Professional Documents
Culture Documents
Abstract – Wind power plants with nominal power of 0.5- The electrical collector network consists of a large
5.5 MW, as a rule, are designed at voltages of 10-35 kV. In number of inverter substations (for solar power stations) and
addition to technical conditions and restrictions, a number of wind turbines (for wind power plants), which are connected
economic criteria must be taken into account when designing by 10-35 kV cable transmission lines. The cross-section of
wind power electrical collector networks. For green energy cable core must be technically and economically justified.
facilities, due to the high green tariff, the energy losses in the
electrical collector networks can significantly affect the Many works are devoted to the problem of choosing
payback period. Therefore, during the design it is necessary to rational cross-section of cable core. In particular, in [4-8]
choose such cross-sections of cable core that will ensure the various algorithms for optimizing the structure of cable lines
minimum cost for the entire period of building and operation of wind power electrical collector networks are considered.
of the wind power plant. An analytical dependence is obtained, In [4] the objective function of the calculation algorithm
which allows to calculate the economically justified current takes into account the energy losses in cable lines of the
density for the cores cross-section of such cables for a nominal power plant’s hi voltage grid, and the cable lines cost. In [5]
voltages of 10, 20 and 35 kV for different periods of maximum the authors suggested the integration method to design the
generation of wind power plants. It is established that changes structure of wind power plant electrical collector network
in the payback period in the range of ±1 year from the and searching of cross-section of cable core. They propose to
estimated cross-section of cable core will not change, because use large cross-section of cable core to reduce the energy
the scale of cores cross-sections is discrete. The values of
losses caused by the impedance in the topology, thereby
economic current densities for different periods of maximum
generation are given in the article. They allow to choose
resulting in a slight increased cable cost. In [6] the authors
rational cross-section of cable core during the design of wind applied a combination of heuristic algorithms mainly for
power electrical collector networks. solving topological problems of the electrical collector
network. In [7] the authors applied an evolutive algorithm for
Keywords – cable line, wind power plant, current density, wind power plant optimal overall design. The algorithm
cross-section of cable core. objective is to optimize the profits given an investment on a
wind power plant. The proposed method uses net present
I. INTRODUCTION value as a main criterion. In [8] a model for choosing of the
cross-sections of cable core within the wind power electrical
For last five years, a large number of power plants using collector network is presented. The suggested economic
renewable energy sources have appeared in the structure of cross sections of the internal wind power plant cables
electric energy systems in the EU, USA, China, Ukraine and provide maximization of the profit generated by the wind
other countries. This is due to the laws that encourage the power plant within its lifetime through an optimization of the
development of renewable energy sources to reduce balance between the investment and operating costs. The
greenhouse gas emissions. One of the most important ways work [9] is devoted to the problem of choosing the cross-
of this policy is establishment of Feed-in tariffs for sections of cable screens in wind power plant networks.
generating the green energy [1,2]. However, none of the works fully takes into account the cost
According to the global trend to reduce emissions, an of energy losses in the wind power electrical collector
important task to be solved is to reduce the power and energy networks.
losses, in particular through electrical collector networks of
solar and wind power stations. It should also be noted that II. THE PURPOSE OF THE ARTICLE
due to the high cost of "green" energy, energy losses in The purpose of this article is to offer a calculation of
transmission lines can be too expensive. Therefore, during economically justified current density for cross-section of
their design it is necessary to take into account both the cost
of equipment and the cost of energy losses, as noted in [3].
Fscreen – cross section of the cable screen. To obtain a cross-section Fcore for which the total
The following regression dependence for cables with equivalent annual cost TEAC will be minimal, it is necessary
aluminum cores on different voltage classes are given in [11] to find the first derivative of the variable Fcore and equate it
in thousands USD/km. In the equation below, the numerical to zero:
values of the coefficients are converted to obtain the result in
thousands Euro/km:
dTEAC
WACC10kV 8.32 0.06 Fcore 0.359 Fscreen ; ( En pa pexpl) a1 l
dFcore
WACC20kV 10.966 0.066 Fcore 0.351 Fscreen ; 1
C0 3 I max
2
l 2
0
WACC35kV 17.294 0.077 Fcore 0.469 Fscreen . Fcore
EAOUC value includes amortization deductions, operating From (7) you can get a cross section of cable core:
I max ( En pa pexpl) a1
j 2
Fcore T
C0 3 0.124 max4 8760
10