You are on page 1of 4

Choosing the Cross-section of Cable Core for Wind

Power Electrical Collector Network taking into


account the economic factor
Vadim Bodunov
Viacheslav Bezruchko Roman Buinyi
dept. Electrical Engineering and
dept. Electrical Engineering and dept. Electrical Engineering and
Information Measuring Technologies
Information Measuring Technologies Information Measuring Technologies
Chernihiv Politechnic
Chernihiv Politechnic Chernihiv Politechnic
National University
National University National University
Chernihiv, Ukraine
Chernihiv, Ukraine Chernihiv, Ukraine
vad1979@ukr.net
slavajm@meta.ua buinyiroman@gmail.com
Andrii Krasnozhon Oleksandr Miroshnyk
dept. Electrical Engineering and dept. of Electricity Supply and Energy
Information Measuring Technologies Management
Chernihiv Politechnic State Biotechnological University,
National University Kharkiv, Ukraine
Chernihiv, Ukraine omiroshnyk@khntusg.info
krasnozhon08@gmail.com

Abstract – Wind power plants with nominal power of 0.5- The electrical collector network consists of a large
5.5 MW, as a rule, are designed at voltages of 10-35 kV. In number of inverter substations (for solar power stations) and
addition to technical conditions and restrictions, a number of wind turbines (for wind power plants), which are connected
economic criteria must be taken into account when designing by 10-35 kV cable transmission lines. The cross-section of
wind power electrical collector networks. For green energy cable core must be technically and economically justified.
facilities, due to the high green tariff, the energy losses in the
electrical collector networks can significantly affect the Many works are devoted to the problem of choosing
payback period. Therefore, during the design it is necessary to rational cross-section of cable core. In particular, in [4-8]
choose such cross-sections of cable core that will ensure the various algorithms for optimizing the structure of cable lines
minimum cost for the entire period of building and operation of wind power electrical collector networks are considered.
of the wind power plant. An analytical dependence is obtained, In [4] the objective function of the calculation algorithm
which allows to calculate the economically justified current takes into account the energy losses in cable lines of the
density for the cores cross-section of such cables for a nominal power plant’s hi voltage grid, and the cable lines cost. In [5]
voltages of 10, 20 and 35 kV for different periods of maximum the authors suggested the integration method to design the
generation of wind power plants. It is established that changes structure of wind power plant electrical collector network
in the payback period in the range of ±1 year from the and searching of cross-section of cable core. They propose to
estimated cross-section of cable core will not change, because use large cross-section of cable core to reduce the energy
the scale of cores cross-sections is discrete. The values of
losses caused by the impedance in the topology, thereby
economic current densities for different periods of maximum
generation are given in the article. They allow to choose
resulting in a slight increased cable cost. In [6] the authors
rational cross-section of cable core during the design of wind applied a combination of heuristic algorithms mainly for
power electrical collector networks. solving topological problems of the electrical collector
network. In [7] the authors applied an evolutive algorithm for
Keywords – cable line, wind power plant, current density, wind power plant optimal overall design. The algorithm
cross-section of cable core. objective is to optimize the profits given an investment on a
wind power plant. The proposed method uses net present
I. INTRODUCTION value as a main criterion. In [8] a model for choosing of the
cross-sections of cable core within the wind power electrical
For last five years, a large number of power plants using collector network is presented. The suggested economic
renewable energy sources have appeared in the structure of cross sections of the internal wind power plant cables
electric energy systems in the EU, USA, China, Ukraine and provide maximization of the profit generated by the wind
other countries. This is due to the laws that encourage the power plant within its lifetime through an optimization of the
development of renewable energy sources to reduce balance between the investment and operating costs. The
greenhouse gas emissions. One of the most important ways work [9] is devoted to the problem of choosing the cross-
of this policy is establishment of Feed-in tariffs for sections of cable screens in wind power plant networks.
generating the green energy [1,2]. However, none of the works fully takes into account the cost
According to the global trend to reduce emissions, an of energy losses in the wind power electrical collector
important task to be solved is to reduce the power and energy networks.
losses, in particular through electrical collector networks of
solar and wind power stations. It should also be noted that II. THE PURPOSE OF THE ARTICLE
due to the high cost of "green" energy, energy losses in The purpose of this article is to offer a calculation of
transmission lines can be too expensive. Therefore, during economically justified current density for cross-section of
their design it is necessary to take into account both the cost
of equipment and the cost of energy losses, as noted in [3].

XXX-X-XXXX-XXXX-X/XX/$XX.00 ©20XX IEEE


cable core selection for wind power electrical collector pa , pexpl – standard amortization and annual costs for
network at voltages 10-35 kV the operation of the cable relatively to WACC ;

III. HYPOTHESES OF RESEARCH C0 – electricity tariff;


The design of wind power plants is carried out in a series W – energy losses in the section of cable.
of phases: the selection of wind turbines, the formation of the
electrical collector network and others. This allows to use According to [12], pa  0.04 and pexpl  0.01 for 35 kV
optimization calculations at each individual stage.
cable and pexpl  0.018 for 10-20 kV cable.
To obtain the value of economically justified current
density for cables used a method that takes into account the The value of energy losses in the cable line section of
costs and benefits of the project [10]. The construction of length l can be obtained by the period of maximum energy
transmission lines is usually carried out in a period not losses [3]:
exceeding one year. Therefore the total equivalent annual
cost of electricity transmission will be determined by the

formula:  W  3  I max
2
  l    
Fcore
 TEAC  EAIC  EAOUC  En WACC  EAOUC  
I max – current flowing through the section of the cable
TEAC – total equivalent annual cost; with a cross-section Fcore in the mode of maximum loads;
EAIC –equivalent annual investment cost;  – resistivity of the cable core material;
EAOUC – equivalent annual operation and unreliability  – period of maximum energy losses, hours/year which
cost, which also include the cost of energy losses;
depends on the period of maximum load (generation) Tmax ,
En – normative efficiency ratio, which is the value hours/year:
inverse to the payback period PP , En  1/ PP ;
WACC – weighted average cost of capital.  Tmax 
2
    0.124    8760  
Value of WACC for cable per unit length can be  104 
obtained from the regression dependence:
From (1) - (4) you can get:
 WACC  a0  a1  Fcore  a2  Fscreen  
TEAC  ( En  pa  pexpl)  (a0  a1  Fcore 
a0 , a1, a2 – regression coefficients;   

 a2  Fscreen )  l  C0  3  I max
2
  l 
Fcore – cross-section of the cable core; Fcore

Fscreen – cross section of the cable screen. To obtain a cross-section Fcore for which the total
The following regression dependence for cables with equivalent annual cost TEAC will be minimal, it is necessary
aluminum cores on different voltage classes are given in [11] to find the first derivative of the variable Fcore and equate it
in thousands USD/km. In the equation below, the numerical to zero:
values of the coefficients are converted to obtain the result in
thousands Euro/km:
dTEAC
WACC10kV  8.32  0.06  Fcore  0.359  Fscreen ;  ( En  pa  pexpl)  a1  l 
 dFcore
   
WACC20kV  10.966  0.066  Fcore  0.351  Fscreen ; 1
  C0  3  I max
2
   l   2
0
WACC35kV  17.294  0.077  Fcore  0.469  Fscreen . Fcore

EAOUC value includes amortization deductions, operating From (7) you can get a cross section of cable core:

cost and the cost of energy losses:


C0  3  I max
2
  
 Fcore   
 EAOUC  EAOUC a  EAOUC expl  EAOUC losses    ( En  pa  pexpl)  a1

for which a minimum of total equivalent annual cost will


  pa WACC  pexpl WACC  C0  W   be provided, TEAC  min .
Taking into account (5) and (8), the economically 0.6-2 MW, which use electrical collector networks at
justified current density for the cable core: voltages of 10 and 20 kV.

I max ( En  pa  pexpl)  a1
 j   2
 
Fcore  T 
C0  3     0.124  max4   8760
 10 

From (9) the values of economically justified current


density for wind power electrical collector networks can be
obtained, taking into account the current tariffs C0 for
electricity generated by such wind turbines. According to [2],
the value of the green tariff for electricity generated by wind
power plant depends on the nominal power of one wind
turbine (see Table I) and, in the future, will be slightly
reduced. Thus, wind power plants with the same installed
power can generate electricity with a few different tariffs.

TABLE I. THE VALUE OF THE GREEN TARIFF


The value of the green tariff for
electricity generated by wind power
Nominal power
plant, eurocents / kWh
of one wind Fig. 1. Dependences of economically justified current density of electrical
in the period
turbine, MW collector networks from the period of maximum generation
01.01.2022- 01.01.2023- 01.01.2025-
31.12.2022 31.12.2024 31.12.2029
0,6-2 5.82 5.71 5.28 Both Fig. 1 and Fig. 2 show that with the same period of
maximum generation with increasing value of the payback
more than 2 9.05 9.05 7.92
period in the construction of wind power plants, the value of
the economically justified current density can be reduced,
and the required cross-section of cable core is slightly
The voltage of the electrical collector networks depends
increased. This can be explained by the fact that investments
on the nominal power of a single wind turbine and their
in the construction of wind power plants, which include the
number in the group. As a rule, 10 kV voltage class is used
cable, with a decrease in the payback period should be
for wind turbines up to 0.8 MW, 20 kV for wind turbines
slightly less.
0.8-2 MW, and 35 kV for wind turbines over 2 MW.
According to the analysis of wind potential
measurements at several real wind power plants in Ukraine
and according to the documentation on wind turbines
(Nordex and GoldWind) it is established that the period of
the maximum generation of wind power plant is within
3200-3800 h/year.
Using the above, according to (9), the graphical
dependences j  f (Tmax) and j  f (PP) are obtained.
Green electricity tariff for powerful wind power plants,
which will operate from 2023 was used in this research.
Fig. 1 shows dependences of economically justified
current density for cable lines on the period of maximum
generation.
With increasing period of the maximum generation
economically justified current density should be reduced and
the cross-section of cable core increased, due to the need to
minimize the costs of energy losses in the cable for the entire
period of its operation.
Fig. 2 shows dependences of economically justified Fig. 2. Dependences of economically justified current density for cable
current density for cable lines on the period of maximum lines on the payback period
generation. During the same payback period with increasing
voltage class, the economically justified current density However, in most cases, changes in the payback period in
should be reduced, and the rational cross-section of cable the range of ± 1 year from the calculated cross-section of
core is increased. This is due to the lower value of the green cable core will not change, because the scale of cross-
tariff, which is applied to wind turbines with a capacity of sections is discrete.
Given the above, the following economic current Graphical dependences j  f (Tmax) and j  f (PP) are
densities may be recommended when selecting cross-section
of cable core (Table II). obtained. "Green" electricity tariff for powerful wind power
plants, which will operate from 2023 was used in the
research. It is established that changes in the payback period
TABLE II. THE ECONOMICALLY JUSTIFIED CURRENT DENSITY in the range of ± 1 year from the estimated cross-section of
j , A/mm2 for the period of maximum cable core will not change, because the scale of cross-section
of cable cores is discrete. In the range of maximum
Cable voltage,
kV generation Tmax , h/year generation period 3200-3800 h/year, the economically
justified current density changes almost linearly.
3200 3400 3600 3800
Economically justified current density for wind power
10 1.22 1.17 1.12 1.07
plants electrical collector networks were calculated for
20 1.17 1.12 1.07 1.03 ranges of nominal voltages 10, 20 and 35 kV with a period of
35 1.03 0.98 0.94 0.91
maximum generation of 3200, 3400, 3600 and 3800 h/year,
which are typical for real wind power plants. The obtained
values are summarized in tables that can be used during the
From (9) it is seen that the value of the economically implementation of real projects of the wind power plants
electrical collector networks.
justified current density is a hyperbolic function of Tmax .
However, from Fig. 2 it can be seen that in the range of REFERENCES
periods of maximum generation 3200-3800 h/year, the
[1] Commission Implementing Regulation (EU) 2020/1294 of 15
economically justified current density changes almost September 2020 on the Union renewable energy financing
linearly. Therefore, linear interpolation can be used to mechanism (Text with EEA relevance). C/2020/6123. OJ L 303,
determine the economically justified current density at 17.9.2020, p. 1–17 (BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT,
LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV). [Online].
values Tmax other than those shown in Table II. Available: https://eur-lex.europa.eu/eli/reg_impl/2020/1294
It should also be noted that for the design of wind power [2] Resolution of the NKREKP №1817. (30.08.2019) On approval of the
Procedure for establishing, revising and terminating the "green" tariff
plants electrical collector networks, which will be put into for electricity for business entities, electricity consumers, including
operation after 2025, the economic current densities listed in energy cooperatives, and private households whose generating plants
Table II should be increased by 4.0% for 10-20 kV and 6.9% produce electricity from alternative energy sources. [Online].
for 35 kV (caused by the reduction of the green tariff from Available: https://zakon.rada.gov.ua/laws/show/v1817874-19#Text
2025 year). [3] Buinyi, R.; Krasnozhon, A.; Zorin, V.; Kvytsynskyi, A. Justification
for use of voltage class 20 kV in urban electrical networks.
During the actual design of the wind power plants Tekhnichna Elektrodynamika, 2019, No.1, 68–71, doi:
electrical collector network, the rational cross-section of 10.15407/techned2019.01.068
cable core can be calculated by equation: [4] Semków, M. Optimisation of Cable Cross in Medium Voltage
Networks of a Wind Farm. Acta Energetica, 2013, No.17, 132–138,
doi:10.12736/issn.2300-3022.2013411
[5] Wang, L.; Wu, J.; Tang, Z.; Wang, T. An Integration Optimization
I max
 Fcore  ,  Method for Power Collection Systems of Offshore Wind Farms.
jtable Energies, 2019, 12, 3965, doi:10.3390/en12203965.
[6] Pillai, A.; Chick, J.; Johanning, L.; Khorasanchi, M.; De Laleu, V.
Offshore wind farm electrical cable layout optimization. Engineering
j table – economically justified current density, defined Optimization, 2014, 47, 1689–1708,
by Table II. doi:10.1080/0305215X.2014.992892.
[7] González, J.S.; Gonzalez-Rodriguez, A.G.; Mora, J.C.; Payán, M.B.;
The numerical value obtained by (10) must be rounded to Santos, J.R. Overall design optimization of wind farms. Renewable
the nearest standard cross-section. After that the cross- Energy, 2011, 36, 1973–1982, doi:10.1016/j.renene.2010.10.034.
section must be checked for heating by the load current in [8] Đorđević, A. and Đurišić, Ž. (2018), General mathematical model for
normal operation mode taking into account the conditions of the calculation of economic cross sections of cables for wind farms
collector systems. IET Renewable Power Generation, 2018, Vol.12,
laying the cable and the method of its laying and for thermal Iss.8, 901-909, doi:10.1049/iet-rpg.2017.0420.
stability during short circuit modes.
[9] Al_Issa, H.A.; Qawaqzeh, M.; Khasawneh, A.; Buinyi, R.;
The analysis of electrical collector networks of several Bezruchko, V.; Miroshnyk, O. Correct Cross-Section of Cable Screen
in a Medium Voltage Collector Network with Isolated Neutral of a
wind power stations operating in Ukraine showed that Wind Power Plant. Energies 2021, 14, 3026. doi:10.3390/en14113026
economically justified cross-sections obtained according to
[10] Chun-Lien, S.; Teng, J. Outage costs quantification for benefit–cost
formula (10), in most cases exceed the minimum required analysis of distribution automation systems. International Journal of
cross-sections according to the technical limitations of Electrical Power & Energy Systems, 2007, Vol.29, Iss.10, 767-774,
normal and short circuit modes. doi:10.1016/j.ijepes.2007.06.026
[11] Buinyi, R., Perepechenyi, V., Zorin, V. Regression relationships for
costs of facilites in electrical power networks 10-35 kV. Bulletin of
IV. CONCLUSION NTU "KhPI". Series: New solutions in modern technologies. –
An analytical dependence for the calculation of Kharkiv: NTU "KhPI", 2017, 7 (1229), 18–23, doi:10.20998/2413-
4295.2017.07.03.
economically justified current density for the cores of cables
of the wind power plants electrical collector networks for 10, [12] HKD 340.000.002-97. Determining the economic efficiency of
capital investments in energy. Methodology. Power systems and
20 and 35 kV voltages is obtained. electrical networks (with Changes 2020); Ministry of Energy of
Ukraine: Kyiv, Ukraine, 2020; 108p.

You might also like