Primavera P6 Professional 20

Global Change: Planned/budgeted labour units

Projects: R1439C- Samnan Project -DE5-removed out of scope

Date: 03 May 2023

===================================================================================
===================================================================================
==============

Activity ID Field Old Value


New Value
----------- ----- ---------
---------
A1479 Planned/budgeted Labour units 1.00
1.00

A1480 Planned/budgeted Labour units 0.87


0.87

A1490 Planned/budgeted Labour units 1.00


1.00

A1510 Planned/budgeted Labour units 0.87


0.87

A1520 Planned/budgeted Labour units 0.87


0.87

ADD-TR-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-ED-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z1-ED-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z1-ED-3 Planned/budgeted Labour units 1.00


1.00

ADD-Z1-ETC-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-ETC-2 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-ETC-4 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-GAS-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z1-GAS-2 Planned/budgeted Labour units 0.92


0.92

ADD-Z1-STL-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-STL-2 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-STL-3 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-STL-4 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-SW-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z1-WD-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z1-WD-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z1-WD-3 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-ED-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-ED-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-ED-3 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-ETC-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-ETC-3 Planned/budgeted Labour units 0.00


0.00

ADD-Z2-ETC-4 Planned/budgeted Labour units 0.00


0.00

ADD-Z2-GAS-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-GAS-2 Planned/budgeted Labour units 0.57


0.57

ADD-Z2-IRR-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z2-STL-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z2-STL-2 Planned/budgeted Labour units 0.00


0.00
ADD-Z2-STL-3 Planned/budgeted Labour units 0.00
0.00

ADD-Z2-STL-4 Planned/budgeted Labour units 0.00


0.00

ADD-Z2-WD-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-WD-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z2-WD-3 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-ED-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-ED-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-ED-3 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-ETC-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-ETC-3 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-ETC-4 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-GAS-1 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-GAS-2 Planned/budgeted Labour units 1.00


1.00

ADD-Z3-IRR-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z3-STL-1 Planned/budgeted Labour units 0.00


0.00

ADD-Z3-STL-2 Planned/budgeted Labour units 0.00


0.00

ADD-Z3-STL-3 Planned/budgeted Labour units 0.00


0.00

ADD-Z3-STL-4 Planned/budgeted Labour units 0.00


0.00

ADD-Z3-SW-1 Planned/budgeted Labour units 0.63


0.63

ADD-Z3-WD-1 Planned/budgeted Labour units 1.00


1.00
ADD-Z3-WD-2 Planned/budgeted Labour units 1.00
1.00

ADD-Z3-WD-3 Planned/budgeted Labour units 1.00


1.00

CON-DE-10 Planned/budgeted Labour units 1.00


1.00

CON-DE-11 Planned/budgeted Labour units 1.00


1.00

CON-DE-12 Planned/budgeted Labour units 0.00


0.00

CON-DE-13 Planned/budgeted Labour units 1.00


1.00

CON-DE-14 Planned/budgeted Labour units 0.00


0.00

CON-DE-15 Planned/budgeted Labour units 1.00


1.00

CON-DE-16 Planned/budgeted Labour units 1.00


1.00

CON-SC-10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-DRN-10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-DRN-11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-DU-10 Planned/budgeted Labour units 0.00


0.00

CON-Z1-DU-11 Planned/budgeted Labour units 0.00


0.00

CON-Z1-DU-12 Planned/budgeted Labour units 0.00


0.00

CON-Z1-ED-10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ED-11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ED-12 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ED-13 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ED-14 Planned/budgeted Labour units 0.00


0.00

CON-Z1-ED-15 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ETC-10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ETC-11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ETC-12 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ETC-13 Planned/budgeted Labour units 0.00


0.00

CON-Z1-ETC-16 Planned/budgeted Labour units 1.00


1.00

CON-Z1-ETC-17 Planned/budgeted Labour units 0.00


0.00

CON-Z1-EW10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-EW11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-EW12 Planned/budgeted Labour units 1.00


1.00

CON-Z1-GAS-10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-GAS-11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-GAS-12 Planned/budgeted Labour units 1.00


1.00

CON-Z1-GAS-13 Planned/budgeted Labour units 1.00


1.00

CON-Z1-GAS-14 Planned/budgeted Labour units 1.00


1.00

CON-Z1-IRR-10 Planned/budgeted Labour units 0.00


0.00

CON-Z1-IRR-11 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-10 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-11 Planned/budgeted Labour units 0.00


0.00
CON-Z1-RW-12 Planned/budgeted Labour units 0.00
0.00

CON-Z1-RW-13 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-14 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-15 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-16 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-17 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-18 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-19 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-20 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-21 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-22 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-23 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-24 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-25 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-26 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-27 Planned/budgeted Labour units 0.00


0.00

CON-Z1-RW-28 Planned/budgeted Labour units 0.00


0.00

CON-Z1-STL-10 Planned/budgeted Labour units 0.00


0.00

CON-Z1-STL-11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-STL-12 Planned/budgeted Labour units 0.00


0.00
CON-Z1-STL-13 Planned/budgeted Labour units 1.00
1.00

CON-Z1-STL-14 Planned/budgeted Labour units 0.00


0.00

CON-Z1-STL-15 Planned/budgeted Labour units 0.00


0.00

CON-Z1-STL-16 Planned/budgeted Labour units 0.00


0.00

CON-Z1-SW-13 Planned/budgeted Labour units 0.00


0.00

CON-Z1-WD-10 Planned/budgeted Labour units 1.00


1.00

CON-Z1-WD-11 Planned/budgeted Labour units 1.00


1.00

CON-Z1-WD-19 Planned/budgeted Labour units 1.00


1.00

CON-Z1-WD-20 Planned/budgeted Labour units 0.00


0.00

CON-Z1-WD-21 Planned/budgeted Labour units 0.00


0.00

CON-Z1-WD-22 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-10 Planned/budgeted Labour units 1.00


1.00

CON-Z2-DRN-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-DRN-12 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-13 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-14 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-15 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-16 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-17 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-18 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-19 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-20 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-21 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-22 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-23 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-24 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-25 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-26 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DRN-29 Planned/budgeted Labour units 0.00


0.00

CON-Z2-DU-12 Planned/budgeted Labour units 0.00


0.00

CON-Z2-ED-10 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ED-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ED-12 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ED-13 Planned/budgeted Labour units 0.00


0.00

CON-Z2-ED-14 Planned/budgeted Labour units 0.00


0.00

CON-Z2-ED-15 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ETC-10 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ETC-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ETC-12 Planned/budgeted Labour units 1.00


1.00
CON-Z2-ETC-13 Planned/budgeted Labour units 0.00
0.00

CON-Z2-ETC-14 Planned/budgeted Labour units 0.00


0.00

CON-Z2-ETC-15 Planned/budgeted Labour units 0.00


0.00

CON-Z2-ETC-16 Planned/budgeted Labour units 1.00


1.00

CON-Z2-ETC-17 Planned/budgeted Labour units 0.00


0.00

CON-Z2-EW-10 Planned/budgeted Labour units 1.00


1.00

CON-Z2-EW-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-EW-12 Planned/budgeted Labour units 1.00


1.00

CON-Z2-GAS-10 Planned/budgeted Labour units 1.00


1.00

CON-Z2-GAS-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-GAS-12 Planned/budgeted Labour units 1.00


1.00

CON-Z2-GAS-13 Planned/budgeted Labour units 1.00


1.00

CON-Z2-GAS-14 Planned/budgeted Labour units 1.00


1.00

CON-Z2-IRR-10 Planned/budgeted Labour units 0.00


0.00

CON-Z2-IRR-11 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-10 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-11 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-12 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-12.1 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-12.2 Planned/budgeted Labour units 0.00


0.00
CON-Z2-RW-13 Planned/budgeted Labour units 0.00
0.00

CON-Z2-RW-14 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-15 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-17 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-18 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-19 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-19.1 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-19.2 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-20 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-21 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-22 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-23 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-24 Planned/budgeted Labour units 0.00


0.00

CON-Z2-RW-27 Planned/budgeted Labour units 0.00


0.00

CON-Z2-STL-10 Planned/budgeted Labour units 0.00


0.00

CON-Z2-STL-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-STL-12 Planned/budgeted Labour units 1.00


1.00

CON-Z2-STL-13 Planned/budgeted Labour units 1.00


1.00

CON-Z2-STL-14 Planned/budgeted Labour units 0.00


0.00

CON-Z2-STL-15 Planned/budgeted Labour units 0.00


0.00

CON-Z2-STL-16 Planned/budgeted Labour units 0.00


0.00

CON-Z2-SW-13 Planned/budgeted Labour units 0.00


0.00

CON-Z2-WD-10 Planned/budgeted Labour units 1.00


1.00

CON-Z2-WD-11 Planned/budgeted Labour units 1.00


1.00

CON-Z2-WD-19 Planned/budgeted Labour units 1.00


1.00

CON-Z2-WD-20 Planned/budgeted Labour units 0.00


0.00

CON-Z2-WD-21 Planned/budgeted Labour units 0.00


0.00

CON-Z2-WD-22 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-DRN-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-DRN-12 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-13 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-14 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-15 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-16 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-17 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-18 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-19 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-20 Planned/budgeted Labour units 0.00


0.00
CON-Z3-DRN-21 Planned/budgeted Labour units 0.00
0.00

CON-Z3-DRN-22 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-23 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-24 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-25 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-26 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DRN-29 Planned/budgeted Labour units 0.00


0.00

CON-Z3-DU-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-DU-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-DU-12 Planned/budgeted Labour units 0.00


0.00

CON-Z3-ED-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ED-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ED-12 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ED-13 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ED-14 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ED-15 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ETC-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ETC-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ETC-12 Planned/budgeted Labour units 1.00


1.00

CON-Z3-ETC-13 Planned/budgeted Labour units 1.00


1.00
CON-Z3-ETC-16 Planned/budgeted Labour units 1.00
1.00

CON-Z3-ETC-17 Planned/budgeted Labour units 0.00


0.00

CON-Z3-EW-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-EW-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-EW-12 Planned/budgeted Labour units 1.00


1.00

CON-Z3-GAS-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-GAS-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-GAS-12 Planned/budgeted Labour units 1.00


1.00

CON-Z3-GAS-13 Planned/budgeted Labour units 1.00


1.00

CON-Z3-GAS-14 Planned/budgeted Labour units 1.00


1.00

CON-Z3-IRR-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-IRR-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-RW-10 Planned/budgeted Labour units 1.00


1.00

CON-Z3-RW-11 Planned/budgeted Labour units 0.72


0.72

CON-Z3-RW-12 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-13 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-14 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-15 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-16 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-17 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-18 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-19 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-20 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-21 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-22 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-23 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-24 Planned/budgeted Labour units 1.00


1.00

CON-Z3-RW-25 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-26 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-27 Planned/budgeted Labour units 0.00


0.00

CON-Z3-RW-28 Planned/budgeted Labour units 0.00


0.00

CON-Z3-STL-10 Planned/budgeted Labour units 0.00


0.00

CON-Z3-STL-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-STL-12 Planned/budgeted Labour units 1.00


1.00

CON-Z3-STL-13 Planned/budgeted Labour units 1.00


1.00

CON-Z3-STL-14 Planned/budgeted Labour units 0.00


0.00

CON-Z3-STL-15 Planned/budgeted Labour units 0.00


0.00

CON-Z3-STL-16 Planned/budgeted Labour units 0.00


0.00

CON-Z3-SW-13 Planned/budgeted Labour units 0.00


0.00
CON-Z3-WD-10 Planned/budgeted Labour units 1.00
1.00

CON-Z3-WD-11 Planned/budgeted Labour units 1.00


1.00

CON-Z3-WD-19 Planned/budgeted Labour units 1.00


1.00

CON-Z3-WD-20 Planned/budgeted Labour units 1.00


1.00

CON-Z3-WD-21 Planned/budgeted Labour units 1.00


1.00

CON-Z3-WD-22 Planned/budgeted Labour units 0.00


0.00

ENG-BP-10 Planned/budgeted Labour units 1.00


1.00

ENG-BP-11 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-10 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-11 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-12 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-13 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-14 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-15 Planned/budgeted Labour units 0.00


0.00

ENG-MAT-AP-16 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-17 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-18 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-19 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-AP-20 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-10 Planned/budgeted Labour units 1.00


1.00
ENG-MAT-SM-11 Planned/budgeted Labour units 1.00
1.00

ENG-MAT-SM-12 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-13 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-14 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-15 Planned/budgeted Labour units 0.00


0.00

ENG-MAT-SM-16 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-17 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-18 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-19 Planned/budgeted Labour units 1.00


1.00

ENG-MAT-SM-20 Planned/budgeted Labour units 1.00


1.00

ENG-MST-AP-10 Planned/budgeted Labour units 1.00


1.00

ENG-MST-AP-11 Planned/budgeted Labour units 1.00


1.00

ENG-MST-AP-12 Planned/budgeted Labour units 1.00


1.00

ENG-MST-AP-13 Planned/budgeted Labour units 1.00


1.00

ENG-MST-SM-10 Planned/budgeted Labour units 1.00


1.00

ENG-MST-SM-11 Planned/budgeted Labour units 1.00


1.00

ENG-MST-SM-12 Planned/budgeted Labour units 1.00


1.00

ENG-MST-SM-13 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-AP-10 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-AP-11 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-AP-12 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-AP-13 Planned/budgeted Labour units 0.00


0.00

ENG-PRQ-AP-14 Planned/budgeted Labour units 0.00


0.00

ENG-PRQ-AP-15 Planned/budgeted Labour units 0.00


0.00

ENG-PRQ-SM-10 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-SM-11 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-SM-12 Planned/budgeted Labour units 1.00


1.00

ENG-PRQ-SM-13 Planned/budgeted Labour units 0.00


0.00

ENG-PRQ-SM-14 Planned/budgeted Labour units 0.00


0.00

ENG-PRQ-SM-15 Planned/budgeted Labour units 0.00


0.00

GP-COR-10 Planned/budgeted Labour units 1.00


1.00

GP-COR-11 Planned/budgeted Labour units 1.00


1.00

GP-GI-TT-10 Planned/budgeted Labour units 1.00


1.00

GP-GI-TT-11 Planned/budgeted Labour units 1.00


1.00

GP-MOB-MM-10 Planned/budgeted Labour units 0.89


0.89

GP-MOB-MM-11 Planned/budgeted Labour units 0.54


0.54

GP-MOB-SO-10 Planned/budgeted Labour units 1.00


1.00

GP-MOB-SO-11 Planned/budgeted Labour units 0.54


0.54

GP-NOC-AP-10 Planned/budgeted Labour units 1.00


1.00
GP-NOC-AP-11 Planned/budgeted Labour units 1.00
1.00

GP-NOC-AP-12 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-13 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-14 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-15 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-16 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-17 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-18 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-19 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-20 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-21 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-31 Planned/budgeted Labour units 1.00


1.00

GP-NOC-AP-41 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-10 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-11 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-12 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-13 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-14 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-15 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-16 Planned/budgeted Labour units 1.00


1.00
GP-NOC-SM-17 Planned/budgeted Labour units 1.00
1.00

GP-NOC-SM-18 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-19 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-20 Planned/budgeted Labour units 1.00


1.00

GP-NOC-SM-21 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-10 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-11 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-12 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-13 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-14 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-15 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-16 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-17 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-18 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-19 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-20 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-21 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-22 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-23 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-24 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-25 Planned/budgeted Labour units 1.00


1.00

GP-SD-AP-26 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-10 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-11 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-12 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-13 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-14 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-15 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-16 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-17 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-18 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-19 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-20 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-21 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-22 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-23 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-24 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-25 Planned/budgeted Labour units 1.00


1.00

GP-SD-SM-26 Planned/budgeted Labour units 1.00


1.00
HO-10 Planned/budgeted Labour units 0.00
0.00

HO-11 Planned/budgeted Labour units 0.00


0.00

HO-12 Planned/budgeted Labour units 0.00


0.00

PR-D-10 Planned/budgeted Labour units 1.00


1.00

PR-D-11 Planned/budgeted Labour units 1.00


1.00

PR-D-12 Planned/budgeted Labour units 1.00


1.00

PR-D-13 Planned/budgeted Labour units 1.00


1.00

PR-D-14 Planned/budgeted Labour units 1.00


1.00

PR-D-15 Planned/budgeted Labour units 0.00


0.00

PR-D-16 Planned/budgeted Labour units 1.00


1.00

PR-D-17 Planned/budgeted Labour units 0.00


0.00

PR-D-18 Planned/budgeted Labour units 0.00


0.00

PR-D-19 Planned/budgeted Labour units 1.00


1.00

PR-D-20 Planned/budgeted Labour units 0.00


0.00

PR-D-21 Planned/budgeted Labour units 0.00


0.00

PR-D-22 Planned/budgeted Labour units 0.00


0.00

PR-O-10 Planned/budgeted Labour units 1.00


1.00

PR-O-11 Planned/budgeted Labour units 1.00


1.00

PR-O-12 Planned/budgeted Labour units 1.00


1.00

PR-O-13 Planned/budgeted Labour units 1.00


1.00
PR-O-14 Planned/budgeted Labour units 1.00
1.00

PR-O-15 Planned/budgeted Labour units 0.00


0.00

PR-O-16 Planned/budgeted Labour units 1.00


1.00

PR-O-17 Planned/budgeted Labour units 0.00


0.00

PR-O-18 Planned/budgeted Labour units 0.00


0.00

PR-O-19 Planned/budgeted Labour units 1.00


1.00

PR-O-20 Planned/budgeted Labour units 0.00


0.00

PR-O-21 Planned/budgeted Labour units 0.00


0.00

PR-O-22 Planned/budgeted Labour units 0.00


0.00

T&C-10 Planned/budgeted Labour units 0.00


0.00

T&C-11 Planned/budgeted Labour units 0.00


0.00

T&C-12 Planned/budgeted Labour units 0.00


0.00