Item Pekerjaan Kode Budget Bobot Okt Nov

24 30 6 13 20
Pekerjaan Geolistrik 0 0
Mob demob Tools and Crew NTT 8400000 0.55414034 0.185
Mob demob Tools and Crew Gor 8000000 0.5277527 0.176
Expert and Surveyor GL 8500000 0.56073724 0.187
Survey Works GL 36500000 2.4078717 0.803
Mobilisasi dan Demobilisasi
Mob demob Rig 1 Unit NTT 19000000 1.25341266
Mob demob Crew 5 pax NTT 35000000 2.30891806
Mob demob Rig 1 Unit Gor 19000000 1.25341266
Mob demob Crew 5 pax GOR 15000000 0.98953631
Operasional Bor
Ops Bor 300000000 19.7907263
Gaji dan Upah
Gaji Iwan 24000000 1.5832581
Gaji Tisa 15000000 0.98953631
Gaji Ahmad 18000000 1.18744358
Gaji Anci 21000000 1.38535084
Gaji Abri 13500000 0.89058268
Gaji Yudi 13500000 0.89058268
Gaji Urip 13500000 0.89058268
Gaji Al 15000000 0.98953631
Gaji Dono 20000000 1.31938175
Gaji Awal 30000000 1.97907263
Mnus 30000000 1.97907263
Administrasi Kantor
Office 2000000 0.13193818
Izin 2500000 0.16492272
Laporan 2500000 0.16492272
Geophysical Logging 40000000 2.6387635
Water Quality 6000000 0.39581453
Entertain PTTEP 14000000 0.92356723
GYT 175000000 11.5445903
PPN 197961500 13.0593395
DD 150000000 9.89536313
Lain2 12500000 0.82461359
Pengadaan
HDPE Pipe d = 6" 56500000 3.72725345
HDPE Pipe screen d = 6" modified 9000000 0.59372179
Riser Pipe diameter 1,5 inchi 6000000 0.39581453
Gravel Pack 3000000 0.19790726
Cement Grouting 6000000 0.39581453
Material Delivery 7000000 0.46178361
Submersible Pump 3 Phase, 8 m3/hr 65000000
Head 100 m
4.28799069
Generator Set 48000000 3.1665162
Well Shelter 30000000 1.97907263
Storage Tank 5000 l and outlets 17000000 1.12147449
Accessories 3000000 0.19790726
Des Jan
27 4 11 18 25 1 8 15 22 29