ID Task Task Name Duration Start Finish March 2020 April 2020 May 2020 June 2020 July

Duration Start Finish March 2020 April 2020 May 2020 June 2020 July 2020 August 2020 September 2020
Mode 17 18 19 20 21 22 23 24 25 26 27 28 29 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15
1
2 DINAMICKI PLAN AKTIVNOSTI NA PROJEKTU RETAIL PARK VRANJE 137.2 days 21-02-20 31-08-20 21-02 DINAMICKI PLAN AKTIVNOSTI NA PROJEKTU RETAIL PARK VRANJE 31-08
3 POTPISIVANJE UGOVORA 0 days 21-02-20 21-02-20 21-02
4 DOSTAVLANJE PGD 0 days 24-02-20 24-02-20 24-02
5 DOSTAVLJANJE GRADJEVINSKE DOZVOLE 0 days 24-02-20 24-02-20 24-02
6 DOSTAVLANJE PZI (SAGLASNOSTI MUP-A I JAVNIH SLUZBI) 0 days 24-02-20 24-02-20 24-02
7 PRIJAVA RADOVA 5 days 24-02-20 02-03-20 24-02 PRIJAVA RADOVA 02-03
8 PRIMOPREDAJA LOKACIJE 0 days 27-02-20 27-02-20 27-02
9 UVODJENJE U POSAO 0 days 02-03-20 02-03-20 02-03
10 ZAVRSETAK RADOVA NA TEMELJIMA OBJEKTA 0 days 30-04-20 30-04-20 30-04
11 ZAVRSETAK RADOVA NA KONSTRUKTIVNOM SKLOPU OBJEKTA 0 days 18-05-20 18-05-20 18-05
12 ZAVRSETAK RADOVA NA KROVU OBJEKTA 0 days 24-06-20 24-06-20 24-06
13 ZAVRSETAK RADOVA NA PODU OBJEKTA 0 days 15-06-20 15-06-20 15-06
14 ZAVRSETAK RADOVA NA FASADI OBJEKTA 0 days 30-07-20 30-07-20 30-07
15 ZAVRSETAK RADOVA NA SPOLJNOM UREDJENJU OBJEKTA 0 days 31-08-20 31-08-20 31-08
16 ZAVRSETAK RADOVA NA PRISTUPNOJ SAOBRACAJNICI 0 days 01-08-20 01-08-20 01-08
17 ZAVRSETAK RADOVA NA PRIVODNOM VODU I TRFOSTANICAMA 0 days 07-08-20 07-08-20 07-08
18 INTERNI TEHNICKI PRIJEM 22 days 31-07-20 31-08-20 31-07 INTERNI TEHNICKI PRIJEM 31-08
19 PRIMOPREDAJA SHELL&CORE FAZE RADOVA 0 days 31-08-20 31-08-20 31-08
20
21 Objekat-Retail Park 130.2 days 02-03-20 31-08-20 02-03 Objekat-Retail Park 31-08
22 Arhitektura / Architectural works 129 days 02-03-20 29-08-20 02-03 Arhitektura / Architectural works 29-08
23 Pripremni radovi / Preliminary works 7 days 02-03-20 11-03-20 02-03 Pripremni radovi / Preliminary works 11-03
24 Zemljani radovi / Earth works 65 days 03-03-20 02-06-20 03-03 Zemljani radovi / Earth works 02-06
25 Masinski iskop humusnog sloja 0.50m sa cele povrsine parcele 8 days 03-03-20 14-03-20 03-03 Masinski iskop humusnog sloja 0.50m sa cele povrsine
14-03
parcele
26 Masinski iskop za temelje samce 18 days 14-03-20 08-04-20 14-03 Masinski iskop za temelje samce 08-04
27 Masinski iskop za temeljne trake I temeljne grede 6 days 11-04-20 20-04-20 11-04 Masinski iskop za temeljne trake I temeljne 20-04
grede
28 Masinski iskop za sekundarne temelje 8 days 08-04-20 20-04-20 08-04 Masinski iskop za sekundarne temelje 20-04
29 Nasipanje I sabijanje ispod temelja samaca -recni sljunak 18 days 16-03-20 09-04-20 16-03 Nasipanje I sabijanje ispod temelja samaca -recni sljunak 09-04
30 Nasipanje ispod temeljnih traka 4 days 17-04-20 22-04-20 17-04 Nasipanje ispod temeljnih22-04
traka
31 Nasipanje I sabijanje ispod podne ploce-recni sljunak do kote 438.80 11 days 03-04-20 18-04-20 03-04 Nasipanje I sabijanje ispod podne ploce-recni sljunak do kote 438.80 18-04
32 Nasipanje I sabijanje ispod podne ploce-recni sljunak do kote 439.30 6 days 13-05-20 21-05-20 13-05 Nasipanje I sabijanje ispod podne ploce-recni
21-05 sljunak do kote 439.30
33 Nasipanje I sabijanje ispod podne ploce-drobljeni kamen 0-63 6 days 20-05-20 28-05-20 20-05 Nasipanje I sabijanje ispod podne ploce-drobljeni
28-05 kamen 0-63
34 Nasipanje I sabijanje ispod podne ploce-drobljeni kamen 0-31.5 5 days 26-05-20 02-06-20 26-05 Nasipanje I sabijanje ispod podne02-06
ploce-drobljeni kamen 0-31.5
35 Armirački radovi / Reinforcing works 18 days 17-03-20 11-04-20 17-03 Armirački radovi / Reinforcing works 11-04
36 Betonski I AB radovi do kote +0,00 / Concrete works up to ground level 64 days 17-03-20 15-06-20 17-03 Betonski I AB radovi do kote +0,00 / Concrete works up to ground level 15-06
37 Podlozni beton-temelji samci 18 days 17-03-20 11-04-20 17-03 Podlozni beton-temelji samci 11-04
38 AB radovi do kote +0,00 - temelji samci 19 days 18-03-20 14-04-20 18-03 AB radovi do kote +0,00 - temelji samci 14-04
39 temeljne casice 19 days 18-03-20 14-04-20 18-03 temeljne casice 14-04
40 AB radovi do kote +0,00 -sekundarni temelji 14 days 11-04-20 30-04-20 11-04 AB radovi do kote +0,00 -sekundarni temelji 30-04
41 AB radovi do kote +0,00 -temeljne trake 8 days 20-04-20 30-04-20 20-04 AB radovi do kote +0,00 -temeljne trake 30-04
42 AB radovi do kote +0,00 -pref.temeljne vezne grede 11 days 01-05-20 16-05-20 01-05 AB radovi do kote +0,00 -pref.temeljne vezne grede 16-05
43 AB radovi do kote +0,00 -podna ploca 5 days 08-06-20 15-06-20 08-06 AB radovi do kote +0,00 -podna ploca
15-06
44 Betonski i AB radovi iznad kote +0,00 / Concrete works above ground level 27 days 10-04-20 18-05-20 10-04 Betonski i AB radovi iznad kote +0,00 / Concrete works above ground level 18-05
45 Zidarski radovi / Masonry works 53 days 18-05-20 30-07-20 18-05 Zidarski radovi / Masonry works 30-07
46 Zidanje zidova d=38cm 19 days 18-05-20 13-06-20 18-05 Zidanje zidova d=38cm 13-06
47 Zidanje zidova d= 25 I 12 cm 20 days 24-06-20 22-07-20 24-06 Zidanje zidova d= 25 I 12 cm 22-07
48 Malterisanje zidova plafona I spaletni 23 days 29-06-20 30-07-20 29-06 Malterisanje zidova plafona I spaletni 30-07
49 Tesarski radovi / Carpentry works 13 days 03-06-20 22-06-20 03-06 Tesarski radovi / Carpentry works 22-06
50 Čelična konstrukcija / Steel structure 35 days 18-05-20 06-07-20 18-05 Čelična konstrukcija / Steel structure 06-07
51 Izolaterski radovi / Waterproofing works 47 days 13-05-20 18-07-20 13-05 Izolaterski radovi / Waterproofing works 18-07
52 Hidroizolacija podzemne konstrukcije 5 days 13-05-20 20-05-20 13-05 Hidroizolacija podzemne konstrukcije
20-05
53 Termoizolacija krova 15 days 29-05-20 18-06-20 29-05 Termoizolacija krova 18-06
54 Hidroizolacija krova 15 days 03-06-20 24-06-20 03-06 Hidroizolacija krova 24-06
55 Termoizolacija ploce I temeljnih greda 9 days 18-05-20 30-05-20 18-05 Termoizolacija ploce I temeljnih greda 30-05
56 Hidroizolacija podne ploce 5 days 02-06-20 09-06-20 02-06 Hidroizolacija podne ploce 09-06
57 Hidroizolacija zajednickih toaleta 2 days 15-07-20 18-07-20 15-07 Hidroizolacija 18-07
zajednickih toaleta
58 Keramičarski radovi / Ceramic tiles 8 days 18-07-20 29-07-20 18-07 Keramičarski radovi / Ceramic tiles 29-07
59 Molersko farbarski radovi / Painting works 8 days 07-07-20 18-07-20 07-07 Molersko farbarski radovi / Painting works 18-07
60 AG bravarija/Metal works 25 days 24-06-20 29-07-20 24-06 AG bravarija/Metal works 29-07
61 Montažni radovi / Dry mounting works 19 days 24-06-20 21-07-20 24-06 Montažni radovi / Dry mounting works 21-07
62 Limarski radovi / Steel sheet works 52 days 19-05-20 30-07-20 19-05 Limarski radovi / Steel sheet works 30-07
63 Krovni lim 15 days 19-05-20 09-06-20 19-05 Krovni lim 09-06
64 Oluci I opsivke 18 days 06-07-20 30-07-20 06-07 Oluci I opsivke 30-07
65 Fasaderski radovi / Façade works 39 days 06-06-20 30-07-20 06-06 Fasaderski radovi / Façade works 30-07
66 Fasani sendvic panel 26 days 06-06-20 13-07-20 06-06 Fasani sendvic panel 13-07
67 Alubond 20 days 03-07-20 30-07-20 03-07 Alubond 30-07
68 Razni radovi / Various works 12 days 12-08-20 29-08-20 12-08 Razni radovi / Various works 29-08
69 Saobraćajnica - Kompleks / Traffic plateau 128 days 02-03-20 27-08-20 02-03 Saobraćajnica - Kompleks / Traffic plateau 27-08
70 Prethodni radovi / Preparatory works 4 days 02-03-20 07-03-20 02-03 Prethodni radovi / Preparatory
07-03 works
71 Zemljani radovi / Earth works 91 days 04-03-20 09-07-20 04-03 Zemljani radovi / Earth works 09-07
72 Siroki iskop u zoni ispod objekta u delu useka 15 days 04-03-20 25-03-20 04-03 Siroki iskop u zoni ispod objekta u delu useka 25-03
73 Siroki iskop u zoni van gabarita objekta u delu useka 17 days 09-03-20 01-04-20 09-03 Siroki iskop u zoni van gabarita objekta u delu useka 01-04
74 Obrada podtla, nasipanje I valjnje povrsina ispod saobracajnica- ispred objekta-sljunak do kote 438.80 27 days 10-03-20 16-04-20 10-03 Obrada podtla, nasipanje I valjnje povrsina ispod saobracajnica- ispred objekta-sljunak do kote 438.80 16-04
75 Obrada podtla, nasipanje I valjnje povrsina ispod saobracajnica- iza objekta-sljunak do kote 438.80 24 days 07-04-20 11-05-20 07-04 Obrada podtla, nasipanje I valjnje povrsina ispod saobracajnica- iza objekta-sljunak do kote 438.80 11-05
76 Obrada podtla, nasipanje I valjnje povrsina ispod saobracajnica-sljunak do kote 439.35 8 days 29-06-20 09-07-20 29-06 Obrada podtla, nasipanje I valjnje povrsina ispod saobracajnica-sljunak
09-07 do kote 439.35
77 Kolovozna konstrukcija / Pavement structure 35 days 10-07-20 27-08-20 10-07 Kolovozna konstrukcija / Pavement structure 27-08
78 Izrada donjeg noseceg sloja 0-63mm 10 days 10-07-20 23-07-20 10-07 Izrada donjeg noseceg sloja 0-63mm 23-07
79 Izrada donjeg noseceg sloja 0-31.5mm 10 days 22-07-20 05-08-20 22-07 Izrada donjeg noseceg sloja 0-31.5mm 05-08
80 Izrada gornjeg noseceg sloja BNS 22sA 6 days 14-08-20 22-08-20 14-08 Izrada gornjeg noseceg sloja BNS 22sA22-08
81 Izrada habajuceg sloja AB 11s 6 days 19-08-20 27-08-20 19-08 Izrada habajuceg sloja AB 11s 27-08
82 Izrada betonskog kolovoza 6 days 20-07-20 28-07-20 20-07 Izrada betonskog kolovoza 28-07
83 Ugradnja ivicnjaka I betonskih kanaleta 13 days 31-07-20 18-08-20 31-07 Ugradnja ivicnjaka I betonskih kanaleta 18-08
84 Ugradnja behaton I raster elemenata 16 days 05-08-20 27-08-20 05-08 Ugradnja behaton I raster elemenata 27-08
85 Hidrotehničke instalacije / Water and sewage 101 days 17-03-20 05-08-20 17-03 Hidrotehničke instalacije / Water and sewage 05-08
86 Pripremni radovi HI / Preliminary works 3 days 17-03-20 21-03-20 17-03 Pripremni radovi HI21-03
/ Preliminary works
87 Zemljani radovi HI / Earth works 54 days 21-03-20 04-06-20 21-03 Zemljani radovi HI / Earth works 04-06
88 Građevinski radovi/Construction works 83 days 25-03-20 20-07-20 25-03 Građevinski radovi/Construction works 20-07
89 Kanalizacija / Sewage works 73 days 28-03-20 08-07-20 28-03 Kanalizacija / Sewage works 08-07
90 Vodovod / Waterline 73 days 03-04-20 14-07-20 03-04 Vodovod / Waterline 14-07
91 Drenažni sistem/ Drainage systems 16 days 21-03-20 13-04-20 21-03 Drenažni sistem/ Drainage systems 13-04
92 Sanitarije/Sanitary facilities 4 days 31-07-20 05-08-20 31-07 Sanitarije/Sanitary facilities
05-08
93 Elektroenergetske instalacije / Electro works 111 days 17-03-20 19-08-20 17-03 Elektroenergetske instalacije / Electro works 19-08
94 Spoljni radovi / External works 48 days 11-05-20 16-07-20 11-05 Spoljni radovi / External works 16-07
95 Razvodni ormani / Distribution boards 11 days 14-07-20 29-07-20 14-07 Razvodni ormani / Distribution boards 29-07
96 Napojni vodovi u objektu / Internal power lines 22 days 03-06-20 04-07-20 03-06 Napojni vodovi u objektu / Internal power lines 04-07
97 Sijalična mesta, priključnice, izvodi / Lighting installations 14 days 04-07-20 23-07-20 04-07 Sijalična mesta, priključnice, izvodi / Lighting installations 23-07
98 Svetiljke / Lights 9 days 18-07-20 30-07-20 18-07 Svetiljke / Lights 30-07
99 Gromobranska instalacija i temeljni uzemljivač / Lightning protection 46 days 17-03-20 16-07-20 17-03 Gromobranska instalacija i temeljni uzemljivač / Lightning protection 16-07
100 Svetiljke spoljne rasvete / Outdoor lighting 10 days 05-08-20 19-08-20 05-08 Svetiljke spoljne rasvete / Outdoor lighting 19-08
101 Dizel elektricni agregat 2 days 29-07-20 01-08-20 29-07 Dizel elektricni01-08
agregat
102 Kompenzacija reaktivne energije / Compensation of reactive energy 3 days 27-07-20 30-07-20 27-07 Kompenzacija reaktivne
30-07 energije / Compensation of reactive energy
103 Elektroenergetske instalacije LIDL / Electro works LIDL 95 days 17-03-20 28-07-20 17-03 Elektroenergetske instalacije LIDL / Electro works LIDL 28-07
104 Spoljni radovi LD/ External works 48 days 11-05-20 16-07-20 11-05 Spoljni radovi LD/ External works 16-07
105 Napojni vodovi u objektu LD / Internal power lines 14 days 30-05-20 18-06-20 30-05 Napojni vodovi u objektu LD / Internal power lines 18-06
106 Priključnice, izvodi / Outlet installations 16 days 06-07-20 28-07-20 06-07 Priključnice, izvodi / Outlet installations 28-07
107 Svetiljke LD / Lights 7 days 18-07-20 28-07-20 18-07 Svetiljke LD / Lights 28-07
108 Gromobranska instalacija I temeljni uzemljivač LD / Lightning protection 46 days 17-03-20 16-07-20 17-03 Gromobranska instalacija I temeljni uzemljivač LD / Lightning protection 16-07
109 Telekomunikacione I signalne inst. / Telecom and signal 21 days 30-06-20 29-07-20 30-06 Telekomunikacione I signalne inst. / Telecom and signal 29-07
110 Spoljašnji telefonski priključak / Exterior telephone connection 5 days 06-07-20 13-07-20 06-07 Spoljašnji telefonski priključak / Exterior
13-07 telephone connection
111 Telefonske instalacije / Telephone instalations 14 days 07-07-20 27-07-20 07-07 Telefonske instalacije / Telephone instalations 27-07
112 Video nadzor / Video control 14 days 10-07-20 29-07-20 10-07 Video nadzor / Video control 29-07
113 Ozvučenje / Sound system 12 days 11-07-20 28-07-20 11-07 Ozvučenje / Sound system 28-07
114 Kablovski regali / Cable trays 15 days 30-06-20 21-07-20 30-06 Kablovski regali / Cable trays 21-07
115 Telekomunikacione I signalne inst. LIDL / Telecom and signal LIDL 6 days 06-07-20 14-07-20 06-07 Telekomunikacione I signalne inst. LIDL14-07
/ Telecom and signal LIDL
116 Spoljašnji telefonski priključak / Exterior telephone connection 6 days 06-07-20 14-07-20 06-07 Spoljašnji telefonski priključak / Exterior
14-07
telephone connection
117 Automatska dojava požara / Fire alarm 12 days 13-07-20 29-07-20 13-07 Automatska dojava požara / Fire alarm 29-07
118 Automatska dojava požara - Tržni centar / Fire alarm 12 days 13-07-20 29-07-20 13-07 Automatska dojava požara - Tržni centar / Fire alarm 29-07
119 Automatska dojava požara - LIDL / Fire alarm LIDL 12 days 13-07-20 29-07-20 13-07 Automatska dojava požara - LIDL / Fire alarm LIDL 29-07
120 Termotehnika / HVAC 17 days 07-07-20 30-07-20 07-07 Termotehnika / HVAC 30-07
121 Zajedničke prostorije / Utility areas 17 days 07-07-20 30-07-20 07-07 Zajedničke prostorije / Utility areas 30-07
122 Saobraćajna signalizacija / Traffic signalization 18 days 05-08-20 31-08-20 05-08 Saobraćajna signalizacija / Traffic signalization 31-08
123 Elementi vertikalne signalizacije / Vertical signalization elements 4 days 05-08-20 11-08-20 05-08 Elementi vertikalne signalizacije
11-08/ Vertical signalization elements
124 Elementi horizontalne signalizacije / Horizontal signalization elements 2 days 28-08-20 31-08-20 28-08 Elementi horizontalne
31-08 signalizacije / Horizontal signalization elements
125 Montažni radovi / Montage works 2 days 25-08-20 27-08-20 25-08 Montažni radovi
27-08
/ Montage works
126 Spoljno uređenje / Landscaping 129.2 days 03-03-20 31-08-20 03-03 Spoljno uređenje / Landscaping 31-08
127 Zemljani radovi SU/ Earth works 27 days 07-07-20 13-08-20 07-07 Zemljani radovi SU/ Earth works 13-08
128 Spoljno uređenje / External works 107 days 03-03-20 30-07-20 03-03 Spoljno uređenje / External works 30-07
129 Dizel agregat SU 6 days 18-07-20 27-07-20 18-07 Dizel agregat SU 27-07
130 Reklamni pilon 8 days 20-07-20 30-07-20 20-07 Reklamni pilon 30-07
131 Potporni zid-jug -iskop 14 days 03-03-20 23-03-20 03-03 Potporni zid-jug -iskop 23-03
132 Potporni zid-jug -obrada podtla,nasipanje I sabijanje 14 days 06-03-20 25-03-20 06-03 Potporni zid-jug -obrada podtla,nasipanje I sabijanje 25-03
133 Potpotni zid -istok-iskop 17 days 31-03-20 23-04-20 31-03 Potpotni zid -istok-iskop 23-04
134 Potporni zid -istok-obrada podtla, nasipanje I sabijanje 19 days 04-04-20 30-04-20 04-04 Potporni zid -istok-obrada podtla, nasipanje I sabijanje 30-04
135 Potporni zid-sever -iskop 18 days 04-03-20 30-03-20 04-03 Potporni zid-sever -iskop 30-03
136 Potporni zid-sever-obrada podtla,nasipanje I sabijanje 18 days 06-03-20 31-03-20 06-03 Potporni zid-sever-obrada podtla,nasipanje I sabijanje 31-03
137 Potporni zid-jug -armiranje I betoniranje 19 days 09-03-20 04-04-20 09-03 Potporni zid-jug -armiranje I betoniranje 04-04
138 Potporni zid-istok -armiranje I betoniranje 20 days 07-04-20 05-05-20 07-04 Potporni zid-istok -armiranje I betoniranje 05-05
139 Potporni zid-sever -armiranje I betoniranje 22 days 07-03-20 07-04-20 07-03 Potporni zid-sever -armiranje I betoniranje 07-04
140 Ograda oko parcele-betonske stope 11 days 11-05-20 26-05-20 11-05 Ograda oko parcele-betonske stope 26-05
141 Razno 17 days 26-05-20 18-06-20 26-05 Razno 18-06
142 Bravarski radovi/Metal works 29 days 03-06-20 31-08-20 03-06 Bravarski radovi/Metal works 31-08
143 PP Zaštita / Fire protection 3 days 07-08-20 11-08-20 07-08 PP Zaštita / Fire protection
11-08
144 Vatrogasna oprema / Firefighting equipment 3 days 07-08-20 11-08-20 07-08 Vatrogasna oprema /11-08
Firefighting equipment
145
146 Pristupna saobracajnica 106.6 days 06-03-20 01-08-20 06-03 Pristupna saobracajnica 01-08
147 AG -Pristupna saobracajnica 103.6 days 06-03-20 29-07-20 06-03 AG -Pristupna saobracajnica 29-07
148 Prethodni radovi SAO / Preparatory works 4 days 06-03-20 11-03-20 06-03 Prethodni radovi SAO / Preparatory
11-03 works
149 Zemljani radovi SAO / Earth works 41 days 11-03-20 04-07-20 11-03 Zemljani radovi SAO / Earth works 04-07
150 Kolovozna konstrukcija SAO / Pavement structure 21 days 30-06-20 29-07-20 30-06 Kolovozna konstrukcija SAO / Pavement structure 29-07
151 Hidrotehničke instalacije / Water and sewage 74 days 31-03-20 13-07-20 31-03 Hidrotehničke instalacije / Water and sewage 13-07
152 Pripremni radovi PS HT / Preliminary works 4 days 31-03-20 06-04-20 31-03 Pripremni radovi PS HT / Preliminary
06-04 works
153 Zemljani radovi PS HT / Earth works 25 days 06-04-20 11-05-20 06-04 Zemljani radovi PS HT / Earth works 11-05
154 Građevinski radovi PS HT/Construction works 55 days 27-04-20 13-07-20 27-04 Građevinski radovi PS HT/Construction works 13-07
155 Kanalizacija-montazni radovi PS HT/ Sewage works 41 days 27-04-20 23-06-20 27-04 Kanalizacija-montazni radovi PS HT/ Sewage works 23-06
156 Vodovod-montazni radovi PS HT/ Waterline 41 days 05-05-20 01-07-20 05-05 Vodovod-montazni radovi PS HT/ Waterline 01-07
157 Elektroenergetske instalacije / Electro works 65 days 28-04-20 28-07-20 28-04 Elektroenergetske instalacije / Electro works 28-07
158 Instalacije spoljne rasvete 65 days 28-04-20 28-07-20 28-04 Instalacije spoljne rasvete 28-07
159 Građevinski radovi ISR/Construction works 48 days 28-04-20 04-07-20 28-04 Građevinski radovi ISR/Construction works 04-07
160 Elektromonterski radovi ISR 38 days 05-06-20 28-07-20 05-06 Elektromonterski radovi ISR 28-07
161 Privodni 10kV kabl 25 days 10-06-20 15-07-20 10-06 Privodni 10kV kabl 15-07
162 Građevinski radov PS 10kVi/Construction works 19 days 10-06-20 07-07-20 10-06 Građevinski radov PS 10kVi/Construction works 07-07
163 Elektromonterski radovi PS 10kVi 15 days 17-06-20 08-07-20 17-06 Elektromonterski radovi PS 10kVi 08-07
164 Dopunski radovi PS 10kVi 3 days 11-07-20 15-07-20 11-07 Dopunski radovi PS 10kVi
15-07
165 TT Instalacije 20 days 17-06-20 15-07-20 17-06 TT Instalacije 15-07
166 Građevinski radovi PS TT/Construction works 15 days 17-06-20 08-07-20 17-06 Građevinski radovi PS TT/Construction works 08-07
167 Dopunski radovi PS TT 3 days 11-07-20 15-07-20 11-07 Dopunski radovi PS TT
15-07
168 Saobraćajna signalizacija / Traffic signalization 8 days 22-07-20 01-08-20 22-07 Saobraćajna signalizacija / Traffic signalization 01-08
169 Elementi vertikalne signalizacije PS / Vertical signalization elements 4 days 22-07-20 27-07-20 22-07 Elementi vertikalne signalizacije
27-07PS / Vertical signalization elements
170 Elementi horizontalne signalizacije PS / Horizontal signalization elements 2 days 30-07-20 01-08-20 30-07 Elementi horizontalne
01-08 signalizacije PS / Horizontal signalization elements
171 Montažni radovi PS / Montage works 2 days 29-07-20 31-07-20 29-07 Montažni radovi
31-07PS / Montage works
172
173 Privodni vod I trafostanice 63.8 days 11-05-20 07-08-20 11-05 Privodni vod I trafostanice 07-08
174 Privodni vod 10 kV 63.8 days 11-05-20 07-08-20 11-05 Privodni vod 10 kV 07-08
175 U novoprojektovanoj saobraćanici u Vranju 62.8 days 11-05-20 06-08-20 11-05 U novoprojektovanoj saobraćanici u Vranju 06-08
176 Pripremni radovi 10 kV / Preparatory works 6 days 11-05-20 19-05-20 11-05 Pripremni radovi 10 kV / Preparatory works
19-05
177 Građevinski radov 10kV/Construction works 30 days 19-05-20 30-06-20 19-05 Građevinski radov 10kV/Construction works 30-06
178 Elektromonterski radovi 10kV 32 days 09-06-20 30-07-20 09-06 Elektromonterski radovi 10kV 30-07
179 Posebni troskovi 10kV 3 days 03-08-20 06-08-20 03-08 Posebni troskovi06-08
10kV
180 Na lokaciji IMMOBALCAN u Vranju 63.8 days 11-05-20 07-08-20 11-05 Na lokaciji IMMOBALCAN u Vranju 07-08
181 Pripremni radovi 10kV ib / Preparatory works 6 days 11-05-20 19-05-20 11-05 Pripremni radovi 10kV ib / Preparatory19-05
works
182 Građevinski radovi 10kV ib/Construction works 30 days 19-05-20 30-06-20 19-05 Građevinski radovi 10kV ib/Construction works 30-06
183 Elektromonterski radovi 10kV ib 25 days 09-06-20 14-07-20 09-06 Elektromonterski radovi 10kV ib 14-07
184 Posebni troskovi 10kV ib 3 days 04-08-20 07-08-20 04-08 Posebni troskovi 10kV
07-08ib
185 Trafostanice 5 days 23-07-20 30-07-20 23-07 Trafostanice 30-07
186 Radovi za koje je Investitor EPS Distribucija doo - Beograd, Ogranak EDV Vranje 5 days 23-07-20 30-07-20 23-07 Radovi za koje je Investitor EPS Distribucija
30-07 doo - Beograd, Ogranak EDV Vranje
187 Radovi za koje je Investitor i Finasijer IMMOBALCAN doo - Beograd 4 days 25-07-20 30-07-20 25-07 Radovi za koje je Investitor 30-07
i Finasijer IMMOBALCAN doo - Beograd

Project: DINAMICKI PLAN -NES Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
Date: 24-02-20