Professional Documents
Culture Documents
Designing strong
walls on weak
soils
Civil engineers
have options to
remedy foundation
soil problems
and meet project
cost and schedule
requirements.
T
he demand for new roadway stabilized earth (MSE) walls. While foundation soil problems include mas-
construction or expansion both systems are commonly used, many sive overexcavation and replacement,
of existing infrastructure for public and private owners have adopted deep foundations, or staged construc-
both public and private own- MSE wall solutions, which represent a tion. Each of these options provides
ers continues to grow. These projects more economical and faster wall con- distinct advantages and disadvantages
commonly involve grade-separation struction approach than cast-in-place and is selected based on the project-
construction and projects are often cantilevered retaining walls. MSE walls specific needs.
restricted by tight schedules, limited can also be designed to tolerate more For instance, overexcavation is most
funding, public opposition, and right- settlement. commonly used when the depth of
of-way limitations, among other things. However, weak or compressible weak or compressible soils is relatively
Although project challenges may vary, foundation soils present significant shallow (less than 10 feet). Removal of
one universal question remains for design and construction challenges. shallow, unsuitable soils and replace-
engineers, contractors, and owners on Wall heights commonly range from 10 ment with compacted, engineered
every project: How do you design and to 40 feet and apply pressures ranging fill is often an inexpensive approach
build the project to meet the owner’s from 4,000 to 7,000 pounds per square to provide improved foundation soils
cost and schedule requirements? foot (psf ) near the wall face, depending in these conditions. Overexcavation
Infrastructure construction involv- on the specific wall design. The increas- and replacement may become less
ing grade separations in urban environ- ing size of these walls poses geotechni- cost-effective, however, when poor
ments is often challenged by tight or cal challenges, including inadequate soils extend to deeper depths, dewa-
difficult access and limited right-of- factors of safety for global stability and tering is required because of shallow
way restrictions for construction. As bearing capacity, as well as excessive groundwater, temporary shoring is
an alternate to sloped embankments, total and differential settlement. required to stabilize an excavation next
which typically require large work Traditional solutions for remedying to an existing roadway, or the presence
areas and property acquisition, grade-
separation solutions typically involve
construction of retaining walls using Construction of cantilevered or mechanically stabilized earth retaining walls to create grade separa-
either conventional cast-in-place con- tions presents significant design and construction challenges when faced with weak or compressible
crete cantilevered walls or mechanically foundation soils.
Rammed Aggregate Pier installation involves drilling a 30-inch-diameter hole; placing thin lifts of
aggregate within the cavity; and vertically ramming the aggregate using a high-energy, patented
of contaminated soil results in high beveled impact tamper.
costs of disposal. Overexcavation and
replacement is significantly affected by
inclement weather, which could present pressure is applied, settlement occurs able to support high loads through very
schedule challenges as well. and the weak foundation soils become soft soils — delivering superior perfor-
When compressible or weak soils stronger, thereby permitting higher mance — but are an expensive solution.
extend to depths of 30 or 40 feet embankment construction. This process The costs incurred include not only the
or greater, options for supporting is repeated in multiple stages until the deep foundations (driven steel or con-
embankments or wall construction may embankment reaches the final design crete piles, augercast-in-place piles, or
include staged construction or deep height. This approach is well suited caissons) but also a load-transfer plat-
foundations. Staging involves embank- when there is significant time in the form constructed using either multiple
ment construction to specific heights, construction schedule. This approach layers of structural geogrid or a concrete
temporarily stopping construction and is not often a viable solution when the mat to transfer embankment pressures
monitoring the embankment until embankment construction is part of the to the deep foundation elements.
settlement is complete, followed by critical path for the project. The balance of cost, schedule, perfor-
continuation of construction to greater Deep foundations are used in similar mance, and ease of construction has led
heights. The purpose is to build the situations with deep, compressible soils design teams to an alternative approach
embankment to specific heights where to support and transfer the embank- for embankment and wall construction
the existing soils will provide suitable ment pressures to more competent called an Intermediate Foundation
support. As the new embankment bearing layers. Deep foundations are solution. This approach uses Rammed
underlain by bedrock at depths as shal- analyses (slope stability programs), Bearing pressures were calculated
low as 13 feet in some locations and HVJ Associates concluded that the at the retaining walls and, using con-
more than 30 feet in other locations. shear strength (resistance) along the ventional Terzaghi bearing capacity
HVJ Associates identified early in critical slip surface extending behind approaches, engineers determined that
the design that construction of the tall the reinforced portion of the wall and the factors of safety for bearing would
walls would result in significant increase through the weak clay was insufficient fall below the required minimum factor
in the shear stress (demand) on the for supporting the walls. Factors of of safety of 2.0 for wall heights greater
underlying weak clay foundation soils. safety for stability may be determined than about 16 feet. While settlement
In addition, the high applied pressures as the ratio of the shear strength within in the areas with relatively shallow rock
at the wall face resulted in unacceptably the contributing soil layers along the was less of a concern, the variability of
low factors of safety for bearing capac- slip surface to the applied shear stress. the clay stiffness and the deeper depth
ity. While settlement control was less The calculated factor of safety for the to rock coupled with the high design
of a concern in areas with shallow rock, long-term case was less than 1.25 for pressures resulted in estimated post-
the high wall pressures applied in areas walls taller than 15 feet, and approxi- construction settlement of more than
of deeper rock were expected to result mately 1.0 for walls taller than 20 feet, 5 inches. An alternative solution was
in unacceptable long-term settlement. indicating a strong likelihood of global required to limit the post-construction
Using conventional limit
12PH-MesaAACEN4C08 equilibrium
3/6/08 4:42 PM instability.
Page 1 settlement to 1 inch or less.
A Civil Approach
for the Road Ahead.
Site • Traffic • Structural • Transportation
Value Engineering • Subsurface Utility
Aerial Mapping • Land Survey