Professional Documents
Culture Documents
net/publication/347357911
CITATIONS READS
0 319
1 author:
Dipesh Majumdar
Jadavpur University
32 PUBLICATIONS 3 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Ultra High Performance Concrete with High Compressive Strength: A Subcontinental Approach View project
All content following this page was uploaded by Dipesh Majumdar on 16 December 2020.
loose delaminated concrete particles and plasters are to be eliminated from column surface in very sensible way.
Minimum impact due to elimination of delaminated concrete from existing column member is to be ensured.
Following process for elimination may be adopted
4.2 Repair Methodology for removing and cleaning of dust / loose particle / spalled concrete from
existing column surface.
• Staging with necessary platform to facilitate work adjacent to distressed portion shall be done.
• The Damaged /loose concrete should be removed carefully by chisel and hammer or by breaker (Direct
hammering should be avoided).
• Cleaning the surfaces by use of high pressure water blower & removal of loose adhering materials.
• The existing surface should be cleaned by gentle hammering, if flakes are observed and by wire brushing
only.
4.3 Some cracks are noticed on beams and columns, those are to be sealed with epoxy grout. Repair
Methodology for Stitching of Cracks and Sealing of Cracks.
• Groove cutting all along the line of cracks, cleaning the same by use of high pressure water blower and
removal of loose adhering materials.
• Drilling the holes by use of drill machine, fixing the 12.5 mm dia G.I nozzles/ PVC nozzle with epoxy
patching mortar along the crack area.
• Sealing the groove with 2 comp. epoxy patching mortar.
• Providing and grouting “Epoxy based, flowable, High early Strength, two stage expanding Grout”
through prefixed PVC nozzle/GI nozzle with proper consistency. The minimum pressure for grouting
shall be 2.0kg/cm².
• After grouting work, removal off the nozzles, sealing the same with 2 comp. epoxy patching mortar.
4.4 Repair Methodology for application of Polymer Modified Mortar on some portion of beam column
and slab, where distress is minor.
• Removal of loose concrete and cleaning of surfaces as per procedure outlined in earlier clause
• Providing & applying one coat of polymer bonding coat in proportion 1:0.5 (i.e. polymer : Cement by
wt.) over cleaned concrete surface etc. complete.
• Providing & applying single component, fibre reinforced high performance polymer modified mortar on
cleaned concrete surface of wall, bottom slab and other surfaces. The mortar shall develop compressive
strength up to 20 MPa in 3 days.
4.5 Repair Methodology for cleaning and removing corrosion from corroded rebar.
• The existing exposed reinforcements should be cleaned by gentle hammering, if flakes are observed and
by wire brushing only.
• Exposed reinforcements are to be cleaned and rust to be removed by use of “Corrosion Removing Gel ”.
4.6 All columns and beams are to be jacketed with free flowing micro-concrete system.
• Dismantling of existing floor and excavation around existing columns is to be done with proper care as
per following Fig. No. 1.
Outer part of
Excavation Line
Inner part of
• During Jacketing of existing RCC columns extra reinforcement is to be provided externally. Anchoring
of vertical reinforcement (16 mm dia) is to be done on existing top of RCC foundations.
P.L. Level
Temporary
wooden
support to
Excavated Side
Earth Side
Fig. No. 2 : After completion of excavation near existing column. 08 (eight) nos. 16mm dia rebar is to be are honed in existing top of
foundation.
• Stirrups of jacketed columns are to be fixed as per following Fig. No. 3. There will be two nos. of stirrup
per set as shown in Fig. No. 3.
Dismantled part of
existing brick work
Stirrup details
Fig. No. 3 : Plan drawing showing anchoring arrangement of 16mm dia rebars and fixing details of stirrup reinforcement.
• Existing RCC slab of 1st floor and 2nd floor is to be punctured to accommodate vertical extension of
vertical reinforcement into next floor level as per following Fig. no. 4.
Fig. No. 4 : Top of first floor slab showing arrangement for extension arrangement of longitudinal reinforcement through minor dismantling
of first floor slab only.
• Existing beams are moderately damaged due to fire exposure. Existing RCC beams are to be
strengthened by jacketing methods. During jacketing of RCC columns three nos. of dowel reinforcement
are to be left for beam jacketing as per Fig. no. 5
Longitudinal
reinforcement
Detail ‘A’
Fig. No. 5 : Sketch showing reinforcement arrangement of vertical column reinforcement. Connection between beam and column
reinforcement is also shown.
Beams are to be jacketed with micro-concrete. At first shear reinforcements are to be anchored in existing roof
slab with HILTI chemical anchor system as per Fig. No. 6. Then main longitudinal reinforcements are to be
fixed as per Fig. No. 7. Finally micro concreting is to be done with Pre Packed Micro- Concrete system.
80mm anchor is to be
done
Existing Beam
Sectional view showing fixing plan of extra shear reinforcement with existing slab.
Fig. No. 6 : Sketch showing fixing arrangement of new stirrup to strengthen existing RCC beams.
Micro-concrete
Shuttering plate
• Existing slab is to be strengthened with overlaying concrete jacketing on top of the slab as per Fig. No. 8.
Shear connector with 10mm dia rebars is to be provided on top of the RCC slab @ 4 nos. per sqm. Area.
Thickness of overlaying concrete will be 65mm. Reinforcement bar details is to be followed as per Fig.
no. 8.
Fig. No. 8 : Sketch showing strengthening arrangement of new stirrup to strengthen existing RCC beams.
Reference
[1] Jirsa, J.O., “Behavior Of Epoxy-Grouted Dowels And Bolts Used For Repair Or Strengthening Of R.C. Structures, “Proceedings,
9wcee.
[2] Aci Committee 318, “Building Code Requirements For Reinforced Concrete,” Aci 318-83, American Concrete Institute, 1983.
[3] Luke, Philip C.C., Chon, Carlos, Jirsa, J.O., “Use Of Epoxies For Grouting Reinforcing Bar Dowels In Concrete, “Pmfsel Report 85-2,
Ferguson Structural Engineering Laboratory, University Of Texas At Austin, September 1985.
[4] H. J. Degenkolb Associates, “Connections To Existing Concrete For Seismic Rehabilitation,” To Be Published In 1988.
[5] Bass, Robert A, Corrasquillo, Ramon L, Jirsa, J.O., “Interface Shear Capacity Of Concrete Surfaces Used In Strengthening Structures,
“Pmfsel Report 85-4, December 1985.
[6] Winer, David F, “Behavior Of Steel To Concrete Connections Used To Strengthen Existing Structures, M.S. Thesis, University Of
Texas At Austin, August 1985.
[7] S.M. Alcocer, Head Of The Seismic Testing Area, National Center For Disaster Prevention; Associate Professor, Institute Of
Engineering, Unam, Mexico ‘Design Of Earthquake-Resistant R/C Beam-Column Joints Rehabilitated Using Jacketing’