Professional Documents
Culture Documents
a.
[11 marks](9/11)
Since the settlement and crack in the paving of the new car park will
certainly impair the performance of the works when it is in use, either
the Project Manager or the Contractor notifies an early warning for
discussion as soon as possible (clause 15.1).
In parallel, the reasons for the settlement have to be found out, whether
it is a Defect or a design fault. The Project Manager will check if a
failure to comply with quality plan by the Contractor has happened.
Supervisor will review the results of any tests and inspections previously
carried out to the location of the settlement to see if errors or mistakes
had been made (clause 41.3).
The Project Manager may instruct the Supervisor to attend the early
warning meeting (clause 15.2). At the early warning meeting, all parties
will act in a spirit of mutual trust and cooperation (clause 10.2). If there
is no fault with the Contractor in compliance with the quality plan or no
anomalies was found in any tests and inspections, the Project Manager
may decide and the Supervisor will instruct the Contractor to search for
Defect in the settled paving according to clause 43.1 including doing
tests and inspections which the Scope does not require.
Since the Defect (the settled paving) is a part of the works which is not
in accordance with the Scope (clause 11.2(6)), correcting the Defect by
the Contractor is not a compensation event (clause 60.1(1)).
According to clause 44.4, if the new car park area has been taken over,
the Project Manager will arrange for the Client to allow the Contractor
access to and use the area where the settled paving exists if it is
needed for correcting the Defect. The defect correction period begins
when the necessary access and use have been provided by the Client.
When the notified Defect has been corrected, the Supervisor issues the
Defects Certificate (clause 44.3).
If the Contractor is given access to correct the Defect but does not
correct the Defect within the defect correction period, the Project
Manager assesses the cost of having the Defect corrected by other
people and the Contractor is responsible to pay the amount (clause
46.1). The Project Manager will do the same assessment if the
Contractor is not given access to correct the Defect before the defects
date (clause 46.2). In such case the Scope is treated as having been
changed to accept the Defect.
.
b.
[4 marks](4/4)
If it was determined after a search for a Defect was carried out by the
Contractor upon an instruction given the Supervisor under clause 43.1,
it constitutes a compensation event under clause 60.1(10). Either the
Project Manager or the Contractor may notify a compensation event
(clauses 61.1 and 61.3).
c.
[4 marks](4/4)
d.
[6 marks](5/6)
Under clause 26.2, the reason for not accepting the SubContractor is
that the appointment will not allow the Contractor to Provide the Works.
If it is the case, the Project Manager should notify it within the period of
reply stating clearing the reasons in sufficient details to enable the
Contractor to correct the matter (clause 13.4). If the reason for
withholding acceptance is that more information is needed to enable full
assessment, the Project Manager notifies the Contracctor for
resubmission within the period of reply. The Contractor should
understand that it is its responsibility to ensure the proposed
SubContractor is competent and is able to Provide the Works.