Professional Documents
Culture Documents
The following report outlines the manufacturing plan options for a manufacturing
company that wants to minimize costs and maximize profits. It is expected that
the year will begin with 200 units on hand. The company faces a stock-out cost of
$100 per unit and an inventory holding cost of $20 per unit per month. As a
consultant, we aim to develop a manufacturing plan that minimizes the company's
costs while meeting the projected demand. Additionally, we will propose a plan
with slight variation to further reduce overall costs for the company during this
demand period.
The three plans under consideration are:
Plan A: Chase Strategy
Plan B: Subcontracting
Plan C: Stable Workforce
Costs
$20/unit/
Inventory Holdings cost month
Stockout cost $100/unit
Hire cost $5000/100units
Layoff cost $7500/100units
Plan A. Chase Strategy
Production
Perio Hire layoff
Demand (previous Inventory(units) Stockout(units)
d units units
month)
Jan 1500 1600 300 - - 100
Feb 1700 1500 100 - 200 -
Mar 1900 1700 - 100 200 -
Apr 1900 1900 - - - -
May 2300 1900 - 400 400 -
Jun 2300 2300 - - - -
Jul 1900 2300 400 - - 400
Aug 1500 1900 800 - - 400
Total 15000 15100 1600 500 800 900
Total inventory units cost would be = total units * cost per unit
=1600*20
=$32000
Plan B: Subcontracting
Under Plan B, the company would produce at a constant rate of 1500 units per
month. The company would then use subcontracting to meet any additional
demand above 1500 units. The subcontracting cost is $75 per unit
Costs
$20/unit/
Inventory Holdings cost month
Stockout cost $75/unit
Plan B
Total inventory units cost would be = total units * cost per unit
=400*20
=$8000
Total subcontract cost would be = total subcontract units * cost per unit
=2800*75
=$210000
The total cost for plan B would be
=8000+210000
=$290000
Plan C: Stable Workforce
Under this plan, the company will maintain a constant production rate equal to
the average monthly demand and allow varying inventory levels. The plan
assumes that there are no idle time costs.
Costs
$20/unit/
Inventory Holdings cost month
Stockout cost $75/unit
Plan C
Average
Period Demand Inventory(units) Stockout(units)
Production
Executive Summary:
Based on the analysis from the sales department, the manufacturing firm has
three options for controlling production during the demand period. Plan A
proposes changing the workforce to produce the quantity required in the prior
month, Plan B suggests producing a constant rate of 1500 units per month and
using subcontracting to meet any extra demand above 1500 units, and Plan C
supports maintaining a dependable staff by maintaining a constant production
rate equal to the average monthly demand.
The total cost for plan A is = $189500
The total cost for plan B is = $290000
The total cost for plan C is = $81125
After evaluating the three plans, we suggest a slight variation in Plan C, which
could further reduce the overall cost to the company. From the provided cost the
invemtory holding cost is cheaper then stockout cost by increasing the by
increasing the production to 1900 units per month we can eliminate the stockout
cost
Plan D
Average
Period Demand Inventory(units) Stockout(units)
Production
Total inventory units cost would be = total units * cost per unit
=3800*20
=$76000
After evaluating the three plans, we also suggest an additional plan with slight
variation in Plan C, which could further reduce the overall cost to the company.