You are on page 1of 4

Detail of Mesuerement

S.No. Particulars No. Length width H/Depth Quantity Unit


1 Earth work in excavation in trenches for foundation
in ordirnary soil as per S.I. No. 2.6.1
Columns foundation ###
long wall 1 x 2 5.63 0.90 1.00 10.13 ###
short wall 1 x 2 4.96 0.90 1.00 8.93 ###
1 x 1 2.50 0.90 1.00 2.25 ###
1 x 1 3.60 0.90 1.00 3.24 ###
1 x 1 1.00 1.00 0.60 0.60 ###
Total 25.15 cum

2 P/L of cement concrete 1:6:12( 1 cement : 6 coarse


sand : 12 graded brick aggregate 40mm nominal size )
and curing complete i/c cost of formwork in
foundation and floors as per S.I.No. 273

1 x 2 5.63 0.90 0.10 1.01 160 ft


1 x 2 4.96 0.90 0.10 0.89 ###
1 x 1 2.50 0.90 0.10 0.23 ###
1 x 1 3.60 0.90 0.10 0.32
Total 2.46 cum
3 1B/W in foundation cement mortar ( 1cemet :
4coarse sand ) as per dsr 6.1.1
1 x 2 5.63 0.69 0.30 2.33
1 x 2 5.63 0.57 0.30 1.93
1 x 2 5.63 0.46 0.30 1.55
1 x 1 3.60 0.69 0.30 0.75
1 x 1 3.60 0.57 0.30 0.62
1 x 1 3.60 0.46 0.30 0.50
1 x 2 4.96 0.69 0.30 2.05
1 x 2 4.96 0.57 0.30 1.70
1 x 2 4.96 0.46 0.30 1.37
1 x 1 2.50 0.69 0.30 0.52
1 x 1 2.50 0.57 0.30 0.43
1 x 1 2.50 0.46 0.30 0.35
1 x 2 0.75 0.12 0.90 0.16
1 x 2 0.98 0.12 0.90 0.21
Total 14.45 cum

4 B/W in super structure cement mortar ( 1cemet :


4coarse sand ) as per dsr 6.1.1
1 x 2 5.63 0.35 0.35 1.38
1 x 2 4.5 0.35 0.35 1.10
1 x 1 2.5 0.35 0.35 0.31
1 x 2 3.60 0.230 3.00 4.97
1 x 1 4.96 0.230 3.00 3.42
1 x 1 3.46 0.230 3.00 2.39
1 x 1 2.96 0.230 3.00 2.04
1 x 1 0.35 0.350 3.00 0.37
1 x 2 1.80 0.230 3.00 2.48
1 x 1 6.09 0.230 0.30 0.42
1 x 1 1.50 0.230 0.30 0.10
1 x 1 2.50 0.230 0.30 0.17
1 x 1 2.03 0.230 0.30 0.14
1 x 2 3.46 0.230 1.35 2.15
1 x 2 3.60 0.230 1.35 2.24
deduction 23.68 cum
room door (D1)(D2) 1 x 2 1.20 0.230 2.10 1.16
window 1 x 4 0.90 0.230 1.50 1.24
2.40
21.28 cum
cement concrete flooring 1:4:8(1 cement :4 coarse
sand :8 graded stone aggregate)finished with a
5 floating coat of neat cement concrete including 1 x 2 5.63 0.35 0.075 0.295575
cement slurry 40 mm thick with 20 mm nominal size
stone aggregate as per dsr 11.3.1
1 x 2 4.5 0.35 0.075 0.23625
1 x 1 2.5 0.35 0.075 0.065625

6 PCC in 1:2 1 x 2 5.63 0.35 0.02 0.07882


1 x 2 4.5 0.35 0.02 0.063
1 x 1 2.5 0.35 0.02 0.0175
0.75677 cum

7 cement concrete flooring 1:2:4(1 cement :2 coarse


sand :4 graded stone aggregate)finished with a
floating coat of neat cement concrete including
cement slurry 40 mm thick with 20 mm nominal size
stone aggregate as per dsr 11.3.1
1 x 2 5.63 0.35 0.35 1.38 ###
1 x 2 4.5 0.35 0.35 1.10
1 x 1 2.5 0.35 0.35 0.31
1 x 2 3.60 0.23 0.150 0.25
1 x 2 3.64 0.23 0.150 0.25
3.29 cum

8 12 mm cement plaster of mix ( 1:6) as per 13.1.2 ###


1 x 4 3.60 3.00 43.20
1 x 2 3.46 3.00 20.76
1 x 2 4.96 3.00 29.76 ###
1 x 4 1.80 3.00 21.60
1 x 2 2.96 3.00 17.76
1 x 4 0.35 3.000 4.20
1 x 1 12.12 0.83 10.06
1 x 1 3.46 1.50 5.19
1 x 2 3.60 1.500 10.80
Deduction 163.33 Sqm
1 x 2 1.20 2.10 5.04
1 x 2 1.10 2.10 4.62
1 x 8 0.90 1.50 10.80
20.46
Total 142.87 Sqm

###
9

providing and laying of RCC ( 1:2:4) c/sand & 20mm


S/Ballast mortar i/c all the complete work in iron
piller foundation as per dsr 4.2.3
1 x 4 1.36 0.23 0.15 0.19
1 x 1 1.66 0.23 0.15 0.06

1 x 1 1.56 0.23 0.15


0.05
1 x 1 6.09 4.96 0.125 3.78
1 x 1 1.50 0.27 0.125 0.05
1 x 4 1.36 0.45 0.125 0.31
1 x 2 4.10 0.27 0.125 0.28
4.71
deduction 1 x 1 2.00 2.00 0.13 0.50
4.21 cum