SCHEDULE OF WORKS and EXECUTION PROCCESS


RIDICULOUS ROADS MURAL PAINTING ( 5 WEEKS PROJECTED DURATION ) *weather condition may disrupt the projected timeline
WORKERS : 4 - ARTISTS, 3 -VIDEOGRAPHER/PHOTOGRAPHER LEGEND EXECUTED AREAS
WORKING DURATION P P P P WORKING DURATION WITH THE PHOTO PROJECTED SCHEDULED DURATION

CURRENT EXPECTED WORK SCHEDULES AND PROGRESS (50% DONE)

AUGUST SEPTEMBER
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK6
SITE ACTIVITIES
M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1
JLU BUILDING FACING PUBLIC MARKET FIRST 2 LANES EXECUTED
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)

SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
ICM FACING KENNY ROASTERS FIRST 2 LANES EXECUTED
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)

SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
ICM FACING KENNY ROASTERS 2ND 2 LANES EXECUTED
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)

SKETCHING

COLORING / FILLING P
DRYING / CURING
CATHEDRAL FACING PLAZA RIZAL FIRST LANE WORK IN PROGRESS
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING
COLORING / FILLING P P
CURING
JLU BUILDING FACING PUBLIC MARKET 2ND 2 LANES
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING
COLORING / FILLING P P
DRYING / CURING
CATHEDRAL FACING PLAZA RIZAL 2ND LANE
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING p
COLORING / FILLING P P P
CURING
REVIEW AND FINAL RETOUCH
REVIEW AND FINAL RETOUCHES P P
FINAL PHOTOSHOOTS P
TURN OVER

PREVIOUS PROJECTED TIMELINE (MAXIMUM WORK DURATION)


SITE ACTIVITIES AUGUST SEPTEMBER
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK6
M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S S M T W TH F S
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1
JLU BUILDING FACING PUBLIC MARKET FIRST 2 LANES
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
ICM FACING KENNY ROASTERS FIRST 2 LANES *JLU AND ICM AREA MUST BE EXECUTED AT THE SAME WEEK IF NECESSARY
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
CATHEDRAL FACING PLAZA RIZAL FIRST LANE
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
JLU BUILDING FACING PUBLIC MARKET 2ND 2 LANES
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
ICM FACING KENNY ROASTERS 2ND 2 LANES
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
CATHEDRAL FACING PLAZA RIZAL 2ND LANE
SITE PREPARATION / LAYOUTING P
SURFACE SEALING (PRIMER)
SKETCHING P
COLORING / FILLING P P P
DRYING / CURING
REVIEW AND FINAL RETOUCH
REVIEW AND FINAL RETOUCH
FINAL PHOTOSHOOTS P
TURN OVER P