Risk assessment form

Name of assessor Abdul Sammad Date 18-01-2022

Time 09:00 AM Work area Construction Area

Task being assessed Welding & cutting, Power tools, Manual Handling

New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
Fire during Workers, Burns due to The workers Fire extinguisher 2 Work Supervisor 20-01-2022
welding activity Visitors, fire, fumes, wearing PPE i.e., 5 Fire blanket
4 20
because of poor smoke effecting face shield, Fire watch
housekeeping Staff, breathing of the coveralls, leather Good
and presence of Members of workers. hand gloves, Housekeeping 2 4
flammable public. safety shoes, Competent
materials in the welding apron. welder Tool box
immediate area. talk
Safety campaign
Designated
smoking area.
Electricity from Damaged /partly No control measures 4 4 16 Put safety sign near 2 3 6 Area Supervisor 19-01-2022
damaged Workers, stripped electrical observed. electrical potential
electrical wires. Staff, wires are scattered points/areas.
Contractors, on the ground which Raise awareness on
Visitors. may cause electrical hazards.
electrocution and Reroute the cables.
result in severe
electric burn injury.
Risk assessment form

New risk
What is the Who might be How might Existing risk Risk rating Additional Action/ Action/
people be control rating monitored by monitored by
hazard? harmed? controls
harmed? measures (Residual) whom? when?
L C R L C R
Trailing cables may Workers wearing 5 4 20 Remove and 1 4 4 Area Supervisor 19-01-2022
Trip hazard from
Workers cause people to trip PPE. rearrange cables
poorly scattered
Staff over and it will Working Gloves. and provide a
electrical wires
Visitors. result in personal Exclusion zone for proper cable route
while workers
injury or broken workers preventing away from the busy
carrying curb
bones. machine interface work area.
stones manually

Exposure to No controls 2 2 4 Make hearing 2 2 4 Area Supervisor 20-01-2022.


Noise hazard from Operator, excessive noise for available for noise protection Aids
a grinding Other workers, longer duration can exposure. available.
machine Visitors. cause hearing loss. Train workers on
operation. noise hazards and
controls.

Review date 18-01-2023 Signature Abdul Sammad