stone ballast) Cum.
59 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc 19,866.26
(crushed or stone ballast) Cum.
60 P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone ballast) with 41,266.89
micro silica & super plasticiser Cum.
61 P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone ballast) with 41,266.89
micro silica & super plasticiser Cum.
62 Torsteel reinforcement bar for R.C.C. work with cutting, bending, binding 115.02
& laying with all complete. Kg.
FORM & PROPS WORK
63 Form work shuttering & centering (COLUMN) with (USED LOCAL 1,864.41
WOOD) all complete. Sqm.
64 Form work shuttering & centering (COLUMN) with (USED PLY 710.88
WOOD) all complete. Sqm.
65 Form work shuttering & centering (BEAM-0.30 Mtr) with (USED 1,344.25
LOCAL WOOD) all complete. Sqm.
66 Form work shuttering & centering (BEAM-0.30-0.80 Mtr) with (USED 1,014.60
LOCAL WOOD) all complete. Sqm.
67 Form work shuttering & centering (COLUMN) with (USED PLY 1,514.59
WOOD) all complete. Sqm.
68 Form work shuttering & centering with MS pipe (prop), plyboard for slab 1,241.52
etc Sqm.
69 Form work shuttering & centering with Bamboo, plyboard for slab etc Sqm. 1,018.58
70 Trench work open type form work (up to 1.50 Mtr.) Sqm. 806.12
71 Trench work open type form work ( 1.50 to 3.00 Mtr.) Sqm. 815.48
72 Trench work open type form work (above 3.00 Mtr.) Sqm. 827.85
Item:Unit Rate
Civil Works
S.N. Description Unit Rate (NRs.)
ROOFING WORK
73 26 (M) 0.50 mm thick Colour G.I. sheet roofing work Sqm 1,567.18

74 150 mm breadth upto 450 mm G. I. plane sheet Gutter fixing work with 1,865.47
3x40 mm M.S. bracke,t nut bolt & washer . Rmtr.
75 Providing and laying Clay tile roofing work sqm. 1,043.67
76 Providing and laying Clay tile ridge cover Rmtr. 650.80
FLOORING WORK
25 mm or 1" thick P.C.C. (1:2:4) work in floor with all complete.
77 Sqm. 551.82
38 mm or 1½" thick P.C.C. (1:2:4) work in floor with all complete.
78 50 mm or 2" thick P.C.C. (1:2:4) work in floor with all complete. Sqm. 755.78
79 Sqm. 926.03
80 75 mm or 3" thick P.C.C. (1:2:4) work in floor with all complete. Sqm. 1,253.43

81 15 mm thick marble tile 600x600 mm paving with 20 mm thick cement 3,921.07


sand mortar 1:2 rubbing & polishing work with all complete. Sqm.
82 Porcelain glazed tile paving work in cement sand (1:4) mortar Sqm. 3,262.34
83 Porcelain Non-glazed tile paving work in cement sand (1:4) mortar Sqm. 3,126.23
84 Dry flat Brick paving work Sqm. 892.34
86 3 mm thick neat cement punning work. Sqm. 1,153.56
PLASTER & POINTING WORK
90 12.5 mm. thick cement sand plaster work 1:3 on wall. Sqm. 427.61
91 12.5 mm. thick cement sand plaster work 1:4 on wall. Sqm. 417.17
92 12.5 mm. thick cement sand plaster work 1:6 on wall. Sqm. 392.46
93 20 mm. thick cement sand plaster work 1:3 on wall etc. Sqm. 555.70
94 20 mm. thick cement sand plaster work 1:4 on wall etc. Sqm. 536.01
95 20 mm. thick cement sand plaster work1:6 on wall etc. Sqm. 497.46
96 12.5 mm. thick cement sand plaster work (1:3 ) on ceilling Sqm. 497.64
97 12.5 mm. thick cement sand plaster work 1:4 on ceilling Sqm. 487.20
98 Flush pointing works in 1:1 Cement sand mortar on Brick masonry wall Sqm. 290.74

99 273.82
Flush pointing works in 1:2 Cement sand mortar on Brick masonry work Sqm.
100 Flush pointing works in 1:3 Cement sand mortar on Brick masonry wall Sqm. 264.86
PAINTING WORK
101 Two coat white washing work on wall. Sqm. 38.03
102 Two coat white washing work on ceilling. Sqm. 44.88
103 One coat distemper painting work without primer coat. Sqm. 61.23
104 Two coat distemper painting work without primer coat. Sqm. 113.71
105 One coat weather proof painting work over primer coat. Sqm. 163.71
106 Two coat weather proof painting work over primer coat. Sqm. 246.66
107 One coat weather proof painting work without primer coat. Sqm. 100.85
108 Two coat weather proof painting work without primer coat. Sqm. 183.80
109 One coat white cement paint painting work . Sqm. 46.62
110 Two coat white cement paint painting work . Sqm. 121.60

111 192.59
One coat water proof cement paint painting work in plastered surface Sqm.
112 334.67
Two coat water proof cement paint painting work in plastered surface Sqm.
Item:Unit Rate
Civil Works
S.N. Description Unit Rate (NRs.)
Misclenious Work
Supplying and fixing of Casement door of aluminium section in naturally
121 anodized color section size 101x45x1.50mm and 5mm glass Sqm. 12,966.25

Supplying and fixing of swing door of aluminium section in naturally


122 anodized color section size 101x45x1.50mm and 5mm glass Sqm. 9,136.83
Providing and fi:ring ofaluminium windows ofsection (102 sc.ics) 1.2 mm
123 th Fitted \rilh 5 nr]n clear glass without fly ncsh shuttcr ($indow size Sqm. 8,166.84
6'X4'6" or 27 sqft / rvindor'r)
Rate Analysis
A - SITE PREPARATION WORK

Cutting of tree, branch & log etc. (12-30 cm. girth above 1.00 mtr.
A1 (1-1A) From G.L.) with lead upto 15 mtr. Nos. 95.55 109.88
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.130 Nos. 735.00 95.55
Total 95.55
Rate analysis for : 1.00 No. 15 % Contractor overhead 14.33
Grand Total 109.88

Cutting of tree, branch & log etc. (31-60 cm. girth above 1.00 mtr.
A1 (1-1B) From G.L.) with lead upto 15 mtr. Nos. 286.65 329.64

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.390 Nos. 735.00 286.65
Total 286.65
Rate analysis for : 1.00 No. 15 % Contractor overhead 42.99
Grand Total 329.64

Cutting of tree, branch & log etc. (61-120 cm. girth above 1.00 mtr.
A1 (1-1C) From G.L.) with lead upto 15 mtr. Nos. 720.30 828.34
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.980 Nos. 735.00 720.30
Total 720.30
Rate analysis for : 1.00 No. 15 % Contractor overhead 108.04
Grand Total 828.34

Removing of tree root (12-30 cm. girth above 1.00 mtr. From G.L.)
A2 (1-2A) with lead upto 15 mtr. Nos. 294.00 338.10

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.400 Nos. 735.00 294.00
Total 294.00
Rate analysis for : 1.00 No. 15 % Contractor overhead 44.10
Grand Total 338.10

Removing of tree root (31-60 cm. girth above 1.00 mtr. From G.L.)
A2 (1-2B) with lead upto 15 mtr. Nos. 389.55 447.98

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.530 Nos. 735.00 389.55
Total 389.55
Rate analysis for : 1.00 No. 15 % Contractor overhead 58.43
Grand Total 447.98

Removing of tree root (61-120 cm. girth above 1.00 mtr. From G.L.)
A2 (1-2C) with lead upto 15 mtr. Nos. 1,852.20 2,130.03

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 2.520 Nos. 735.00 1,852.20
Total 1,852.20
Rate analysis for : 1.00 No. 15 % Contractor overhead 277.83
Grand Total 2,130.03

Cutting of grass, taking of root & brocken of uplecutting of raised


A3 soil & site leveling with all complete Sqm. 16.90 19.44

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.230 Nos. 735.00 169.05
Total 169.05
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 25.35
Grand Total 194.40
Rate Analysis
Surface dressing work with cutting of raised soil & filling the
A4 ditches. sqm. 7.35 8.45

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.010 Nos. 735.00 7.35
Total 7.35
Rate analysis for : 1.00 Sqm. 15 % Contractor overhead 1.10
Grand Total 8.45

Soil test, digging bor hole,sample collection & testing all complete.
A7 Nos. 48,759.00 56,072.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Skilled 1.000 Nos. 1,050.00 1,050.00
Unskilled 2.000 Nos. 735.00 1,470.00
Engineer 4.000 Nos. 970.00 3,880.00
Helper 1.000 Nos. 1,050.00 1,050.00
Collection bag 15.000 Nos. 20.60 309.00
Lab equipment:-(Sieve Analyusis,
Hydrometer Analysis, Atterberg's Limit,
Specific Gravity, Natural Moisture
Content, Direct Shear Test, Unconfined
Compression Test, Conlolidation Test,
Conducting SPT at 1.5m interval using
auto trip hammer syster including
collection of samples, sealing etc,
Retrieving undisturbed samples for
consolidation and shear strength tests for
per BH.
1.000 L.S 20,000.00 20,000.00 L.S.
Assistant lab equipment with agar ( ls 2000.00
per hr.) 8.000 Hour 2,000.00 16,000.00
Report, writing & submission 1.000 Nos. 5,000.00 5,000.00
Total 48,759.00
Rate analysis for : 1.00 Nos. 15 % Contractor overhead 7,313.85
Grand Total 56,072.85

B - EARTH & SAND WORK

Earth work excavation in foundation in clay & silty soft soil lead upto
B1 (2-1) 10 mtr. & lift 1.5 mtr. Cum. 432.60 497.49
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 0.700 Nos. 600.00 420.00
Materials T&P 3 % of labour 12.60
Total 432.60
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 64.89
Grand Total 497.49
Rate Analysis
Earth work excavation in foundation in clay & soft murram stone (30
B1 (2-2) cm.) hard soil lead upto 10 mtr. & lift 1.5 mtr. Cum. 605.64 696.48

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.800 Nos. 735.00 588.00
Materials T&P 3 % of labour 17.64
Total 605.64
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 90.84
Grand Total 696.48

Earth filling work in every 15-15 cm. layer with watering & lead
B2 (2-25A) upto 1o.00 mtr. & proper manual compaction. Cum. 525.00 603.75

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.500 Nos. 1,050.00 525.00
Total 525.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 78.75
Grand Total 603.75

Earth filling (Earth transported from 5 Km. surronding) work in


B2 (2-25A) every 15-15 cm. layer with watering & proper manual compaction. Cum. 1,216.55 1,399.03

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.500 Nos. 735.00 367.50
Mud 1.500 Cum. 565.00 847.50
Materials
Water 5.000 Ltr. 0.31 1.55
Total 1,216.55
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 182.48
Grand Total 1,399.03

Earth filling work in every 15-15 cm. layer without watering &
B2 (2-25B) proper manual compaction. Cum. 183.75 211.31

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.250 Nos. 735.00 183.75
Total 183.75
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 27.56
Grand Total 211.31

Earth filling (Earth transported from 5 Km. surronding) work in


B2 (2-25B) every 15-15 cm. layer without watering & proper manual Cum. 918.25 1,055.98
compaction.

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.250 Nos. 735.00 183.75
Materials Mud 1.300 Cum. 565.00 734.50
Total 918.25
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 137.73
Grand Total 1,055.98

Sand filling work with watering & proper manual compaction.


B3 (2-42A) Cum. 3,211.05 3,692.70

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.700 Nos. 735.00 514.50
Sand local 1.100 Cum. 2,450.00 2,695.00
Materials
Water 5.000 Cum. 0.31 1.55
Total 3,211.05
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 481.65
Grand Total 3,692.70
Rate Analysis
Gravel Sand mixed (agg-50% + sand 50%) filling work with proper
B3 (2-42B) manual compaction. Cum. 3,246.25 3,733.18

Resources Level/Type Quantity Unit Rate Amount Remarks


Labour Unskilled 0.750 Nos. 735.00 551.25
Materials Gravel (sand mixed) 1.100 Cum. 2,450.00 2,695.00
Total 3,246.25
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 486.93
Grand Total 3,733.18

Pumping of water from foundation or trench


B4 (2-34) 1000 ltr 30.00 34.50

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Water pump 0.500 Hour 300.00 150.00
Total 150.00
Rate analysis for : 5000.00 Ltr. 15 % Contractor overhead 22.50
Grand Total 172.50

Compaction of filled earth by 8-10 M.T. roller in 20/20 cm layer


B5 Cum. 18.37 21.12

Resources Level/Type Quantity Unit Rate Amount Remarks


Equipment Road roller 8-10 M.T. 1.670 Hour 1,100.00 1,837.00
Total 1,837.00
Rate analysis for : 100.00 Cum. 15 % Contractor overhead 275.55
Grand Total 2,112.55

Earth work excavation in foundation in SOFT SOIL(USED 0.80


B7 CUM. CAPACITY Hydraulic EXCAVATOR) Cum. 69.51 79.93

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1248 Ltr. 85.00 10.60
Equipment Hydraulic Excavator 0.80 Cum. 0.0104 Hour 5,665.00 58.91
Total 69.51
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 10.42
Grand Total 79.93

Earth work excavation in foundation in HARD SOIL USED 0.80


B7 CUM. CAPACITY Hydraulic EXCAVATOR) Cum. 86.26 99.19

Resources Level/Type Quantity Unit Rate Amount Remarks


Materials Diesel 0.1500 Ltr. 103.00 15.45
Equipment Hydraulic Excavator 0.80 Cum. 0.0125 Hour 5,665.00 70.81
Total 86.26
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 12.93
Grand Total 99.19
Rate Analysis

C - MASONRY WORK

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
mortar in G. F. Cum. 12,263.30 14,102.79
5-2A)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled ( for Scaffolding ) 0.200 Nos. 1,050.00 210.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.130 M.T. 15,500.00 2,015.00
Materials Sand 0.270 Cum. 2,450.00 661.50
Water 150.000 Ltr. 0.31 46.50
Scaffolding material 3 % of Scaffolding labour 6.30
Total 12,263.30
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,839.49
Grand Total 14,102.79

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
mortar in F. F. Cum. 12,804.05 14,724.65
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled 0.700 Nos. 1,050.00 735.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.130 M.T. 15,500.00 2,015.00
Materials Sand 0.270 Cum. 2,450.00 661.50
Water 150.000 Ltr. 0.31 46.50
Scaffolding material 3 % of Scaffolding labour 22.05
Total 12,804.05
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,920.60
Grand Total 14,724.65

C2(5-1-B1 & First class chimney brick masonry work in (1:3) cement sand
mortar in S. F. Cum. 13,561.10 15,595.26
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled 1.400 Nos. 1,050.00 1,470.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.130 M.T. 15,500.00 2,015.00
Materials Sand 0.270 Cum. 2,450.00 661.50
Water 150.000 Ltr. 0.31 46.50
Scaffolding material 3 % of Scaffolding labour 44.10
Total 13,561.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,034.16
Grand Total 15,595.26

C2( 5-1-B2 & First class chimney brick masonry work in (1:4) cement sand
mortar in G. F. Cum. 11,816.60 13,589.09
5-2A)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled ( for Scaffolding ) 0.200 Nos. 1,050.00 210.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.100 M.T. 15,500.00 1,550.00
Materials Sand 0.280 Cum. 2,450.00 686.00
Water 130.000 Ltr. 0.31 40.30
Scaffolding material 3 % of Scaffolding labour 6.30
Total 11,816.60
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,772.49
Grand Total 13,589.09
Rate Analysis

C25-1-B2 & First class chimney brick masonry work in (1:4) cement sand
mortar in F. F. Cum. 12,357.35 14,210.95
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled 0.700 Nos. 1,050.00 735.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.100 M.T. 15,500.00 1,550.00
Materials Sand 0.280 Cum. 2,450.00 686.00
Water 130.000 Ltr. 0.31 40.30
Scaffolding material 3 % of Scaffolding labour 22.05
Total 12,357.35
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,853.60
Grand Total 14,210.95

C2(5-1-B2 & First class chimney brick masonry work in (1:4) cement sand
mortar in S. F. Cum. 13,114.40 15,081.56
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled 1.400 Nos. 1,050.00 1,470.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.100 M.T. 15,500.00 1,550.00
Materials Sand 0.280 Cum. 2,450.00 686.00
Water 130.000 Ltr. 0.31 40.30
Scaffolding material 3 % of Scaffolding labour 44.10
Total 13,114.40
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,967.16
Grand Total 15,081.56

C2(5-1-B3 & First class chimney brick masonry work in (1:6) cement sand
mortar in G. F. Cum. 11,391.30 13,099.99
5-2A)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.5000 Nos. 1,050.00 1,575.00
Labour Unskilled 2.2000 Nos. 735.00 1,617.00
Unskilled ( for Scaffolding ) 0.2000 Nos. 1,050.00 210.00
Brick chimney 438.0000 Nos. 14.00 6,132.00
Cement 0.0700 M.T. 15,500.00 1,085.00
Materials Sand 0.3000 Cum. 2,450.00 735.00
Water 100.0000 Ltr. 0.31 31.00
3 % of Scaffolding labour 6.30
Total 11,391.30
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,708.69
Grand Total 13,099.99

C2(5-1-B3 & First class chimney brick masonry work in (1:6) cement sand
mortar in F. F. Cum. 11,932.05 13,721.85
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled 0.700 Nos. 1,050.00 735.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.070 M.T. 15,500.00 1,085.00
Materials Sand 0.300 Cum. 2,450.00 735.00
Water 100.000 Ltr. 0.31 31.00
Scaffolding material 3 % of Scaffolding labour 22.05
Total 11,932.05
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,789.80
Grand Total 13,721.85
Rate Analysis

C2( 5-1-B3 & First class chimney brick masonry work in (1:6) cement sand
mortar in S F. Cum. 12,689.10 14,592.46
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour Unskilled 2.200 Nos. 735.00 1,617.00
Unskilled 1.400 Nos. 1,050.00 1,470.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Cement 0.070 M.T. 15,500.00 1,085.00
Materials Sand 0.300 Cum. 2,450.00 735.00
Water 100.000 Ltr. 0.31 31.00
Scaffolding material 3 % of Scaffolding labour 44.10
Total 12,689.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,903.36
Grand Total 14,592.46

C2(5-1-B6 & First class chimney brick masonry work in mud mortar in G. F.
Cum. 8,916.10 10,253.51
5-2A)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labour Unskilled 1.700 Nos. 735.00 1,249.50
Unskilled 0.200 Nos. 1,050.00 210.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Mud 0.420 Cum. 565.00 237.30
Materials
Water 100.000 Ltr. 0.31 31.00
Scaffolding material 3 % of Scaffolding labour 6.30
Total 8,916.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,337.41
Grand Total 10,253.51

C2( 5-1-B6 & First class chimney brick masonry work in mud mortar in F. F.
Cum. 9,456.85 10,875.37
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labour Unskilled 1.700 Nos. 735.00 1,249.50
Unskilled 0.700 Nos. 1,050.00 735.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Mud 0.420 Cum. 565.00 237.30
Materials
Water 100.000 Ltr. 0.31 31.00
Scaffolding material 3 % of Scaffolding labour 22.05
Total 9,456.85
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,418.52
Grand Total 10,875.37

C2(5-1-B6 & First class chimney brick masonry work in mud mortar in S. F.
Cum. 10,213.90 11,745.98
5-2B)
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labour Unskilled 1.700 Nos. 735.00 1,249.50
Unskilled 1.400 Nos. 1,050.00 1,470.00
Brick chimney 438.000 Nos. 14.00 6,132.00
Mud 0.420 Cum. 565.00 237.30
Materials
Water 100.000 Ltr. 0.31 31.00
Scaffolding material 3 % of Scaffolding labour 44.10
Total 10,213.90
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,532.08
Grand Total 11,745.98
Rate Analysis

R.R. stone masonry work in cement sand (1:3) mortar


C6( 6-1-1A) Cum. 11,468.20 13,188.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 1,050.00 1,575.00
Labour
Unskilled 5.000 Nos. 735.00 3,675.00
Cement 0.194 M.T. 15,500.00 3,007.00
Sand 0.420 Cum. 2,450.00 1,029.00
Materials Stone block 1.000 Cum. 1,950.00 1,950.00
Stone bond 0.100 Cum. 1,950.00 195.00
Water 120.000 Ltr. 0.31 37.20
Total 11,468.20
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,720.23
Grand Total 13,188.43

C6( 6-1-1B) R.R. stone masonry work in cement sand (1:4) mortar Cum. 10,993.00 12,641.95
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour
Unskilled 5.000 Nos. 735.00 3,675.00
Cement 0.159 M.T. 15,500.00 2,464.50
Sand 0.450 Cum. 2,450.00 1,102.50
Materials Stone block 1.000 Cum. 1,950.00 1,950.00
Stone bond 0.100 Cum. 1,950.00 195.00
Water 100.000 Ltr. 0.31 31.00
Total 10,993.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,648.95
Grand Total 12,641.95

C6( 6-1-1C) R.R. stone masonry work in cement sand (1:6) mortar Cum. 10,211.20 11,742.88
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.500 Nos. 1,050.00 1,575.00
Labour
Unskilled 5.000 Nos. 735.00 3,675.00
Cement 0.106 M.T. 15,500.00 1,643.00
Sand 0.470 Cum. 2,450.00 1,151.50
Materials
Stone block 1.000 Cum. 1,950.00 1,950.00
Stone bond 0.100 Cum. 1,950.00 195.00
Water 70.000 Ltr. 0.31 21.70
Total 10,211.20
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,531.68
Grand Total 11,742.88

C10( 6-5) Stone filling in trench with proper leveling Cum. 3,442.50 3,958.87
Resources Level/Type Quantity Unit Rate Amount Remarks
Labour Unskilled 1.50 Nos. 735.00 1,102.50
Stone block 1.00 Cum. 1,950.00 1,950.00
Materials
Stone bond 0.20 Cum. 1,950.00 390.00
Total 3,442.50
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 516.37
Grand Total 3,958.87
Rate Analysis
D - CEMENT CONCRETE WORK

D1(7-2B) P.C.C. (1:4:8) work in foundation, wall (River bed) Cum. 11,031.43 12,686.14
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Cement 0.170 M.T. 15,500.00 2,635.00
Aggrigate 40 mm-River bed 0.650 Cum. 3,592.13 2,334.88
Materials Aggrigate 20 mm-River bed 0.240 Cum. 3,704.38 889.05
Sand 0.470 Cum. 2,450.00 1,151.50
Water 100.000 Ltr. 0.31 31.00
Total 11,031.43
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,654.71
Grand Total 12,686.14

D1(7-2C) P.C.C. (1:3:6) work in foundation, wall (River bed) Cum. 11,812.63 13,584.52
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Cement 0.220 M.T. 15,500.00 3,410.00
Aggrigate 40 mm-River bed 0.650 Cum. 3,592.13 2,334.88
Materials Aggrigate 20 mm-River bed 0.240 Cum. 3,704.38 889.05
Sand 0.470 Cum. 2,450.00 1,151.50
Water 120.000 Ltr. 0.31 37.20
Total 11,812.63
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,771.89
Grand Total 13,584.52

D1(7-2D) P.C.C. (1:2:4) work in foundation, wall (River bed) Cum. 13,148.28 15,120.52
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Cement 0.320 M.T. 15,500.00 4,960.00
Aggrigate 40 mm-River bed 0.520 Cum. 3,592.13 1,867.90
Aggrigate 20 mm-River bed 0.220 Cum. 3,704.38 814.96
Materials
Aggrigate 10 mm-River bed 0.110 Cum. 3,442.46 378.67
Sand 0.445 Cum. 2,450.00 1,090.25
Water 150.000 Ltr. 0.31 46.50
Total 13,148.28
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,972.24
Grand Total 15,120.52

P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (River bed)
D2(7-4A) Cum. 15,143.28 17,414.77
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 1,050.00 840.00
Labour
Unskilled 7.000 Nos. 735.00 5,145.00
Cement 0.320 M.T. 15,500.00 4,960.00
Aggrigate 40 mm-River bed 0.520 Cum. 3,592.13 1,867.90
Aggrigate 20 mm-River bed 0.220 Cum. 3,704.38 814.96
Materials
Aggrigate 10 mm-River bed 0.110 Cum. 3,442.46 378.67
Sand 0.445 Cum. 2,450.00 1,090.25
Water 150.000 Ltr. 0.31 46.50
Total 15,143.28
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,271.49
Grand Total 17,414.77
Rate Analysis

P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (River bed)
D2(7-4B) Cum. 16,398.05 18,857.75

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 1,050.00 840.00
Labour
Unskilled 7.000 Nos. 735.00 5,145.00
Cement 0.400 M.T. 15,500.00 6,200.00
Aggrigate 20 mm-River bed 0.570 Cum. 3,704.38 2,111.49
Materials Aggrigate 10 mm-River bed 0.290 Cum. 3,442.46 998.31
Sand 0.425 Cum. 2,450.00 1,041.25
Water 200.000 Ltr. 0.31 62.00
Total 16,398.05
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,459.70
Grand Total 18,857.75

P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (River bed)
D2(7-4C) Cum. 19,667.96 22,618.15

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 1,050.00 840.00
Labour
Unskilled 7.000 Nos. 735.00 5,145.00
Cement 0.610 M.T. 15,500.00 9,455.00
Aggrigate 20 mm-River bed 0.640 Cum. 3,704.38 2,370.80
Materials Aggrigate 10 mm-River bed 0.210 Cum. 3,442.46 722.91
Sand 0.425 Cum. 2,450.00 1,041.25
Water 300.000 Ltr. 0.31 93.00
Total 19,667.96
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,950.19
Grand Total 22,618.15

P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall (River


D3(A) bed) Cum. 11,298.23 12,992.96

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.220 M.T. 15,500.00 3,410.00
Aggrigate 40 mm-River bed 0.650 Cum. 3,592.13 2,334.88
Aggrigate 20 mm-River bed 0.240 Cum. 3,704.38 889.05
Materials Sand 0.425 Cum. 2,450.00 1,041.25
Water 100.000 Ltr. 0.31 31.00
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 11,298.23
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,694.73
Grand Total 12,992.96
Rate Analysis
P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall (River
D3(B) bed) Cum. 12,772.94 14,688.88

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.320 M.T. 15,500.00 4,960.00
Aggrigate 40 mm-River bed 0.520 Cum. 3,592.13 1,867.90
Aggrigate 20 mm-River bed 0.330 Cum. 3,704.38 1,222.44
Materials Sand 0.445 Cum. 2,450.00 1,090.25
Water 130.000 Ltr. 0.31 40.30
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 12,772.94
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,915.94
Grand Total 14,688.88

P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam


D4(A) etc (River bed) Cum. 14,005.10 16,105.86

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.400 M.T. 15,500.00 6,200.00
Aggrigate 20 mm-River bed 0.570 Cum. 3,704.38 2,111.49
Aggrigate 10 mm-River bed 0.290 Cum. 3,442.46 998.31
Materials Sand 0.425 Cum. 2,450.00 1,041.25
Water 200.000 Ltr. 0.31 62.00
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 14,005.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,100.76
Grand Total 16,105.86

P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam


D4(B) etc (River bed) Cum. 17,275.01 19,866.26

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.610 M.T. 15,500.00 9,455.00
Aggrigate 20 mm-River bed 0.640 Cum. 3,704.38 2,370.80
Aggrigate 10 mm-River bed 0.210 Cum. 3,442.46 722.91
Materials Sand 0.425 Cum. 2,450.00 1,041.25
Water 300.000 Ltr. 0.31 93.00
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 17,275.01
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,591.25
Grand Total 19,866.26
Rate Analysis
P.C.C. (1:1:2) for R.C.C. work in slab (River bed) with micro silica
D(5) & super plasticiser Cum. 35,884.26 41,266.89

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.600 M.T. 15,500.00 9,300.00
Aggrigate 20 mm-River bed 0.825 Cum. 3,704.38 3,056.11
Sand 0.412 Cum. 2,450.00 1,009.40
Super plasticiser 12.000 Ltr. 283.25 3,399.00
Micro silica 40.000 Kg. 387.03 15,481.20
Materials
Water 150.000 Ltr. 0.31 46.50
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Vibrator 0.250 Hour 100.00 25.00
Total 35,884.26
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 5,382.63
Grand Total 41,266.89

P.C.C. (1:4:8) work in foundation, wall (crushed or stone ballast)


D1(7-2B) Cum. 11,031.43 12,686.14

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 1,050.00 1,050.00
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Cement 0.170 M.T. 15,500.00 2,635.00
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 3,592.13 2,334.88
Materials Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 3,704.38 889.05
Sand 0.470 Cum. 2,450.00 1,151.50
Water 100.000 Ltr. 0.31 31.00
Total 11,031.43
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,654.71
Grand Total 12,686.14

P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)


D1(7-2C) Cum. 11,812.63 13,584.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 1,050.00 1,050.00
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Cement 0.220 M.T. 15,500.00 3,410.00
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 3,592.13 2,334.88
Materials Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 3,704.38 889.05
Sand 0.470 Cum. 2,450.00 1,151.50
Water 120.000 Ltr. 0.31 37.20
Total 11,812.63
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,771.89
Grand Total 13,584.52

P.C.C. (1:2:4) work in foundation, wall (crushed or stone ballast)


D1(7-2D) Cum. 13,148.28 15,120.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.000 Nos. 1,050.00 1,050.00
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Cement 0.320 M.T. 15,500.00 4,960.00
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 3,592.13 1,867.90
Aggrigate 20 mm-crushed/ballast stone 0.220 Cum. 3,704.38 814.96
Materials
Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 3,442.46 378.67
Sand 0.445 Cum. 2,450.00 1,090.25
Water 150.000 Ltr. 0.31 46.50
Total 13,148.28
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,972.24
Grand Total 15,120.52
Rate Analysis
P.C.C. (1:2:4) for R.C.C. work in slab, beam etc (crushed or stone
D2(7-4A) ballast) Cum. 15,143.28 17,414.77
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.800 Nos. 1,050.00 840.00
Labour
Unskilled 7.000 Nos. 735.00 5,145.00
Cement 0.320 M.T. 15,500.00 4,960.00
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 3,592.13 1,867.90
Aggrigate 20 mmcrushed/ballast stone 0.220 Cum. 3,704.38 814.96
Materials
Aggrigate 10 mm-crushed/ballast stone 0.110 Cum. 3,442.46 378.67
Sand 0.445 Cum. 2,450.00 1,090.25
Water 150.000 Ltr. 0.31 46.50
Total 15,143.28
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,271.49
Grand Total 17,414.77

P.C.C. (1:1½:3) for R.C.C. work in slab, beam etc (crushed or stone
D2(7-4B) ballast) Cum. 16,398.05 18,857.75

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 1,050.00 840.00
Labour
Unskilled 7.000 Nos. 735.00 5,145.00
Cement 0.400 M.T. 15,500.00 6,200.00
Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 3,704.38 2,111.49
Materials Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 3,442.46 998.31
Sand 0.425 Cum. 2,450.00 1,041.25
Water 200.000 Ltr. 0.31 62.00
Total 16,398.05
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,459.70
Grand Total 18,857.75

P.C.C. (1:1:2) for R.C.C. work in slab, beam etc (crushed or stone
D2(7-4C) ballast) Cum. 19,667.96 22,618.15

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.800 Nos. 1,050.00 840.00
Labour
Unskilled 7.000 Nos. 735.00 5,145.00
Cement 0.610 M.T. 15,500.00 9,455.00
Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 3,704.38 2,370.80
Materials Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 3,442.46 722.91
Sand 0.425 Cum. 2,450.00 1,041.25
Water 300.000 Ltr. 0.31 93.00
Total 19,667.96
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,950.19
Grand Total 22,618.15

P.C.C. (1:3:6) work (USED MACHINE) in foundation, wall


D3(A) (crushed or stone ballast) Cum. 11,298.23 12,992.96

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.220 M.T. 15,500.00 3,410.00
Aggrigate 40 mm-crushed/ballast stone 0.650 Cum. 3,592.13 2,334.88
Aggrigate 20 mm-crushed/ballast stone 0.240 Cum. 3,704.38 889.05
Materials Sand 0.425 Cum. 2,450.00 1,041.25
Water 100.000 Ltr. 0.31 31.00
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 11,298.23
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,694.73
Grand Total 12,992.96
Rate Analysis
P.C.C. (1:2:4) work (USED MACHINE) in foundation, wall
D3(B) (crushed or stone ballast) Cum. 12,772.94 14,688.88

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.320 M.T. 15,500.00 4,960.00
Aggrigate 40 mm-crushed/ballast stone 0.520 Cum. 3,592.13 1,867.90
Aggrigate 20 mm-crushed/ballast stone 0.330 Cum. 3,704.38 1,222.44
Materials Sand 0.445 Cum. 2,450.00 1,090.25
Water 130.000 Ltr. 0.31 40.30
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 12,772.94
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 1,915.94
Grand Total 14,688.88

P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam


D4(A) etc (crushed or stone ballast) Cum. 14,005.10 16,105.86

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.400 M.T. 15,500.00 6,200.00
Aggrigate 20 mm-crushed/ballast stone 0.570 Cum. 3,704.38 2,111.49
Aggrigate 10 mm-crushed/ballast stone 0.290 Cum. 3,442.46 998.31
Materials Sand 0.425 Cum. 2,450.00 1,041.25
Water 200.000 Ltr. 0.31 62.00
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 14,005.10
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,100.76
Grand Total 16,105.86

P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam


D4(B) etc (crushed or stone ballast) Cum. 17,275.01 19,866.26

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.610 M.T. 15,500.00 9,455.00
Aggrigate 20 mm-crushed/ballast stone 0.640 Cum. 3,704.38 2,370.80
Aggrigate 10 mm-crushed/ballast stone 0.210 Cum. 3,442.46 722.91
Materials Sand 0.425 Cum. 2,450.00 1,041.25
Water 300.000 Ltr. 0.31 93.00
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Equipment
Vibrator 0.250 Hour 100.00 25.00
Total 17,275.01
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 2,591.25
Grand Total 19,866.26
Rate Analysis
P.C.C. (1:1:2) for R.C.C. work in slab (crushed or stone ballast)
D(5) with micro silica & super plasticiser Cum. 35,884.26 41,266.89

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 3.500 Nos. 735.00 2,572.50
Cement 0.600 M.T. 15,500.00 9,300.00
Aggrigate 20 mm-crushed/ballast stone 0.825 Cum. 3,704.38 3,056.11
Sand 0.412 Cum. 2,450.00 1,009.40
Super plasticiser 12.000 Ltr. 283.25 3,399.00
Micro silica 40.000 Kg. 387.03 15,481.20
Materials
Water 150.000 Ltr. 0.31 46.50
Diesel 3.000 Ltr. 103.20 309.60
Petrol 0.100 Ltr. 99.50 9.95
Mixture Machine (0.20-0.28 Cum.) 0.600 Hour 250.00 150.00
Vibrator 0.250 Hour 100.00 25.00
Total 35,884.26
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 5,382.63
Grand Total 41,266.89

Torsteel reinforcement bar for R.C.C. work with cutting, bending,


D9(7-5) binding & laying with all complete. Kg. 100.02 115.02

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 12.000 Nos. 1,050.00 12,600.00
Labour
Unskilled 12.000 Nos. 735.00 8,820.00
TOR/TMT reinforcement bar 1.050 M.T. 74,000.00 77,700.00
Materials
Binding wire 10.000 Kg. 90.00 900.00
Total 100,020.00
Rate analysis for : 1.00 MT 15 % Contractor overhead 15,003.00
Grand Total 115,023.00

E - FORM & PROPS WORK

Form work shuttering & centering (COLUMN) with (USED


E1(8-3A) LOCAL WOOD) all complete. Sqm. 1,621.22 1,864.41

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.748 Nos. 1,050.00 3,935.40 Scrap
Labour
Unskilled 5.622 Nos. 735.00 4,132.17 value .75x.526/6
= 0.07
Wood Local 0.070 Cum. 112,960.00 7,907.20
Materials
Killa 2.500 Kg. 95.00 237.50
Total 16,212.27
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 2,431.84
Grand Total 18,644.11

Form work shuttering & centering (COLUMN) with (USED PLY


E2(51B) WOOD) all complete. Sqm. 618.16 710.88

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.574 Nos. 1,050.00 1,652.70
Labour
Unskilled 2.361 Nos. 735.00 1,735.33
Ply board 19 mm thick 0.693 Sqm. 1,215.88 842.60
Wood Local 0.019 Cum. 40,595.00 771.30
Materials
MS Black pipe(MNB 50-M) 0.540 Nos. 1,744.82 942.20
Killa 2.500 Kg. 95.00 237.50
Total 6,181.63
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 927.24
Grand Total 7,108.87
Rate Analysis
Form work shuttering & centering (BEAM-0.30 Mtr) with (USED
E3(8-4A) LOCAL WOOD) all complete. Sqm. 1,168.91 1,344.25

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 4.000 Nos. 1,050.00 4,200.00
Labours
Unskilled 6.000 Nos. 735.00 4,410.00
Wood Local 0.070 Cum. 40,595.00 2,841.65
Materials
Killa 2.500 Kg. 95.00 237.50
Total 11,689.15
Rate analysis for : 10.00 Sqm. 15 % Contractor Overhead 1,753.37
Grand Total 13,442.52

Form work shuttering & centering (BEAM-0.30-0.80 Mtr) with


E4(8-4B) (USED LOCAL WOOD) all complete. Sqm. 882.26 1,014.60

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.670 Nos. 1,050.00 2,803.50
Labours
Unskilled 4.000 Nos. 735.00 2,940.00
Wood Local 0.070 Cum. 40,595.00 2,841.65
Materials
Killa 2.500 Kg. 95.00 237.50
Total 8,822.65
Rate analysis for : 10.00 Sqm. 15 % Contractor Overhead 1,323.39
Grand Total 10,146.04

Form work shuttering & centering (COLUMN) with (USED PLY


E5(51A) WOOD) all complete. Sqm. 1,317.04 1,514.59

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.670 Nos. 1,050.00 2,803.50
Labour
Unskilled 4.000 Nos. 735.00 2,940.00
Ply board 19 mm thick 1.650 Sqm. 1,215.88 2,006.20
Wood Local 0.040 Cum. 40,595.00 1,623.80
Materials
MS Black pipe(MNB 50-M) 2.040 Nos. 1,744.82 3,559.43 0.40*5.10
Killa 2.500 Kg. 95.00 237.50
Total 13,170.43
Rate analysis for : 10.00 Sqm. 15 % Contractor overhead 1,975.56
Grand Total 15,145.99

Form work shuttering & centering with MS pipe (prop), plyboard


E6(8-4A) for slab etc Sqm. 1,079.58 1,241.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 17.200 Nos. 1,050.00 18,060.00
Labours
Unskilled 25.700 Nos. 735.00 18,889.50
Ply board 19 mm thick 16.500 Sqm. 1,215.88 20,062.02
Wood Local 0.232 Cum. 40,595.00 9,418.04
Materials
MS Black pipe(MNB 50-M) 22.440 Nos. 1,744.82 39,153.76 4.40*5.10
Killa 25.000 Kg. 95.00 2,375.00
Total 107,958.32
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 16,193.74
Grand Total 124,152.06

Form work shuttering & centering with Bamboo, plyboard for slab
E6(8-4A) etc Sqm. 885.72 1,018.58

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.560 Nos. 1,050.00 11,088.00 60% of17.2
Labours
Unskilled 10.380 Nos. 735.00 7,629.30 60% of17.3
Ply board 19 mm thick 16.500 Sqm. 1,215.88 20,062.02
Wood Local 0.232 Cum. 194,150.00 45,042.80
Materials
Bamboo 6.250 Nos. 380.07 2,375.43 6.25
Killa 25.000 Kg. 95.00 2,375.00
Total 88,572.55
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 13,285.88
Grand Total 101,858.43
Rate Analysis

E12(8-13A) Trench work open type form work (up to 1.50 Mtr.) Sqm. 700.97 806.12
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.250 Nos. 1,050.00 262.50
Labours
Unskilled 0.250 Nos. 735.00 183.75
Wood Local 0.105 Cum. 194,150.00 20,385.75
Materials
Wood Local 0.25375 Cum. 194,150.00 49,265.56
Total 70,097.56
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 10,514.63
Grand Total 80,612.19
=
E12(8-13B) Trench work open type form work ( 1.50 to 3.00 Mtr.) Sqm. 709.11 815.48
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 1,050.00 525.00
Labours
Unskilled 1.000 Nos. 735.00 735.00
Wood Local 0.105 Cum. 194,150.00 20,385.75 4.16*0.0254
Materials
Wood Local 0.25375 Cum. 194,150.00 49,265.56
Total 70,911.31
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 10,636.69
Grand Total 81,548.00

E13(8-13C) Trench work open type form work (above 3.00 Mtr.) Sqm. 719.87 827.85
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.000 Nos. 1,050.00 1,050.00
Labours
Unskilled 1.750 Nos. 735.00 1,286.25
Wood Local 0.105 Cum. 194,150.00 20,385.75 4.16*0.0254
Materials
Wood Local 0.25375 Cum. 194,150.00 49,265.56
Total 71,987.56
Rate analysis for : 100.00 Sqm. 15 % Contractor Overhead 10,798.13
Grand Total 82,785.69

2.03
 33 . 33

 6
 0 . 75  4 . 16  0 . 7 5  0 . 2 5 37 5 
6

F - ROOFING WORK

=
F6 26 (M) 0.50 mm thick Colour G.I. sheet roofing work Sqm 1,362.76 1,567.18
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.100 Nos. 1,050.00 1,155.00
Labour
Unskilled 1.250 Nos. 735.00 918.75

CGI sheet 26 (H) 0.50 mm thick colour 12.000 Sqm. 754.29 9,051.42
Materials J-hook 30.000 Nos. 11.00 330.00
Nut bolt 8 mm 25.000 Nos. 31.90 797.50
Bitumen washer 55.000 Nos. 25.00 1,375.00
Total 13,627.67
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 2,044.15
Grand Total 15,671.82

150 mm breadth upto 450 mm G. I. plane sheet Gutter fixing work


F7 Rmtr. 1,622.15 1,865.47
with 3x40 mm M.S. bracke,t nut bolt & washer .

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.750 Nos. 1,050.00 1,837.50
Labour
Unskilled 2.000 Nos. 735.00 1,470.00
G. I. plane sheet Gutter 0.50mm thick 13.500 Rmtr 754.29 10,182.85
M.S. bracket 3*40 mm 32.000 Nos. -
Materials
Nut bolt 48.000 Nos. 31.90 1,531.20
Bitumen washer 48.000 Nos. 25.00 1,200.00
Total 16,221.55
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 2,433.23
Grand Total 18,654.78

F10( 9-6) Providing and laying Clay tile roofing work sqm. 907.54 1,043.67
Rate Analysis
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 1.500 Nos. 735.00 1,102.50
Materials Clay tile 125.000 Nos. 59.58 7,447.91
Total 9,075.41
Rate analysis for : 10.00 sqm. 15 % Contractor overhead 1,361.31
Grand Total 10,436.72

F11( 9-7) Providing and laying Clay tile ridge cover Rmtr. 565.91 650.80
Resources Level/Type Quantity
Unit Rate Amount Remarks
Skilled 0.500
Nos. 1,050.00 525.00
Labour
Unskilled 0.500
Nos. 735.00 367.50
Materials Clay tile ridge cover 80.000
Nos. 59.58 4,766.66
Total 5,659.16
Rate analysis for : 10.00 Rmtr. 15 % Contractor overhead 848.87
Grand Total 6,508.03
G - DOOR & WINDOW WORK

G1(10-1) Sal wood works for chaukhats with all complete. Cum. 254,110.00 292,226.50
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 34.000 Nos. 1,050.00 35,700.00
Labour
Unskilled 3.400 Nos. 735.00 2,499.00
Wood Sal 1.100 Nos. 194,150.00 213,565.00
Materials Hold fast 92.000 Nos. 16.00 1,472.00
pech killas 184.000 Nos. 4.75 874.00
Total 254,110.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 38,116.50
Grand Total 292,226.50

G1(10-1) Local wood works for chaukhats with all complete. Cum. 164,801.00 189,521.15
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 34.000 Nos. 1,050.00 35,700.00
Labour
Unskilled 3.400 Nos. 735.00 2,499.00
Wood Local 1.100 Nos. 112,960.00 124,256.00
Materials Hold fast 92.000 Nos. 16.00 1,472.00
pech killas 184.000 Nos. 4.75 874.00
Total 164,801.00
Rate analysis for : 1.00 Cum. 15 % Contractor overhead 24,720.15
Grand Total 189,521.15

38 mm thick sal wood fully paneled shutter fixing work with all
G2(10-2) complete. Size of shutter 1.07 x 1.982 =2.114 Sqm. Sqm. 15,566.03 17,900.94

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 10.000 Nos. 1,050.00 10,500.00
Labour
Unskilled 1.000 Nos. 735.00 735.00
Wood Sal 0.084 Cum. 194,150.00 16,308.60
Hinge 100 mm 6.000 Nos. 27.00 162.00
Towerbolt 150 mm. 1.000 Nos. 247.50 247.50
Materials Towerbolt 300 mm. 1.000 Nos. 412.50 412.50
Lockingset 250-300mm. 1.000 Nos. 1,718.20 1,718.20
Handle 2.000 Nos. 1,373.90 2,747.80
Pech killas L.S. 75.00
Total 32,906.60
Rate analysis for : 2.114 Sqm. 15 % Contractor overhead 4,935.99
Grand Total 37,842.59
Rate Analysis

H - FLOORING WORK

25 mm or 1" thick P.C.C. (1:2:4) work in floor with all complete.


H1(11-1A) Sqm. 479.85 551.82

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.100 Nos. 1,050.00 1,155.00
Labour
Unskilled 1.500 Nos. 735.00 1,102.50
Cement 0.090 M.T. 15,500.00 1,395.00
Materials Sand 0.120 Cum. 2,450.00 294.00
Aggrigate 12 mm-River bed 0.230 Cum. 3,704.38 852.00
Total 4,798.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 719.77
Grand Total 5,518.27

38 mm or 1½" thick P.C.C. (1:2:4) work in floor with all complete.


H1(11-1B) Sqm. 657.20 755.78

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 1,050.00 1,312.50
Labour
Unskilled 2.000 Nos. 735.00 1,470.00
Cement 0.130 M.T. 15,500.00 2,015.00
Materials Sand 0.180 Cum. 2,450.00 441.00
Aggrigate 12 mm-River bed 0.360 Cum. 3,704.38 1,333.57
Total 6,572.07
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 985.81
Grand Total 7,557.88

50 mm or 2" thick P.C.C. (1:2:4) work in floor with all complete.


H1(11-1C) Sqm. 805.25 926.03

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 1,050.00 1,312.50
Labour
Unskilled 2.500 Nos. 735.00 1,837.50
Cement 0.170 M.T. 15,500.00 2,635.00
Materials Sand 0.230 Cum. 2,450.00 563.50
Aggrigate 20 mm-River bed 0.460 Cum. 3,704.38 1,704.01
Total 8,052.51
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,207.87
Grand Total 9,260.38

75 mm or 3" thick P.C.C. (1:2:4) work in floor with all complete.


H1(11-1D) Sqm. 1,089.94 1,253.43

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.250 Nos. 1,050.00 1,312.50
Labour
Unskilled 3.000 Nos. 735.00 2,205.00
Cement 0.260 M.T. 15,500.00 4,030.00
Materials Sand 0.340 Cum. 2,450.00 833.00
Aggrigate 20 mm-River bed 0.680 Cum. 3,704.38 2,518.97
Total 10,899.47
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,634.92
Grand Total 12,534.39

20 mm thick Terrazo tile paving with 20 mm thick cement sand


H5(11-5) mortar 1:4 rubbing & polishing work with all complete. Sqm. 2,058.71 2,367.52

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.000 Nos. 1,050.00 2,100.00
Labour
Unskilled 12.600 Nos. 735.00 9,261.00
Terrazo tile 20 mm thick 11.000 Sqm. 660.00 7,260.00
Cement 0.081 M.T. 15,500.00 1,255.50
Sand 0.220 Cum. 2,450.00 539.00
Materials Oxalic acid powder 0.370 Kg. 199.00 73.63
Main Polish 0.118 Kg. 375.00 44.25
Tarpaintain oil 0.538 Ltr. 100.00 53.80
Carborendam Stone 2.000 Nos. - - 2 Nos.
Total 20,587.18
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 3,088.07
Grand Total 23,675.25
Rate Analysis

15 mm thick marble tile 600x600 mm paving with 20 mm thick


11-6 cement sand mortar 1:2 rubbing & polishing work with all Sqm. 3,409.63 3,921.07
complete.
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.000 Nos. 1,050.00 2,100.00
Labour
Unskilled 8.000 Nos. 735.00 5,880.00
Marble tile 15mm 11.000 Sqm. 1,936.80 21,304.80
Cement 0.133 M.T. 15,500.00 2,061.50
Sand 0.183 Cum. 2,450.00 448.35
Materials Oxalic acid powder 0.370 Kg. 199.00 73.63
Main Polish 0.118 Kg. 375.00 44.25
Tarpaintain oil 0.538 Ltr. 100.00 53.80
Carborendam Stone 2.000 Nos. 1,065.00 2,130.00 L.S. 2 Nos.
Total 34,096.33
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 5,114.44
Grand Total 39,210.77

Porcelain glazed tile paving work in cement sand (1:4) mortar


H6(11-7) Sqm. 2,836.82 3,262.34

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 13.000 Nos. 1,050.00 13,650.00
Labour
Unskilled 4.500 Nos. 735.00 3,307.50
Porecelain glazed/non glazed tile 11.000 Sqm. 914.60 10,060.60
Cement 0.056 M.T. 15,500.00 868.00
Materials
Sand 0.152 Cum. 2,450.00 372.40
White cement 3.228 Kg. 34.00 109.75
Total 28,368.25
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,255.23
Grand Total 32,623.48

Porcelain Non-glazed tile paving work in cement sand (1:4) mortar


H6(11-7) Sqm. 2,718.46 3,126.23

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 13.000 Nos. 1,050.00 13,650.00
Labour
Unskilled 4.500 Nos. 735.00 3,307.50
Spartik non glazed tile 11.000 Sqm. 807.00 8,877.00
Cement 0.056 M.T. 15,500.00 868.00
Materials
Sand 0.152 Cum. 2,450.00 372.40
White cement 3.228 Kg. 34.00 109.75
Total 27,184.65
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 4,077.69
Grand Total 31,262.34

Dry flat Brick paving work


H15(11-15A) Sqm. 775.95 892.34

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 0.500 Nos. 1,050.00 525.00
Labour
Unskilled 1.000 Nos. 735.00 735.00
Brick chimney 340.000 Nos. 14.00 4,760.00
Materials
Sand 0.710 Cum. 2,450.00 1,739.50
Total 7,759.50
Rate analysis for :10.00 Sqm. 15 % Contractor overhead 1,163.92
Grand Total 8,923.42
Rate Analysis
I - PLASTER & POINTING WORK

I1(12-1B) 12.5 mm. thick cement sand plaster work 1:3 on wall. Sqm. 371.83 427.61
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 1,050.00 12,600.00
Labour
Unskilled 16.000 Nos. 735.00 11,760.00
Cement 0.625 M.T. 15,500.00 9,687.50
Materials
Sand 1.280 Cum. 2,450.00 3,136.00
Total 37,183.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,577.52
Grand Total 42,761.02

I1(12-1C) 12.5 mm. thick cement sand plaster work 1:4 on wall. Sqm. 362.76 417.17
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 1,050.00 12,600.00
Labour
Unskilled 16.000 Nos. 735.00 11,760.00
Cement 0.538 M.T. 15,500.00 8,339.00
Materials
Sand 1.460 Cum. 2,450.00 3,577.00
Total 36,276.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,441.40
Grand Total 41,717.40
Rate Analysis
I1(12-1D) 12.5 mm. thick cement sand plaster work 1:6 on wall. Sqm. 341.27 392.46
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 12.000 Nos. 1,050.00 12,600.00
Labour
Unskilled 16.000 Nos. 735.00 11,760.00
Cement 0.382 M.T. 15,500.00 5,921.00
Materials
Sand 1.570 Cum. 2,450.00 3,846.50
Total 34,127.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 5,119.12
Grand Total 39,246.62

I4(12-4A) 20 mm. thick cement sand plaster work 1:3 on wall etc. Sqm. 483.22 555.70
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 1,050.00 14,700.00
Labour
Unskilled 19.000 Nos. 735.00 13,965.00
Cement 0.960 M.T. 15,500.00 14,880.00
Materials
Sand 1.950 Cum. 2,450.00 4,777.50
Total 48,322.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 7,248.37
Grand Total 55,570.87

I4(12-4B) 20 mm. thick cement sand plaster work 1:4 on wall etc. Sqm. 466.10 536.01
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 1,050.00 14,700.00
Labour
Unskilled 19.000 Nos. 735.00 13,965.00
Cement 0.810 M.T. 15,500.00 12,555.00
Materials
Sand 2.200 Cum. 2,450.00 5,390.00
Total 46,610.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,991.50
Grand Total 53,601.50

I4(12-4C) 20 mm. thick cement sand plaster work1:6 on wall etc. Sqm. 432.57 497.46
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 14.000 Nos. 1,050.00 14,700.00
Labour
Unskilled 19.000 Nos. 735.00 13,965.00
Cement 0.570 M.T. 15,500.00 8,835.00
Materials
Sand 2.350 Cum. 2,450.00 5,757.50
Total 43,257.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,488.62
Grand Total 49,746.12

I7(12-1B) 12.5 mm. thick cement sand plaster work (1:3 ) on ceilling Sqm. 432.73 497.64
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 15.000 Nos. 1,050.00 15,750.00
Labour
Unskilled 20.000 Nos. 735.00 14,700.00
Cement 0.625 M.T. 15,500.00 9,687.50
Materials
Sand 1.280 Cum. 2,450.00 3,136.00
Total 43,273.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,491.02
Grand Total 49,764.52

12.5 mm. thick cement sand plaster work 1:4 on ceilling


I7(12-1C) Sqm. 423.66 487.20

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 15.000 Nos. 1,050.00 15,750.00
Labour
Unskilled 20.000 Nos. 735.00 14,700.00
Cement 0.538 M.T. 15,500.00 8,339.00
Materials
Sand 1.460 Cum. 2,450.00 3,577.00
Total 42,366.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 6,354.90
Grand Total 48,720.90
Rate Analysis

J - PAINTING WORK

Two coat white washing work on wall.


J1(13-1B) Sqm. 33.07 38.03

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 1.500 Nos. 1,050.00 1,575.00
Labour
Unskilled 1.100 Nos. 735.00 808.50
White lime 22.000 Kg. 34.00 748.00
Materials
gum 0.880 Kg. 200.00 176.00
Total 3,307.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 496.12
Grand Total 3,803.62

J1(13-1B) Two coat white washing work on ceilling. Sqm. 39.03 44.88
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.875 Nos. 1,050.00 1,968.75 25% Add for
Labour
Unskilled 1.375 Nos. 735.00 1,010.62 ceilling
White lime 22.000 Kg. 34.00 748.00
Materials
gum 0.880 Kg. 200.00 176.00
Total 3,903.37
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 585.50
Grand Total 4,488.87

J3(13-3B) One coat distemper painting work without primer coat. Sqm. 53.25 61.23
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 2.00 Nos. 1,050.00 2,100.00
Labour
Unskilled 2.00 Nos. 735.00 1,470.00
Materials Distemper washable 6.50 Kg. 270.00 1,755.00
Total 5,325.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 798.75
Grand Total 6,123.75

J3(13-3BC) Two coat distemper painting work without primer coat. Sqm. 98.88 113.71
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 3.80 Nos. 1,050.00 3,990.00
Labour
Unskilled 3.80 Nos. 735.00 2,793.00
Materials Distemper washable 11.50 Kg. 270.00 3,105.00
Total 9,888.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,483.20
Grand Total 11,371.20

J3(13-3AB) One coat weather proof painting work over primer coat. Sqm. 142.36 163.71
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 4.00 Nos. 1,050.00 4,200.00
Labour
Unskilled 4.00 Nos. 735.00 2,940.00
Weather proof primer 8.00 Ltr. 237.00 1,896.00
Materials
Weather proof paint 6.50 Kg. 800.00 5,200.00
Total 14,236.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,135.40
Grand Total 16,371.40
Rate Analysis
Two coat weather proof painting work over primer coat.
J3(13-3ABC) Sqm. 214.49 246.66
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.80 Nos. 1,050.00 6,090.00
Labour
Unskilled 5.80 Nos. 735.00 4,263.00
Weather proof primer 8.00 Ltr. 237.00 1,896.00
Materials
Weather proof paint 11.50 Kg. 800.00 9,200.00
Total 21,449.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 3,217.35
Grand Total 24,666.35

One coat weather proof painting work without primer coat.


J3(13-3B) Sqm. 87.70 100.85

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 2.00 Nos. 1,050.00 2,100.00
Labour
Unskilled 2.00 Nos. 735.00 1,470.00
Materials Weather proof paint 6.50 Kg. 800.00 5,200.00
Total 8,770.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,315.50
Grand Total 10,085.50

Two coat weather proof painting work without primer coat.


J3(13-3BC) Sqm. 159.83 183.80

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.80 Nos. 1,050.00 3,990.00
Labour
Unskilled 3.80 Nos. 735.00 2,793.00
Materials Weather proof paint 11.50 Kg. 800.00 9,200.00
Total 15,983.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,397.45
Grand Total 18,380.45

J4(13-4A) One coat white cement paint painting work . Sqm. 40.54 46.62
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 1.70 Nos. 1,050.00 1,785.00
Labour
Unskilled 1.70 Nos. 735.00 1,249.50
Materials White cement 30.00 Kg. 34.00 1,020.00
Total 4,054.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 608.17
Grand Total 4,662.67
Rate Analysis
J4(13-4B) Two coat white cement paint painting work . Sqm. 105.74 121.60
Resources Level/Type Quantity Unit Rate Amount Remarks
Skilled 5.00 Nos. 1,050.00 5,250.00
Labour
Unskilled 5.00 Nos. 735.00 3,675.00
Materials White cement 48.50 Kg. 34.00 1,649.00
Total 10,574.00
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 1,586.10
Grand Total 12,160.10

One coat water proof cement paint painting work in plastered


J12(13-12A) surface Sqm. 167.47 192.59

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 3.50 Nos. 1,050.00 3,675.00
Labour
Unskilled 3.50 Nos. 735.00 2,572.50
Materials Water proof cement paint 30.00 Kg. 350.00 10,500.00
Total 16,747.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 2,512.12
Grand Total 19,259.62

Two coat water proof cement paint painting work in plastered


J12(13-12AB) surface Sqm. 291.02 334.67

Resources Level/Type Quantity Unit Rate Amount Remarks


Skilled 6.50 Nos. 1,050.00 6,825.00
Labour
Unskilled 6.50 Nos. 735.00 4,777.50
Materials Water proof cement paint 50.00 Kg. 350.00 17,500.00
Total 29,102.50
Rate analysis for :100.00 Sqm. 15 % Contractor overhead 4,365.37
Grand Total 33,467.87
Items: District Rates

S.N. Description District rate Unit

Civil Items
1 Skilled 1,050.00 Per day
2 Unskilled/Labor/Helper 735.00 Per day
3 Medium Skilled Painter 1,050.00 Per day
4 Plumber (Helper) 735.00 Per day
5 Cement-Nepali OPC 15,500.00 MT
6 Sand 2,450.00 Cum
7 Mud 565.00 Cum
8 Aggregate Sieved in river(10-40mm)
5-10mm 3,442.46 Cum
10-20mm 3,704.38 Cum
20-40mm 3,592.13 Cum
Sub-base 63mm down 2,656.68 Cum
9 Crusher Aggregate(5-40mm)
10mm 3,442.46 Cum
20mm 1,900.00 Cum
40mm 1,850.00 Cum
Sub-base 63mm down 1,850.00 Cum
10 Re-bars-TMT NS
8mm 74,000.00 Mt
10mm to 25mm 74,000.00 Mt
11 Binding wire 90.00 Kg
12 Stone
Boulder 1,950.00 Cum
carborendum (60 no.) 1,065.00 No
marble chips 25.00 Kg
13 Primer (Wood Primer) 434.00 Ltr
14 Enamel (Coloured) 450.00 Ltr
15 Weather coat paint 800.00 Kg
16 Nail 95.00 Kg
17 Saal wood (chiran) 194,150.00 Cum
18 Sisau Wood (chiran) 112,960.00 Cum
Salla wood 40,595.00 Cum
19 Hold fast 16.00 No.
20 Hinge ISI Mark (Kabja)-Simple-4" 27.00 No.
21 Brick (No. 1) 14.00 No
22 Ply wood
Ply wood - Commercial
3mm 387.36 Sqm
6mm 570.28 Sqm
12mm 860.80 Sqm
19 mm board water proof 1,215.88 Sqm
Items: District Rates

S.N. Description District rate Unit

Civil Items
Ply wood teak- Artificial
3mm 753.54 Sqm
6mm 947.30 Sqm
23 CGI Sheet
colour CGI sheet.(0.5mm)Medium 26 gage (N.S
Sqm
141) 754.29
Plain CGI sheet.(0.5mm) light 24gage 72kg 609.71 Sqm
24 Bitumen Washer 25.00 No.
25 Nut bolt (8mm) 31.90 No
26 J-hook 11.00 Kg
27 Locking set(300mm)brass 1,718.20 No.
28 Handle (brass 8'') 1,373.90 No.
29 Marble 13mm 1936.8 Sqm
30 Cement Tile 660.00 Sqm
31 Oxalic acid 199.00 Kg
32 Tarpentine 100.00 Ltr
33 Candle Polish 375.00 Kg
34 Water 0.31 Ltr
35 White cement 34.00 Kg
36 Distemper washable 270.00 kg
37 Weather proof primer 237.00 Ltr
38 Weather proof paint 800.00 kg
39 Glue 200.00 Kg
40 Cement putty 40 Kg
41 Glazed tile 914.6 Sqm
42 Unglazed tile 807 Sqm
43 Terrajo Tile (roof) 715.00 sqm
44 Black pipe of different sizes 113 kg
45 Snowcem Paint 330 kg
46 Iron Angle 110 kg
47 Spring 1100 No
48 Rivet 132 kg
49 GI Cover Lock Plate 132 kg
50 Plane Sheet 132 kg

51 Hexaglon interlock pavers (grey color) 80 mm No


thik (226*200*80) 68
52 Channel Side Flag 1100 No
53 Mortar Plasticiser 1320 ltr
54 Grass 440 Sqm
आ.व.२०७५/०७६ को जिल्ला दररेट

S. N Description Unit 077/078 Remarks

A Aluminium Door and windows


Providing and fi:ring ofaluminium windows ofsection (102 sc.ics) 1.2
1 mm th Fitted \rilh 5 nr]n clear glass without fly ncsh shuttcr ($indow sqm. 7101.60
size 6'X4'6" or 27 sqft / rvindor'r)
Supplying and fixing of swing door of aluminium section in naturally
2 anodized color section size 101x45x1.50mm and 5mm glass sqm. 7945.08

B Fabrication of steel railing


Fabrication of steel railing with 3 row of 1" horizontal pipe and
vertical post and hand rail of 2" rm 3831.04
1
Item: Quantity Estimate of Debate Chamber block
S.N. Description No. Length Breadth Height Quantity

1 Clearing of grass, removing roots, breaking sods levelling the surface and disposal as per specification
Site area 1 2400 2400.00

2 Earth work excavation in foundation in clay & silty soft soil lead upto 10 mtr. & lift 1.5 mtr.
Footing
F1 8 3.25 3.25 2.50 211.25
F2 1 4.45 4.45 2.50 49.51
F3 4 3.85 3.85 2.50 148.23
F4 3 4.75 4.75 2.50 169.22
F5 1 5.10 5.10 2.50 65.03
F6 7 4.45 4.45 2.50 346.54
F7 9 3.25 3.25 2.50 237.66
CF1 1 7.50 3.15 2.50 59.06
CF2 1 1134.75 692.35 2.50 1106.00
Tie Beam
Grid A-A 1 9.34 0.70 2.00 13.08
Grid B-B 1 8.07 0.70 2.00 11.30
Grid C-C 1 7.94 0.70 2.00 11.12
Grid D-D 1 8.04 0.70 2.00 11.26
Grid E-E 1 8.04 0.70 2.00 11.26
Grid F-F 1 7.28 0.70 2.00 10.19
Grid G-G 1 10.34 0.70 2.00 14.48
Grid H-H 1 9.59 0.70 2.00 13.43
Grid I-I 1 7.94 0.70 2.00 11.12
Grid J-J 1 7.34 0.70 2.00 10.28
Grid K-K 1 8.94 0.70 2.00 12.52
Grid L-L 1 8.54 0.70 2.00 11.96
Grid M-M 1 7.94 0.70 2.00 11.12
Grid N-N 1 7.69 0.70 2.00 10.77
Grid O-O 1 9.44 0.70 2.00 13.22
Beam around th dome
Inner 1 163.57 0.70 2.00 229.00
Outer 1 197.17 0.70 2.00 276.04

Total Excavation = 3074.58

3 Sand filling work 150mm thick proper manual compaction.


Footing
F1 8 3.25 3.25 0.15 12.68
F2 1 4.45 4.45 0.15 2.97
F3 4 3.85 3.85 0.15 8.89
F4 3 4.75 4.75 0.15 10.15
F5 1 5.10 5.10 0.15 3.90
F6 7 4.45 4.45 0.15 20.79
F7 9 3.25 3.25 0.15 14.26
CF1 1 7.50 3.15 0.15 3.54
CF2 1 1134.75 692.35 0.15 66.36
Tie Beam
Grid A-A 1 9.34 0.70 0.15 0.98
Grid B-B 1 8.07 0.70 0.15 0.85
Grid C-C 1 7.94 0.70 0.15 0.83
Grid D-D 1 8.04 0.70 0.15 0.84
Grid E-E 1 8.04 0.70 0.15 0.84
Grid F-F 1 7.28 0.70 0.15 0.76
Grid G-G 1 10.34 0.70 0.15 1.09
Grid H-H 1 9.59 0.70 0.15 1.01
Grid I-I 1 7.94 0.70 0.15 0.83
Grid J-J 1 7.34 0.70 0.15 0.77
Grid K-K 1 8.94 0.70 0.15 0.94
Grid L-L 1 8.54 0.70 0.15 0.90
Grid M-M 1 7.94 0.70 0.15 0.83
Grid N-N 1 7.69 0.70 0.15 0.81
Grid O-O 1 9.44 0.70 0.15 0.99
Beam around th dome
Inner 1 163.57 0.70 0.15 17.17
Outer 1 197.17 0.70 0.15 20.70
Floor 1 2272.00 2272.00
1 900.00 900.00

Total Excavation = 3366.71

4 Dry flat Brick paving work


Footing
F1 8 3.25 3.25 84.50
F2 1 4.45 4.45 19.80
F3 4 3.85 3.85 59.29
F4 3 4.75 4.75 67.69
F5 1 5.10 5.10 26.01
F6 7 4.45 4.45 138.62
F7 9 3.25 3.25 95.06
CF1 1 7.50 3.15 23.63
CF2 1 1134.75 692.35 442.40
Tie Beam
Grid A-A 1 9.34 0.70 6.54
Grid B-B 1 8.07 0.70 5.65
Grid C-C 1 7.94 0.70 5.56
Grid D-D 1 8.04 0.70 5.63
Grid E-E 1 8.04 0.70 5.63
Grid F-F 1 7.28 0.70 5.10
Grid G-G 1 10.34 0.70 7.24
Grid H-H 1 9.59 0.70 6.71
Grid I-I 1 7.94 0.70 5.56
Grid J-J 1 7.34 0.70 5.14
Grid K-K 1 8.94 0.70 6.26
Grid L-L 1 8.54 0.70 5.98
Grid M-M 1 7.94 0.70 5.56
Grid N-N 1 7.69 0.70 5.38
Grid O-O 1 9.44 0.70 6.61
Beam around th dome
Inner 1 163.57 0.70 114.50
Outer 1 197.17 0.70 138.02

Floor 1 2272.00 2272.00


1 900.00 900.00

Total Excavation = 4470.04

5 Earth filling work in every 15-15 cm. layer with watering & lead upto 1o.00 mtr. & proper manual
compaction. Total excavation 3074.58
Total filling 40% of excavation 1229.83
Filling upto plinth 1 2272.00 1.5 3408.00
1 900.00 0.6 540.00

Total 5177.83

7 P.C.C. (1:3:6) work in foundation, wall (crushed or stone ballast)


Footing
F1 15 3.05 3.05 0.075 10.47
F2 6 4.25 4.25 0.075 8.13
F3 6 3.65 3.65 0.075 6.00
F4 4 4.25 4.25 0.075 5.42
F5 1 4.90 4.90 0.075 1.80
F6 10 5.50 5.50 0.075 22.69
CF1 1 7.30 2.95 0.075 1.62
CF2 2 17.56 4.08 0.075 10.75

Tie Beam
Grid A-A 1 13.79 0.4 0.075 0.41
Grid B-B 1 7.89 0.4 0.075 0.24
Grid C-C 1 7.89 0.4 0.075 0.24
Grid D-D 1 7.92 0.4 0.075 0.24
Grid E-E 1 7.92 0.4 0.075 0.24
Grid F-F 1 7.89 0.4 0.075 0.24
Grid G-G 1 13.66 0.4 0.075 0.41
Grid H-H 1 12.97 0.4 0.075 0.39
Grid I-I 1 7.92 0.4 0.075 0.24
Grid J-J 1 7.89 0.4 0.075 0.24
Grid K-K 1 13.01 0.4 0.075 0.39
Grid L-L 1 12.16 0.4 0.075 0.36
Grid M-M 1 7.92 0.4 0.075 0.24
Grid N-N 1 7.89 0.4 0.075 0.24
Grid O-O 1 12.75 0.4 0.075 0.38
Grid P-P 1 13.79 0.4 0.075 0.41
Beam around th dome
Inner 1 92.20 0.4 0.075 2.77
Middle 1 150.32 0.4 0.075 4.51
Outer 1 184.36 0.4 0.075 5.53

Floor 1 2272.00 0.075 170.40


1 900.00 0.075 67.50

Total= 322.46

8 P.C.C. (1:1:2) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Up to plinth
Footing
F1 8 3.05 3.05 0.6 44.65
F2 1 4.25 4.25 0.6 10.84
F3 4 3.65 3.65 0.6 31.97
F4 3 4.55 4.55 0.65 40.37
F5 1 4.90 4.90 0.65 15.61
F6 7 4.25 4.25 0.7 88.51
F7 9 3.05 3.05 1.7 142.33
CF1 1 7.32 3.00 0.65 14.27
CF2 1 107.90 4.90 0.75 396.53
Column
C 11 0.75 0.75 2 12.38
C1 7 0.75 0.75 2 7.88
C2 16 0.75 0.75 2 18.00
C3 16 1.25 0.90 2 36.00
Ground Floor
Column
C 11 0.75 0.75 4.45 27.53
C1 7 0.75 0.75 4.45 17.52
C2 16 0.75 0.75 4.45 40.05
C3 16 1.25 0.90 4.45 80.10
1st Floors
Column
C 11 0.75 0.75 4.45 27.53
C1 7 0.75 0.75 4.45 17.52
C2 16 0.75 0.75 4.45 40.05
C3 16 1.25 0.90 4.45 80.10
2nd Floor
Column
C2 16 0.75 0.75 4.45 40.05
C3 16 1.25 0.90 4.45 80.10

Total = 1309.89

9 P.C.C. (1:1½:3) for R.C.C. work(USED MACHINE) in slab, beam etc (crushed or stone ballast)
Up to plinth
Tie Beam
Grid A-A 1 13.79 0.40 0.70 3.86
Grid B-B 1 7.89 0.40 0.70 2.21
Grid C-C 1 7.89 0.40 0.70 2.21
Grid D-D 1 7.92 0.40 0.70 2.22
Grid E-E 1 7.92 0.40 0.70 2.22
Grid F-F 1 7.89 0.40 0.70 2.21
Grid G-G 1 13.66 0.40 0.70 3.82
Grid H-H 1 12.97 0.40 0.70 3.63
Grid I-I 1 7.92 0.40 0.70 2.22
Grid J-J 1 7.89 0.40 0.70 2.21
Grid K-K 1 13.01 0.40 0.70 3.64
Grid L-L 1 12.16 0.40 0.70 3.40
Grid M-M 1 7.92 0.40 0.70 2.22
Grid N-N 1 7.89 0.40 0.70 2.21
Grid O-O 1 12.75 0.40 0.70 3.57
Grid P-P 1 13.79 0.40 0.70 3.86
Beam around th dome
Inner 1 92.20 0.40 0.70 25.82
Middle 1 150.32 0.40 0.70 42.09
Outer 1 184.36 0.40 0.70 51.62

Beam at 0m level
Main Beam
Grid A-A 1 14.39 0.40 0.70 4.03
Grid B-B 1 8.49 0.40 0.70 2.38
Grid C-C 1 8.49 0.40 0.70 2.38
Grid D-D 1 8.52 0.40 0.70 2.39
Grid E-E 1 8.52 0.40 0.70 2.39
Grid F-F 1 7.89 0.40 0.70 2.21
Grid G-G 1 13.66 0.40 0.70 3.82
Grid H-H 1 12.97 0.40 0.70 3.63
Grid I-I 1 7.92 0.40 0.70 2.22
Grid J-J 1 7.89 0.40 0.70 2.21
Grid K-K 1 13.01 0.40 0.70 3.64
Grid L-L 1 12.76 0.40 0.70 3.57
Grid M-M 1 8.52 0.40 0.70 2.39
Grid N-N 1 8.49 0.40 0.70 2.38
Grid O-O 1 13.35 0.40 0.70 3.74
Grid P-P 1 14.39 0.40 0.70 4.03
Beam around th dome
Inner 1 92.20 0.40 0.70 25.82
Middle 1 150.32 0.40 0.70 42.09
Outer 1 30.12 0.40 0.70 8.43

Ground Floor 4.5 m level


Main Beam
Grid A-A 1 14.39 0.40 0.70 4.03
Grid B-B 1 8.49 0.40 0.70 2.38
Grid C-C 1 8.49 0.40 0.70 2.38
Grid D-D 1 8.52 0.40 0.70 2.39
Grid E-E 1 8.52 0.40 0.70 2.39
Grid F-F 1 7.89 0.40 0.70 2.21
Grid G-G 1 13.66 0.40 0.70 3.82
Grid H-H 1 12.97 0.40 0.70 3.63
Grid I-I 1 7.92 0.40 0.70 2.22
Grid J-J 1 7.89 0.40 0.70 2.21
Grid K-K 1 13.01 0.40 0.70 3.64
Grid L-L 1 12.76 0.40 0.70 3.57
Grid M-M 1 8.52 0.40 0.70 2.39
Grid N-N 1 8.49 0.40 0.70 2.38
Grid O-O 1 13.35 0.40 0.70 3.74
Grid P-P 1 14.39 0.40 0.70 4.03
Beam around th dome
Inner 1 92.20 0.40 0.65 23.97
Middle 1 150.32 0.40 0.70 42.09
Outer 1 30.12 0.40 0.70 8.43
Secondary beam
Beam between inner & middle 1 61.21 0.40 0.70 17.14
Between Grid A & B 1 8.08 0.30 0.40 0.97
Between Grid B & C 1 8.08 0.30 0.40 0.97
Between Grid D & E 1 8.10 0.30 0.40 0.97
Between Grid E & F 1 8.10 0.30 0.40 0.97
Between Grid G & H 1 8.10 0.30 0.40 0.97
Between Grid H & I 1 3.16 0.30 0.40 0.38
Between Grid I & J 1 8.10 0.30 0.40 0.97
Between Grid J & K 1 8.08 0.30 0.40 0.97
Between Grid K & L 1 8.08 0.30 0.40 0.97
Between Grid L & M 1 8.08 0.30 0.40 0.97
Between Grid M & N 1 8.08 0.30 0.40 0.97
Between Grid N & O 1 8.08 0.30 0.40 0.97
Between Grid P & A 1 4.50 0.30 0.40 0.54

Beam between inner & middle 1 48.19 0.30 0.40 5.78


Beam inside inner beam 1 56.20 0.30 0.40 6.74
1 13.79 0.30 0.40 1.65
Stair beam 1 8.46 0.40 0.65 2.20
1 4.55 0.40 0.65 1.18
1 8.50 0.40 0.65 2.21
1 2.87 0.40 0.65 0.75

Slab 1 1237.49 0.125 154.69

Stair SC1
landing 1 7.78 0.150 1.17
1st and 2nd flight 2 1.60 3.20

Stair S1
landing 1 2.93 0.150 0.44
1 2.51 0.150 0.38
1st flight 1 1.60 1.60
3rd flight 1 1.38 1.38
2nd flight 1 0.39 0.39

Stair S2
landing 1 7.78 0.150 1.17
1st and 2nd flight 2 1.77 3.53

Lintel Band
230 mm wall 1 0.23 0.075 0.00
110mm wall 1 0.11 0.075 0.00
Sill Band
230 mm wall 1 0.23 0.075 0.00
110mm wall 1 0.11 0.075 0.00
1st Floors
Main Beam
Grid A-A 1 14.65 0.40 0.70 4.10
Grid B-B 1 5.43 0.40 0.70 1.52
Grid C-C 1 5.43 0.40 0.70 1.52
Grid D-D 1 5.46 0.40 0.70 1.53
Grid E-E 1 5.44 0.40 0.70 1.52
Grid F-F 1 5.44 0.40 0.70 1.52
Grid G-G 1 14.54 0.40 0.70 4.07
Grid H-H 1 13.86 0.40 0.70 3.88
Grid I-I 1 5.44 0.40 0.70 1.52
Grid J-J 1 5.92 0.40 0.70 1.66
Grid K-K 1 13.86 0.40 0.70 3.88
Grid L-L 1 13.06 0.40 0.70 3.66
Grid M-M 1 5.43 0.40 0.70 1.52
Grid N-N 1 5.43 0.40 0.70 1.52
Grid O-O 1 13.62 0.40 0.70 3.81
Grid P-P 1 0.89 0.40 0.70 0.25
Beam around th dome
Inner 1 92.20 0.40 0.65 23.97
Middle 1 129.20 0.40 0.70 36.18
Outer 1 30.75 0.40 0.70 8.61
Secondary beam
Beam between inner & middle 1 113.39 0.40 0.70 31.75
Between Grid A & B 1 4.82 0.30 0.40 0.58
Between Grid B & C 1 4.82 0.30 0.40 0.58
Between Grid D & E 1 4.82 0.30 0.40 0.58
Between Grid E & F 1 4.82 0.30 0.40 0.58
Between Grid G & H 1 21.26 0.30 0.40 2.55
Between Grid H & I 1 4.82 0.30 0.40 0.58
Between Grid I & J 1 4.82 0.30 0.40 0.58
Between Grid J & K 1 4.82 0.30 0.40 0.58
Between Grid K & L 1 22.21 0.30 0.40 2.67
Between Grid L & M 1 4.82 0.30 0.40 0.58
Between Grid M & N 1 4.82 0.30 0.40 0.58
Between Grid N & O 1 4.82 0.30 0.40 0.58
Between Grid O & P 1 7.34 0.30 0.40 0.88
Between Grid P & A 1 23.09 0.30 0.40 2.77

Beam inside inner beam 1 95.28 0.30 0.40 11.43


Stair beam 1 5.12 0.40 0.65 1.33
1 5.33 0.40 0.65 1.39

Slab 1 1129.19 0.125 141.15


Stair
landing 2 5.10 0.125 1.28
1st and 3rd flight 2 0.51 1.03
2nd flight 1 0.53 0.53

Stair SC1
landing 1 7.78 0.150 1.17
1st and 2nd flight 2 1.60 3.20

Stair S1
landing 1 2.93 0.150 0.44
1 2.51 0.150 0.38
1st flight 1 1.60 1.60
3rd flight 1 1.38 1.38
2nd flight 1 0.39 0.39

Lintel Band
230 mm wall 1 0.23 0.075 0.00
110mm wall 1 0.11 0.075 0.00
Sill Band
230 mm wall 1 0.23 0.075 0.00
110mm wall 1 0.11 0.075 0.00

2nd Floor
Main Beam
Inner 1 92.20 1.225 1.225 138.36
Around centre 1 22.30 0.55 0.55 6.75

Dome slab 1 4619.25 0.175 808.37

Total = 1900.88

Torsteel reinforcement bar for R.C.C.


10 work with cutting, bending, binding &
laying with all complete.
2% of RCC work 504.09
Total= 504.09

11 Trench work open type form work ( 1.50 to 3.00 Mtr.)


Up to plinth
Footing
F1 16 3.05 0.6 29.28
F2 2 4.25 0.6 5.10
F3 8 3.65 0.6 17.52
F4 6 4.55 0.65 17.75
F5 2 4.90 0.65 6.37
F6 14 4.25 0.7 41.65
F7 18 3.05 1.7 93.33
CF1 2 7.32 0.65 9.52
2 3.00 0.65 3.90
CF2 2 107.90 0.75 161.85
2 4.90 0.75 7.35

Total = 393.61

Form work shuttering & centering


(BEAM-0.30-0.80 Mtr) with (USED
12 LOCAL WOOD) all complete.
Up to plinth
Tie Beam
Grid A-A 1 13.79 0.4 5.52
2 13.79 0.7 19.31
Grid B-B 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid C-C 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid D-D 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid E-E 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid F-F 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid G-G 1 13.66 0.4 5.46
2 13.66 0.7 19.12
Grid H-H 1 12.97 0.4 5.19
2 12.97 0.7 18.16
Grid I-I 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid J-J 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid K-K 1 13.01 0.4 5.20
2 13.01 0.7 18.21
Grid L-L 1 12.16 0.4 4.86
2 12.16 0.7 17.02
Grid M-M 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid N-N 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid O-O 1 12.75 0.4 5.10
2 12.75 0.7 17.85
Grid P-P 1 13.79 0.4 5.52
2 13.79 0.7 19.31
Beam around th dome
Inner 1 163.57 0.4 65.43
2 163.57 0.7 229.00
Outer 1 197.17 0.4 78.87
2 197.17 0.7 276.04

Beam at 0m level
Main Beam
Grid A-A 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Grid B-B 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid C-C 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid D-D 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid E-E 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid F-F 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid G-G 1 13.66 0.4 5.46
2 13.66 0.7 19.12
Grid H-H 1 12.97 0.4 5.19
2 12.97 0.7 18.16
Grid I-I 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid J-J 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid K-K 1 13.01 0.4 5.20
2 13.01 0.7 18.21
Grid L-L 1 12.76 0.4 5.10
2 12.76 0.7 17.86
Grid M-M 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid N-N 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid O-O 1 13.35 0.4 5.34
2 13.35 0.7 18.69
Grid P-P 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Beam around th dome
Inner 1 163.57 0.4 65.43
2 163.57 0.7 229.00
Outer 1 197.17 0.4 78.87
2 197.17 0.7 276.04

Ground Floor
Main Beam
Grid A-A 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Grid B-B 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid C-C 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid D-D 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid E-E 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid F-F 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid G-G 1 13.66 0.4 5.46
2 13.66 0.7 19.12
Grid H-H 1 12.97 0.4 5.19
2 12.97 0.7 18.16
Grid I-I 1 7.92 0.4 3.17
2 7.92 0.7 11.09
Grid J-J 1 7.89 0.4 3.16
2 7.89 0.7 11.05
Grid K-K 1 13.01 0.4 5.20
2 13.01 0.7 18.21
Grid L-L 1 12.76 0.4 5.10
2 12.76 0.7 17.86
Grid M-M 1 8.52 0.4 3.41
2 8.52 0.7 11.93
Grid N-N 1 8.49 0.4 3.40
2 8.49 0.7 11.89
Grid O-O 1 13.35 0.4 5.34
2 13.35 0.7 18.69
Grid P-P 1 14.39 0.4 5.76
2 14.39 0.7 20.15
Beam around th dome
Inner 1 92.20 0.4 36.88
2 92.20 0.7 129.08
Middle 1 150.32 0.4 60.13
2 150.32 0.7 210.45
Outer 1 30.12 0.4 12.05
2 30.12 0.7 42.17
Secondary beam
Beam between inner & middle 1 61.21 0.4 24.48
2 61.21 0.7 85.69
Between Grid A & B 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid B & C 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid D & E 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid E & F 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid G & H 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid H & I 1 3.16 0.3 0.95
2 3.16 0.4 2.53
Between Grid I & J 1 8.10 0.3 2.43
2 8.10 0.4 6.48
Between Grid J & K 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid K & L 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid L & M 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid M & N 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid N & O 1 8.08 0.3 2.42
2 8.08 0.4 6.46
Between Grid P & A 1 4.50 0.3 1.35
2 4.50 0.4 3.60
Beam between inner & middle 1 48.19 0.3 14.46
2 48.19 0.4 38.55
Beam inside inner beam 1 56.20 0.3 16.86
2 56.20 0.4 44.96
1 13.79 0.3 4.14
2 13.79 0.4 11.03
Stair beam 1 8.46 0.4 3.38
2 8.46 0.65 11.00
1 4.55 0.4 1.82
2 4.55 0.65 5.92
1 8.50 0.4 3.40
2 8.50 0.65 11.05
1 2.87 0.4 1.15
2 2.87 0.65 3.73

Lintel Band
230 mm wall 2 0.075 0.00
110mm wall 2 0.075 0.00
Sill Band
230 mm wall 2 0.075 0.00
110mm wall 2 0.075 0.00

1st Floors
Main Beam
Grid A-A 1 14.65 0.4 5.86
2 14.65 0.7 20.51
Grid B-B 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid C-C 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid D-D 1 5.46 0.4 2.18
2 5.46 0.7 7.64
Grid E-E 1 5.44 0.4 2.18
2 5.44 0.7 7.62
Grid F-F 1 5.44 0.4 2.18
2 5.44 0.7 7.62
Grid G-G 1 14.54 0.4 5.82
2 14.54 0.7 20.36
Grid H-H 1 13.86 0.4 5.54
2 13.86 0.7 19.40
Grid I-I 1 5.44 0.4 2.18
2 5.44 0.7 7.62
Grid J-J 1 5.92 0.4 2.37
2 5.92 0.7 8.29
Grid K-K 1 13.86 0.4 5.54
2 13.86 0.7 19.40
Grid L-L 1 13.06 0.4 5.22
2 13.06 0.7 18.28
Grid M-M 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid N-N 1 5.43 0.4 2.17
2 5.43 0.7 7.60
Grid O-O 1 13.62 0.4 5.45
2 13.62 0.7 19.07
Grid P-P 1 0.89 0.4 0.36
2 0.89 0.7 1.25
Beam around th dome
Inner 1 92.20 0.4 36.88
2 92.20 0.7 129.08
Middle 1 129.20 0.4 51.68
2 129.20 0.7 180.88
Outer 1 30.75 0.4 12.30
2 30.75 0.7 43.05

Secondary beam
Beam between inner & middle 1 113.39 0.4 45.36
2 113.39 0.7 158.75
Between Grid A & B 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid B & C 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid D & E 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid E & F 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid G & H 1 21.26 0.3 6.38
2 21.26 0.4 17.01
Between Grid H & I 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid I & J 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid J & K 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid K & L 1 22.21 0.3 6.66
2 22.21 0.4 17.77
Between Grid L & M 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid M & N 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid N & O 1 4.82 0.3 1.45
2 4.82 0.4 3.86
Between Grid O & P 1 7.34 0.3 2.20
2 7.34 0.4 5.87
Between Grid P & A 1 23.09 0.3 6.93
2 23.09 0.4 18.47
Beam inside inner beam 1 95.28 0.3 28.58
2 95.28 0.4 76.22
Stair beam 1 5.12 0.4 2.05
2 5.12 0.65 6.66
1 5.33 0.4 2.13
2 5.33 0.65 6.93

Lintel Band
230 mm wall 2 0.075 0.00
110mm wall 2 0.075 0.00
Sill Band 0.00
230 mm wall 2 0.075 0.00
110mm wall 2 0.075 0.00

2nd Floor
Main Beam
Inner 1 92.20 1.225 112.95
2 92.20 1.225 225.89
Around centre 1 22.30 0.55 12.27
2 22.30 0.55 24.53

Total = 4612.03

13 Form work shuttering & centering (COLUMN) with (USED LOCAL WOOD) all complete.
Up to plinth
C 44 0.75 2 66.00
C1 4 0.75 2 6.00
C2 64 0.75 2 96.00
C3 32 1.25 2 80.00
32 0.90 2 57.60
Ground Floor
C 44 0.75 4 132.00
C1 4 0.75 4 12.00
C2 64 0.75 4 192.00
C3 32 1.25 4 160.00
32 0.90 4 115.20
1st Floors
C 44 0.75 4 132.00
C1 4 0.75 4 12.00
C2 64 0.75 4 192.00
C3 32 1.25 4 160.00
32 0.90 4 115.20
2nd Floor
C2 64 0.75 4 192.00
C3 32 1.25 4 160.00
32 0.90 4 115.20

Total = 1995.20

14 Form work shuttering & centering with MS pipe (prop), plyboard for slab etc
Ground Floor
Slab 1 1237.49 0.125 1237.49
1 302.89 0.125 37.86

Stair SC1
landing 1 7.78 7.78
Riser 26 1.50 0.15 5.85
1st and 2nd flight 2 6.54 13.08
4 1.50 0.245 1.47
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
Riser 26 1.50 0.15 5.85
1st flight 1 6.54 6.54
2 1.50 0.245 0.74
2nd flight 1 1.60 1.60
2 1.60 0.245 0.78
3rd flight 1 5.63 5.63
2 1.40 0.245 0.69
Stair S2
landing 1 7.78 7.78
Riser 26 1.96 0.15 7.64
1st and 2nd flight 2 7.21 14.43
4 1.96 0.245 1.92

1st Floors
Slab 1 1129.19 1129.19
1 317.51 0.125 39.69

Stair SC1
landing 1 7.78 7.78
Riser 26 1.50 0.15 5.85
1st and 2nd flight 2 6.54 13.08
4 1.50 0.245 1.47
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
Riser 26 1.50 0.15 5.85
1st flight 1 6.54 6.54
2 1.50 0.245 0.74
2nd flight 1 1.60 1.60
2 1.60 0.245 0.78
3rd flight 1 5.63 5.63
2 1.40 0.245 0.69
Stair S2
landing 1 7.78 7.78
Riser 26 1.96 0.15 7.64
1st and 2nd flight 2 7.21 14.43
4 1.96 0.245 1.92

Dome slab 1 4619.25 4619.25


Total = 7237.90

15 First class chimney brick masonry work in (1:4) cement sand mortar in G. F.
Below Ground level
Tie Beam
Grid A-A 1 13.79 0.23 0.8 2.54
Grid B-B 1 7.89 0.23 0.8 1.45
Grid C-C 1 7.89 0.23 0.8 1.45
Grid D-D 1 7.92 0.23 0.8 1.46
Grid E-E 1 7.92 0.23 0.8 1.46
Grid F-F 1 7.89 0.23 0.8 1.45
Grid G-G 1 13.66 0.23 0.8 2.51
Grid H-H 1 12.97 0.23 0.8 2.39
Grid I-I 1 7.92 0.23 0.8 1.46
Grid J-J 1 7.89 0.23 0.8 1.45
Grid K-K 1 13.01 0.23 0.8 2.39
Grid L-L 1 12.16 0.23 0.8 2.24
Grid M-M 1 7.92 0.23 0.8 1.46
Grid N-N 1 7.89 0.23 0.8 1.45
Grid O-O 1 12.75 0.23 0.8 2.35
Grid P-P 1 13.79 0.23 0.8 2.54
Beam around th dome
Inner 1 92.20 0.23 0.8 16.96
Middle 1 150.32 0.23 0.8 27.66
Outer 1 184.36 0.23 0.8 33.92

Ground Floor
Outer wall
Grid P-P 1 17.33 0.23 4.45 17.74
Grid O-O 1 13.62 0.23 4.45 13.94
Grid G-G 1 14.06 0.23 4.45 14.39
Grid H-H 1 12.64 0.23 4.45 12.94
Grid K-K 1 13.55 0.23 4.45 13.87
Grid L-L 1 12.24 0.23 4.45 12.53

Inner wall
1 85.26 0.23 4.45 87.26
1 129.20 0.11 4.45 63.24
1 46.20 0.23 4.45 47.29
Inner wall 1 91.50 0.11 4.45 44.79
Toilet partation 1 31.70 0.11 4.45 15.52
Toilet partation 1 46.80 0.11 4.45 22.91
Deduction
inner wall opening
D1 -8 1.2 0.11 2.1 -2.218
D2 -17 1 0.11 2.1 -3.927
D3 -21 0.75 0.11 2.1 -3.638
w -4 1.5 0.11 2.4 -1.584

Total = 463.63

16 First class chimney brick masonry work in (1:4) cement sand mortar in F. F.
First floor
Outer wall
Grid 2-2 27.00 0.23 3.2 0.00
Grid 6-6 27.00 0.23 3.2 0.00
Grid A-A 27.00 0.23 3.2 0.00
Grid E-E 27.00 0.23 3.2 0.00
Inner wall
1 135.20 0.11 4.45 66.18
Inner wall 1 54.70 0.11 4.45 26.78
Toilet partation 1 26.90 0.11 4.45 13.17
1 27.60 0.11 4.45 13.51
Deduction 4.45
Lintel Band 4.45
230 mm wall 108.00 0.23 0.075 0.00
110mm wall 244.40 0.11 0.075 0.00
Sill Band
230 mm wall 108.00 0.23 0.075 0.00
110mm wall 0.11 0.075 0.00

Outer wall opening


W1 11.5 0.23 2.24 0.000
W4 5.21 0.23 3.31 0.000
W5 1 0.23 3 0.000
W8 12.3 0.23 4 0.000
4.45 0.23 1.3 0.000
W8 north 10.13 0.23 3 0.000
5.42 0.23 1.5 0.000
W9 4.82 0.23 3 0.000
5.23 0.23 1.5 0.000
W10 3.4 0.23 2.7 0.000
W13 3.46 0.23 3 0.000
W20 3.4 0.23 3 0.000
W21 0.9 0.23 3 0.000
W22 2.83 0.23 1.88 0.000
V1 0.6 0.23 1 0.000
V2 0.6 0.23 1.32 0.000
V3 0.9 0.23 1.32 0.000
inner wall opening
D1 -6 1.2 0.11 2.1 -1.663
D2 -7 1 0.11 2.1 -1.617
D3 -18 0.75 0.11 2.1 -3.119

Total = 113.24

17 First class chimney brick masonry work in (1:4) cement sand mortar in S. F.
Second floor
Outer wall
Grid 2-2 27.00 0.23 3.2 0.00
Grid 6-6 27.00 0.23 3.2 0.00
Grid A-A 27.00 0.23 3.2 0.00
Grid E-E 27.00 0.23 3.2 0.00
Inner wall
Inner 1 97.70 0.11 5.9 63.41
Between Grid 3 & 4 1 14.90 0.11 5.9 9.67
Deduction
Lintel Band
230 mm wall 108.00 0.23 0.075 0.00
110mm wall 112.60 0.11 0.075 0.00
Sill Band
230 mm wall 108.00 0.23 0.075 0.00
110mm wall 112.60 0.11 0.075 0.00

Outer wall opening


W1 11.5 0.23 2.24 0.000
W4 5.21 0.23 3.31 0.000
W5 1 0.23 4 0.000
W6 5 0.23 2 0.000
W7 3 0.23 2.32 0.000
W8 10.44 0.23 2 0.000
W8 north 3.4 0.23 4 0.000
7.64 0.23 2 0.000
W9 10 0.23 3.2 0.000
5.26 0.23 1.6 0.000
W10 3.4 0.23 3.2 0.000
W13 3.46 0.23 3 0.000
W14 2 0.23 4.46 0.000
W20 3.4 0.23 3 0.000
W21 0.9 0.23 3 0.000
W22 2.83 0.23 1.88 0.000
V1 0.6 0.23 1 0.000
V2 0.6 0.23 1.32 0.000
V3 0.9 0.23 1.32 0.000
inner wall opening
D1 0.75 0.11 2.1 0.000
D2 1 0.11 2.1 0.000
D3 1 0.11 2.1 0.000
D4 1.2 0.11 2.1 0.000

Total = 73.08

18 25 mm or 1" thick P.C.C. (1:2:4) work in floor with all complete.


Ground Floor 1 1237.49 1237.49
1st Floors 1 1237.49 1237.49
2nd Floor 1 1129.19 1129.19

Total = 3604.17

19 12.5 mm. thick cement sand plaster work 1:4 on wall.


Ground Floor
Outer wall
Grid P-P 2 17.33 4.45 154.24
Grid O-O 2 13.62 4.45 121.22
Grid G-G 2 14.06 4.45 125.13
Grid H-H 2 12.64 4.45 112.50
Grid K-K 2 13.55 4.45 120.60
Grid L-L 2 12.24 4.45 108.94

Inner wall 0.00


2 85.26 4.45 758.81
2 129.20 4.45 1149.88
2 46.20 4.45 411.18
Inner wall 2 91.50 4.45 814.35
Toilet partation 2 31.70 4.45 282.13
Toilet partation 2 46.80 4.45 416.52
Deduction
inner wall opening
D1 -16 1.2 2.1 -40.32
D2 -34 1 2.1 -71.40
D3 -42 0.75 2.1 -66.15
w -8 1.5 2.4 -28.80

First floor
Inner wall
2 135.20 4.45 1203.28
Inner wall 2 54.70 4.45 486.83
Toilet partation 2 26.90 4.45 239.41
2 27.60 4.45 245.64
Deduction
inner wall opening
D1 -12 1.2 2.1 -30.24
D2 -14 1 2.1 -29.40
D3 -36 0.75 2.1 -56.70

Second floor
Inner wall
Inner 2 97.70 5.9 1152.86
Between Grid 3 & 4 2 14.90 5.9 175.82

Total plaster = 7756.32

20 12.5 mm. thick cement sand plaster work 1:4 on ceilling


Ground Floor
Slab 1 1237.49 0.125 1237.49

Stair SC1
landing 1 7.78 7.78
1st and 2nd flight 2 6.54 13.08
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
1st flight 1 6.54 6.54
2nd flight 1 1.60 1.60
3rd flight 1 5.63 5.63
Stair S2
landing 1 7.78 7.78
1st and 2nd flight 2 7.21 14.43

1st Floors
Slab 1 1129.19 1129.19

Stair SC1
landing 1 7.78 7.78
1st and 2nd flight 2 6.54 13.08
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
1st flight 1 6.54 6.54
2nd flight 1 1.60 1.60
3rd flight 1 5.63 5.63
Stair S2
landing 1 7.78 7.78
1st and 2nd flight 2 7.21 14.43

Dome slab 2 4619.25 9238.50

Total= 11729.72

21 Sal wood works for chaukhats with all complete.


Ground Floor
MD 5.4 0.1 0.075 0.00

Total= 0.00

38 mm thick sal wood fully paneled


shutter fixing work with all complete.
22 Size of shutter 1.07 x 1.982 =2.114 Sqm.

Ground Floor
MD 1.2 2.1 0.00

Total= 0.00

Supplying and fixing of aluminium


sliding window without ventilator section
21
101x45x1.80mm including 4mm glass
and gasket all complete
Ground Floor
outer window 1 65.17 4.45 290.01
1 28.86 1.5 43.29
1 32.76 2.25 73.71
D1 4 1.2 2.1 10.08
D2 8.5 1 2.1 17.85
D3 10.5 0.75 2.1 16.54
w 2 1.5 2.4 7.20

First floor
inner wall opening 0.00
D1 3 1.2 2.1 7.56
D2 3.5 1 2.1 7.35
D3 9 0.75 2.1 14.18

Total = 487.76

22
Two coat white washing work on wall.
Outer wall
Ground Floor
Grid 1-1 18.15 2.9 0.00
Grid 4-5(projection part) 22.14 2.9 0.00
Grid A-A 12.95 2.9 0.00
Grid F-F 12.95 2.9 0.00

Total = 0.00

22 Two coat white washing work on ceilling.


Same as ceiling plaster 1 11729.72 11729.72
Total = 11729.72

23 Two coat distemper painting work without primer coat.


Ground Floor
Outer wall
Grid P-P 1 17.33 4.45 77.12
Grid O-O 1 13.62 4.45 60.61
Grid G-G 1 14.06 4.45 62.57
Grid H-H 1 12.64 4.45 56.25
Grid K-K 1 13.55 4.45 60.30
Grid L-L 1 12.24 4.45 54.47

Inner wall 0.00


2 85.26 4.45 758.81
2 129.20 4.45 1149.88
2 46.20 4.45 411.18
Inner wall 2 91.50 4.45 814.35
Toilet partation 2 31.70 4.45 282.13
Toilet partation 2 46.80 4.45 416.52
Deduction
inner wall opening
D1 -16 1.2 2.1 -40.32
D2 -34 1 2.1 -71.40
D3 -42 0.75 2.1 -66.15
w -8 1.5 2.4 -28.80

First floor
Inner wall
2 135.20 4.45 1203.28
Inner wall 2 54.70 4.45 486.83
Toilet partation 2 26.90 4.45 239.41
2 27.60 4.45 245.64
Deduction
inner wall opening
D1 -12 1.2 2.1 -30.24
D2 -14 1 2.1 -29.40
D3 -36 0.75 2.1 -56.70

Second floor
Inner wall
Inner 2 97.70 5.9 1152.86
Between Grid 3 & 4 2 14.90 5.9 175.82

Dome slab 1 4619.25 4619.25

Total = 12004.26

24 Two coat weather proof painting work over primer coat.


Ground Floor
Outer wall
Grid P-P 1 17.33 4.45 77.12
Grid O-O 1 13.62 4.45 60.61
Grid G-G 1 14.06 4.45 62.57
Grid H-H 1 12.64 4.45 56.25
Grid K-K 1 13.55 4.45 60.30
Grid L-L 1 12.24 4.45 54.47

Dome slab 1 4619.25 4619.25

Total = 4990.56

25 Two coat water proof cement paint painting work in plastered surface
Ground Floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
Ground Floor (wall)
Male Toilet 22.800 2 0.00
Female toilet 29.450 2 0.00
Toilet for disable 6.430 2 0.00
First Floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
First Floor (wall)
Male Toilet 22.800 2 0.00
Female toilet 29.450 2 0.00
Toilet for disable 6.430 2 0.00
Second floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
Second floor (wall)
Male Toilet 22.800 2 0.00
Female toilet 29.450 2 0.00
Toilet for disable 6.430 2 0.00
Third floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
Third floor (wall)
Male Toilet 22.800 2 0.00
Female toilet 29.450 2 0.00
Toilet for disable 6.430 2 0.00

Total = 0.00

26 Porcelain Non-glazed tile paving work in cement sand (1:4) mortar


Ground Floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
First Floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
Second floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00
Third floor (Flooring)
Male Toilet 12.900 0.00
Female toilet 15.230 0.00
Toilet foe disable 3.110 0.00

Total floor tile area 0.00

27 Porcelain glazed tile paving work in cement sand (1:4) mortar


Ground Floor (wall)
Male Toilet 22.800 1.5 0.00
Female toilet 29.450 1.5 0.00
Toilet for disable 6.430 1.5 0.00
First Floor (wall)
Male Toilet 22.800 1.5 0.00
Female toilet 29.450 1.5 0.00
Toilet for disable 6.430 1.5 0.00
Second floor (wall)
Male Toilet 22.800 1.5 0.00
Female toilet 29.450 1.5 0.00
Toilet for disable 6.430 1.5 0.00
Third floor (Flooring)
Male Toilet 22.800 1.5 0.00
Female toilet 29.450 1.5 0.00
Toilet for disable 6.430 1.5 0.00

Total Glazed tiles= 0.00

15 mm thick marble tile 600x600 mm


paving with 20 mm thick cement sand
28 mortar 1:2 rubbing & polishing work
with all complete.
Ground Floor
Stair SC1
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S2
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
First floor
Stair SC1
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S1
landing 1 2.93 2.93
1 2.51 2.51
tread 27 0.45 12.15
riser 26 0.23 5.85
Stair S2
landing 1 7.78 7.78
tread 27 0.45 12.15
riser 26 0.23 5.85
Total = 150.00

28 Fabrication of steel railing with 3 row of 1" horizontal pipe and vertical post and hand rail of 2"
Ground Floor
Stair SC1 1 7.5 7.50
Stair S1 1 8.5 8.50
Stair S2 1 7.5 7.50
First floor
Stair SC1 1 7.5 7.50
Stair S1 1 8.5 8.50
Stair S2 1 7.5 7.50

Total= 47.00

29 Fabricating, supplying & fixing of different size M.S. black pipe Truss with metal primer
123.25 0
Assuming 1m2 of truss work weights 35 kgs
Total = 0.00

30 Providing and laying Clay tile roofing work


18.68 0
Total = 0.00

31 26 (M) 0.50 mm thick Colour G.I. sheet roofing work


123.25 0
Total = 0.00

150 mm breadth upto 450 mm G. I. plane


sheet Gutter fixing work with 3x40 mm
32 M.S. bracke,t nut bolt & washer .

29.5 0
Total = 0.00
93557
119635
Unit

specification 19.44
m2

497.49

197.17

m3

15,120.52
197.17

m3

0.00
197.17

m2

r manual 603.75

m3

13,584.52
m3

19,866.26
m3

16,105.86
0.15 0.3
3 3
0.45 0.9 1.0062305899
m3

Mt

815.48
1,014.60
m2

1,864.41

m2

1,241.52
m2

13,589.09
m3

14,210.95
m3

15,081.56
5.9
m3

551.82

m2

417.17 2
m2
m2

292,226.50

m3

17,900.94

m2

8,166.84

-0.5

m2

38.03
m2

44.88

m2

113.71

0.5
m2

246.66

m2

334.67
m2

3,126.23

m2

3,262.34
m2

3,921.07

26.666666667
m2

3831.04

Rm

214.67

kg 387.54324

1,043.67

Sqm

1,567.18

Sqm

1,865.47

Rm
Item: Abstract of Cost of Debate Chamber Block
S.N. Description Unit Quantity Rate NRs.
Clearing of grass, removing roots, breaking sods
1 levelling the surface and disposal as per m2 2400.00 19.44
specification
Earth work excavation in foundation in clay &
2 m3 3074.58 497.49
silty soft soil lead upto 10 mtr. & lift 1.5 mtr.

Sand filling work 150mm layer wih waering and m3 3366.71 2,250.00
proper manual compaction.
Earth filling work in every 15-15 cm. layer with
3 watering & lead upto 1o.00 mtr. & proper m3 5177.83 603.75
manual compaction.
4 Dry flat Brick paving work m2 4470.04 892.34

5 P.C.C. (1:3:6) work in foundation, wall (crushed m3 322.46 13,584.52


or stone ballast)
P.C.C. (1:1:2) for R.C.C. work(USED
6 MACHINE) in slab, beam etc (crushed or stone m3 1309.89 19,866.26
ballast)
P.C.C. (1:1½:3) for R.C.C. work(USED
7 MACHINE) in slab, beam etc (crushed or stone m3 1900.88 16,105.86
ballast)
Torsteel reinforcement bar for R.C.C. work with
8 cutting, bending, binding & laying with all Mt 504.09 115,020.00
complete.

9 Trench work open type form work ( 1.50 to m2 393.61 815.48


3.00 Mtr.)
Form work shuttering & centering (BEAM-0.30-
10 0.80 Mtr) with (USED LOCAL WOOD) all m2 4612.03 1,014.60
complete.
Form work shuttering & centering (COLUMN)
11 with (USED LOCAL WOOD) all complete. m2 1995.20 1,864.41

Form work shuttering & centering with MS pipe


12 (prop), plyboard for slab etc m2 7237.90 1,241.52

13 First class chimney brick masonry work in (1:4) m3 463.63 13,589.09


cement sand mortar in G. F.

14 First class chimney brick masonry work in (1:4) m3 113.24 14,210.95


cement sand mortar in F. F.

15 First class chimney brick masonry work in (1:4) m3 73.08 15,081.56


cement sand mortar in S. F.
16 25 mm or 1" thick P.C.C. (1:2:4) work in floor m2 3604.17 551.82
with all complete.

17 12.5 mm. thick cement sand plaster work 1:4 on m2 7756.32 417.17
wall.
12.5 mm. thick cement sand plaster work 1:4 on
18 ceilling m2 11729.72 487.20

19 m3 0.00 292,226.50
Sal wood works for chaukhats with all complete.
38 mm thick sal wood fully paneled shutter
20 fixing work with all complete. Size of shutter m2 0.00 17,900.94
1.07 x 1.982 =2.114 Sqm.

Supplying and fixing of aluminium sliding


19 window without ventilator section m2 487.76 8,166.84
101x45x1.80mm including 4mm glass and
gasket all complete
20 Two coat white washing work on wall. m2 0.00 38.03
22 Two coat white washing work on ceilling. m2 11729.72 44.88
Two coat distemper painting work without
23 primer coat. m2 12004.26 113.71

Two coat weather proof painting work over


24 primer coat. m2 4990.56 246.66

Two coat water proof cement paint painting


25 work in plastered surface m2 0.00 334.67

26 Porcelain Non-glazed tile paving work in m2 0.00 3,126.23


cement sand (1:4) mortar

27 Porcelain glazed tile paving work in cement m2 0.00 3,262.34


sand (1:4) mortar
15 mm thick marble tile 600x600 mm paving
25 with 20 mm thick cement sand mortar 1:2 m2 150.00 3,921.07
rubbing & polishing work with all complete.
Fabrication of steel railing with 3 row of 1"
26 horizontal pipe and vertical post and hand rail of Rm 47.00 3,831.04
2"
### Providing and laying Clay tile roofing work Sqm 0.00 1,043.67
26 (M) 0.50 mm thick Colour G.I. sheet roofing
### work Sqm 0.00 1,567.18

Total Civil works


Sanitary Works (10%)
Electrical Work (10%)
Total =

`
Amount NRs.

46,656.00

1,529,573.55

7,575,089.18

3,126,116.43

3,988,797.28

4,380,486.16

26,022,682.36

30,615,230.93

57,980,509.64

320,981.90

4,679,364.62

3,719,870.83

8,986,003.57

6,300,275.28

1,609,178.34

1,102,121.19
1,988,853.09

3,235,704.01

5,714,721.14

0.00

0.00

3,983,449.71

0.00
526,429.98

1,365,004.40

1,230,970.54

0.00

0.00

0.00

588,160.50

180,058.88

0.00

0.00

180,796,289.53
18,079,628.95
18,079,628.95
216,955,547.43
s
Total Wt.,Kg= 158012.95 72870.51

Unit wt.,Kg/m= 0.617 0.888


256290.87 82078.57

Ø of Cut
No: of
S.N. Description Bar,m no of Length/
Footing
m top / bot bar pc (m 10Ø 12Ø

FOOTING
A) Footing F1
Top & Bottom 8.000 16 37.00 3.95

Top & Bottom 8.000 16 37.00 3.95

B) Footing F2
Top & Bottom 1.000 16 51.00 5.15

Top & Bottom 1.000 16 51.00 5.15

C) Footing F3
Top & Bottom 4.000 16 44.00 4.55

Top & Bottom 4.000 16 44.00 4.55

D) Footing F4
Top & Bottom 3.000 16 54.00 5.45

Top & Bottom 3.000 16 54.00 5.45

E) Footing F5
Top & Bottom 1.000 16 59.00 5.80

Top & Bottom 1.000 16 59.00 5.80

F) Footing F6
Top & Bottom 7.000 16 51.00 5.15

Top & Bottom 7.000 16 51.00 5.15

G) Footing F7
Top & Bottom 9.000 16 37.00 3.95

Top & Bottom 9.000 16 37.00 3.95

H) Footing CF1
Top & Bottom 1.000 20 42.00 8.32

Top & Bottom 1.000 20 100.00 4.00

I) Footing CF2
Top & Bottom 1.000 16 80.00 108.90
lap 1.00 16 800.00 0.96
Top & Bottom 1.000 16 1728.00 5.90

J) Strap beam B1
Top & Bottom 21.000 16 6.00 9.50

stirrups 21.000 10 71.20 1.45 2168.04

K) Strap beam B2 inner


Top & Bottom 1.000 16 8.00 162.30
lap 1.00 16 112.00 0.96
stirrups 1.000 10 1298.40 1.85 2402.04

L) Strap beam B2 outer


Top & Bottom 1.000 16 8.00 196.35
lap 1.00 16 136.00 0.96
stirrups 1.000 10 1570.80 1.85 2905.98

M) Tie beam B3
Top & Bottom circular 1.000 20 8.00 268.90
lap 1.00 20 184.00 1.20
1.000 16 2.00 268.90
lap 1.00 16 46.00 0.96
stirrups 1.000 10 2151.20 3.90 8389.68

Top & Bottom 24.000 20 8.00 10.30


24.000 16 2.00 9.50
stirrups 24.000 10 71.20 3.90 6664.32

COLUMN
A) Columnn C
Main bar 11.000 20 20 11.70

Stirrups 1 11.000 10 94 2.79 2872.58


Stirrups 2 11.000 10 374 1.99 8195.62

B) Column C1
Main bar
Grid O, O', P, P', A', G, H 7.000 20 20 12.65
Stirrups 1 7.000 10 101 2.79 1976.44
Stirrups 2 7.000 10 405 1.99 5638.86

C) Column C2
Main bar
Ground to First 16.000 25 24 8.95
Stirrups 1 16.000 10 72 2.79 3196.22
Stirrups 2 16.000 10 72 2.01 2302.66
Stirrups 3 16.000 10 143 2.35 5384.32
Main bar
First to Second 16.000 25 8 7.00
16.000 20 16 6.40
Stirrups 1 16.000 10 32 2.79 1428.48
Stirrups 2 16.000 10 32 2.01 1029.12
16.000 10 32 1.91 977.92
Stirrups 3 16.000 10 64 2.35 2406.40

Main bar
Second to Top 16.000 20 24 6.40

Stirrups 1 16.000 10 32 2.79 1428.48


Stirrups 2 16.000 10 32 2.01 1029.12
16.000 10 32 1.91 977.92
Stirrups 3 16.000 10 64 2.35 2406.40

Main bar curved


Second to Top 16.000 20 24 10.40

Stirrups 1 16.000 10 32 2.79 1428.48


Stirrups 2 16.000 10 32 2.01 1029.12
16.000 10 32 1.91 977.92
Stirrups 3 16.000 10 64 2.35 2406.40

D) Column C3
Main bar
16.000 32 42 17.37
lap 16.00 32 42 1.92
Stirrups 1 16.000 10 139 4.09 9093.54
Stirrups 2 16.000 10 278 2.67 11872.74
Stirrups 3 16.000 10 278 3.09 13740.36

BEAM
A) Plinth beam B3
Top & Bottom circular 1.000 20 8.00 268.90
lap 1.00 20 184.00 1.20
1.000 16 2.00 268.90
lap 1.00 16 46.00 0.96
stirrups1 1.000 10 2151.20 2.15 4625.08
stirrups2 1.000 10 2151.20 1.75 3764.60

Top & Bottom Grid 1 1.000 20 8.00 11.60


1.000 16 2.00 10.80
stirrups 1.000 10 81.60 2.15 175.44
stirrups 1.000 10 81.60 1.75 142.80

Top & Bottom Grid 2 1.000 20 8.00 9.70


1.000 16 2.00 8.90
stirrups 1.000 10 66.40 2.15 142.76
stirrups 1.000 10 66.40 1.75 116.20

Top & Bottom Grid 3 1.000 20 8.00 18.20


1.000 16 2.00 17.40
stirrups 1.000 10 134.40 2.15 288.96
stirrups 1.000 10 134.40 1.75 235.20

Top & Bottom Grid A to P 16.000 20 8.00 10.30


16.000 16 2.00 9.50
stirrups 16.000 10 71.20 2.15 2449.28
stirrups 16.000 10 71.20 1.75 1993.60

Top & Bottom Grid A', G', H', K', L', O' 6.000 20 8.00 7.40
6.000 16 2.00 6.60
stirrups 6.000 10 48.00 2.15 619.20
stirrups 6.000 10 48.00 1.75 504.00

B) First Floor Beam


Beam B4
Top & Bottom Grid 1 1.000 25 8.00 11.60
1.000 16 2.00 10.80
stirrups 1.000 10 81.60 1.75 142.80
stirrups 1.000 10 81.60 0.00 0.00

Top & Bottom Grid 2 1.000 25 8.00 9.70


1.000 16 2.00 8.90
stirrups 1.000 10 66.40 1.75 116.20
stirrups 1.000 10 66.40 0.00 0.00

Top & Bottom Grid 3 1.000 25 8.00 18.20


lap 1.00 25 8.00 1.50
1.000 16 2.00 17.40
lap 1.00 16 8.00 0.96
stirrups 1.000 10 134.40 1.75 235.20
stirrups 1.000 10 134.40 0.00 0.00

Top & Bottom outer circular B4 1.000 25 8.00 162.30


lap 1.00 25 112.00 1.50
1.000 16 2.00 162.30
lap 1.00 16 28.00 0.96
stirrups1 1.000 10 1298.40 2.15 2791.56
stirrups2 1.000 10 1298.40 1.75 2272.20

Top & Bottom inner circular 1.000 25 8.00 106.60


lap 1.00 25 72.00 1.50
1.000 16 2.00 106.60
lap 1.00 16 18.00 0.96
stirrups1 1.000 10 852.80 2.05 1748.24
stirrups2 1.000 10 852.80 1.65 1407.12
Beam B4
Top & Bottom Grid A to E, L to O, I 10.000 25 8.00 11.90
10.000 16 2.00 9.50
stirrups 10.000 10 84.00 2.05 1722.00
stirrups 10.000 10 84.00 1.65 1386.00

Top & Bottom Grid F, G, H, J, K 5.000 25 8.00 10.30


5.000 16 2.00 9.50
stirrups 5.000 10 71.20 2.05 729.80
stirrups 5.000 10 71.20 1.65 587.40

Top & Bottom Grid G', H', K', L', O',


25 8.00 8.30
A' B4 6.000
6.000 16 2.00 9.50
stirrups 6.000 10 55.20 2.05 678.96
stirrups 6.000 10 55.20 1.65 546.48

Top & Bottom Beam B4 1.000 25 8.00 33.20


lap 1.00 25 16.00 1.50
1.000 16 2.00 33.20
lap 1.00 16 6.00 0.96
stirrups1 1.000 10 260.00 2.05 533.00
stirrups2 1.000 10 260.00 1.65 429.00

Top & Bottom Beam B4 1.000 25 8.00 7.40


1.000 16 2.00 7.40
stirrups1 1.000 10 53.60 2.05 109.88
stirrups2 1.000 10 53.60 1.65 88.44

Top & Bottom Beam B5 1.000 25 8.00 17.75


1.000 16 2.00 17.75
stirrups1 1.000 10 126.40 2.05 259.12
stirrups2 1.000 10 126.40 1.65 208.56

Top & Bottom Beam B6


1.000 16 6.00 75.20
lap 1.00 16 42.00 0.96
stirrups1 1.000 10 592.00 1.45 858.40

Top & Bottom Beam B7


1.000 16 6.00 49.50
lap 1.00 16 30.00 0.96
stirrups1 1.000 10 384.80 1.35 519.48

C) Second Floor Beam


Top & Bottom Beam B3 Grid 1 1.000 20 8.00 10.20
1.000 16 2.00 10.20
stirrups1 1.000 10 81.60 2.15 175.44
stirrups2 1.000 10 81.60 1.75 142.80
Top & Bottom Beam B3 Grid 2 1.000 20 8.00 8.30
1.000 16 2.00 8.30
stirrups1 1.000 10 66.40 2.15 142.76
stirrups2 1.000 10 66.40 1.75 116.20

Top & Bottom Beam B3 circular 1.000 20 8.00 142.48


lap 1.00 20 96.00 1.20
1.000 16 2.00 142.48
lap 1.00 16 24.00 0.96
stirrups1 1.000 10 1139.84 2.15 2450.66
stirrups2 1.000 10 1139.84 1.75 1994.72

Top & Bottom Beam B3 Grid A to O 15.000 20 8.00 7.40


15.000 16 2.00 7.40
stirrups1 15.000 10 59.20 2.15 1909.20
stirrups2 15.000 10 59.20 1.75 1554.00

Top & Bottom Beam B3 Grid G, H, K , L 4.000 20 8.00 5.90


4.000 16 2.00 5.90
stirrups1 4.000 10 47.20 2.15 405.92
stirrups2 4.000 10 47.20 1.75 330.40

Top & Bottom Beam B6 Circular


1.000 16 6.00 97.20
lap 1.00 16 54.00 0.96
stirrups1 1.000 10 777.60 1.45 1127.52

Beam B7
Grid 1' 1.000 16 6.00 10.20
stirrups1 1.000 10 81.60 1.35 110.16

Grid 2' 1.000 16 6.00 8.30


stirrups1 1.000 10 66.40 1.35 89.64

Grid 3, 3' 2.000 16 6.00 16.10


lap 2.00 16 6.00 0.96
stirrups1 2.000 10 128.80 1.35 347.76

Grid circular 1.000 16 6.00 114.07


lap 1.00 16 60.00 0.96
stirrups1 1.000 10 912.56 1.35 1231.96

Grid A' to E' & H' to N' 12.000 16 6.00 5.20


stirrups1 12.000 10 41.60 1.35 673.92

1.000 16 6.00 31.30


lap 1.00 16 24.00 0.96
stirrups1 1.000 10 250.40 1.35 338.04
Grid A', O 2.000 16 6.00 5.30
stirrups1 2.000 10 42.40 1.35 114.48

Grid P' 1.000 16 6.00 8.50


stirrups1 1.000 10 68.00 1.35 91.80

Beam B8
Circular Grid 1.000 20 8.00 107.85
lap 1.00 20 72.00 1.20
1.000 16 2.00 107.85
lap 1.00 16 18.00 0.96
stirrups1 1.000 10 862.80 2.05 1768.74
stirrups2 1.000 10 862.80 1.65 1423.62

Circular Grid 1.000 20 8.00 4.20


1.000 16 2.00 4.20
stirrups1 1.000 10 33.60 2.05 68.88
stirrups2 1.000 10 33.60 1.65 55.44

Grid F' 1.000 20 8.00 5.30


1.000 16 2.00 5.30
stirrups1 1.000 10 42.40 2.05 86.92
stirrups2 1.000 10 42.40 1.65 69.96

Grid 2.000 20 8.00 5.20


2.000 16 2.00 5.20
stirrups1 2.000 10 41.60 2.05 170.56
stirrups2 2.000 10 41.60 1.65 137.28

D) Dome Beam
Circular Grid Beam B9 1.000 20 4.00 22.33
lap 1.00 20 4.00 1.20
1.000 16 4.00 22.33
lap 1.00 16 4.00 0.96
stirrups1 1.000 10 178.64 2.15 384.08
stirrups2 1.000 10 178.64 1.55 276.89

Circular Grid Beam B10 1.000 25 30.00 110.44


lap 1.00 25 300.00 1.50
stirrups1 1.000 10 883.52 4.95 4373.42
stirrups2 1.000 10 30.00 3.75 112.50
stirrups3 2.000 10 883.52 3.45 6096.29

SLAB & STAIRECASE


A) Dome slab from first to second
Top & Bottom 2.0 12 34.67 153.03 10610.08
lap 2.00 12 450.67 0.72 648.96
Top & Bottom 2.0 12 1090.47 6.64 14481.40

B) Dome slab from second to third


Top & Bottom 2.0 12 42.67 126.47 10791.68
lap 2.00 12 469.33 0.72 675.84
Top & Bottom 2.0 12 949.93 7.84 14894.95

C) Dome slab from third to roof


Top & Bottom 2.0 12 42.67 64.65 5516.37
lap 2.00 12 256.00 0.72 368.64
Top & Bottom 2.0 12 736.27 15.64 23030.42
lap 2.00 12 736.27 0.72 1060.22
D) First floor slab
Top & Bottom 2.0 10 74.40 163.57 24339.22
lap 2.00 10 967.20 0.60 1160.64
Top & Bottom 2.0 10 1308.56 9.30 24339.22

E) Second floor slab


Top & Bottom 2.0 10 59.20 142.48 16869.63
lap 2.00 10 710.40 0.60 852.48
Top & Bottom 2.0 10 1139.84 7.40 16869.63

E) Third floor slab


Top & Bottom 2.0 10 7.20 102.75 1479.60
lap 2.00 10 64.80 0.60 77.76
Top & Bottom 2.0 10 1139.84 0.90 2051.71

F) Stairecase
Stairecase 1
Main bar 2.0 16 10.00 8.64
4.0 16 10.00 3.76
Distribution bar 2.0 10 57.60 1.50 172.80
4.0 10 25.07 1.50 150.40
Nosing 2.0 10 11.00 1.44 31.57
2.0 10 11.00 1.50 33.00
landing beam 3.0 16 6.00 5.20
stirrups 3.0 10 36.00 1.35 145.80

Stairecase 1
Main bar 2.0 16 10.00 8.64
4.0 16 10.00 3.76
Distribution bar 2.0 10 57.60 1.50 172.80
4.0 10 25.07 1.50 150.40
Nosing 2.0 10 11.00 1.44 31.57
2.0 10 11.00 1.50 33.00
landing beam 3.0 16 6.00 5.20
stirrups 3.0 10 36.00 1.35 145.80

Stairecase 2
Main bar 3.00 16 12.00 6.65
3.00 16 12.00 6.65
Distribution bar 6.00 10 44.33 1.80 478.80
Nosing 3.00 10 9.00 1.44 38.75
3.00 10 9.00 1.80 48.60
landing beam 3.00 16 6.00 6.20
stirrups 3.00 10 44.00 1.35 178.20

Stairecase 2
Main bar 3.00 16 12.00 6.65
3.00 16 12.00 6.65
Distribution bar 6.00 10 44.33 1.80 478.80
Nosing 3.00 10 9.00 1.44 38.75
3.00 10 9.00 1.80 48.60
landing beam 3.00 16 6.00 6.20
stirrups 3.00 10 44.00 1.35 178.20

Stairecase 3
Main bar 2.00 16 10.00 7.28
4.00 16 10.00 2.46
Distribution bar 2.00 10 48.53 1.50 145.60
4.00 10 16.40 1.50 98.40
Nosing 2.00 10 12.00 1.44 34.44
2.00 10 12.00 1.50 36.00
landing beam 2.00 16 8.00 5.08
stirrups 2.00 10 34.24 1.45 99.30

Main bar 2.00 16 10.00 4.58


Distribution bar 2.00 10 30.53 1.50 91.60
Nosing 2.00 10 3.00 1.44 8.61
landing Z beam 1.00 16 8.00 5.38
stirrups 1.00 10 36.64 1.45 53.13
74386.67 63078.20 50495.97 81839.13 500.683 mt
1.578 2.466 3.853 6.313
47129.80 25577.60 13104.40 12962.88

Remark
16Ø 20Ø 25Ø 32Ø

1169.20

1169.20

262.65

262.65

800.80

800.80

882.90

882.90

342.20

342.20

1838.55

1838.55

1315.35

1315.35

349.44

400.00
8712.00
768.00
10195.20

1197.00

1298.40
107.52

1570.80
130.56

2151.20
220.80
537.80
44.16

1977.60
456.00

2574.00

1771.00

3436.80
896.00
1638.40

2457.60

3993.60

11672.64
1290.24

2151.20
220.80
537.80
44.16

92.80
21.60

77.60
17.80
145.60
34.80

1318.40
304.00

355.20
79.20

92.80
21.60

77.60
17.80

145.60
12.00
34.80
7.68

1298.40
168.00
324.60
26.88

852.80
108.00
213.20
17.28
952.00
190.00

412.00
95.00

398.40

114.00

265.60
24.00
66.40
5.76

59.20
14.80

142.00
35.50

451.20
40.32

297.00
28.80

81.60
20.40
66.40
16.60

1139.84
115.20
284.96
23.04

888.00
222.00

188.80
47.20

583.20
51.84

61.20

49.80

193.20
11.52

684.42
57.60

374.40

187.80
23.04
63.60

51.00

862.80
86.40
215.70
17.28

33.60
8.40

42.40
10.60

83.20
20.80

89.32
4.80
89.32
3.84

3313.20
450.00
172.80
150.40

93.60

172.80
150.40

93.60

239.40
239.40
111.60

239.40
239.40

111.60

145.60
98.40

81.28

91.60

43.04

You might also like