Professional Documents
Culture Documents
Loadflow Panel
Loadflow Panel
Slide 2
Load Flow Problem
• Given
– Load Power Consumption at all buses
– Configuration
– Power Production at each generator
• Basic Requirement
– Power Flow in each line and transformer
– Voltage Magnitude and Phase Angle at each bus
Slide 3
Load Flow Studies
• Determine Steady State Operating Conditions
– Voltage Profile
– Power Flows
– Current Flows
– Power Factors
– Transformer LTC Settings
– Voltage Drops
– Generator’s Mvar Demand (Qmax & Qmin)
– Total Generation & Power Demand
– Steady State Stability Limits
– MW & Mvar Losses
Slide 4
Size & Determine System
Equipment & Parameters
• Cable / Feeder Capacity
• Capacitor Size
• Transformer MVA & kV Ratings (Turn Ratios)
• Transformer Impedance & Tap Setting
• Current Limiting Reactor Rating & Imp.
• MCC & Switchgear Current Ratings
• Generator Operating Mode (Isochronous / Droop)
• Generator’s Mvar Demand
• Transmission, Distribution & Utilization kV
Slide 5
Optimize Operating
Conditions
• Bus Voltages are Within Acceptable Limits
• Fast in speed, but high requirement on • Fast in speed, but low in solution
initial values. precision.
• First order derivative is used to speed up • Better for radial systems and
calculation. systems with long lines.
Slide 8
Load Nameplate Data
Slide 9
Constant Power Loads
• In Load Flow calculations induction,
synchronous and lump loads are treated
as constant power loads.
• The power output remains constant even
if the input voltage changes (constant
kVA).
• The lump load power output behaves like
a constant power load for the specified %
motor load.
Slide 10
Constant Impedance Loads
• In Load Flow calculations Static Loads, Lump Loads
(% static), Capacitors and Harmonic Filters and Motor
Operated Valves are treated as Constant Impedance
Loads.
• The Input Power increases proportionally to the
square of the Input Voltage.
• In Load Flow Harmonic Filters may be used as
capacitive loads for Power Factor Correction.
• MOVs are modeled as constant impedance loads
because of their operating characteristics.
Constant Current Loads
• The current remains constant even if the
voltage changes.
• DC Constant current loads are used to test
Battery discharge capacity.
• AC constant current loads may be used to test
UPS systems performance.
• DC Constant Current Loads may be defined in
PowerStation by defining Load Duty Cycles
used for Battery Sizing & Discharge purposes.
Slide 12
Constant Current Loads
Slide 13
Generic Loads
Exponential Load
Polynomial Load
Comprehensive
Load
Slide 14
Generator Operation Modes
Feedback Voltage
•AVR: Automatic Voltage
Regulation
•Fixed: Fixed Excitation
(no AVR action)
Slide 15
Governor Operating Modes
• Isochronous: This governor setting allows the
generator’s power output to be adjusted based on
the system demand.
• Droop: This governor setting allows the generator
to be Base Loaded, meaning that the MW output is
fixed.
Slide 16
In PowerStation Generators and Power Grids have four
operating modes that are used in Load Flow calculations.
Swing Mode
•Governor is operating in
Isochronous mode
•Automatic Voltage Regulator
Voltage Control
•Governor is operating in
Droop Mode
•Automatic Voltage Regulator
Mvar Control
•Governor is operating in
Droop Mode
•Fixed Field Excitation (no AVR
action)
PF Control
•Governor is operating in
Droop Mode
•AVR Adjusts to Power Factor
Setting
Slide 17
Slide 18
Lump Load Negative
Loading
Slide 19
Load Flow Adjustments
• Transformer Impedance
– Adjust transformer impedance based on possible length variation
tolerance
• Reactor Impedance
– Adjust reactor impedance based on specified tolerance
• Overload Heater
– Adjust Overload Heater resistance based on specified tolerance
• Cable Length
– Adjust Cable Impedance based on possible length variation tolerance
Slide 20
Load Flow Study Case
Adjustment Page
Adjustments applied
•Individual
•Global
Temperature Correction
• Cable Resistance
• Transmission Line
Resistance
Slide 21
Load Flow Example 1 Power Grid
1000 MVAsc
Part 1 X/R = 22
Gen1
10 MW
Voltage Control
Design:
%Pf = 85
Transformers MW = 5
T1 = 30 MVA Max Q = 4
T2 = 15 MVA Min Q = -1
T3 = 5 MVA
T4 = 3 MVA
Select typical %Z &
X/R
Cable1
ICEA 15kV 3/C CU,
100%
Size= 250 Impedance
Length= 400 ft Z1
13.8 kV
Cable2 100MVA
KERITE 5kV 3/C % Z = 0.01+j1
CU, 100%
Size= 500
Length= 300 ft
Load Flow Example 1 Transformer
T5 = 5 MVA
Part 2 Select typical %Z
& X/R
Cable3
ICEA 5kV 3/C
CU, 133%
Size= 500
Length= 100 ft
Slide 23
Load Flow Alerts
Slide 24
Equipment Overload Alerts
Slide 26
If the Auto Display
feature is active, the
Alert View Window
will appear as soon as
the Load Flow
calculation has
finished.
Load Flow Convergence
• Negative Impedance
Slide 28
Voltage Control
• Under/Over Voltage Conditions must be
fixed for proper equipment operation and
insulation ratings be met.
Slide 29
Under-Voltage Example
• Create Under Voltage • Method 2 - Shunt
Condition Capacitor
– Change Syn2 Quantity to 6. – Add Shunt Capacitor to Bus8
(Info Page, Quantity Field) – 300 kvar 3 Banks
– Run LF – Voltage is improved
– Bus8 Turns Magenta (Under • Method 3 - Change Tap
Voltage Condition)
– Place LTC on Primary of T6
• Method 1 - Change Xfmr – Select Bus8 for Control Bus
– Change T4 from 3 MVA to 8 – Select Update LTC in the
MVA, will notice slight Study Case
improvement on the Bus8 kV – Run LF
– Too Expensive and time – Bus Voltage Comes within
consuming specified limits
Slide 30
Mvar Control
• Vars from Utility • Method 2 – Add Capacitor
– Add Switch to CAP1 – Close Switch
– Open Switch – Run Load Flow
– Run LF
– Var Contribution from the
Utility reduces
• Method 1 – Generator
– Change Generator from • Method 3 – Xfmr MVA
Voltage Control to Mvar
Control – Change T1 Mva to 40 MVA
– Set Mvar Design Setting to 5 – Will notice decrease in the
Mvars contribution from the Utility
Slide 31