You are on page 1of 2

Risk assessment form

Name of assessor MOHAMMAD SHAHBAZ SOHAIL Date 10/10/2022

Time 11:00 AM Work area CONSTRUCTION OF BOILER

Task being assessed CIVIL AND MECHANICAL WORKS

New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
confined space every one entering in case of any confined space 4 blower fan to 3 safety officer, site before commencing
into confined space difficulty in attendant deployed provided for engineer of work
breathing due to with entry and exit continuous air
insufficient oxygen log sheet and valid circulation to
in confined space work permit 4 16 maintain oxygen 2 6
may result in level and provide
unconsciousness multi gas detector
and injury

height work technicians and fall from height may ladders are been 3 mechanize the 2 site engineer, site before starting of
workers result in permanent used for ascending process by supervisor work
or temporary and descending of replacing ladder by
disabilities, piercing workers with man elevated work
o material or bone provision of full placer(MEWP)
4 12 2 4
fracture body harness
Risk assessment form

New risk
How might Existing Risk rating rating Action/ Action/
What is the Who might be Additional
people be risk control (Residual) monitored by monitored by
hazard? harmed? controls
harmed? measures whom? when?
L C R L C R
vibration jack hammer prolong exposure of tool box talk are 3 provision of anti 2 site foremen before starting of
operator and operators to delivered regularly vibration gloves to work
masonry workers vibration may lead and health dampen vibration
to numbness and surveillance is done
tingling effect for jack hammer
4 12 3 6
operator

fire welders and welding operation sand buckets and 4 flammable 3 site foremen and before commencing
workers was done near portable fire materials to be safety officer of work
flammable material extinguisher were removed from
which has potential provided near vicinity of welding
to ignite fire when welding area area, fire resistance
gets contact with 4 16 3 9
blankets to be used
sparks for covering of
welding activity

Review date 10/11/2022 Signature MOHAMMAD SHAHBAZ SOHAIL